© 2012 delmar, cengage learning chapter 6 advanced shielded metal arc welding
TRANSCRIPT
© 2012 Delmar, Cengage Learning
Chapter 6
Advanced Shielded Metal Arc Welding
© 2012 Delmar, Cengage Learning
Objectives
• Discuss how metal must be prepared before welding
• Describe the process, and demonstrate making the root pass, filler weld, and cover pass in all positions and techniques
• Explain the purpose of a hot pass• Tell what should be checked with a visual
inspection, and describe the appearance of an acceptable weld
© 2012 Delmar, Cengage Learning
Objectives (cont'd.)
• Demonstrate how to make: – A root pass on plate in all positions
– A root pass on plate with an open root in all positions
– An open root weld on plate using the step technique in all positions
– A multiple pass filler weld on a V-joint in all positions using E7018 electrodes
– A cover bead in all positions
© 2012 Delmar, Cengage Learning
Objectives (cont'd.)
– A single V-groove open root butt joint with an increasing root opening
– A single V-groove open root butt joint with a decreasing root opening
– SMAW welds of plate to plate
– SMAW welds of pipe to pipe
© 2012 Delmar, Cengage Learning
Introduction
• SMAW process produces high-quality welds– Welders frequently make welds in difficult situations
to a code or standard
• Metal edges must be prepared – 100% joint penetration
– Code-quality welds
– Metal thicker than ¼ inch
• Preparation improves strength – Prepared joints require more than one weld pass
© 2012 Delmar, Cengage Learning
Introduction (cont'd.)
• Root pass – Fuses and seals parts together
• Hot pass – Improves weld contour
• A test for one company may not qualify a welder for another company– AWS Certified Welder program
• Available from AWS's office in Miami, Florida
© 2012 Delmar, Cengage Learning
Root Pass
• First of a multiple pass weld– Fuses two parts together
– Establishes depth of weld metal penetration
– Needed to obtain a sound weld
– May be open or closed
– Can use a backing strip or backing ring• Backing strip used in a closed root can remain as
part of the weld or be removed• Removable backup tapes have been developed• Tape can be peeled off after weld is completed
© 2012 Delmar, Cengage Learning
FIGURE 6-2 Root pass maximum deposit 1/4 in. (6 mm) thick. © Cengage Learning 2012
© 2012 Delmar, Cengage Learning
Root Pass (cont'd.)
• Widely used in plate and pipe designs– Face side is not as important as root surface on
back or inside
– If root surface is correct: front side can be ground, gouged, or burned out
• Weld is evaluated from root side only
– Root face for most grooves will be about the same size
© 2012 Delmar, Cengage Learning
FIGURE 6-4 Using back gouging to ensure a sound weld root. © Cengage Learning 2012
© 2012 Delmar, Cengage Learning
Root Pass (cont'd.)
• Control penetration on joints with varying root gaps – Stepping electrode manipulation
– Key hole• Electrode is moved in and out of molten weld pool• Metal flows through key hole to root surface• Key hole ensures 100% penetration• Process requires more welder skill
© 2012 Delmar, Cengage Learning
FIGURE 6-7 Electrode movement to open and use a key hole. © Cengage Learning 2012
© 2012 Delmar, Cengage Learning
Hot Pass
• Surface of a root pass may be irregular• High-strength code welds
– Root pass and each filler pass must be ground• Grinding is important when high-strength, low alloy
welding electrodes are used
• Hot pass – Cleans out trapped slag
– Makes a root pass more uniform
– Uses high amperage and a fast travel rate
– Rapidly melts a large surface area
© 2012 Delmar, Cengage Learning
Hot Pass (cont'd.)
• Small amount of metal should be deposited– Resulting weld is concave
• Concave weld is easier cleaned• Failure to clean a convex root leaves wagon tracks
• Can be used to repair or fill small spots– Incomplete fusion or pinholes
• Normal weave pattern – Straight step or “T” pattern
© 2012 Delmar, Cengage Learning
FIGURE 6-19 Slag trapped between passes will show on an X ray. © Cengage Learning 2012
© 2012 Delmar, Cengage Learning
Hot Pass (cont'd.)
• Key points– Do not allow molten weld pool to cool completely
– Do not blow shielding gas covering away from the molten weld pool
– Penetration of the molten weld pool must be deep• Free all trapped slag• All porosity must be burned out
© 2012 Delmar, Cengage Learning
Filler Pass
• Fills groove after root pass– Made with stringer or weave beads
• Characteristics– Weld beads must overlap
• Stringer beads overlap 50%• Weave beads overlap 25%
– Finish bead is smooth
– Each weld bead must be cleaned before the next bead is started
© 2012 Delmar, Cengage Learning
FIGURE 6-24 Filler pass buildup sequence.© Cengage Learning 2012
© 2012 Delmar, Cengage Learning
Filler Pass (cont'd.)
• Ways to remove slag between filler weld passes– Chipping, wire brushing, and grinding
• Weld can be checked by ultrasonic or radiographic nondestructive testing– Most schools are not equipped to do this testing
– Check soundness by destructive testing
© 2012 Delmar, Cengage Learning
Cover Pass
• Last weld bead on a multipass – May use a different electrode weave
– Must be uniform and neat looking
– Appearance might be the only factor in accepting or rejecting welds
– Should not be more than 1/8 inch wider than the groove opening
© 2012 Delmar, Cengage Learning
FIGURE 6-26 The cover pass should not be excessively large. © Cengage Learning 2012
© 2012 Delmar, Cengage Learning
Plate Preparation
• Weld groove prepares the plate– Can be cut into one side or both sides
– May be cut into one or both plates of the joint
• Depth, angle, and location– Determined by a code standard
• SMA welds on plate 1/4 inch or thicker that need to have a weld with 100% joint penetration – Plate must be grooved
• May be ground, flame cut, gouged, or machined
© 2012 Delmar, Cengage Learning
Plate Preparation (cont'd.)
• Bevels and V-grooves – Best if cut before parts are assembled
• J-grooves and U-grooves – Can be cut either before or after assembly
• Groove on both sides– Tee joints, welds with little distortion, and welds that
will be loaded equally from both sides
• Back gouging – Cuts a groove in back side of a joint that has been
welded
© 2012 Delmar, Cengage Learning
FIGURE 6-29 Typical butt joint preparations. © Cengage Learning 2012
© 2012 Delmar, Cengage Learning
Preparing Specimens for Testing
• Maximum allowable size for fissures in a guided-bend test – Given in codes for specific applications
• Some standards are listed– ASTM E190
– AWS QC10
– AWS QC11
• Copies available from appropriate organization
© 2012 Delmar, Cengage Learning
Acceptance Criteria for Face Bends and Root Bends
• Key points– Weld is uniform
– No arc strikes on the plate other than the weld
– Free of incomplete fusion and cracks
– Penetration must be 100% or as specified
– Weld must be free of overlap
– Correct weld specimen preparation is essential
© 2012 Delmar, Cengage Learning
Acceptance Criteria for Face Bends and Root Bends (cont'd.)
• Specimen cut out of test weldment– Abrasive disc
– Sawing
– Cutting with a torch
• Flame-cut specimens – Grind or smooth the edges
• All corners must be rounded– Radius of 1/8 inch maximum
– Grinding or machining marks must run lengthwise
© 2012 Delmar, Cengage Learning
Restarting a Weld Bead
• Welding bead must be restarted – After stopping to change electrodes
• Weld bead near completion– Should be tapered
• Increase the travel rate
• Before restarting– Chip slag and clean weld crater
• Restart the arc in the joint ahead of the weld– Electrodes must be allowed to heat up
© 2012 Delmar, Cengage Learning
Restarting a Weld Bead (cont'd.)
• Movement to root of weld and back up on bead– Builds up weld
– Reheats metal
• Avoid starting and stopping weld beads in corners– Tapering and restarting are especially difficult in
corners• Often results in defects
© 2012 Delmar, Cengage Learning
Preheating and Postheating
• Preheating – Application of heat to metal before welding
– Helps to reduce:• Cracking• Hardness• Distortion• Stresses
© 2012 Delmar, Cengage Learning
Preheating and Postheating (cont'd.)
• Preheating is often required:– On large thick plates
– When plate is very cold
– When temperature is very cold
– When using small diameter electrodes
– On high-carbon or manganese steels
– On complex shapes
– With fast welding speeds
© 2012 Delmar, Cengage Learning
Preheating and Postheating (cont'd.)
• Postheating – Applies heat to metal after welding
– Used to slow the cooling rate
– Reduces hardening
• Interpass temperature– Temperature of metal during welding
– Given as a minimum and maximum
© 2012 Delmar, Cengage Learning
Poor Fitup
• Some welding must be done on joints that are poorly fitted– Requires a good welder
– Skilled welders can watch the molten weld pool and knows how to avoid disaster
• Considerations– Amperage setting may have to be adjusted
– May be necessary to break and restart the arc
– May need to change the electrode angle
© 2012 Delmar, Cengage Learning
Summary
• Grooved welds on one-half inch thick plate – Most common test plates
• Grooved welds – Used by many companies in testing
• Vertical and overhead positions – Most common positions used in testing
• Visually defect-free welds – Assumed to pass destructive testing
– Always make welds as uniform as possible