• Incident summary
• Progress since last SUG
• Forward release schedule
• Service feedback…
© Amor Group 2009
Incident Summary
• 58 new Incidents raised since last SUG
• 4 RDA raised incidents resolved outwith Service Levels
• Summary of incidents types relate to:– Aggregate claim XML submission issues– General queries in relation to usage of MCIS and Cognos– Data manipulation to claims and re-profiling project dates
© Amor Group 2009
Progress Since Last SUG• Release v2.3.4 (Irregularity and Clawback Enhancements)
• MI Deployments
• Further Payment Interface Testing (EEDA)
• R3 Declarations development underway
© Amor Group 2009
Forward Release ScheduleRelease Date Enhancements Additional Progress
v3.0 (R3 It. 1)
30 Oct 2009 Declaration creation and management.
Model office planned for 21 Oct.
Declarations reports developed as an MI release.
Assessment on extension of NWDA Web Services solution to support AWM and other RDAs.
SAP Payments Integration Requirements being progressed.
v3.1(R3 It. 2)
23 Nov 2009 AA 16 Visits amendment to support additional fields.
Support for payment advances and certificates of expenditure.
SAP Payments Integration development underway.
Financial Engineering Instruments requirements being progressed.
v3.3(R3 It. 3)
18 Dec 2009 Irregularity NIFF/SFIR rule changes. Amendment to Core Irregularity and Visits submission (decoupling from Agg. Claim).
SAP Payments interface completed.
SFC2007 interface development being progressed.
© Amor Group 2009
Additional Requirements
• Additional requirements identified but yet to be prioritised
– Revision to claim expenditure to support public and private funding
– Revision to support Major projects (core user upload and amendment of N+2 target/profile)
– Revision to support CA 5% checks
– Maintenance of programme details