Optimising Building Performance
Dr Paul Bannister
![Page 2: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/2.jpg)
Where does the energy go?HVAC technologiesLighting technologiesOffice equipmentOther technologiesConclusions
Overview
![Page 3: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/3.jpg)
Where does the Energy Go?
![Page 4: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/4.jpg)
HVAC consists ofChillersCooling towersBoilersCogen/trigenFans and PumpsPackage unitsHVAC control systemAnd some other bits and pieces
HVAC Technologies
![Page 5: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/5.jpg)
Optimum chiller technologies<300kW – scroll300-700kW – magnetic bearing VSD centrif700-1000kW mag bearing VSD centrif, small VSD screw1000-2000kW VSD screw, VSD mag bearing centrif
Savings – up to 50% relative to 10-15 year old technologiesEconomics: long payback, coordinate with routine replacement if possible. Note: R22/R123 (HCFCs) are becoming obsolete
Chiller Hardware
![Page 6: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/6.jpg)
Don’t run when they aren’t neededOutdoor temperature lockout
Operate at higher chilled water temperaturesOperate at lower condenser water temperaturesStage up and down at the right timeEconomics: great
Chiller Operation
![Page 7: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/7.jpg)
Hardware:Replace old tired cooling towersUse induced draft towers not forced draft towersVariable speed fans
OperationSpread load out across multiple towersOptimise temperature set-point in conjunction with chillers
Cooling Towers
![Page 8: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/8.jpg)
Hardware:Replace tired old boilersEliminate steam boilers as far as possibleUpgrade burners to fully modulating burnersUse condensing boilers
OperationTune the burner regularlyTurn off as much as possibleReduce operating temperature when loads permit
Boilers
![Page 9: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/9.jpg)
Hardware:Not a magic bullet, and very expensiveSizing a critical issueCan you actually use the waste heat?
OperationConsider third party operation and managementMaximise run hours during peak electricity cost periods to get returnDon’t create false loads to justify thermal useNot a substitute for efficiency
Cogen/trigen
![Page 10: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/10.jpg)
Hardware:Replace stuffed bearings and sagging V-belts Use VSD control not guide vane
OperationSet up controls to minimise operating speed and pressure to meet loadTurn off when not needed
Fans
![Page 11: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/11.jpg)
Hardware:Replace stuffed bearingsUse VSD control not throttling valves
OperationSet up controls to minimise operating speed and pressure to meet loadTurn off when not needed
Pumps
![Page 12: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/12.jpg)
Hardware:Replace dying unitsInstall condenser water shut-off valves
OperationTurn off when not neededWiden dead bandsRefrigerant chargeFilter cleaning
Water Cooled Package Units
![Page 13: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/13.jpg)
Hardware:Replace with inverter units
OperationTurn off when not neededWiden dead bandsRefrigerant chargeFilter cleaning
Air Cooled Package Units
![Page 14: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/14.jpg)
Hardware:Replace pneumatic systems
OperationSee operational measuresWiden dead bandsCommission!Time-of-use control
HVAC Controls
![Page 15: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/15.jpg)
Outside air controlOptimise economy cycleMinimise unnecessary outside air
Air FiltersClean regularlyUse high energy efficiency filters (Eurovent standard)
Other HVAC Bits and Pieces
![Page 16: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/16.jpg)
Halogen downlightsReplace with LED (with care!)
Metal HalideConsider LED replacements if control possible
FluorescentAim for <9W/m² in office spaceT5 or T8 with electronic ballastGrid spacing and design important
Lighting is a DESIGN issue
Lighting Technologies
![Page 17: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/17.jpg)
Time of use control is paramountManual switches rarely effectiveTime-clocks tend to longer hours than necessaryUse occupancy sensors
Manual on, auto-off Zone size <250m²
DimmingGood theory but often unsuccessfulKeep focussed on the time of use control!
Lighting Control
![Page 18: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/18.jpg)
Time of use control is paramountWorking week is less than a third of the hours in a weekTurn off!!
Use low-power PCs (laptops and some desktops; thin client)Use power management settings
Screen savers do not save energy
Office Equipment - Computers
![Page 19: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/19.jpg)
Time of use control is paramountUse power management settings
Avoid excess equipmentUse central print stations, MFDs
Kitchen equipmentUse 3+star fridges, etcTime-clock boiling water/ chilled water units
Office Equipment - General
![Page 20: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/20.jpg)
Don’t over-conditionASHRAE air-on recommendations:
18-28°C, <60% RH, 5.5°C<dewpoint<15°CMake sure air goes through not around the racks
“Hot aisle/cold aisle” approachEnsure that separate conditioners are not fightingVirtualise/modernise serversRemove old, underutilised servers
Office Equipment – Server Rooms
![Page 21: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/21.jpg)
Upgrade technologyMassive costBenefit can be >40%
Tune operating parameters to match real-occupancyDon’t over condition the lift motor roomUpgrade the lights in the lift carsTurn off some lifts overnight (remarkably difficult)
Other Equipment – Lifts
![Page 22: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/22.jpg)
Convert electric to gas or heat pumpReduce tap flowsTurn off circulation pump out of hours
Other Equipment – Domestic Hot Water
![Page 23: Optimising Building Performance - City of Melbourne...18-28 C,](https://reader033.vdocuments.net/reader033/viewer/2022060406/5f0f5ec97e708231d443d2b5/html5/thumbnails/23.jpg)
Wide range of possible upgrades for all technologyIn each case measures may be
Hardware – longer paybacksOperational – shorter paybacks
Remember: Most buildings have many operational savings availableImproved efficiency frequently means better service