EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE. Organization of the Instrument Team. Andrea Santangelo IAAT, Eberhard-Karls Univerität Tübingen. - Preamble - Recommendations by the Steering Committee - Organization of the EUSO- Balloon team - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: -  Preamble -  Recommendations by the Steering Committee

- Preamble

- Recommendations by the Steering Committee

- Organization of the EUSO-Balloon team

- Remark on the International JEM-EUSO Team

E U S O - B A L L O O N D E S I G N R E V I E W, 1 8 . 1 2 . 2 0 1 2 , C N E S T O U L O U S E

Andrea Santangelo IAAT, Eberhard-Karls Univerität Tübingen

Organization of the Instrument Team

Page 2: -  Preamble -  Recommendations by the Steering Committee

Preamble

This talk describes the key points of the EUSO Balloon instrument Organization.

All details on the topic can be found in the “Organization Note of the EUSO-Balloon Instrument” EUSO-ON-INST-201-LALV2.6

The EUSO Balloon mission has been proposed by a consortium of three French Laboratories members of the JEM-EUSO international collaboration:

The EUSO Balloon mission is fully supported by the JEM-EUSO collaboration

CDR – 18.12.2012

Organization of the EUSO-Balloon Team 2

Page 3: -  Preamble -  Recommendations by the Steering Committee

Preamble (2)

CNES is in charge of the mission and leads and supervises the mission development.CNES supports the French contribution to the instrument and the French participation to the development of the mission. The French Institutes of the consortium shall deliver the Instrument for the flights.The JEM-EUSO collaboration provides a complete and dedicated support to the definition and building of the subsystems, components and sub-assembly items of the Instrument.

The development is under the management and responsibility of the French team in coordination with the JEM-EUSO management.CDR – 18.12.2012

Organization of the EUSO-Balloon Team 3

Page 4: -  Preamble -  Recommendations by the Steering Committee

CDR – 18.12.2012

4

PRR Steering Committee Report Recc. 1: Project Organization

Define the CNES Organization (Action 1.3) Introduce an electrical architect

M. Dupieux, Electrical ArchitectIdentify harness activities (Action 1.2)

See EUSO-IC-INST-407-IRAP_V2.0 and EUSO-EA-INST-408-IRAP_V1.0

Clarify the participations to AIT (Action 1.2) See EUSO-AI-INST-251-LAL_V1.0B. Mot, AIT/AIV manager

Identify Ground Support Equipment responsibilities (Action 1.2) See EUSO-AI-INST-251-LAL_V1.0

Organization of the EUSO-Balloon Team

Page 5: -  Preamble -  Recommendations by the Steering Committee

CDR – 18.12.2012

5

PRR Steering Committee Report Recc. 3: Project Organization

To define an efficient and reactive management structure- See new management scheme

To freeze requirementsSee new ITS

Identify a set of minimal and sufficient documentation Received by CNES and prepared.

Provide a realistic schedule, including AIT/AIVSee EUSO-AI-INST-251-LAL_V1.0See EUSO-DP.INST-207-LAL

Organization of the EUSO-Balloon Team

Page 6: -  Preamble -  Recommendations by the Steering Committee

CDR – 18.12.2012

6

EUSO Balloon management

Organization of the EUSO-Balloon Team

Page 7: -  Preamble -  Recommendations by the Steering Committee

CDR – 18.12.2012

(short) title of presentation 7

Update: Project Manager (PM, Guillaume Prévôt)

The PM is responsible of the overall instrument technical performances, of the schedule, the costs and the coordination of all the activities

- Organizes technical work, manages the interfaces (also with the Gondola)

- Coordinates the technical work on the EUSO-Balloon within the JEM-EUSO collaboration in coordination with the JEM-EUSO management

- Defines tasks, sets up schedules, checks the results, handles the delays in one word ensures the compliance to the schedule

Interfaces the CNES- Follows the various project procedures- Organizes regular meetings and milestone reviews- Organizes the preparation of the documentation needed in each

development phase

Page 8: -  Preamble -  Recommendations by the Steering Committee

CDR – 18.12.2012

8

Update: System Manager (SM, Sylvie Dagoret)

The SM is responsible for the development of the Instrument in compliance with the technical specifications:

- Responsible for the instrument configuration and for the management of the external and internal interfaces

- He reports and assists the PM and is assisted by the electrical, mechanical and thermal Architects and by the subsystem-managers

- Interfaces the JEM-EUSO technical responsible persons (key role!!!)

Organization of the EUSO-Balloon Team

Page 9: -  Preamble -  Recommendations by the Steering Committee

CDR – 18.12.2012

9

Update: Architets

Gilles Roudil is the architect for the Mechanics. G. Medina-Tanco for the thermal aspects.The architects are responsible for the mechanical and thermal configuration of the Instrument They are responsible for the preparation of the documentation relative to the internal and external thermal and mechanical interfaces. Michel Dupieux is the electrical architect.He is responsible for all electrical interfaces / interface documents and coordinates the activity among components responsible persons to ensure that connectors and cables are properly developed.

The Architects report to and support the SM.

Organization of the EUSO-Balloon Team

Page 10: -  Preamble -  Recommendations by the Steering Committee

Update: AIT/AIV Manager (AIT-M, B. Mot)

The AIT/AIV manager (AIT-M) is responsible for the definition, the development and the planning of the integration of the instrument and its sub-systems. With the help of each sub-system manager, he defines the various tasks, sets up the schedule, checks the results, handles the delays and tries to cope with the possible drifts in AIT tasks.

The AIT/AIV manager is assisted by AIT responsible persons for the various sub-systems: - AIT of PDM at LAL (Salleh Ahmad new person by LAL)- AIT of the DP at LAL (Sylvie Dagoret)- AIT of the mechanics at IRAP (Gilles Roudil)- the electric AIT at IRAP (Michel Dupieux)- AIT of the optics at IRAP (Baptiste Mot Camille Catalano)

CDR – 18.12.2012

10Organization of the EUSO-Balloon Team

Page 11: -  Preamble -  Recommendations by the Steering Committee

Update: Component Managers

There are four component managers:Optics (TLE): T. Ebisuzaki Photo Detector Module (PDM): M. CasolinoData processing (DP): G. OsteriaInfrared Camera (IR-CAM): M. Rodriguez-Frias

They are responsible for the design, production, integration and testing of the components in compliance with the Instrument specifications and the external and internal interfaces.

Such a large international collaboration requires a clear distribution of responsibilities also at the sub-assembly level: Sub-assembly responsible persons have been identified.

CDR – 18.12.2012

11Organization of the EUSO-Balloon Team

Page 12: -  Preamble -  Recommendations by the Steering Committee

CDR – 18.12.2012

12

A complex but clear organization

Recc. 1 act. 1.4

Letters of Commitment have been prepared by all key contributors (and, by the way, most of the necessary items have been purchased and are available or are being manufactured)

Page 13: -  Preamble -  Recommendations by the Steering Committee

Organization in France (1)

In bold persons involved in management tasks at project level or at group-laboratory level

Page 14: -  Preamble -  Recommendations by the Steering Committee

Organization in France (2)

Page 15: -  Preamble -  Recommendations by the Steering Committee

Conclusions

The proposed structure can of course be updated following the suggestion of the committee…The EUSO Balloon is fully included in the JEM-EUSO roadmap.The EUSO consortium is fully committed to the EUSO Balloon activity: key persons of JEM-EUSO are taking concrete responsibilities.Most important: the team has shown in the last months high motivation and commitment and that a strict schedule can be indeed met!

Page 16: -  Preamble -  Recommendations by the Steering Committee

Back-up slides

Page 17: -  Preamble -  Recommendations by the Steering Committee

JEM-EUSO Collaboration

Japan, USA, Korea, Mexico, Russia

Europe: Bulgaria, France, Germany, Italy, Poland, Slovakia, Spain, Switzerland

13 Countries, 80 Institutions, more than 290 researchers

RIKEN: Leading institution

Page 18: -  Preamble -  Recommendations by the Steering Committee

EUSO Balloon

The EUSO Balloon mission is conceived as a pathfinder of the JEM-EUSO mission and of the challenging technique of observing UHE CR from space It should perform:

End-to-end tests of the subsytems and components of the JEM-EUSO mission.To prove the global detection chain, and improve the TRLTo improve our understanding the atmospheric and terrestrial UV background.It might detect for the first time ever a cosmic shower from above.

Page 19: -  Preamble -  Recommendations by the Steering Committee

Principal Investigator (PI, Peter Von Ballmoos)

The PI defines the scientific program and the specification of the mission in coordination with the JEM-EUSO management (PI P. Picozza, Deputy PI T. Ebisuzaki, Global Coordinator A. Santangelo) and the JEM-EUSO Instrument scientist Bertaina.

The PI, with the PM, ensures compliance between the system and mission specifications and the Instrument technical specifications and verifies that they are properly taken into account by the technical project team

Page 20: -  Preamble -  Recommendations by the Steering Committee

CO-Principal Investigator (Co-PI, Andrea Santangelo)

In coordination with the PI defines the scientific program and the specification of the mission, and acts to ensure compliance between the system specifications and the instrument technical specifications and to ensure that the project is conducted in compliance with the objectives.

A central assignment of the Co-PI concerns the interface between balloon project and the JEM-EUSO collaboration.