Claim Handling Section 105.15 Dispute Resolution

Upload: domenic-parks

Post on 17-Jan-2018

220 views

Category:

Documents


0 download

DESCRIPTION

 Wydot documentation ◦ Create a file at notice or before - Start of claim manual ◦ Documentation is vital, have good practices in place from the beginning.  Regular and complete diaries, letters, photos, videos  Pay documentation  T-109s, E-78s, grading reports ◦ Other resources  Trauner manual  DCE, Construction staff

TRANSCRIPT

Page 1: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Claim HandlingSection 105.15 Dispute Resolution

Page 2: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs

Begins with the contractors notice 5 working days after the resident engineers decision.◦ From this point all correspondence sent certified

return receipt

Claim Handling

Page 3: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Wydot documentation◦ Create a file at notice or before - Start of claim

manual◦ Documentation is vital, have good practices in

place from the beginning. Regular and complete diaries, letters, photos, videos Pay documentation

T-109s, E-78s , grading reports◦ Other resources

Trauner manual DCE, Construction staff

Claim Handling

Page 4: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Section 105.15◦ The Claim Package

List of supporting documentation 105.15.2 Certification Basis for entitlement stated and supported

May have evolved over time Correspondence- 5 day letter Pictures Diaries, time cards

Claim Handling

Page 5: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Section 105.15◦ The Claim Package

Impacts stated and supported Schedules, analysis

Costs/ time extension stated and supported tied to impacts Bid calculations Actual costs and supporting documentation

Ask for what you need if it is not provided - certified letter Restart 30 days

Get explanations of documents you don’t understand Bid calculations, accounting records

Claim Handling

Page 6: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Analysis◦ Focus on the three elements

Entitlement –Impact-Cost All three elements at this stage

Claim Handling

Page 7: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Analysis◦ Entitlement

Contract based evaluation Is it a change from the bidding condition? 104.2.2 differing site conditions

Latent conditions Unusual unknown conditions

Claim Handling

Page 8: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Analysis◦ Entitlement

104.2.3 Significant changes in the character of the work Change in character (Grading) Changes in quantity

104.2.3 Engineer ordered suspensions Contract provisions

LQDs, Quality assurance assessments Warranty work(2 weeks on chip seal, plants for city) Remove and replace quality issues

Claim Handling

Page 9: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Impacts◦ Where the contractor often falls short◦ Delays, inefficiencies, acceleration, change

method and means

Claim Handling

Page 10: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

◦ Change in method and means◦ Delays

Critical path and noncritical path Non-excusable Excusable

Compensable-related to a change Non- compensable - Force majeure Trauner Manual Schedule analysis

As constructed schedule vs as-planned schedule Production analysis(measured mile)

Claim Handling

Page 11: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Claims Handling

Excusable Non compensable delay

Page 12: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Claim anaysis RC Wall Dell Creek

Production over timeproject

Date Days Concrete Concreteworked Placed Placed

CY CY TTD

11/5/2009 excavation began 0 0 02/9/2010 footer l 46 92.5 92.5 92.5

2/17/2010 footer k 54 121 213.5 213.52/19/2010 wall l 56 40 253.5 253.52/25/2010 wall k 61 40 293.5 293.5

3/9/2010 footer j 71 80 373.5 373.53/15/2010 wall j 76 40 413.5 413.53/18/2010 slab 79 38 451.5 451.53/23/2010 curb 83 8 459.5 459.53/30/2010 slab 89 32 491.5 491.53/31/2010 curb j 90 7.25 498.75 498.75

4/1/2010 footer A 91 102.5 601.25 601.254/9/2010 wall A 96 25 626.25 626.25

4/23/2010 footer B 108 100 726.25 726.254/30/2010 Wall B 114 33 759.25 759.25

5/3/2010 foorter I 117 44 803.25 803.255/7/2010 footer I 121 140 943.25 943.25

5/18/2010 wall I 129 77 1020.25 1020.255/24/2010 Wall J? … Slab? 133 32 1052.25 1052.255/27/2010 Footer C 136 99.5 1151.75 1151.756/10/2010 Wall C 146 41 1192.75 1192.756/21/2010 curb J ? 155 41 1233.75 1233.756/22/2010 curb J? 156 8.5 1242.25 1242.256/29/2010 slab I 161 29 1271.25 1271.256/30/2010 Cub a 162 6.5 1277.75 1277.757/12/2010 slab A ? B? 170 39 1316.75 1316.757/13/2010 Curb A 171 8.5 1325.25 1325.257/15/2010 slab B 173 29 1354.25 1354.257/16/2010 curb b 174 7.5 1361.75 1361.757/21/2010 Footer H 181 134 1495.75 1495.757/29/2010 footer g 185 130 1625.75 1625.757/30/2010 wall H 186 69 1694.75 1694.75

8/5/2010 wall g 191 56 1750.75 1750.758/10/2010 e joint bridge 195 3 1753.75 1750.758/11/2010 bridge abutment 196 18 1771.75 1750.758/12/2010 bridge abutment 197 18 1789.75 1750.758/13/2010 bridge abutment 198 1 1790.75 1750.758/24/2010 bridge abutment 207 20.25 1811 1750.758/25/2010 bridge abutment 208 18 1829 1750.758/26/2010 bridge abutment 209 3 1832 1750.75

9/2/2010 slab g 216 34 1866 1784.759/3/2010 head wall 217 3 1877.5 1784.759/8/2010 curb g 219 8.5 1874.5 1793.25

9/10/2010 footer F 221 122.5 2000 1907.259/15/2010 footer E 225 126.5 2126.5 2033.759/17/2010 wall f 227 47.5 2174 2081.259/24/2010 footer d 233 126 2300 2207.259/27/2010 Wall E 234 40 2340 2247.259/30/2010 Wall D 237 37 2377 2284.2510/6/2010 head walls 242 5.5 2382.5 2292.7510/8/2010 head walls 244 2.5 2385 2292.75

10/18/2010 slab G 253 34 2419 2326.7510/19/2010 curbg 254 8.25 2427.25 233510/22/2010 Slab F 257 35.5 2463.75 2370.510/23/2010 curb f 258 9.5 2472.25 238010/28/2010 Slab E 263 34 2506.25 2414

11/2/2010 Curb C 266 8.5 2514.75 2422.511/3/2010 slab A ? B? 267 5 2519.75 2427.511/5/2010 Curb D 269 36 2555.75 2463.511/6/2010 curb 270 9 2564.75 2472.5

11/10/2010 slab C, D 274 46.5 2612.25 251911/12/2010 curb CD 276 10.75 2622 2529.75

0

500

1000

1500

2000

2500

3000

0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270

Figure 1Class B Concrete vs. Working days

Series1

11/5/2009

Average Production

Original Schedule

Actual Production

E-61 No.2 March 26, 2010

E-61 No. 6 Aug 19,2010

Nov 8, 2010 last day of paving

Cubic YardsPlaced

Working days

Page 13: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Costs◦ Should be straight forward if the other two

elements are done properly◦ Costs tied to impacts

Actual costs Force account

◦ Profit - not allowed for claims◦ Overhead

Job overhead ok Home office overhead - No

Claim Handling

Page 14: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Costs◦ Bid price calculation and production estimates

Don’t just get the one item Mobilization

◦ Are there mitigating impacts to costs What is in the unit price

Fixed cost Direct cost Job OH Labor

Claim Handling

Page 15: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Costs◦ Contractors source documents

Labor records if there are labor cost involved Time cards Payrolls

Production records (crushing)What, when and how much

Claim Handling

Page 16: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Costs(cont)◦ Contractors source documents

Accounting records OH rate

Home office- Not usually recoverable Job overhead

Equipment bare rates canceled checks

Equipment costs Rental agreements

Material costs Purchase orders

Claim Handling

Page 17: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

The Letter – last chance◦ Certified return receipt ◦ Entitlement impacts and costs◦ Thorough, but don’t get lost in the minutia◦ Analysis, charts and graphs◦ A fair tone - strict but fair

Contractor has 30 days from receipt to respond

Claim Handling

Page 18: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Appeal to the District Engineer◦ The claim manual

Brief history/executive summary Completion report

Correspondence Numbered and tabbed, oldest is #1, appeal to the District

Engineer last Diaries -tabbed Analysis

Charts and graphs and source documents Schedules

Pictures The contractors claim package

Claim Handling

Page 19: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Presenting to the District Engineer◦ Agenda

General overview of the project and claim - RE Presentation of the contractors claim - Contractor Questions for the contractor - District engineer Analysis of the claim and Basis for decision – RE Questions for the RE – District Engineer Discussion

Claim Handling

Page 20: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Preparation Organize logically, like your letter Visual aids

Power point Know what their arguments will be Be prepared for theatrics, be composed

◦ Show you did your best to consider their arguments

From this point on you are just the keeper of the claim manual

Appeal to the Chief engineer◦ Wear a tie

Claim Handling

Page 21: Section 105.15 Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days

Claim Handling

Questions/Discussion?