© siemens ag all rights reserved. the importance of infrastructure june 2011

11
© Siemens AG All rights reserved. The importance of infrastructure June 2011

Upload: justina-todd

Post on 24-Dec-2015

219 views

Category:

Documents


2 download

TRANSCRIPT

© Siemens AG All rights reserved.

The importance of infrastructure

June 2011

© Siemens AG All rights reserved.

Infrastructure for transport

- Port facilities

- Delivery to site

- Site conditions

Grid connection

- Availability of a good grid connection

Agenda

© Siemens AG All rights reserved.

Page 3 March 2011© Siemens AG All rights reserved.

Siemens Wind PowerAsia/Pacific

Infrastructure for transport – Port facilities

Normally WTG’s are delivered by heavy lift vessel. Besides this fact below criteria are

important to discharge WTG’s.

- Suitable port / Suitable berthing area

- Availability of temporary storage area at the port

- Available equipment (Crane’s, reach stackers, fork lifts) in the port which can be used for handling of WTG’s

- Clearance of cargo having arrived in the port

- Potential hazards in the port

Page 4 March 2011© Siemens AG All rights reserved.

Siemens Wind PowerAsia/Pacific

Infrastructure for transport – Port facilities

Page 5 March 2011© Siemens AG All rights reserved.

Siemens Wind PowerAsia/Pacific

WTG’s are delivered on heavy haulage trucks. Each WTG normally consists of 8-10 heavy / over dimensional loads.

- Height / width / weight / turning restrictions such as tunnels, bridges, cities, mountains etc.

- Trucks / trailers available to execute the project- Actual condition of the road- Geography and time of the road will be travelled- Availability of police escorts / permit procedures / curfews- Procedures for road modifications- Alternatives to road transport

Infrastructure for transport – Delivery to site

Page 6 March 2011© Siemens AG All rights reserved.

Siemens Wind PowerAsia/Pacific

Infrastructure for transport – Delivery to site

Page 7 March 2011© Siemens AG All rights reserved.

Siemens Wind PowerAsia/Pacific

The site must be accessible for both WTG’s and equipment needed for the construction Phase as well. Further there might be other obstacles at the site which require special attention.

- Planning the pad locations on site is vital to avoid any constraints with protected wild life, environmental heritage sites, weather, aviation requirements and construction consents

- Site roads must be constructed to accommodate trucks/cranes using the roads- Hardstands can vary in size. Smaller which requires less civil works but demands JIT delivery of

more WTG components- Rate of delivery in connection with the construction method on site- Storage of components at site- Additional equipment needed on more difficult sites - Infrastructure for the many people attending the site- Consequences if planning / preparations fail

Infrastructure for transport – Site conditions

Page 8 March 2011© Siemens AG All rights reserved.

Siemens Wind PowerAsia/Pacific

Infrastructure for transport – Site conditions

Page 9 March 2011© Siemens AG All rights reserved.

Siemens Wind PowerAsia/Pacific

Grid connection – Availability of a good grid connection.

Getting the turbines installed and having them producing electricity is off course the primary target, but it’s the grid connection which determines how much energy can be released into

the grid.

- Site location is preferred to be close to an existing transmission line / sub station of right capacity- A stronger grid is preferred over weaker strength grids which is a stronger connection to the grid- Smart grid is the present trend. Since wind farms can be considered to a part of distributed

energy efficient transmission network is required in planning- Dynamic rating of transmission line as per IEEE 738-2006 needs to be considered for efficient

use of transmission lines in system planning- Good relations with government, wind farm developers and the wind turbine manufacturers will

enhance the acceleration of the green projects

Page 10 March 2011© Siemens AG All rights reserved.

Thanks for your attention!

© Siemens AG All rights reserved.

Page 11 March 2011© Siemens AG All rights reserved.

BACKUP SLIDES