PROJECT EXECUTION MANUAL
JOB PACAKAGES FOR THE FABRICATION AND ERECTION
OF TANKS
CLIENT: ENGRO FOODS SUPPLY LTD
CONTACTOR: FAUZ ENGINEERING
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 1
![Page 2: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/2.jpg)
PROJECT EXECUTION MANUAL
PROJECT BRIEF:
FAUZ has been awarded with the fabrication and erection of five liquid storage tanks at Integrated Rice Process Complex of Engro Foods Supply Ltd.
FAUZ SCOPE OF WORK:
The Scope of Work of FAUZ includes the following:
Mobilization and de-mobilization. Procurement of all direct materials and consumables. Skilled manpower for the fabrication and installation. Provision of all necessary tools and plants. Erection and installation of storage tanks. Scaffolding. Hydro-testing. Welder qualification. QA/QC documentation. PPE’s as per requirement. Boarding & lodging of workers. Internal rubber lining for treated water tank. Internal epoxy coating for condensate tank. Electrical power supply and water at work location. Radiography 10%. Sandblasting & Painting. Transportation of shop fabricated tanks (02 Nos.) to site.
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 2
![Page 3: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/3.jpg)
PROJECT EXECUTION MANUAL
However following is excluded from FAUZ Scope of Work
Basic design, detailed design and fabrication drawings. Any type of civil works at site. Arrangement of Third Party Inspection. Any type of E & I work. Water for hydro-test. Area for site office, store and site camp. Area for material storage and workshop.
PROJECT COMPLETION PERIOD
The project is to be completed and delivered to client in the duration of 60 days
PROJECT DETAILS
Following are the details of dimension/weight of tanks to be fabricated and erected by FAUZ ENGINEERING.
SR
CAPACITYUOM
MATERIAL Diameter/M Height/M Weight/KG Tag NoWeight
/Ton1 900 M3 A-283C S235 JR 12.00 10.00 35,000 T-200 352 600 M3 A-283C S235 JR 9.89 8.00 25,000 T-300 253 200 M3 A-283C S235 JR 7.00 6.00 15,000 T-6071 154 100 M3 A-283C S235 JR 5.00 6.00 15,000 - 155 30 M3 A-516 GR-70 3.30 4.00 4,500 T-6072 4.56 20 M3 A-516 GR-70 1.80 5.50 5,483 T-701 5.5
DESCRIPTION
Water Storage TankTreated Water Tank
Diesel TankCondensate TankDiesel Day Tank
Air Receival Vessel
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 3
![Page 4: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/4.jpg)
PROJECT EXECUTION MANUAL
PROJECT LOCATIONAL LAYOUT
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 4
![Page 5: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/5.jpg)
PROJECT EXECUTION MANUAL
MANPOWER REQUIRED TO EXECUTE THE JOB
Following is the manpower required to execute the job
Supervisor 1 Nos Rigging Foreman 1 Nos Fabricators 9 Nos Welders 14 Nos Fitters 18 Nos Scaffolders/Riggers 12 Nos Electrician 1 Nos Electrician Helper 1 Nos Helper 20 Nos
FAUZ PROJECT TEAM
Following Management Team has been deployed on the Project Site.
Project Manager: Khalid Nizami Mechanical Supervisor: Mr Saeed Planning Engineer: Mr Nasir Quality Inspector: Mr Adnan HSE Inspector: Mr Khursheed Store Personel: To be Nominated Administrator: Mr Qaiser
The Project will be supported by supporting departments in Head Office, that includes the following
Head Operations: Mr Mutahir Aziz. Administration/HR: Mr Aijaz Chaudry Stores: Mr Nauman Planning : Mr Muhammad Ammar Finance Dept: Mr Khalid Razzaque
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 5
![Page 6: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/6.jpg)
PROJECT EXECUTION MANUAL
PROJECT RESPONSIBILITY MATRIX
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 6
![Page 7: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/7.jpg)
PROJECT EXECUTION MANUAL
JOB DESCRIPTIONS AND RESPONSIBILITIES OF MANANGEMENT STAFF DEPLOYED AT PROJECT
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 7
![Page 8: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/8.jpg)
PROJECT EXECUTION MANUAL
EFSL`S/FAUZ PROJECT REQUIRMENTS
ADEHERENCE TO SCHEDULE AS PER ATTACHED ANNEXURE A
ADHERENCE TO QHSE POLICY AS PER ATTACHED ANNEXURE B
ADEHERENCE TO LIST OF NON TOLERANT ITEMS ANNEXURE C
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 8
![Page 9: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/9.jpg)
PROJECT EXECUTION MANUAL
ANNEXURE A
LEVEL III SCHEDULE
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 9
![Page 10: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/10.jpg)
PROJECT EXECUTION MANUAL
ANNEXURE B
QHSE POLICY
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 10
![Page 11: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/11.jpg)
PROJECT EXECUTION MANUAL
ANNEXURE C
LIST OF NON-TOLERANT ITEMS
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 11
![Page 12: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/12.jpg)
PROJECT EXECUTION MANUAL
IMPLEMENTATION OF PROJECT PROTOCOLS
Project protocols includes implementation of following documents at site for project execution
Project Manager must ensure that these formats are implemented on site by respective departments
1. Material Indent Form Annexure A12. Document Transmittal Annexure A23. Material Issue Requisition Annexure A34. Quality Inspection plan Annexure A45. Welding Procedure Specifications (WPS) Annexure A56. Radiographic Examination Report Annexure A67. Liquid Penetration Examination Report Annexure A78. Welding Electrode Issuance Annexure A89. Non Conformance Report Annexure A910. Inspection Stickers Annexure A1011. Material Inspection Report Annexure A1112. Calibration Certificates Annexure A1213. Welders Qualification Record Annexure A1314. Dimensional Inspection Report Annexure A1415. Hydro testing Report Annexure A1516. Daily Diary Report Annexure A1617. Weekly Report Annexure A17
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 12
![Page 13: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/13.jpg)
PROJECT EXECUTION MANUAL
PROJECT EXECUTION METHADOLOGY
1. SITE VISIT
1. Make Site Visit and make sure that space provided for TSF is leveled.2. Make sure that the accesses to the site is clear3. Mark the location of temporary site facility as per TSF Layout below.4. Covered Laydown Area is 40 Ft X 40 Ft5. Uncovered Laydown Area 40ft X 40Ft6. Mark the temporary site facility. Area required 200Ft X 150Ft7. Carries out the site activities as per responsibility mentioned in responsibility matrix.
All Execution to be done as per following work packages
2. EXECUTION STRAGEDY
8. Diesel Day Tank/Condensate Tank/Diesel Storage Tank are going to be assembled at ground and will be lifted to foundation once all assembly is completed
9. Water Storage Tank/Treated Water Tank are going to be assembled on foundations.
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 13
![Page 14: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/14.jpg)
PROJECT EXECUTION MANUAL
JOB PACKAGE
WATER STORAGE TANK
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 14
![Page 15: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/15.jpg)
PROJECT EXECUTION MANUAL
DRAWINGS
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 15
![Page 16: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/16.jpg)
PROJECT EXECUTION MANUAL
SCHEDULE
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 16
![Page 17: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/17.jpg)
PROJECT EXECUTION MANUAL
QUALITY INSPECTION PLAN
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 17
![Page 18: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/18.jpg)
PROJECT EXECUTION MANUAL
MANPOWER HISTOGRAM
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 18
![Page 19: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/19.jpg)
PROJECT EXECUTION MANUAL
JOB PACKAGE
TREATED WATER TANK
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 19
![Page 20: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/20.jpg)
PROJECT EXECUTION MANUAL
DRAWINGS
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 20
![Page 21: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/21.jpg)
PROJECT EXECUTION MANUAL
SCHEDULE
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 21
![Page 22: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/22.jpg)
PROJECT EXECUTION MANUAL
QUALITY INSPECTION PLAN
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 22
![Page 23: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/23.jpg)
PROJECT EXECUTION MANUAL
MANPOWER HISTOGRAM
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 23
![Page 24: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/24.jpg)
PROJECT EXECUTION MANUAL
JOB PACKAGE
DIESEL STORAGE TANK
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 24
![Page 25: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/25.jpg)
PROJECT EXECUTION MANUAL
DRAWINGS
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 25
![Page 26: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/26.jpg)
PROJECT EXECUTION MANUAL
SCHEDULE
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 26
![Page 27: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/27.jpg)
PROJECT EXECUTION MANUAL
QUALITY INSPECTION PLAN
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 27
![Page 28: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/28.jpg)
PROJECT EXECUTION MANUAL
MANPOWER HISTOGRAM
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 28
![Page 29: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/29.jpg)
PROJECT EXECUTION MANUAL
JOB PACKAGE
CONDENSATE TANK
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 29
![Page 30: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/30.jpg)
PROJECT EXECUTION MANUAL
DRAWINGS
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 30
![Page 31: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/31.jpg)
PROJECT EXECUTION MANUAL
SCHEDULE
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 31
![Page 32: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/32.jpg)
PROJECT EXECUTION MANUAL
QUALITY INSPECTION PLAN
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 32
![Page 33: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/33.jpg)
PROJECT EXECUTION MANUAL
MANPOWER HISTOGRAM
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 33
![Page 34: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/34.jpg)
PROJECT EXECUTION MANUAL
JOB PACKAGE
DIESEL DAY TANK
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 34
![Page 35: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/35.jpg)
PROJECT EXECUTION MANUAL
DRAWINGS
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 35
![Page 36: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/36.jpg)
PROJECT EXECUTION MANUAL
SCHEDULE
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 36
![Page 37: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/37.jpg)
PROJECT EXECUTION MANUAL
QUALITY INSPECTION PLAN
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 37
![Page 38: 00 Master Document](https://reader030.vdocuments.net/reader030/viewer/2022033104/563dbb23550346aa9aaa91b3/html5/thumbnails/38.jpg)
PROJECT EXECUTION MANUAL
MANPOWER HISTOGRAM
| JOB PACAKAGES FOR THE FABRICATION AND ERECTION OF TANKS 38