00 project control tools
DESCRIPTION
planningTRANSCRIPT
TOOLS TO MANAGE SCOPE, TIME AND COST IN AN EPC CONTRACT
Mimoune [email protected]
http://www.plannertuts.com/author/minoune-djouallah /
The Purpose The purpose of this presentation is the
description of the process for Project Controls (covering engineering, procurement and construction) for the execution small size projects
The tools are developed as database systems, with a clear separation between datasets and reports.
Excel was used for simplicity, but for more data integrity it is advisable to use RDMS ( Like MS Access )
The Approach
The approach used in this presentation : There is no real time integration or one system to
manage the different process. instead every process is managed using a
separate tool, the integration is done using well defined interface.
The data generated from different process is integrated in one place to generate Reports, curves, and dashboards.
All the stakeholder must agree before the start of the project on the interfaces and the level of the details and integration between the different process.
The interfaces WBS : Work Breakdown structure. CBS : Cost Breakdown structure. AREA : a geographic division of the plant. Workpackage is a group of deliverables. - Construction: Group of items ( building, piperack). - Engineering : Group of drawing. - Procurement : Group of equipment, material etc. Task_Code is a standard activity with efficiency and
physical quantity SCOPE_ID is the business rule primary key It is a concatenation of Area, Task_Code and Workpackage Steps is further detail of Task_code to basic activities
WBS
Level 1 & 2 L1 : the project. L2 : Phase (General, Engineering,
Procurement, Construction, Precommissioning, Commissioning, Start-up, Handover.
Level 3 : General
L4 : Milestones, Management L5 : - Milestones are split between contractual Milestones and Project Milestones. - Management is split between the different Department output for the project.
Level 3 : Engineering
L4 : Disciplines L5 : Work Packages
Level 3 : Procurement
L4 : Subcontract, Long lead items, Disciplines ( auxiliary, Civil ) and Bulk Materials.
L5 : Work Packages ( group of equipment)
Level 3: Construction
L4 : Zone L5 : Area L6 : Work Packages
Level 3: Precom, Commissioning
L4 : systems
Tools SCOPE: provide The whole scope of work(EPC),
including manhours and quantities Schedule: Time Management ( Planning software) PRT : Progress reporting and tracking, excel
tool to managed update progress and reporting Time_Sheet: The manhours spent in Construction. Job Card : detailed Progress report at level 5 DPR : Document Progress Register. PSR : Procurement status report. Cost : Cost Control is managed by Separate tool.
Task_Code
Task_Code Descipline Task Class Unique identifierLevel L1 L2 L3 XXXXXX XX XX XX Example CV1020 CV 10 20
CivilConcrete Works Foundation Civil Works
CV1060 CV 10 60
CivilConcrete Works Pipe support Civil Works
Task_Code : is a unique six digit Code. It is the concatenation of Discipline, Task
Class and a unique identifier The efficiency per Task_Code is a based
on a historical data of the company.
SCOPE
SCOPE is a live List incorporating all new update to the scope of works (EPC).
The integration between the planning software and SCOPE is using SCOPE_ID.
When there is a significant change in Scope of Work, the Planning software is update from SCOPE
SCOPE Flow Chart
SCOPE_ID
SCOPE ( Budget manhours, Quantities, weightage to the client as by the contract
revenue)
Construction ITEM List
Document Progress Register
Procurement Status Report
SCOPE_IDSCOPE_ID
Construction
Productivity database
Master Schedule Level 4
SCOPE_ID
Contract Value
PRT The data in the PRT is mapped at the
activity level in The Planning software, basically it is the same schedule but handled in a separate spreadsheet.
It is easier to record period performance in excel then in a planning software.
Anyone with basic Excel skills, can update the progress and produce reports without the need to operate a Planning software.
PRT ( Progress Reporting and Tracking) Flow Chart
PRT (Progress Reporting and Tracking)Weekly
Planning software (Weekly, Or Monthly)
Progress report
S Curve
Invoice
SCOPE_ID
Time sheet
ProductivityInternal Report
Cost
Dates by CBS
WBS
Job Card
Procurement register
Engineering Register
Planning software Planning software is used only to manage time, by using the
CPM calculation. In the initial baseline, load the physical quantities to level your
production output. A hammock can be used to split an Activity assigned to
SCOPE_ID The Frequency of updating the schedule, depend if you want to
generate a Forecast curve, Weekly or Monthly. The actual start, actual finish ( the facts) are imported from PRT. There is no magic formula to generate remaining duration, talk
to the guy doing the work, he is the best one to provide this information.
After scheduling, the new forecast dates are exported to PRT, to generate the forecast data.
Any planning tool can be used (MS Project, Primavera, etc). Never Ever input dates directly in Excel !!!!!
Time Sheet
For the sake of simplification the spent hours in the site will be recorded only by subcontractor, but in order to have a more accurate Productivity analysis, the hours should be at least recorded at the Subcontractor/ discipline level.
The data is recorded in a daily basis, the productivity factor in a weekly basis.
The time sheet records the roles by direct and indirect.
Cost
Cost control is a separate process. The cost breakdown structure is implemented using
the activity codes in the planning software. The spread of cost by cost account is done using the
dates from the schedule. PRT generate progress report by CBS, it should be
considered as an approximation, as progress based on cost weight and revenue weight are little bit different.
It is important to avoid the use the “best guess method” in distributing cost data.
The more CBS is detailed the more the distribution is accurate.
The Weight Factor
Engineering and construction the budget is in manhours.
Procurement the budget is the cost. The revenue Factor Revenue = Budget X Factor The overall Progress (EPC) is based on
the contract Value.
Reporting Format
The Primary Progress reports for the client are based on the WBS.
For different audience, there is a different reports.
1. By Contractor.2. By discipline.3. By Work Package4. By systems.
Effective reporting
Separate datasets from the reports. Never Hard Code a report Understand your Primary key. Use codes, standardize your codifications. Always prepare and generate data as
database. Pivot table in Excel is very powerful reporting
utility. Automatize your workflow, manual data entry
is a waste of time. Use both WBS and activity codes for
maximum flexibility in reporting.
Change Management Two Approaches1- Keep two revision of PRT. Stable Revision issued to the client, the
budget is frozen. An internal live revision incorporating the
latest changes from SCOPE.2- update the current schedule with the latest data from SCOPE ( without adding weightage) The period performance ( % complete) does
not change, as it is calculated in the JOB CARD using always the latest update from Construction ITEM LIST
PS : I added a new Excel file Project
dashboard, it is much easier to use, and all the calculation are automated