01-blue star energy meter user manual

Upload: winsajeewa

Post on 03-Jun-2018

576 views

Category:

Documents


69 download

TRANSCRIPT

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    1/24

    MICROSTAR

    Meter Reading & Programming Software

    Meterview

    User Manual

    Nanjing Bluestar Electr ical Meter Research Institute

    Microstar Electric Company Limited

    10 Dajiang Road Nanjing 210039, China

    Tel: 86-25-86504148 Fax: 86-25-86601945

    www.bluestarmeters.com

    [email protected]

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    2/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 2/24

    Table of contents1 Overview ....................................................................................................................................3

    2 Meterview Startup and main user interface .................................................................4

    2.1 Meterview start up .....................................................................................................4

    2.1 Meterview Main user interface ..............................................................................4

    3 Read data from energy meter ............................................................................................6

    3.1 Steps of reading data from energy meter..........................................................6

    3.1.1 Step 1 Select meter type ..............................................................................6

    NB on meter types: ....................................................................................................6

    3.1.1.1 MODBUS Meter ..................................................................................................6

    3.1.1.2 DLMS Meter........................................................................................................6

    3.1.2 Step 2 Select communication mode .........................................................7

    3.1.3 Step 3 Select Meter reading node ..........................................................8

    3.1.4 Step 4 Start to read meter parameters and data ................................8

    3.2 Meter reading result ..................................................................................................9

    3.2.1Correct result .................................................................................................93.2.2Meter reading error message.................................................................103.2.2.1 No meter reading node selected.......................................................10

    3.2.2.1 Communication error ............................................................................10

    4 Program energy meter parameters ...............................................................................11

    4.1 Steps of meter programming ...............................................................................11

    4.1.1 Step 1 Select meter type .........................................................................11

    4.1.2 Step 2 Select communication mode .......................................................11

    4.1.3 Step 3 Select Meter programming node ...............................................12

    4.1.4 Step 4 Modify and select programming data items .......................13

    4.1.5 Step 5 Set meter into programming status .........................................13

    4.1.6 Step 6 Start Programming ......................................................................14

    4.2 Programming result .................................................................................................14

    4.2.1Correct Programming ...............................................................................144.2.2Programming error messages ...............................................................15

    5 Export energy meter data .................................................................................................17

    5.1 Steps to export data to Excel ...............................................................................17

    5.1.1 Step 1 Select meter reading node or meter programming node .175.1.2 Step 2 Start export .......................................................................................18

    5.2 Copy data to clipboard ............................................................................................20

    6. Meterview User Management.........................................................................................21

    6.1 User Group Management .......................................................................................21

    6.1.1 Add new user group .....................................................................................21

    6.1.2 Delete user group..........................................................................................21

    6.1.3View password ............................................................................................216.1.4 Save....................................................................................................................21

    6.2 User management ....................................................................................................23

    7. Technical support and bug report .................................................................................24

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    3/24

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    4/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 4/24

    2 Meterview Startup and main user interface

    2.1 Meterview start up

    When Meterview starts, it will show the following log in dialog, only after

    correct user name and password input can user log in and use Meterview.

    When Meterview starts, in the login dialog it will list all existing users.

    NOTE: Meterview supports empty password, i.e. to set no password, so just

    click OK or push enter key will login;

    2.1 Meterview Main user interface

    1. Application name

    2. Main menu

    3. Toolbar buttons

    4. Root node of Meter Reading5. Meter reading nodes

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    5/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 5/24

    6. Root node of Meter Programming

    7. Meter programming nodes

    8. Status bar including the log in user name

    9. Meter reading or programming data area

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    6/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 6/24

    3 Read data from energy meter

    3.1 Steps of reading data from energy meter

    3.1.1 Step 1 Select meter type

    Select the meter connected to your computer from the Select Meter Type

    combo box.

    Meterview will record the selected meter type, and use the same meter type for

    next time

    NB on meter types:

    3.1.1.1 MODBUS Meter

    If MODBUS type meter is selected, then Meterview will force to open a

    MODBUS registers definition file *.cfg, which lists all the registers information,

    including data type, name, and ID etc. After open, user can choose MODBUS

    slave (can be more than 1 slave) and data IDs to read from MODBUS meters.

    3.1.1.2 DLMS Meter

    If DLMS meter type is selected, then Meterview will try to open the DLMS tree

    file, by default is LN.LN, in the same folder of Meterview installation folder, or

    the one has been opened last time; for the first time running of Meterview

    (there was no DLMS/COSEM tree file opened before), it is recommended to

    open DLMS tree file installed with the software. To do this, go to menu: File \

    Open COSEM tree file, then a open file dialog will pop up for user to select the

    tree file *.LN. Then go to Meterview installation folder to open this file.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    7/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 7/24

    If there was no tree file opened before reading DLSM meter, then Meterview

    will read this tree from meter, or user can click button Read COSEMto do this

    too, and this will take a lot of time. If one tree file is opened before reading it

    can save time by reading data directly.

    If there was no tree file opened, Meterview display empty interface; if there isCOSEM tree file opened, it will display the tree data as following picture:

    3.1.2 Step 2 Select communication mode

    Select the meter communication port, serial port number or

    Ethernet (TCP/IP).

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    8/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 8/24

    3.1.3 Step 3 Select Meter reading node

    Check any nodes of meter reading that you want to read data

    If root node of meter reading is checked, then all meter reading nodes will be

    checked.

    3.1.4 Step 4 Start to read meter parameters and data

    Click Read button on tool bar, or select menu Read\Start meter reading,

    Meterview will start to read data from energy meter and display on theinterface.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    9/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 9/24

    3.2 Meter reading result

    3.2.1Correct resultIf all settings are correct and meter is properly connected with computer

    communication port, Meterview will start to read meter data, and display on

    screen; the node being read will be shown by bold font, and the data grid will

    display data in blue font.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    10/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 10/24

    3.2.2Meter reading error message

    3.2.2.1 No meter reading node selected

    If there is no meter reading node is selected, then Meterview will display the

    following message box to prompt user to select meter reading nodes.

    3.2.2.1 Communication error

    If communication can not be established with meter, Meterview will show the

    following message box:

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    11/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 11/24

    4 Program energy meter parameters

    This function is to configure energy meter parameters and download into

    meters.

    4.1 Steps of meter programming

    4.1.1 Step 1 Select meter type

    Select the meter connected to your computer from the Select Meter Typecombo box.

    Meterview will record the selected meter type, and use the same meter type for

    next time

    4.1.2 Step 2 Select communication mode

    Select the meter communication serial port number;

    Note: Ethernet port can not be used to program meter.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    12/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 12/24

    4.1.3 Step 3 Select Meter programming node

    Select the programming category node by checking the box in front

    of it. If root node is checked, then all programming nodes are

    selected.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    13/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 13/24

    4.1.4 Step 4 Modify and select programming data

    items

    As shown in above picture, each programmable data item has a check box, soeach data item can be selected independently to program or not.

    If you want to modify one data item in meter, then you must check the box of

    this parameter.

    Click the root node of meter programming to view all the data items selected to

    be programmed and its values, as shows in following:

    4.1.5 Step 5 Set meter into programming status

    Push meter reset key (red one) and hold for about 8 seconds until LCD displays

    Prg, now meter it ready to be programmed by computer.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    14/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 14/24

    4.1.6 Step 6 Start Programming

    You can click tool bar button Program, or you can click menu Program\Start

    Program to start downloading parameters into meter.

    4.2 Programming result

    4.2.1Correct ProgrammingIf all settings are correct and meter is correctly connected to computer, then

    Meterview will start to set parameters into meter and display the progress on

    screen. The node being programmed will shown highlighted in blue font.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    15/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 15/24

    4.2.2Programming error messages

    4.2.2.1 No Programming node selected

    If there is no meter programming node selected, Meterview will show the

    following message box to ask user to select at least one meter programming

    node.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    16/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 16/24

    4.2.2.1 Communication error

    If communication can not be established with meter, Meterview will show the

    following message box:

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    17/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 17/24

    5 Export energy meter data

    Meterview export meter reading or programming data to Excel file for graphing

    or printing; or it can copy data to clipboard.

    5.1 Steps to export data to Excel

    5.1.1 Step 1 Select meter reading node or meter

    programming node

    Check the box in front of meter reading nodes or programming ROOT node,

    Meterview will export the data of selected meter reading data or all

    programming data.

    If meter reading root node is checked, it will select all meter reading nodes.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    18/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 18/24

    5.1.2 Step 2 Start export

    Click Export button on tool bar

    or right click mouse and choose menu Export.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    19/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 19/24

    Meterview will start to export to designated Excel file and display the following

    dialog after finish:

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    20/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 20/24

    5.2 Copy data to clipboard

    For fast data copy, Meterview also supports to copy data to clipboard. In any

    meter reading data, select any number of cells, and right click mouse, selectmenu Copy to Clipboard

    This will copy all data to clipboard.

    Or select any cells of data as following picture, and push key Ctrl+Cto copy the

    selected data to clipboard.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    21/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 21/24

    6. Meterview User Management

    To ensure system security, only super user is allowed to do user management

    work.

    Meterview user management includes the following 2 parts:

    6.1 User Group Management

    User group defines the properties of user groups to which the users belong,

    including group name, group password level, and the password levels required

    for all operations. Only after user group has been created then can a new user

    be added to this group. User management function includes the following

    (buttons on the toolbar):

    6.1.1 Add new user group

    After a user group has been added, all the properties can be modified and

    saved again.

    6.1.2 Delete user group

    Only after all the users in this group have been deleted then the group can be

    deleted. Because super user can not be deleted, therefore the group to which

    super user belong can not be deleted.6.1.3View passwordMeterview displays password in plain text shortly (about 10 seconds)

    6.1.4 Save

    To save user group information on computer.

    Meterview user management interface is as follows:

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    22/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 22/24

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    23/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28

    Page 23/24

    6.2 User management

    Meterview user management interface is as follows:

    NOTE: The first user (No. 1) is super user, its user role and access rights can not be edited,

    and it can not be deleted. By default super user can execute all operations; its other

    properties like full name can be edited like other users.

  • 8/12/2019 01-Blue Star Energy Meter User Manual

    24/24

    MICORSTAR Meterview User Manual Rev 1.6.18 2011.11.28