TRANSCRIPT

Page 1: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 1

CITY OF CAMBRIDGE

TOBIN MONTESSORI AND VASSAL LANE UPPER SCHOOLS PROJECT01/16/2020

COMMUNITY MEETING

Page 2: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 2

6:30 - 7:00 pm Presentation• Initial Feedback• Educational Program• Process• Traffic & Parking• Design Revisions• Open Space Thoughts

7:00 - 8:30 pm Discussion

AGENDA16 JANUARY 2020

Page 3: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 3

0% 10% 20% 30% 40%

DesignBuilding Program

ProcessTraffic and Parking

Play Space TypesBuilding SizeOpen SpaceOther Issues

Teacher Workshop Community435 WRITTEN COMMENTS*: WHAT WAS IMPORTANT% OF FEEDBACK

*AS OF 01/15/20MANY COMMENTS ADDRESS MORE THAN ONE ISSUE

106 comments

41 comments

95 comments

154 comments

116 comments

126 comments

50 comments

127 comments

Page 4: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 4

WHO WE ARE

Page 5: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 5

●Age 3 to grade 5 Tobin Montessori School.

●Grade 6 to 8 Vassal Lane Upper School

●Both schools have separate principals and staff.

● In Cambridge, upper schools correspond to typical middle school grades in other districts.

●Both schools draw students from throughout Cambridge. Like all Cambridge Public Schools, they are not neighborhood schools.

ONE BUILDING, TWO SCHOOLSWHO WE ARE

Page 6: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 6

● In addition to its general education classrooms, the Vassal Lane Upper School houses the District's Sheltered English Immersion (SEI) program for grades 6-8. Students in SEI are students whose first language is not English.

● The Upper School also houses students in substantially sub-separate special education classrooms.

● The Tobin currently has one special start classroom for students age 3-4 who have been identified as requiring Special Education services due to a disability.

SPECIAL PROGRAMSWHO WE ARE

Page 7: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 7

● The Tobin houses a JK/K classroom for students with Autism Spectrum Disorder (ASD), that needs to grow as children age up to higher grades.

● The King Open, Fletcher Maynard and Cambridge Street Upper Schools also house ASD programs.

●Several other schools house special start classrooms as well

WHO WE ARESPECIAL PROGRAMS WITHIN THE CURRENT BUILDING

Page 8: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 8

UPPER SCHOOL NETWORKSWHO WE ARE

VASSAL LANE- Graham & Parks School- Haggerty School- Tobin Montessori School

PUTNAM AVE (opened 2016)- Kennedy Longfellow School- King School- Morse School

RINDGE AVE- Baldwin School School- Peabody School

CAMBRIDGE STREET (opened 2019)- King Open School- Cambridgeport School- Fletcher Maynard Academy

AMIGOS SCHOOL- The Amigos School is a two way Spanish Immersion K-8 School.

Page 9: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 9

153,000

117,000128,171

175,000

273,000294,000

0

50,000

100,000

150,000

200,000

250,000

300,000

350,000

Gro

ss S

quar

e Fe

et

Original Building New Building

SCHOOL SIZE

MLK/Putnam Ave

King Open/Cambridge Street

New Tobin/ Vassal Lane

Page 10: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 10

PROGRAM

Page 11: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 11

PROJECT GOALS

1. Maintain Tobin Montessori School in current location

2. Upper School to meet increased enrollment needs

3. Meet ¼ of additional city-wide preschool need

4. Equitable assignment of resources across city

Page 12: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 12

DISTRICT ENROLLMENTOVER TIME

2964

1114

4078

3310

1233

4543

4087

1591

5678

0

1000

2000

3000

4000

5000

6000

Num

ber o

f Stu

dent

s

2012 2019 2030 2012 2019 2030 2012 2019 2030

+23%

+12%

K-5 6-8 TOTAL

+25%

+11%

+29%+11%

Page 13: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 13

3144

63

42

35

28

45

35

49 29

45

0

20

40

60

80

100

120

140

Num

ber o

f Stu

dent

s

Morse

Dr. MLK Jr.

Kennedy-Longfellow

King Open

Fletcher Maynard

Cambridge-port

Tobin

Haggerty

Graham and Parks

Baldwin

Peabody

O.L.A. PROGRAMS INCLUDED

S.E.I. PROGRAMS INCLUDED

108

120

5TH GRADE ENROLLMENTAS OF DECEMBER 13, 2019

Putnam Ave Cambridge Street Vassal Lane Rindge Ave

6TH GRADE CAPACITY

128

90

Page 14: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 14

20

7540 40

160

400

495

376386

300

450

0

100

200

300

400

500

600

Num

ber o

f Stu

dent

s

Special Start Preschool Lower School Upper School

SCHOOL CAPACITY

MLK/Putnam Ave

King Open/Cambridge Street

New Tobin/ Vassal Lane

Page 15: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 15

153,000

117,000128,171

175,000

273,000294,000

0

50,000

100,000

150,000

200,000

250,000

300,000

350,000

Gro

ss S

quar

e Fe

et

Original Building New Building

SCHOOL AREA

MLK/Putnam Ave

King Open/Cambridge Street

New Tobin/ Vassal Lane

Page 16: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 16

160 160312

322 336

283

355450

23

115

139

618

952

1085

0

200

400

600

800

1000

1200

2020 2024 2030

Preschool Tobin Vassal Special Programs

Includes S.E.I. & O.S.S. Students

STUDENT ENROLLMENTPROJECTIONS

Page 17: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 17

39 39

92

92 92

70

74 7450

79 79212

284 284

0

50

100

150

200

250

300

2020 2024 2030

Preschool Tobin Vassal Shared

ADULT POPULATIONPROJECTIONS

Page 18: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 18

EARLY CHILDHOOD EDUCATION

● The City has committed to universal pre-K for 4 year olds

●4 year olds likely served through combination of schools, City programs and community based programs.

●Existing programs can serve about 700 of the 1000 4-year olds

Page 19: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 19

4-YEAR OLDS IN CAMBRIDGE

70% 8% 22%

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Percent of Students

Future Demand

Existing Facilities

Other Locations

New Preschool

NEW PRESCHOOL MEETS 26% OF FUTURE DEMAND

Page 20: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 20

EARLY CHILDHOOD EDUCATIONPRESCHOOL DISTRIBUTION

● More programs serving 3 and 4 year olds are available on eastern side of city

● Human Services has 5 programs on the eastern side of city and just two, at Haggerty and Peabody in the north or west.

● Large population of young children on west and north and fewer programs to serve them

Page 21: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 21

PROCESS

Page 22: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 22

DESIGN PROCESS

Feasibility Study

•Establish Program

•Establish Building Organization & Form

Schematic Design

•Begin Building & Site Design

•Choose Structure & Mechanical Systems

Design Development

•Refine Design•Choose Products•Begin Details

Construction Documents

•Document Design•Create Construction

Details

6 MONTHS 6 MONTHS 10 MONTHS10 MONTHS*

* Schedule extended to allow for additional community input

Page 23: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 23

DESIGN PROCESS

We are here

* Schedule extended to allow for additional community input

10 MONTHS*

Feasibility Study Schematic Design

Design Development

Construction Documents

Proposed Community Meetings

Special Meetings as needed

Page 24: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 24

●What it is●Selection of building location

●Selection of building scale

●General configuration

●What it is Not●Actual building design

●Final choice of site elements

●Final choice of traffic and parking solution

PREFERRED OPTIONPROCESS

Page 25: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 25

STRATEGIES BASED ON COMMUNITY INPUTPROCESS

Develop Circulation

Options

Reduce Paved Area with Drop-off &

Parking Under Building

Program Open Areas

for Age-appropriate

Play

Make Building Taller to Increase

Open Space

Program Open Areas

for Community

Use

Page 26: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 26

TRAFFIC & PARKING

Page 27: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 27

SITE CIRCULATION - BUSES

OPTION A

Enter on ConcordShared use lane on east side of siteExit on Vassal

OPTION B

Enter and exit on ConcordBus loop at north end of building

(least preferred option)

OPTION C

Enter and exit on VassalBus loop at south end of building

OPTIONS

NORTH

Page 28: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 28

SITE CIRCULATION – CARS

OPTION A

Cars off Vassal LaneEnter AND exit at southwest corner Circulation below building

OPTION B

Cars off Vassal LaneEnter at southwest cornerCirculation below buildingExit at southeast corner

OPTIONS

NORTH

Pros for Underground Parking• More green space• Covered drop-off

Page 29: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 29

Cons for Underground Parking• High water table + flood zone• More contaminated fill to

remove• High cost premium• May not curb neighborhood

parking• Increase in dedicated space for

vertical building entrance

SITE CIRCULATION – UNDERGROUND PARKING

2070 100-YEAR STORM + SEA LEVEL RISE EXTENT OF CONTAMINATED FILL

OPTIONS

NORTH

Page 30: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 30

SITE CIRCULATION – COMMUNITY PATH

OPTION A

Enter near Fern Street at northTravel along west sideEnter near Lakeview at south

OPTION B

Enter near Fern or Corporal Burns at northTravel along east sideEnter near Standish at south

OPTIONS

NORTH

Page 31: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 31

SITE CIRCULATION – SERVICE

OPTION A

Access from Vassal LaneEnter and exit in Southwest corner

OPTION B

Access from ConcordEnter and exit across from Fern St

OPTIONS

NORTH

Page 32: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 32

DESIGN REVISIONS

Page 33: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 33

DESIGNS IN NOVEMBER

RENOVATION / ADDITION• Re-uses existing building• Buses on Vassal Lane• Cars on Concord Ave• Service and parking at site interior• Playing fields on east side

WINGS• All new building• On-site drive aisle for buses and cars• Service and parking at site interior• Playing fields on south side

PAVILIONS• All new building• On-site drive aisle for buses and cars• Service and parking at site interior• Playing fields on west side

Page 34: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 34

OPTION 1A: REPLACEMENT V1• New building instead of Addition/Renovation• T shape

OPTION 3: PAVILIONS V2• Eliminated interior courtyards• Reduced building footprint• Increase in open area

INTERIM DESIGN REVISIONS

Page 35: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 35

OPTION 1A: REPLACEMENT V2

• More compact shape

• Playing fields on north side

• Community path on both sides

• Cars enter and exit on Vassal in SW corner of site

• Bus loop on Vassal

• Service entry on VassalTOBIN

NEW BUILDING INSTEAD OF ADDITION/RENOVATION

NORTH

SHARED

Page 36: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

REPLACEMENTVIEW FROM SOUTHEAST CORNER

TOBIN

VASSAL

NOV. 2019

SHARED

Page 37: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 37

OPTION 2: WINGS V2BUILDING ORIENTED AROUND A COURTYARD

• No significant form changes

• Playing fields on south side

• Community path on both sides

• Cars enter and exit on Vassal in SW corner of site

• Bus loop on Concord (other options under consideration)

• Service entry on VassalNORTH

SHARED

Page 38: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

WINGSVIEW FROM SOUTHEAST CORNER

TOBIN

VASSAL

NOV. 2019

SHAREDSHARED

Page 39: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 39

OPTION 3: PAVILIONS V3SCHOOLS CONNECTED BY COMMON SPACE

• Simplified building form

• Playing fields on west side

• Community path on both sides

• Cars enter and exit on Vassal near center of site

• Bus lane from Vassal to Concord

• Service entry on ConcordNORTH

Page 40: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PAVILIONSVIEW FROM SOUTHEAST CORNER

TOBIN

VASSAL

NOV. 2019

SHARED

Page 41: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 41

STACKING DIAGRAMSDESIGN REVISIONS

REPLACEMENT WINGS PAVILIONS

NOTE: Mechanical penthouses and rooftop terraces not shown

Page 42: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 42

SETBACK FROM PROPERTY LINE

RENOVATION / ADDITION

Note: previous presentation incorrectly showed existing setback on Vassal Lane as 90’

WINGS PAVILIONS

NOVEMBER DESIGNS

NORTH

Page 43: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 43

SETBACK FROM PROPERTY LINE

REPLACEMENT

WAS:115’ from Vassal (+22’)35’ from Alpine (-10’)150’ from Concord (+233’)

WINGS

WAS:250’ from Vassal (+24’)55’ from Alpine (-1’)140’ from Concord (-27’)

PAVILIONS

WAS:90’ from Vassal (+82’)85’ from Alpine (-24’)150’ from Concord (-33’)

DESIGN REVISIONS

NORTH

Page 44: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 44

SITE CIRCULATION

COMBINATION 1

Shown on Replacement

Also works with Pavilions

COMBINATION 2

Shown on Wings

Also works with Replacement

COMBINATION 3

Shown on Pavilions

Also works with Wings

POSSIBLE COMBINATIONS

NORTH

Page 45: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 45

OPEN AREA

REPLACEMENT: 6.3 ACRES+ 0.4 ACRES GREEN ROOF

Building: 2.2 acresRoads: 0.6 acres

WINGS: 6 ACRES+ 0.4 ACRES GREEN ROOF

Building: 2.5 acresRoads: 0.6 acres

PAVILIONS: 5.8 ACRES+ 0.5 ACRES MULTI-USE LANE+ 0.8 ACRES GREEN ROOF

Building: 2.5 acresRoads: 0.3 acres

DESIGN REVISIONS

NORTH

Page 46: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 46

TOTAL FOOTPRINT SIZEDESIGN REVISIONS

Building Footprint November (square feet) Current (square feet) Change (square feet)

Existing 62,162

Renovation + Addition 117,000 - 20,500

Replacement 96,500Wings 106,500 108,000 + 1,500

Pavilions 109,000 106,500 - 2,500

Open Area November (acres) Current (acres) Change (acres)

Existing 6.6

Renovation + Addition 5.4+ 0.8

Replacement 6.3Wings 5.4 6 + 0.4

Pavilions 5.2 5.8 + 0.6

Page 47: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 47

OPEN SPACE IDEAS

REPLACEMENT WINGS PAVILIONS

Page 48: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 48

PLAY SPACE EXAMPLES – PRESCHOOL & ELEMENTARYOPEN SPACE

Page 49: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 49

PLAY SPACE EXAMPLES – UPPER SCHOOLOPEN SPACE

Page 50: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 50

LEARNING GARDEN EXAMPLESOPEN SPACE

Page 51: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 51

COMMUNITY PATH EXAMPLESOPEN SPACE

Page 52: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 52

OPTION 1A: REPLACEMENT• Community use on all

sides

• Play spaces segregated by age

• Contiguous, separated sports fields

• Community path on east and west

• Bioswale at Southeast corner

• Most play area near fields

• Gardening and outdoor learningNORTH

Page 53: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 53

OPTION 2: WINGS

• Community use on all sides

• Large central play area for all age groups

• Contiguous, separated sports fields

• Community path on east and west

• Bioswale near Vassal

• Some play area near fields

• Gardening and outdoor learning NORTH

Page 54: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 54

• Community use on all sides

• Smaller play areas in “pocket parks” segregated by age

• Shared-use lane on west

• Contiguous, separated sports fields

• Community path on east and west

• Bioswale near Vassal

• More play area near fields

• Gardening and outdoor learning

OPTION 3: PAVILIONS

NORTH

Page 55: 01/16/2020 COMMUNITY MEETING - Cambridge · 1/16/2020  · perkins eastman tobin montessori/vassal lane schools project 1 city of cambridge. tobin montessori and vassal lane upper

PERKINS EASTMAN TOBIN MONTESSORI/VASSAL LANE SCHOOLS PROJECT 55

HUMAN BY DESIGN- PASSIONATE ABOUT WHAT WE DO…HERE’S WHY