01_power transformer saudi arbia

Upload: murugan

Post on 07-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/19/2019 01_power Transformer Saudi Arbia

    1/37

    1

    A STUDY TO DETERMINE THE ROOT 

    CAUSES OF REPEATED FAILURES ON MV 

    CABLE 

    TERMINATIONS 

    AT 

    NATIONAL 

    GRID SA SYSTEM12 May 2013

    Jeddah ‐ Saudi Arabia

    Hussain Mueidh Al Yami

    Lines Maintenance Department Manager 

  • 8/19/2019 01_power Transformer Saudi Arbia

    2/37

    The 

    Main 

    Goal 

    of  

    the 

    Electric 

    Utilities 

    isThe world Illumination! 

    But there is an aggressive Enemy

    Which is 

    Electrical 

    Equipment 

    Failures! 

  • 8/19/2019 01_power Transformer Saudi Arbia

    3/37

    Table 

    of  

    Contents

    Introduction

    Data Collection 

    Brain Storming

    Data Analysis 

    Samples Investigations and Site Visit

    Conclusion and Recommendations

    Substations with High Failure Rate

  • 8/19/2019 01_power Transformer Saudi Arbia

    4/37

    4

    •   National Grid

     SA

     has

     more

     than

     two

     thousand

     transformers

     (2012

     transformers

     up

     to

     mid of  March 2013) in its system.

    •   MV Cross‐linked Polyethylene (XLPE) insulated cables cables are used to connect 

    these step down transformers to MV switchgears.

    •   National Grid SA network were interrupted by several MV cable failures.

    •   MV cable terminations were the source of  these cable failures.

    •   In addition

     to

     the

     high

     cost

     of 

     repairing

     these

     failures,

     they

     cause

     a negative

     effect

     on

     the availability and reliability of  National Grid SA network.

    •   It was decided to study this problem to find out the root cause of  these failures and 

    recommend the solution.

    Introduction

  • 8/19/2019 01_power Transformer Saudi Arbia

    5/37

    5

    Before starting the study, the problem size must be identified

    by collecting the statistical data of the MV cable termination

    failures from all Operating Areas. The failures numbers were

    collected from the following areas:

    Data 

    Collection 

    •   Central Operating Area (COA)

    •   Eastern Operating Area (EOA)

    •   Western Operating

     Area

     (WOA)

    •   Southern Operating Area (SOA)

  • 8/19/2019 01_power Transformer Saudi Arbia

    6/37

    6

    Data 

    Collection 

    The collected data were covering the last 5 years.In terms of the number of failures, the following chart shows a comparison

    between these different working areas.

    The great deal of termination failures were concentrated in COA.

    As a result, the study focused on that Area.

  • 8/19/2019 01_power Transformer Saudi Arbia

    7/37

    7

    Data 

    Collection 

    The COA consists of three sub‐areas, namely Riyadh, Qassim and Hail.

    The following chart shows a comparison between these three sub‐areas.

    All Sub Areas have significant failures . As a result, all sub areas will be studied .

  • 8/19/2019 01_power Transformer Saudi Arbia

    8/37

    8

    Brain 

    Storming

    A brain storming for the main possible root causes that may affect the service

    lifetime of the MV cable terminations and may lead to the MV cable termination

    failure was done. The possible causes were as follow:

    •   Bad workmanship.

    •   Overheat ( overloaded )

    •   Overvoltage.

    •   Termination Design problems..

    •   Manufacturer Installation Instruction problem.

    •  Wrong selection for the termination size.•   Wrong Grounding and /or high grounding resistance.

    •   Cable lug design.

    •   Improper design of transformer's LV cable box.

  • 8/19/2019 01_power Transformer Saudi Arbia

    9/37

    9

    Brain 

    Storming

    Since these terminations were manufactured by the same manufacturer

    in all areas and the failures were concentrated in COA only, so all causes

    related to termination materials and design were eliminated. The study

    focused on the following root causes:

    •   Bad workmanship.

    •   Overheat ( overloaded )

    •   Overvoltage.

    •   Manufacturer Installation Instruction problem.•   Improper design of transformer's LV cable box.

  • 8/19/2019 01_power Transformer Saudi Arbia

    10/37

    10

    Data 

    Analysis 

    •  The data were collected for both 33 kV and 13.8 kV.  13.8 kV terminationfailures present only   (approx. 6%). The design principle and operational

    conditions are the same, the two voltage levels can be considered together

    neglecting the factor of voltage level.

    •   The concern was taken   about dimensions of transformer LV cable boxeswhich might introduce electrical stress on cable terminations. Drawings of 

    cable boxes were selected randomly   for reviewed and they were found

    complying with the specifications.

    •   The data of  transformers loads and voltage profiles of 33kV & 13.8kV bus

    bars were requested in order to use them in the study. The available data

    was not comprehensive and not sufficient as it was expected to be.

    However, the available data gives some hints about where to look.

  • 8/19/2019 01_power Transformer Saudi Arbia

    11/37

    11

    •   The entire failures in COA for the last five years   ( 112 failures )   were

    concentrated at  39 substations  out of 227 substations (100 % of Faults

    occurred at 17.2% of Sub. ) .

    •   About 68% of these interruptions occurred in 11 substations out of these

    227 substations (68 % of Faults occurred at 4.85 % of Sub. )

    •   These substations with high failure rate were reviewed, case by case.

    Data 

    Analysis 

  • 8/19/2019 01_power Transformer Saudi Arbia

    12/37

    12

    Substations 

    with 

    High 

    Failure 

    Rate

    Riyadh 

    Area•   In Riyadh area, the entire   34 interruptions   in the last five years occurred in 19

    substations out of 162 substations   ( 100 % of Faults at 11.7% of Sub.).

    •   47% of these interruptions occurred in 3 substations out of all ( 47 % of Faults at

    less than 2% of Sub.).

    •   These substations are  8508, 8505 and 8034.

    6 6

    4

    2   2

    1   1   1   1   1 1   1   1   1   1   1   1   1   1

    0

    1

    2

    3

    45

    6

    7

            8       5        0       5

            8       5        0        8

            8        0        3        4

            8        0        2       7

            8        0        3        8

            8        0        2        1

            8        0        1        4

            8        0        2        6

            8        0        9        6

            8        0        1        0

            8       7        0       5

            8        6        0       5

            9        0        1        3

            8        0        1        9

            8        0       7       5

            8        0        3        6

            8        0        4       7

            8        1        2        9

            8        0        3        3

    47 %

    2 %

  • 8/19/2019 01_power Transformer Saudi Arbia

    13/37

    13

    Substation: 

    8508 2

    0   0

    2

    0

    1

    0

    1

    0   0   0   00

    0.5

    1

    1.5

    2

    2.5

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Bar Chart showing the Number of  Failures on a Monthly Basis during 

    the last Five Years

    Substations 

    with 

    High 

    Failure 

    Rate

    Riyadh 

    Area

    5

    0

    1

    0   00

    2

    4

    6

    2008 2009 2010 2011 2012

    0   0   0   0   0

    2

    0   0

    2

    0   0   0   0   0

    1

    0   0   0   0   0   0

    1

    0   00

    0.5

    1

    1.5

    2

    2.5

    66% of  Failures occur in the winter and spring 

    66% of  Failures occur in  (AM)

    Bar Chart showing the Number of  Failures on an Incident Time Basis 

    during the last Five Years

    Bar Chart showing the Number of  Failures on a Yearly Basis during 

    the last Five Years

    •   It was having a very light load ( 2001 to 2007).

    •  Rapid increasing in the infra‐structure development.

    •   The load of the substation was also on the rise.

    •   Late 2010, all terminations were replaced.

    •  As a result, no failures occurred after that.

  • 8/19/2019 01_power Transformer Saudi Arbia

    14/37

    14

    Substation: 8505

    0

    1

    0   0   0   0 0   0   0   0   0   0

    2

    0 0 0

    1   1

    0   0

    1

    0   0   00

    0.5

    1

    1.5

    2

    2.5

    2   2

    1

    0

    1

    0

    0.5

    1

    1.5

    2

    2.5

    2008 2009 2010 2011 2012

    1

    0

    3

    0   0

    1

    0   0   0   0   0

    1

    0

    1

    2

    3

    4

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Substations 

    with 

    High 

    Failure 

    Rate

    Riyadh 

    AreaBar Chart showing the Number of  Failures on a Monthly Basis during 

    the last Five Years

    Bar Chart showing the Number of  Failures on an Incident Time Basis 

    during the last Five Years

    Bar Chart showing the Number of  Failures on a Yearly Basis during 

    the last Five Years

    83.3 % of  Failures occur in the winter

    83% of 

     Failures

     occur

     in

     (PM)

    •  Radial Substation•  All MV cables were replaced at late 2010.

    •  But it is still showing interruptions.

    •  More investigation is needed.

  • 8/19/2019 01_power Transformer Saudi Arbia

    15/37

    15

    Substation: 8034

    0   0   0   0   0   0   0   0   0   0

    3

    1

    0

    1

    2

    3

    4

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Substations 

    with 

    High 

    Failure 

    Rate

    Riyadh Area

    0

    1

    0

    3

    00

    1

    2

    3

    4

    2008 2009 2010 2011 2012

    0   0   0   0   0   0   0   0   0

    2

    0

    1

    0   0 0 0   0   0   0   0

    1

    0   0   00

    0.5

    1

    1.5

    2

    2.5

    Bar Chart showing the Number of  Failures on a Monthly Basis during 

    the last Five Years

    Bar Chart showing the Number of  Failures on an Incident Time Basis 

    during the last Five Years

    Bar Chart showing the Number of  Failures on a Yearly Basis during 

    the last Five Years

    100 % of  Failures occur in the autumn & winter (  just after summer)

    75% of  Failures occur in  (AM)

    •  Was subjected to a fire incident mid of 2006.

    •  MV cables were affected and replaced in 2006.

    •  Heavily loaded in the last three years.•  Out of firm capacity in the last year.

    •  This situation leads to accelerate the failure.

    •  More investigation is needed.

  • 8/19/2019 01_power Transformer Saudi Arbia

    16/37

    16

    Substations 

    with 

    High 

    Failure 

    Rate

    Qassim Area

    •   In Qassim area, the entire 37 interruptions in the last five years occurred in 14

    substations out of 37 substations. (100 % of Faults at 37.8% of Sub. )

    •   57% of these interruptions occurred in 4 substations out of all. (57 % of Faults

    at 11 % of Sub. )

    •   These substations are 8818, 8606, 8811 and 8802.

    8

    54   4

    2   2   2   2   2   21   1 1   1

    0

    2

    4

    68

    10

    57%

    11%

  • 8/19/2019 01_power Transformer Saudi Arbia

    17/37

    17

    Substation: 8818

    0   0   0   0   0

    1

    3

    0

    1

    2

    0

    1

    0

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Substations 

    with 

    High 

    Failure 

    Rate

    1

    0

    1

    3  3

    0

    1

    2

    3

    4

    2008 2009 2010 2011 2012

    0

    1   1

    0   0   0 0   0   0   0   0

    1   1   1 1

    0   0   0   0   0

    1   1

    0   00

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    Qassim Area

    Bar Chart showing the Number of  Failures on a Monthly Basis during 

    the last Five Years

    Bar Chart showing the Number of  Failures on an Incident Time Basis 

    during the last Five Years

    Bar Chart showing the Number of  Failures on a Yearly Basis during 

    the last Five Years

    87.5% of  Failures  occur in the summer & early autumn

    62% 

    of  

    Failures 

    occur 

    in 

    (PM)

    •   Heavily loaded.

    •   The tap changers were operated manually.

    •   From the failed terminations investigation and site visit , there were a clear

    evidences of :

    A. Bad workmanshipB. Overvoltage at the LV side of the transformer

    C. Over heat inside the cable box.

    •   Examine all terminations physically and replace the defective.

    •   Notify the Dispatcher about the sign of overvoltage.

    •   Monitor the situation.

  • 8/19/2019 01_power Transformer Saudi Arbia

    18/37

    18

    Substation: 8606

    0   0   0   0   0

    2

    0

    1

    2

    0   0   00

    0.5

    1

    1.5

    2

    2.5

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Substations 

    with 

    High 

    Failure 

    Rate

    0

    1

    3

    1

    00

    1

    2

    3

    4

    2008 2009 2010 2011 2012

    1

    0   0   0   0

    1

    0   0

    1

    0   0   0   0   0 0

    1

    0   0   0

    1

    0   0   0   00

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    Qassim Area

    Bar Chart showing the Number of  Failures on a Monthly Basis during 

    the last Five Years

    Bar Chart showing the Number of  Failures on An Incident Time Basis 

    during the last Five Years

    Bar Chart showing the Number of  Failures on a Yearly Basis during 

    the last Five Years

    100% of  Failures  occur in the  summer 

    60% of 

     Failures

     occur

     in

     (AM)

    •   All MV cables were replaced at late 2010.

    •   But it is still showing interruptions.

    •   The dimensions of cable boxes at the auxiliary transformers were

    not as per the standards.

    •   The manufacturer was called to study the case.

    •   The cable boxes of the auxiliary transformers were replaced.

    •   No fault occurred after this correction.

  • 8/19/2019 01_power Transformer Saudi Arbia

    19/37

    19

    Substation: 8811

    1

    2

    0   0   0

    1

    0   0   0   0   0   00

    0.5

    1

    1.5

    2

    2.5

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Substations 

    with 

    High 

    Failure 

    Rate

    Qassim Area

    0

    1   1

    2

    00

    1

    2

    3

    2008 2009 2010 2011 2012

    0   0   0   0

    1

    0 0   0

    1   1

    0   0   0   0 0 0   0   0   0

    1

    0   0   0   00

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    Bar Chart showing the Number of  Failures on a Monthly Basis during 

    the last Five Years

    Bar Chart showing the Number of  Failures on an Incident Time Basis 

    during the last Five Years

    Bar Chart showing the Number of  Failures on a Yearly Basis during 

    the last Five Years

    75% of  Failures  occur in the  Winter

    75% of 

     Failures

     occur

     in

     (AM)

    •   Radial Substation

    •   No failed terminations were available for investigation.

    •   More investigation is needed.

  • 8/19/2019 01_power Transformer Saudi Arbia

    20/37

    20

    Substation: 8802

    0

    1

    0   0   0

    2

    0   0   0   0

    1

    00

    0.5

    1

    1.5

    2

    2.5

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Substations 

    with 

    High 

    Failure 

    Rate

    Qassim Area

    0

    2

    0

    1   1

    0

    0.5

    1

    1.5

    2

    2.5

    2008 2009 2010 2011 2012

    0   0   0   0   0   0   0   0   0 0   0

    1

    0

    2

    0 0   0   0   0   0   0   0   0

    1

    0

    0.5

    1

    1.5

    2

    2.5

    Bar Chart showing the Number of  Failures on a Monthly Basis during 

    the last Five Years

    Bar Chart showing the Number of  Failures on an Incident Time Basis 

    during the last Five Years

    Bar Chart showing the Number of  Failures on a Yearly Basis during 

    the last Five Years

    75% of  Failures  occur in the  summer & autumn

    75% of  Failures  occur in  (PM)•  Heavily loaded in the last five years.

    •  Out of firm capacity in the last three years.

    •  No failed terminations were available for investigation.

    •  More investigation is needed.

  • 8/19/2019 01_power Transformer Saudi Arbia

    21/37

    21

    Substations 

    with 

    High 

    Failure 

    Rate

    •   In Hail area, the entire 41 interruptions in the last five years occurred in 6 switching

    substations out of 28 switching substations (100 % of Faults at 21.4% of Sub.).

    •   95 % of these interruptions occurred in 4 substations out of all (95% of Faults at

    14.3 % of Sub. ) .

    •   These substations are 8901, 8914 , 8915 and 8913.

    Hail Area

    18

    11

    7

    31   1

    0

    5

    10

    15

    20

    95%

    14.3%

  • 8/19/2019 01_power Transformer Saudi Arbia

    22/37

    22

    Substation: 8901

    0

    3

    2   2

    1

    3   3

    0

    1

    2

    0

    1

    0

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Substations 

    with 

    High 

    Failure 

    Rate

    Hail Area

    1

    8

    0

    7

    2

    0

    2

    4

    6

    8

    10

    2008 2009 2010 2011 2012

    0

      0

    1

    0

    1   1

    0  0

    1   1   1

    0

    2

    1

    2

    0   0

    1

    2

    0   0

    2

    0

    2

    0

    0.5

    1

    1.5

    2

    2.5

    Bar Chart showing the Number of  Failures on a Monthly Basis during 

    the last Five Years

    Bar Chart showing the Number of  Failures on an Incident Time Basis 

    during the last Five Years

    Bar Chart showing the Number of  Failures on a Yearly Basis during 

    the last Five Years

    66.6% of  Failures  occur in the  summer

    66.6% of 

     Failures

     occur

     in

     (PM)

    •   Radial Substation.

    •   The MV cables were replaced at late 2009.

    •   But it is still showing interruptions

    •   No failed terminations were available for investigation.

    •   More Investigation is needed.

  • 8/19/2019 01_power Transformer Saudi Arbia

    23/37

    23

    Substation: 8913

    0   0

    1

    0

    1   1

    0

    1

    0

    2

    1

    00

    0.5

    1

    1.5

    2

    2.5

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Substations 

    with 

    High 

    Failure 

    Rate

    Hail Area

    2

    3

    0

    2

    00

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    2008 2009 2010 2011 2012

    0

    1

    0   0   0   0

    1

    0   0 0

    1

    0

    1

    0 0 0

    1

    0

    1

    0   0

    1

    0   0

    0

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    Bar Chart showing the Number of  Failures on a Monthly Basis during 

    the last Five Years

    Bar Chart showing the Number of  Failures on an Incident Time Basis 

    during the last Five Years

    Bar Chart showing the Number of  Failures on a Yearly Basis during 

    the last Five Years

    85.7% of  Failures  occur in the  summer

    57% of  Failures  occur in  (PM)

    •   Radial Substation.

    •   The MV cables were replaced at late 2009.•   But it is still showing interruptions.

    •   No failed terminations were available for investigation.

    •   More Investigation is needed.

  • 8/19/2019 01_power Transformer Saudi Arbia

    24/37

    24

    Substation: 8915

    0   0   0

    1

    0

    1   1

    0   0   0   0   00

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Substations 

    with 

    High 

    Failure 

    Rate

    Hail Area

    1

    0   0 0

    2

    0

    0.5

    1

    1.5

    2

    2.5

    2008 2009 2010 2011 2012

    0  0

      0   0   0   0   0   0   0   0   0  0

      0

    1

    0 0   0  0

      0  0

    1

    0  0

    1

    0

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    Bar Chart showing the Number of  Failures on a Monthly Basis during 

    the last Five Years

    Bar Chart showing the Number of  Failures on an Incident Time Basis 

    during the last Five Years

    Bar Chart showing the Number of  Failures on a Yearly Basis during 

    the last Five Years

    66 % of  Failures  occur in the  summer

    100% of 

     Failures

     occur

     in

     (PM)

    •  The cables were newly energized (2012).

    •  Failed terminations were investigated.

    •  There were a clear sign of Bad workmanship.

    •  All cables and cable terminations were replaced.

    •  No fault recorded since the time of replacement.

  • 8/19/2019 01_power Transformer Saudi Arbia

    25/37

    25

    Substation: 8914

    0   0   0

    1

    0

    1   1

    3

    0   0

    4

    1

    0

    1

    2

    3

    4

    5

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

    Substations 

    with 

    High 

    Failure 

    Rate

    Hail Area

    4

    2   2   2

    1

    0

    1

    2

    3

    4

    5

    2008 2009 2010 2011 2012

    0   0   0   0   0

    1

    2

    0   0

    1

    0

    1

    0   0 0 0

    1

    0

    2

    0

    1

    0

    1   1

    0

    0.5

    1

    1.5

    2

    2.5

    Bar Chart showing the Number of  Failures on a Monthly Basis during 

    the last Five Years

    Bar Chart showing the Number of  Failures on an Incident Time Basis 

    during the last Five Years

    Bar Chart showing the Number of  Failures on a Yearly Basis during 

    the last Five Years

    90% of  Failures  occur in the  summer & autumn

    54.5% of  Failures  occur in  (PM)•   The MV cables were replaced in 2008.

    •   But it is still showing interruptions.

    •   No failed terminations were available for investigation.

    •   More Investigation is needed.

  • 8/19/2019 01_power Transformer Saudi Arbia

    26/37

    26

    Samples 

    Investigations 

    and 

    Site 

    Visit

    A site visit was made to Substation 8818 which is one of the substations that has high

    failure concentration, in order to have a close look to the operational environment and

    try to find some clues about possible root causes.

    It was noticed that the tap changers of the transformers were operated manuallywhich affects the accuracy of voltage control at the low voltage side.

  • 8/19/2019 01_power Transformer Saudi Arbia

    27/37

    27

    Samples 

    Investigations 

    and 

    Site 

    Visit

    Flashovers on the cable box wall

    indicates overvoltage that breaks

    the gap between connecting bar and  box's walls.

    The edges of the connecting bar 

    were melted because of arcs.

    Voltage stresses were suspected on the terminations of that substation since there were a clearspark between connection bar and cable box’s wall. This evidence was obtained from some previous

    pictures.

    Substation 8818 

  • 8/19/2019 01_power Transformer Saudi Arbia

    28/37

    28

    Samples 

    Investigations 

    and 

    Site 

    Visit

    Healthy termination removed from Substation 8818 for investigation . It shows non‐

    compliance of installation instructions and effect of overheating or improper

    application of stress control tube

    Brown color due to loose stress control tube (SCT).

    Improper application of SCT or overheating of 

    cables affects termination's mechanical integrity.

    Failure due to bad workmanship. Non

    compliance of the installation instruction

    led to failures

    Substation 8818 

  • 8/19/2019 01_power Transformer Saudi Arbia

    29/37

    29

    Samples 

    Investigations 

    and 

    Site 

    Visit

    Failed termination removed from Substation 8915 in Hail area, shows the use of thewrong tool to cut the semiconducting layer.

    Failure due to bad workmanship.

    The use of wrong tools led to

    failure.

  • 8/19/2019 01_power Transformer Saudi Arbia

    30/37

    30

    Conclusion 

    and 

    Recommendations

    •   It can be inferred that the termination is most likely to fail if it is operated in

    an environment that has one the following characteristics:A. Radial Substation.

    B. Heavily loaded Substation .

    C. Lightly loaded Substation.

    •   Because of lack of data, identifying an exact contribution of each factor on the

    failures was difficult. Thus, informative database must be built starting from 2013.

    •   However, it was obvious that the installation instructions were not followed exactly

    and human errors is the greatest among other factors in all investigated

    terminations.

  • 8/19/2019 01_power Transformer Saudi Arbia

    31/37

    31

    Conclusion 

    and 

    Recommendations

    •   Confirmation that all terminations were brought from the correct source is needed.The Batch No. of each termination must be provided and recorded in the As‐Built

    Drawing.

    •   The installation of each termination must be performed by a Certified Jointer.

    •   The installation of each termination must be supervised by the COMPANY personal.

    •   Each termination must have a name plate.

    •   The name plate should consist (Contract Information, Name of jointer, SECSupervisor Name, Installation Date, Manufacture Date and Enegization Date).

  • 8/19/2019 01_power Transformer Saudi Arbia

    32/37

    32

    Conclusion 

    and 

    Recommendations

    More investigation is needed in the following Substations :

    •   Riyadh Area ( 8505 , 8034 )

    •   Qassim Area ( 8802 , 8811 , 8818 ( Monitor Only after the correction ) )

    •   Hail Area ( 8901 , 8913 , 8914 )

    In term of the following aspects :

    •   Does it subjected to Over loading? Record from Jan 2013 to Dec 2013

    •   Does it subjected to Over voltage? Record from Jan 2013 to Dec 2013

    •   Does the actual cables ampacity within the rated value ?•   Does the terminations import from the main source?

    •   Investigate each single faulty termination and record the result.

    •   Cable and Substation earthing system.

  • 8/19/2019 01_power Transformer Saudi Arbia

    33/37

    33

    Thanks For your Kind Attention

    Q&A 

  • 8/19/2019 01_power Transformer Saudi Arbia

    34/37

    34

    Conclusion 

    and 

    Recommendations

    In order to contain the failures by building an informative database and enhancinginstallation and maintenance procedures, the following recommendations are to be

    followed:

    1. The contractor must provide proof that  all terminations   were brought from the

    correct source. The Batch No. of each termination must be provided and recorded inthe As‐Built Drawing.

    2. The installation of each termination must be performed by a Certified Jointer and

    the contractor must comply with this. The contractor must submit a  name plate for

    each termination. The name plate should consist (Contract Information, Name of  jointer, SEC Supervisor Name, Installation Date, Manufacture Date and Enegization

    Date). This name plate must be provided and recorded in the As‐Built Drawing.

  • 8/19/2019 01_power Transformer Saudi Arbia

    35/37

    35

    Conclusion 

    and 

    Recommendations

    3. The installation of each termination must be supervised by the COMPANY personal.

    The COMPANY supervisor name must be added to the name plate of each termination.

    4. Each sample is an evidence and therefore, samples should be preserved and

    documented in a correct way that keeps the sample integrity as it was, whenremoved.

    5. Accurate data about the incidents, events that happened at the same time and

    weather and operational records are very important in the analysis stage. In

    addition, terminations that are installed under the same contract or by the same

    contractor should be stored together because they are more likely to have thesame failure cause.

  • 8/19/2019 01_power Transformer Saudi Arbia

    36/37

    36

    Conclusion 

    and 

    Recommendations

    6.   Installation instructions should be clear and easy to follow and read. Manufacturers

    shall be called to   conduct short courses about   their products and installation

    instructions. In the case of unclear or missing instruction, feedback should be sent to

    the manufacturer to update their instructions and make them clearer.

    7. After the samples are collected and documented properly, a group of experts shall

    analyze the failure and identify the possible root cause. As a result, an informative

    database will be built and recommendation shall be made to improve the service life of 

    terminations. In case of human errors, the most common human errors should be

    presented to SEC personnel in order to consider them carefully in the new projects andmaintenance work. In addition, feedback should be sent to manufacturer in case of 

    design errors or unclear instructions.

  • 8/19/2019 01_power Transformer Saudi Arbia

    37/37

    37

    Conclusion 

    and 

    Recommendations

    8. All findings should be reported and documented in order to build a strong

    experience about this subject. By building the experience, we will gain many benefits

    such as; training improvement, outages reduction, cost reduction and reduction of the

    need of diagnostics. In addition, we will be able to predict failures and increase the

    network reliability.

    9. A database for the over voltage and the over load on the 33kV & 13.8 KV

    transformers should be available and easy to access in order to have an idea about the

    maximum voltage and maximum load that might affect the termination service life.

    Moreover, all transformers with manual tap changer should be modified to be

    automatic controlled tap changer.