July 2011 Rip RapSection 02274
02274 - 2
5. Flat or needle shapes shall not be used unless the thickness of the piece is
more than one-third the length.
B. Grouted Rubble Rip-rap:
1. Provide portland cement mortar grouted rip-rap in locations as shown on the
Drawings.2. Stone shall meet all applicable requirements listed above for random rip-rap.
3. Consistency of the grout shall be approved by the KCS.
C. Geotextile Fabric:
When specified on the Plans, geotextile fabric shall be furnished and installed onsubgrade prior to placement of rip-rap. Geotextile fabric shall be Mirafi 1100 N or
approved equal 10 oz. non-woven fabric.
PART 3 - EXECUTION
3.1 PLACING
A. Subgrade: The subgrade for rip-rap bedding shall be prepared to the required lines
and grades. When the rip-rap is below normal stream level the subgrade shall bemucked out to the grade required. All loose material shall be removed.
B. Random Rip-rap:
1. The minimum total thickness of the rip-rap layer shall be 1.5 times greater
than the diameter of the maximum size rip-rap stone.
2. The stones shall be placed from the bottom of the embankment upward suchthat the weight of the stone is carried by the underlying material. The larger
stones shall be placed in the lower courses.3. Open joints shall be filled with spalls.
4. Rip-rap may be placed by equipment; however, care shall be taken in placing
to obtain a good gradation of material such that the rip-rap is firm and solid.Surfaces shall be barred to the required alignment and slopes. Large voids
shall be filled by hand placement of stone unless otherwise approved by the
KCS.5. When specified on the Plans, geotextile fabric shall be placed on the subgrade
prior to placement of rip-rap. This fabric shall be installed as described in
Section 02273 of these specifications. During placement of rip-rap onto thefabric, care should be taken to not puncture, tear, or otherwise damage theunderlying fabric.
C. Grouted Rip-rap:
1. Stones shall be placed as described above for random riprap and grouted with
portland cement mortar.
-
8/13/2019 02274 Rip Rap
3/3
July 2011 Rip RapSection 02274
02274 - 3
2. Unless hand mixing is specifically approved by the KCS, grout shall be
machined mixed for not less than 1- minutes.
PART 4 COMPENSATION
4.1 Rip-rap shall be paid for at the unit price per ton complete and accepted in place, and shall
include all labor, materials, equipment, tools, and incidentals necessary for the satisfactorycompletion of the work. Tonnage will be determined based on delivery tickets obtained
from a certified scale.
4.2 No separate payment will be made for grout or geotextile fabric required for installation of
rip-rap. Both items shall be included under the unit price for rip-rap.
END OF SECTION