GENERAL MODE OF PROCUREMENT
Procurement is done through CompetitiveBidding. (Sec. 10 RA 9184; NPM 67-2012)
Exception: Alternative Methods ofProcurement.
2
-
8/17/2019 03 Bidding Procedure for Goods and Infra
3/99
COMPETITIVE BIDDING
WHAT IS COMPETITIVE BIDDING?
It is a method of procurement which is open toparticipation by any interested party and which
consists of the following processes: eligibilityscreening of prospective bidders, evaluation of bids,post-qualification, and award of contract. (Section5(e) of RA 9184 and its IRR)
3
-
8/17/2019 03 Bidding Procedure for Goods and Infra
4/99
COMPETITIVE BIDDING
Garcia vs. Burgos (291 SCRA 546)
“By its nature and characteristics, a competitive publicbidding aims to protect public interest by giving the
public the best possible advantages through opencompetition”
COA vs. RTC-NCRJR (GR NO. 85285, 7/7/89)
“Purpose is to avoid/preclude suspicion of favoritism andanomalies in the execution of public contracts.”
4
-
8/17/2019 03 Bidding Procedure for Goods and Infra
5/99
COMPETITIVE BIDDING
Municipal Order requiring an accreditation processfor Bidders as a condition precedent for theirparticipation in procurement activities of the localgovernment unit runs counter RA 9185 and its IRRwould limit the participation of bidders only to thoseaccredited suppliers, to the exclusion and prejudice ofother bidders in the market, it in fact contravenes thevery basic principles of competitive bidding. (NPM
47-2013)
5
-
8/17/2019 03 Bidding Procedure for Goods and Infra
6/99
STANDARDIZED BIDDING PROCEDURE
FOR GOODS AND INFRA
Pre-ProcurementConf.
Advertisement Pre-BidConference
Opening of1st Env. - Eligibility
Docs & Technical
Proposal
Opening of 2nd Envelope – Financial
Proposal
Submission ofBids
Bid Evaluation
& RankingPost-qualification Award of
Contract
6
-
8/17/2019 03 Bidding Procedure for Goods and Infra
7/99
Purpose: Determine readiness of procurement
Conducted prior to advertisement/posting of theInvitation to Bid
Mandatory for projects with ABC above PhP 2M(goods), 5M (infra projects), 1M (consulting services)
Attended by the following:a) BACb) BAC Secretariat
c) TWGd) Consultantse) End-user unit/Other officials
I. PRE-PROCUREMENT
CONFERENCE
7
-
8/17/2019 03 Bidding Procedure for Goods and Infra
8/99
-
8/17/2019 03 Bidding Procedure for Goods and Infra
9/99
Importance:
Signals the start of the bidding process. Procurementprocess should be made within 3 months starting
from posting and advertisement until awarding ofcontract. (Sec. 38.1 IRR)
Signals the availability of the bidding documents tothe prospective bidders. (if not mentioned in the
Invitation to Bid) (Sec. 17.3 IRR)
II. ADVERTISEMENT/POSTING OF
THE INVITATION TO BID
9
-
8/17/2019 03 Bidding Procedure for Goods and Infra
10/99
At least once in one (1) newspaper of general nationwidecirculation, which has been regularly published for at least two(2) years before advertisement date.
Posted continuously for 7 calendar days – – PhilGEPS
– website of the PE, if any.
– website of IFI, if applicable.
– At any conspicuous place in the premises of the PE.
Not required for projects with ABC of 2M and below.
II. ADVERTISEMENT/POSTING OF
THE INVITATION TO BID
10
-
8/17/2019 03 Bidding Procedure for Goods and Infra
11/99
II. ADVERTISEMENT/POSTING OF
THE INVITATION TO BID
MediumAbove2M/5M
2M/5M andbelow
Newspaper of General NationwideCirculation
PhilGEPS website PE’s Website, if available
Conspicuous Place
Website prescribed by the foreigngovernment/foreign or internationalfunding institution, in case of foreignfunded procurement
11
-
8/17/2019 03 Bidding Procedure for Goods and Infra
12/99
Forum where the PE’s representatives & the biddersdiscuss the different aspects of the project
Mandatory ABC 1M or more; Discretionary – ABC lessthan 1M
Held at least 12 cd before deadline for bid submission.May be held at least 30 cd considering the following:a) Method, nature, and complexity of contract
b) International participation is more advantageous
At the option of procuring entity, only bidders whopurchased bid documents are allowed to attend or askquestions
III. PRE-BID CONFERENCE
12
-
8/17/2019 03 Bidding Procedure for Goods and Infra
13/99
Section 22 affords bidders the opportunity to raise
concerns or clarifications on the requirements, terms,
conditions, and specifications stipulated in the bidding
documents for the contract to be bid.
Questions or clarifications pertaining to the matters that
may be discussed during the pre-bid conference must
be raised at least ten (10) calendar days before the
deadline set for the submission and receipt of bids.
(NPM 49-2013)
III. PRE-BID CONFERENCE
13
-
8/17/2019 03 Bidding Procedure for Goods and Infra
14/99
• Section 22.1 of the IRR of RA 9184 provides that at least one (1)pre-bid conference should be conducted by the procuring entityfor projects costing at least PhP1 Million, in order to affordprospective bidders the opportunity to inquire on or clarify any of
the requirements, terms, conditions, and specifications stipulatedin the Bidding Documents.
• Failure to conduct a pre-bid conference for the Project amounts toa violation of a mandatory provision of law, which will render theprocurement activity void under Article 5 of the Civil Code of the
Philippines. (NPM 48-2013)
III. PRE-BID CONFERENCE
14
-
8/17/2019 03 Bidding Procedure for Goods and Infra
15/99
Supplemental/Bid Bulletins
– issued by BAC to answerrequests for clarification (query submitted 10 c.d.before deadline) or interpretation, and upon BAC’s initiative to clarify or modify any provision of Bidding
Docs. (at least 7 c.d. before deadline for bids).
Posted in PhilGEPS and PE’s website
Bidders who have submitted bids before issuance ofSupplemental/Bid Bulletin must be informed inwriting and allowed to modify or withdraw theirrespective bids
CLARIFICATION OF BIDDING
DOCUMENTS
15
-
8/17/2019 03 Bidding Procedure for Goods and Infra
16/99
§22.5.2 RA 9184 IRR allows PEs to issue Supplemental/Bid
Bulletins upon their initiative for the purpose of clarifying or
modifying any provision in the Bidding Documents, including the IB.
PE has the authority to revise or amend any statement in theBidding Documents, including the IB, specifically when such revision
or amendment is made for the purpose of clarifying or modifying its
provisions.
Supplemental/Bid Bulletins must be posted in the PhilGEPS and atthe PE’s website, in order to address aspects of competition and
transparency. (NPM 46-2013)
CLARIFICATION OF BIDDINGDOCUMENTS
16
-
8/17/2019 03 Bidding Procedure for Goods and Infra
17/99
PE cannot compel prospective bidders or the winning bidder to
submit or comply with requirements not initially provided in the
Bidding Documents or through any Supplemental/Bid Bulletin
issued by the PE for the project that must be posted at the
PhilGEPS’
and the PE’
s website.
If no Supplemental/Bid Bulletin is issued to reflect changes in the
Bidding Documents, or even if the same was issued but not posted
at the PhilGEPS ’ and PE ’ s websites, the original provisions
contained in the Bidding Documents remain and the prospective
bidder, including the winning bidder cannot be compelled to abideor comply with the changes made by the PE. (NPM 24-2013)
ADDITIONAL REQUIREMENTS
17
-
8/17/2019 03 Bidding Procedure for Goods and Infra
18/99
Two-Envelope System 1st Envelope – Eligibility Requirements and Technical Component
2nd Envelope – Financial Component
Submitted to the BAC on the date, time, and place specified in theInvitation to Bid. Bids submitted after the deadline should not beaccepted.
Date of submission should not be later than the following period fromthe last day of posting of the Invitation to Bid.
IV. SUBMISSION AND RECEIPT OF
BIDS
Category Maximum Period (cd)Goods 45
Infra (50M and below) 50
Infra (above 50M) 65
18
-
8/17/2019 03 Bidding Procedure for Goods and Infra
19/99
IV. SUBMISSION AND RECEIPT OF
BIDS
Bidders are no longer required to submit awritten LOI together with their applicationfor eligibility as previously required in IRRPart A of RA 9184.
Bidders only have to submit their bids notlater than the deadline for the submission
and receipt of bids, which can be extended orrescheduled together with the opening of bidsas provided in Section 29 of the IRR of RA9184. (NPM 55-2013)
19
-
8/17/2019 03 Bidding Procedure for Goods and Infra
20/99
IV. SUBMISSION AND RECEIPT OF
BIDS
The practice of pre-qualification has been abandonedin RA 9184 and its IRR. the results of a pre-qualification have no legal force and effect, bearing orweight, and cannot preempt the findings of the BAC
during the preliminary examination of bidsconducted during the opening of bids. Hence, a biddermay still be declared ineligible during the opening ofbids despite a finding of qualification during the
purported pre-qualification exercise. (NPM 54-2013)
20
-
8/17/2019 03 Bidding Procedure for Goods and Infra
21/99
IV. SUBMISSION AND RECEIPT OF
BIDS
Procuring entity cannot validly and legally refuse toaccept a bid submitted before the deadline for thesubmission indicated the Invitation to Bid or Requestfor Quotation.
This shall open a ground for the aggrieved bidder tofile a request for reconsideration and, subsequently,protest as provided in Section 55 of RA 9184 and its
IRR, without prejudice to the institution of civil,administrative and/or criminal actions against theerring officials under applicable laws and rules.(NPM 67-2013)
21
-
8/17/2019 03 Bidding Procedure for Goods and Infra
22/99
CONTENTS:
1. Eligibility requirements
2. Bid Security
3. Technical specifications (Goods) / Projectrequirements (Infra)
4. Omnibus sworn statementNon-inclusion in blacklist Authenticity of documents Verification authority
V. OPENING AND EVALUATION OF 1
ST
ENVELOPE
22
-
8/17/2019 03 Bidding Procedure for Goods and Infra
23/99
CONTENTS (continuation):
4. Omnibus Sworn Statement
Signatory’s authority
Disclosure of relationsResponsibilities of biddersLabor laws and standardsNon-payment (directly or indirectly) any
commission, amount, fee, or any form ofconsideration in relation to anyprocurement project or activity
V. OPENING AND EVALUATION OF 1
ST
ENVELOPE
23
-
8/17/2019 03 Bidding Procedure for Goods and Infra
24/99
Section 30 requires that the preliminary examination of
bids be conducted by merely checking for the presence
or absence of documentary requirements using a non-
discretionary “pass/fail” criterion.
However, the BAC has the right to review the
qualifications of a bidder during the same stage if it has
reasonable grounds to believe that a misrepresentation
has been made or there has been changes in the
bidder ’s capability to undertake the project. (NPM 54-
2013)
V. OPENING AND EVALUATION OF 1ST ENVELOPE
24
-
8/17/2019 03 Bidding Procedure for Goods and Infra
25/99
BAC should open a reconsidered bid under the
same circumstances as it opened the bids that
were not disqualified, i.e., upon a duly
scheduled opening of bid with proper notices tothe concerned entities. (NPM 69-2013)
V. OPENING AND EVALUATION OF 1ST ENVELOPE
25
-
8/17/2019 03 Bidding Procedure for Goods and Infra
26/99
ELIGIBILITY REQUIREMENTS
GOODS INFRASTRUCTURE
Class Documents
1. DTI/SEC/CDA
Registration
1. DTI/SEC/CDA
Registration2. Mayor’s permit 2. Mayor’s permit
3. Tax clearance perExecutive Order 398, series
of 2005, as finally reviewedand approved by the BIR.
3. Tax clearance perExecutive Order 398, series
of 2005, as finally reviewedand approved by the BIR.
4. Statement of ongoingcontracts.
4. Statement of ongoingcontracts.
5. Statement of SLCC 5. Statement of SLCC 26
-
8/17/2019 03 Bidding Procedure for Goods and Infra
27/99
ELIGIBILITY REQUIREMENTS
GOODS INFRASTRUCTURE
Class Documents
5. Audited financial
statement
5. PCAB license and
registration.6. NFCC 6. Audited financial
statement
7. NFCC
Class B Document
JVA or notarized statement from the partners that theywill enter into joint venture if awarded the contract.
27
-
8/17/2019 03 Bidding Procedure for Goods and Infra
28/99
ELIGIBILITY REQUIREMENTS
Mayor
’
Permit allows an entity to legally performthe requirements and obligations of the project andthe resultant contract.
It is therefore necessary for the BAC to determinewhether the Mayor ’ s Permit for constructionbusiness issued to the construction company likewiseauthorizes it to engage in the business of supplying
dump trucks. (NPM 36-2013)
28
-
8/17/2019 03 Bidding Procedure for Goods and Infra
29/99
ELIGIBILITY REQUIREMENTS
A valid PCAB license required as an eligibilityrequirement for the procurement of infrastructureprojects under Section 23.1 (a) (iv) of the revised IRRof RA 9184 should be valid at the time of the deadlinefor the submission and opening of bids.
The submission of a PCAB license with validity periodafter the date of the opening of the bids is a ground
for the prospective bidder’s disqualification. (NPM 71- 2013)
29
-
8/17/2019 03 Bidding Procedure for Goods and Infra
30/99
EO 398 specifically requires the submission of Tax
Clearance issued by the BIR. It refers to the clearance
issued by the Collection Enforcement Division of BIR
attesting that the bidder has no outstanding Final
Assessment Notice and/or delinquent account.
Hence, submission of tax clearance of the previous year
and application for tax clearance cannot be considered
as compliance. (NPM 02-2013)
TAX CLEARANCE
30
-
8/17/2019 03 Bidding Procedure for Goods and Infra
31/99
Submission of BIR receipt for renewal of Tax Clearance will not
suffice in lieu of a valid Tax Clearance Requirement since
substitution is not allowed under Section 34.2 of the IRR of RA
9184.
The Tax Clearance must be valid and existing at the time it is
submitted to BAC and must be submitted within three (3) calendar
days from receipt of the notice from the BAC that the bidder has
the LCB. Failure to comply with the requirement for the submission
of a valid Tax Clearance shall be a ground for post-disqualification
of the bidder. (NPM 48-2013)
TAX CLEARANCE
31
-
8/17/2019 03 Bidding Procedure for Goods and Infra
32/99
FOR FOREIGN BIDDERS
A Delinquency Verification Certificate issued to Non-
Resident Foreign Corporations (NRFC)/Non-Resident
Aliens Not Engaged in Trade or Business (NRANETB)
pursuant to BIR RR 3-2005, attesting to the fact that thetaxpayer has no outstanding Final Assessment Notice
and/or delinquent account may be submitted as a form of
Tax Clearance required under Sec 34.2 of the IRR. (NPM
02-2013)
TAX CLEARANCE
32
-
8/17/2019 03 Bidding Procedure for Goods and Infra
33/99
In the case of foreign bidders, the foregoing eligibilityrequirements under Class “A” Documents may besubmitted:
Equivalent documents issued by country
Accompanied by English translation certified byappropriate embassy or consulate in the Philippines
ELIGIBILITY REQUIREMENTS FOR
FOREIGN BIDDERS
33
-
8/17/2019 03 Bidding Procedure for Goods and Infra
34/99
Foreign bidders may substitute eligibility documentary
requirements with the appropriate equivalent documents
in their country.
Only upon actual determination and confirmation of this
equivalence through post qualification by the BAC may it
be categorically resolved that the foreign documents
submitted are acceptable substitutes of the required
eligibility documents pursuant to §23.2 of the IRR. (NPM
42-2013)
ELIGIBILITY REQUIREMENTS FORFOREIGN BIDDERS
34
-
8/17/2019 03 Bidding Procedure for Goods and Infra
35/99
Government corporate entities may be eligible toparticipate only if they can establish that they:
1. are legally and financially autonomous,2. operate under commercial law, and3. are not attached agencies of the procuring
entity.
ELIGIBILITY REQUIREMENTS FOR GOVT.
CORPORATE ENTITIES
35
-
8/17/2019 03 Bidding Procedure for Goods and Infra
36/99
1. WITH AN EXISTING JOINT VENTURE: submissionof a valid joint venture agreement
2. WITHOUT AN EXISTING JOINT VENTURE:submission by each of the potential joint venturemembers of a duly notarized statement stating thatthey will enter into and abide by the provisions of the
joint venture in case their bid is successful.
ELIGIBILITY REQUIREMENTS FOR
JOINT VENTURES
36
-
8/17/2019 03 Bidding Procedure for Goods and Infra
37/99
SUBMISSION OF ELIGIBILITY REQUIREMENTS:
All co-venturers of the joint venture should submit
legal eligibility documents.
Any of the co-venturers can submit technical andfinancial eligibility requirements
ELIGIBILITY REQUIREMENTS FOR
JOINT VENTURES
37
-
8/17/2019 03 Bidding Procedure for Goods and Infra
38/99
• JV Bidders are required to submit a Joint License issued by the
PCAB in compliance with the eligibility requirement for a “valid
PCAB license and registration.
•§38 RA 4566 prohibits 2 or more contractors from jointly submittinga bid without first securing a Joint License to engage or act in the
capacity of such a joint venture.
• Failure of the JV Bidder to submit a Joint License may be a ground
for its disqualification despite the submission of the individual
licenses of each joint venture partner. (NPM 17-2013)
ELIGIBILITY REQUIREMENTS FOR JOINTVENTURES
38
-
8/17/2019 03 Bidding Procedure for Goods and Infra
39/99
LEGAL ELIGIBILITY CRITERIA
GOODS INFRASTRUCTURE
• General rule: 60% Filipino • General rule: 75% Filipino
• Foreign bidder allowed if:• Stated in treaty or international or
executive agreement
• National of a country offeringreciprocity rights to Filipinos
• Goods not available from localsuppliers
• To prevent situations that defeatcompetition or restrain trade
• Foreign contractors allowed if statedin treaty or international or
executive agreement
• If joint venture, less than 75% isallowed if -• Structures to be built require
techniques not possessed by 75%Filipinos
• Not less than 25% Filipino
39
-
8/17/2019 03 Bidding Procedure for Goods and Infra
40/99
TECHNICAL ELIGIBILITY CRITERIA
Previous contract
Similar to the contract to be bid out (as defined by the BiddingDocuments)
Completed within a period as defined by the Bidding Documents
25% of the ABC (expendable supplies)
50% of the ABC (non-expendable supplies)- Based on the value of the previous completed contract, as
adjusted to current prices using the NSO consumer priceindex.
For foreign funded procurement, a different track record may beagreed upon
40
-
8/17/2019 03 Bidding Procedure for Goods and Infra
41/99
TECHNICAL ELIGIBILITY CRITERIA
GOODS SINGLE LARGEST CONTRACT
General Rule Exceptions Then require the ff.:
1. Expendable Supplies• 25% of the ABC
2. Services and Non-expendable supplies• 50% of the ABC
If, at the outset andafter market
research, applying thegeneral rule willlikely result to:
1. Failure of bidding;or
2. Monopoly
a) At least 2 similarcontracts aggregate
amount at leastequivalent to requiredpercentage; and
b) Largest of the similarcontracts amounts toat least 50% ofrequired percentage
41
-
8/17/2019 03 Bidding Procedure for Goods and Infra
42/99
TECHNICAL ELIGIBILITY CRITERIA
GOODS SINGLE LARGEST CONTRACT (Illustration)
Expendable Goods Non-expendable Goods
ABC = P1,000,000
GR: 25% of the ABC
THUS: Previous contract should be at leastP250,000
EXCEPTION: At least 2 similar contractsaggregate amount at least equivalent torequired percentage; and Largest of thesimilar contracts amounts to at least 50%
of required percentage.
THUS: 1st contract = P100,002nd contract = P200,00
ABC = P1,000,000
GR: 50% of the ABC
THUS: Previous contract should be at leastP500,000
EXCEPTION: At least 2 similar contractsaggregate amount at least equivalent torequired percentage; and Largest of thesimilar contracts amounts to at least 50% of
required percentage.
THUS: 1st contract = P300,0002nd contract = P400,00[
42
-
8/17/2019 03 Bidding Procedure for Goods and Infra
43/99
TECHNICAL ELIGIBILITY CRITERIA
INFRASTRUCTURE PROJECTS SINGLE LARGEST
CONTRACT
Previous contract
Similar to the contract to be bid out (having the same civil works
components) 50% of the ABC
- Based on the value of the previous completed contract, asadjusted to current prices using the NSO consumer priceindex.
For foreign funded procurement, a different track record may beagreed upon
43
-
8/17/2019 03 Bidding Procedure for Goods and Infra
44/99
TECHNICAL ELIGIBILITY CRITERIA
Construction experience/track record of a soleproprietor, cannot be carried over to a corporationdespite the fact that the sole proprietor ’s assets,
personnel and other resources have been infused intothe corporation inasmuch as the latter has a separateand distinct juridical personality from the former.(NPM 31-2013)
44
-
8/17/2019 03 Bidding Procedure for Goods and Infra
45/99
FINANCIAL ELIGIBILITY CRITERIA
FOR GOODS AND INFRASTRUCTURE
PROJECTS:
• Audited Financial Statement (showingprospective bidder’s total and currentassets and liabilities. )
•NFCC at least equal to ABC.
45
-
8/17/2019 03 Bidding Procedure for Goods and Infra
46/99
Net Financial Contracting Capacity (NFCC) =
(current assets - current liabilities) (K) MINUS(outstanding, uncompleted portions under ongoingcontracts + contracts awarded but not yet started)
(K) = 10 (contract is 1 year or less)
15 (contract is more than 1 year to 2 years)
20 (contract is more than 2 years)* The values of the bidder’s current assets and currentliabilities shall be based on the data submitted to the BIR,through its Electronic Filing and Payment System (EFPS)
NFCC COMPUTATION
46
-
8/17/2019 03 Bidding Procedure for Goods and Infra
47/99
Participating bidder should be required to submit
an NFCC that is at least equal to all the lots to
which it participated in, in order to establish the
bidder ’ s financial liquidity and absorptivecapacity in carrying out the contractual
obligations required by the lots to which it
participated in. (NPM 76-2013)
NFCC COMPUTATION or CLCAMOUNT
47
-
8/17/2019 03 Bidding Procedure for Goods and Infra
48/99
Procuring entity shall indicate in the Bidding Documents at least2 acceptable forms of bid security, one of which should be the BidSecuring Declaration.
In general, bank issued securities must be issued by a universalor commercial bank
However, in biddings conducted by LGUs, securities may beissued by banks certified by BSP as authorized to issue saidinstruments
Surety Bonds must be accompanied by certification fromInsurance Commission that issuer is authorized to issue suchsecurity
BID SECURITY
48
-
8/17/2019 03 Bidding Procedure for Goods and Infra
49/99
BID SECURITY
Form of Bid Security
Amount
Bid Security
( = ABC)
a) Cash or cashier’s/manager’s
check2%b) Bank guarantee/draft or
Irrevocable LC
c) Surety bond callable upondemand 5%
d) Combination of theforegoing
Proportionate to share of form with respect tothe total amount of security
e) Bid Securing Declaration No percentage required
49
-
8/17/2019 03 Bidding Procedure for Goods and Infra
50/99
BID SECURITY
50
• For biddings conducted by LGUs , theBidder may also submit bid securities inthe form of cashier’s/manager’s check,
bank draft/guarantee, or irrevocable letterof credit from other banks certified by theBSP as authorized to issue such financial
statement.
-
8/17/2019 03 Bidding Procedure for Goods and Infra
51/99
BID SECURING DECLARATION
Bid Securing Declaration
- an additional form of bid security
- A document/undertaking signed by the biddercommitting to pay the corresponding fine and besuspended for a period of time from being qualifiedto participate in any government activity in theevent of violation of any of the conditions stated
therein as required by the GPPB Guidelines. (GPPBResolution No. 03-2012, 27 January 2012)
51
-
8/17/2019 03 Bidding Procedure for Goods and Infra
52/99
BID SECURING DECLARATION
Penalties
- Automatic blacklisting for 2 years in ALLgovernment procurement activities, and
- Payment of fine
• For multiple bidders: difference between theevaluated bid prices of LCRB/HRB with the nextLCRB/HRB.In case bidder is the LCRB/HRB, the amount
shall be based on the difference between theevaluated bid price and ABC. • For a single bidder: difference between the
evaluated bid price and ABC.
52
-
8/17/2019 03 Bidding Procedure for Goods and Infra
53/99
Bids and bid securities (including bid securingdeclaration) shall be valid for a reasonable period asdetermined by the HOPE as indicated in the Bid Docs.
Not to exceed 120 days
If the period is extended, PE shall request in writingall those who submitted bids for such extension beforethe expiration date.
NOTE: Bidders have a right to refuse to grant suchextension w/o forfeiting their bid security.
BID VALIDITY PERIOD
53
-
8/17/2019 03 Bidding Procedure for Goods and Infra
54/99
Relatives within the third civil degree of the followingshall be disqualified:
Head of the procuring entity
Members of the BAC, Secretariat and TWG
Head of the end-user unit or project managementoffice
Project consultants
DISCLOSURE OF RELATIONS
54
-
8/17/2019 03 Bidding Procedure for Goods and Infra
55/99
The firm that has been engaged to provide consulting services for
the preparation or implementation of a project, and each of its
affiliates, will be disqualified from subsequently providing goods,
works, or services resulting from or directly related to the firm’s
consulting services for such preparation or implementation.
There is conflict of interest when the entity that prepared the
plans/drawings likewise participates in the ensuing procurement
activities for the Project. (NPM 10-2013)
CONFLICT OF INTEREST
55
-
8/17/2019 03 Bidding Procedure for Goods and Infra
56/99
CONTENTS:
1. Financial Bid Form (includes bid prices and bill ofquantities, as well as applicable price schedules)
2. In case of Goods, Certification from the DTI, SEC,or CDA, if claiming preference as Domestic Bidderor Domestic Entity
3. Other documents required in the bidding
documents
VI. OPENING AND EVALUATION OF
2
ND
ENVELOPE
56
-
8/17/2019 03 Bidding Procedure for Goods and Infra
57/99
Purpose is to determine the Lowest Calculated Bid(LCB), by:
1. Establishing correct calculated prices of bids; and
2. Ranking calculated total bid prices from lowest to
highest
A non-discretionary criterion shall be used, whichshall include consideration of:
1. completeness of bids; and2. minor arithmetical corrections
VII. DETAILED EVALUATION
OF BIDS
57
VII DETAILED EVALUATION
-
8/17/2019 03 Bidding Procedure for Goods and Infra
58/99
No Contact Rule - prohibition on communication w/ bidders frombid evaluation until award of contract.
The “no contact” rule applies only to those whose bids are being
evaluated by the BAC after passing the preliminary examination.
No communication should be made by bidders until a decision to
award a contract is made by the BAC.
Bidders who waived their right to utilize the protest mechanism or
those whose request for reconsideration and/or protest weresubsequently denied are not covered by the prohibition under §32.1
of RA 9184 IRR. (NPM 07-2013)
VII. DETAILED EVALUATIONOF BIDS
58
VII DETAILED EVALUATION
-
8/17/2019 03 Bidding Procedure for Goods and Infra
59/99
Bid Evaluation shall not be more than 7 cd.
In case of discrepancies, the ff. shall prevail:- words over figures
- unit prices over total prices- actual sum of prices over total price- bill of quantities over detailed estimates
Section 32.2.3(c) of the IRR states that where there is a
discrepancy between the stated total price and the actualsum of prices of component items, the latter shall prevail.
(NPM 51-2013)
VII. DETAILED EVALUATIONOF BIDS
59
-
8/17/2019 03 Bidding Procedure for Goods and Infra
60/99
Unless the ITB specifically allows partial bids, thosenot providing all required items shall be considerednon-responsive
Placing no price is considered as non-responsive
Specifying a “0” or “-” means it is offered for free
VII. DETAILED EVALUATION
OF BIDS
60
-
8/17/2019 03 Bidding Procedure for Goods and Infra
61/99
Applicable only for GOODS
Applies where the lowest bid has a foreign component(foreign bid/entity) and the next lowest bid has adomestic component (domestic bidder/entity)
Requires procuring entity to give preference todomestic bidder PROVIDED that:
1. The lowest foreign bid is increased by 15%; and2. The lowest domestic bidder matches the lowest bid
of the foreign bidder
DOMESTIC PREFERENCE
61
-
8/17/2019 03 Bidding Procedure for Goods and Infra
62/99
DOMESTIC PREFERENCE
SAMPLE COMPUTATION
Lowest Calculated Bid Next Lowest Calculated Bid
Foreign Bidder Domestic Bidder/Entity
Bid 2,653,360.00 3,009,492.00% Preference x 15%
398,004.00
+ 2,653,360.00
Bid as increased 3,051,364.00 3,009,492.00
Result
Award to Domestic Bidder/Entity at 2,653,360.00, or Award to Foreign Bidder if Domestic Bidder/Entity
refuses
62
-
8/17/2019 03 Bidding Procedure for Goods and Infra
63/99
To determine whether bidder with LCB complies withand is responsive to all requirements and conditionsof eligibility and the bidding of the contract – to bedeclared the Lowest Calculated and Responsive Bid
(LCRB)
A non-discretionary pass/fail criterion shall be usedto “Verify, Validate and Ascertain” all statements anddocuments (licenses, certificates, etc.)
To be accomplished not more than 7 c.d. fromdetermination of LCB. (Exceptional cases not toexceed 30 c.d.)
VIII. POST-QUALIFICATION
63
-
8/17/2019 03 Bidding Procedure for Goods and Infra
64/99
BAC will notify the Bidder with the Lowest CalculatedBid that it was determined as such.
Within 3 c.d. from receipt of Notice, submit the ff:
1. Latest Income and Business Tax Returns;2. Certificate of PhilGEPS Registration; and,
3. Other appropriate Licenses and permits requiredby law and stated in the Bidding Documents.
VIII. POST-QUALIFICATION
64
-
8/17/2019 03 Bidding Procedure for Goods and Infra
65/99
BAC shall recommend award of contract to theLOWEST CALCULATED AND RESPONSIVE BID(LCRB) at submitted price or calculated price ,whichever is lower.
In case of approval by HOPE, Notice of Award shouldbe IMMEDIATELY issued by HOPE to the LCRB.(HOPE has 7 days to decide w/n to issue NOA)
VIII. POST-QUALIFICATION
65
-
8/17/2019 03 Bidding Procedure for Goods and Infra
66/99
The three (3) calendar day period under §34.2 of theIRR is mandatory and should not be extended.
In case PE accepts the post-qualification documentary
requirements beyond the reglementary period, it must
show that there is a compelling, sufficient, valid,
reasonable, and justifiable cause for such extension, so
that penal sanction or liability will not set in. Applicable
administrative and civil sanctions or liabilities may also
be imposed against the concerned officials. (NPM 27-2013)
VIII. POST-QUALIFICATION
66
-
8/17/2019 03 Bidding Procedure for Goods and Infra
67/99
PE may request for the submission of additional
documents from the bidder in support of the information
it has provided in the bidding documents.
However, non-submission of the additional supporting
documents requested cannot be a ground for thebidder ’s post-disqualification, as a bidder may be post-
disqualified only upon ascertainment, validation, and
verification of its non-compliance with the legal,
technical, and financial requirements of the project asprovided in the bidding documents. (NPM 25-2013)
VIII. POST-QUALIFICATION
67
-
8/17/2019 03 Bidding Procedure for Goods and Infra
68/99
Should PE decides to extend the period, it must show
and provide compelling, sufficient, valid, reasonable,
and justifiable cause. Such valid justification, however,
will only free officials from penal sanction or liability, but
not from applicable administrative and civil sanctions orliabilities under existing laws, rules and regulations.
(NPM 57-2013)
VIII. POST-QUALIFICATION
68
-
8/17/2019 03 Bidding Procedure for Goods and Infra
69/99
GROUNDS:
1) No bids received
2) Bids received but no one was eligible3) All bids failed to post qualify
4) Someone post qualified but refused w/o justifiablecause to accept the award.
FAILURE OF BIDDING
69
-
8/17/2019 03 Bidding Procedure for Goods and Infra
70/99
EFFECTS:
1) Mandatory review shall be conducted by BAC
2) Based on findings, BAC shall: Revise terms, conditions, specificationsAdjust ABC, subject to required approvals
3) Re-bidding
4) Re-advertisement
FAILURE OF BIDDING
70
-
8/17/2019 03 Bidding Procedure for Goods and Infra
71/99
Contract shall be awarded to the bidder with the
Lowest Calculated and Responsive Bid (LCRB) at itssubmitted price or total calculated bid price,whichever is lower
Notice of Award (NOA) is issued by the HOPE
NGAs and LGUs – 7 cd GOCCs and GFIs – 15 cd
IX. AWARD OF CONTRACT
71
-
8/17/2019 03 Bidding Procedure for Goods and Infra
72/99
NOA is subject to the following conditions:
◦ If joint venture, submission of JVA
◦ If foreign-funded and stated in treaty, international orexecutive agreement, PCAB License
◦ Posting of Performance Security◦ Signing of Contract (within 10 cd)
◦ If required, approvals by higher authority
PROCUREMENT PROCESSFrom Opening of Bids to Award of Contract shall
NOT EXCEED 3 MONTHS
IX. AWARD OF CONTRACT
72
-
8/17/2019 03 Bidding Procedure for Goods and Infra
73/99
PERFORMANCE SECURITY
Posted by winning bidder upon signing of contract toguarantee performance of obligation, in such form andamount specified in the Bidding Documents.
EFFECTS OF FAILURE TO POST:
1. Ground for disqualification2. Next-ranked LCRB shall undertake post-
disqualification3. Bid security shall be forfeited without prejudice to
the imposition of sanctions
73
-
8/17/2019 03 Bidding Procedure for Goods and Infra
74/99
PERFORMANCE SECURITY
Submission by the winning bidder of a Performance Security inthe form of a personal check after the signing of the contractcould be considered as a failure to post the Performance Securityin the required form under §39.2 of the IRR and in the required
period for posting under § 37.1.4(b) of the IRR.
§4.1.5 of the Guidelines provides that the refusal or failure of acontractor to post the required Performance Security within theprescribed period is one of the grounds for blacklisting. (NPM 35- 2013)
74
-
8/17/2019 03 Bidding Procedure for Goods and Infra
75/99
PERFORMANCE SECURITY
Form of Performance Security
Amount
Performance Security
( equal to the Contract Price)
a) Cash or
cashier’s/manager’s check 5% (Goods ) & 10% (Infra)
b) Bank guarantee/draft orIrrevocable LC
c) Surety bond callable upon
demand30%
d) Combination of theforegoing
Proportionate to share of form with respect tothe total amount of security
75
-
8/17/2019 03 Bidding Procedure for Goods and Infra
76/99
RESERVATION CLAUSE
HOPE reserves the right to:◦ Reject any and all bids;
◦ Declare a failure of bidding;
◦ Not award the contract.
GROUNDS:1. Prima facie evidence of collusion;
2. BAC is found to have failed in following the prescribed biddingprocedures;
3. For justifiable reasons, the award of contract will not redound to thebenefit of the Government:
Physical and economic conditions have significantly changed; Project is no longer necessary Source of funds for the project has been withdrawn/reduced.
76
-
8/17/2019 03 Bidding Procedure for Goods and Infra
77/99
NOTICE TO PROCEED
Issued to the successful bidder together with the copyof the approved contract within 3 cd from date ofapproval
For infrastructure projects with ABC of 50M and
below, the maximum period is 2 cd Contract effectivity date should be provided in the
NTP, which should not be later than 7 cd from itsissuance
BAC Secretariat should post a copy of the NTP andthe approved contract in the PhilGEPS or PE’s website within 15 cd from issuance of NTP
77
-
8/17/2019 03 Bidding Procedure for Goods and Infra
78/99
CONTRACT IMPLEMENTATION
GUIDELINES FOR THE
PROCUREMENT OF GOODS,
SUPPLIES AND MATERIALS
78
-
8/17/2019 03 Bidding Procedure for Goods and Infra
79/99
-
8/17/2019 03 Bidding Procedure for Goods and Infra
80/99
SUSPENSION OF WORK
PE may suspend the work wholly or partly by writtenorder for a certain period of time due to force majeureor fortuitous events.
When the suspension order is lifted, or if the period ofthe order expires, the supplier or consultant shallresume work.
80
-
8/17/2019 03 Bidding Procedure for Goods and Infra
81/99
LIQUIDATED DAMAGES
When bidder fails to perform obligations within specifiedschedule, inclusive of duly granted time extensions, he shall beliable for damages and shall pay the PE liquidates damages.
Bidder shall pay an amount equal to 1/10 of 1 of the cost of thecost of delayed goods scheduled for delivery for every day of delayuntil such goods are finally delivered and accepted by theprocuring entity.
PE need not prove it incurred actual damages.
81
-
8/17/2019 03 Bidding Procedure for Goods and Infra
82/99
LIQUIDATED DAMAGES
Whichever is convenient to the procuring entity,amount shall be deducted from:1. any money due or which may become due to the
supplier, or2. collected from any securities or warranties posted
by the supplier,
If sum of liquidated damages reach 10% of thecontract amount, PE shall automatically rescind thecontract.
82
-
8/17/2019 03 Bidding Procedure for Goods and Infra
83/99
ADVANCE PAYMENT
Made only after prior approval of the President.
Single advance payment not to exceed 50% of thecontract for the following services:◦ Hotel and restaurant services
◦ Use of conference/seminar and exhibit areas◦ Lease of office space
Advance payment not to exceed 15% allowed toaddress contingencies arising from natural or man-
made calamities in areas where “state of calamity” has been declared
83
-
8/17/2019 03 Bidding Procedure for Goods and Infra
84/99
ADVANCE PAYMENT
For goods, 10% of the contract price shall be paidwithin 60 days from signing of contract and uponsubmission of a claim and a bank guarantee.(Amended by M.O. 15, series of 2011)
NOTE: Progress payments shall first be chargedagainst the advance payment until the latter is fullyexhausted. (UNLESS otherwise approved by the
President)
84
-
8/17/2019 03 Bidding Procedure for Goods and Infra
85/99
CONTRACT IMPLEMENTATION
GUIDELINES FOR THE
PROCUREMENT OF
INFRASTRUCTURE PROJECTS
85
-
8/17/2019 03 Bidding Procedure for Goods and Infra
86/99
-
8/17/2019 03 Bidding Procedure for Goods and Infra
87/99
VARIATION ORDER
Conditions:
1. Does not exceed 10% of the original contract price.
2. Scope of works shall not be reduced to accommodate
positive variation order.3. Any cumulative positive variation order beyond 10%
of the original contract price shall be subject ofanother contract to be bid out if works are separable
from the original contract.
87
-
8/17/2019 03 Bidding Procedure for Goods and Infra
88/99
VARIATION ORDER
For an increase/decrease in quantities of work to be covered by Variation Order, it should be:
within the general scope of the Project as bid and awarded,
due to the change of plans, design, or alignment to suit actualfield conditions resulting in disparity between thepreconstruction plans used for purposes of bidding and the “asstaked plans” or the construction drawings prepared after the joint survey by the contractor and the government after award
of contract. (NPM 56-2013)
88
-
8/17/2019 03 Bidding Procedure for Goods and Infra
89/99
ADVANCE PAYMENT
REQUIREMENTS:
1. Written request of the contractor
2. Submission of :
a. an irrevocable standby letter of credit of equivalent valuefrom a commercial bank;
b. bank guarantee,; or
c. surety bond
3. Amount not to exceed 15% of the contract price
4. Amount shall be repaid by the contractor
89
-
8/17/2019 03 Bidding Procedure for Goods and Infra
90/99
ADVANCE PAYMENT
Section 4 of the Contract Implementation Guidelinesfor the Procurement of Infrastructure Projects(Guidelines) under Annex “ E ” of the revisedImplementing Rules and Regulations (IRR) of
Republic Act (RA) No. 9184
The President approved an advance payment notexceeding fifteen percent (15%) of the total contractprice, provided that requirements under Section 4 of
the Guidelines are complied with. (NPM 12-2013)
90
-
8/17/2019 03 Bidding Procedure for Goods and Infra
91/99
ADVANCE PAYMENT
Advance payment in case of infrastructure projects may begranted by the procuring entity upon compliance with theconditions provided in Section 4 of the Guidelines and only forthe purpose of mobilization.
Thus, if the contractor has already mobilized its equipment andhas commenced with the required works under the contract,advance payment can no longer be provided as doing so alreadynegates the very purpose of granting such privilege to thecontractor. (NPM 56-2013)
91
-
8/17/2019 03 Bidding Procedure for Goods and Infra
92/99
PROGRESS PAYMENT
Payments made by the Procuring Entity to thecontractor for portions of the work done.
Contractor may submit:
1. A statement of works accomplished (SWA) or progress billing
2. Request for progress payment for the work accomplished inamounts the contractor considers itself to be entitled to.
92
-
8/17/2019 03 Bidding Procedure for Goods and Infra
93/99
PROGRESS PAYMENT
The procuring entity shall deduct the following from thecertified gross amounts to be paid to the contractor asprogress payment:
1. Cumulative value of the work previously certified and paid for.
2. Portion of the advance payment to be recouped for the month.3. Retention money in accordance with the condition of contract.
4. Amount to cover third party liabilities.
5. Amount to cover uncorrected discovered defects in the works
93
-
8/17/2019 03 Bidding Procedure for Goods and Infra
94/99
RETENTION MONEY
Progress payments are subject to retention of ten percent (10%)referred to as the "retention money.“ This is to cover uncorrecteddefects after each progress billing.
It shall be based on the total amount due to the contractor priorto any deduction and shall be retained from every progresspayment until fifty percent (50 ) of the value of works, asdetermined by the procuring entity, are completed.
94
-
8/17/2019 03 Bidding Procedure for Goods and Infra
95/99
RETENTION MONEY
SUBSTITUTE FOR RETENTION MONEY:
( provided that the project is on schedule and is satisfactorily undertaken)
1. Irrevocable letter of credit from commercial bank
2. bank guarantee or surety bond callable on demand.
*Valid for a duration determined by PE
No more retention if:
- work is satisfactorily done- work is on schedule
95
-
8/17/2019 03 Bidding Procedure for Goods and Infra
96/99
LIQUIDATED DAMAGES
When contractor fails to perform obligations withinspecified contract time, inclusive of duly granted timeextensions, he shall be liable for damages and shallpay the PE liquidates damages equal to at least one
tenth (1/10) of one (1) percent of the cost of the
unperformed portion of the works for every day .ofdelay
If sum of liquidated damages reach 10% of the
contract amount, PE shall automatically rescind thecontract.
96
-
8/17/2019 03 Bidding Procedure for Goods and Infra
97/99
SUSPENSION OF WORK
Contractor or its duly authorized representative shall have the rightto suspend work operation fifteen (15) calendar days from date ofreceipt of written notice from the contractor to the districtengineer/regional director/consultant or equivalent official, due to
the following:
1. There exist right-of-way problems.
2. Requisite construction plans which must be owner-furnished arenot issued to the contractor.
97
-
8/17/2019 03 Bidding Procedure for Goods and Infra
98/99
SUSPENSION OF WORK
3. Peace and order conditions certified in writing by the PhilippineNational Police (PNP) and confirmed by the Department ofInterior and Local Government (DILG) Regional Director.
4. Failure on the part of the procuring entity to delivergovernment-furnished materials and equipment
5. Delay in the payment of contractor's claim for progress billingbeyond forty-five (45) calendar days from the time thecontractor's claim has been certified
98
-
8/17/2019 03 Bidding Procedure for Goods and Infra
99/99
THANK YOU!!
Contact us:
Unit 2506 Raffles Corporate CenterF. Ortigas Road, Ortigas Center
Pasay City, Philippines 1605
TeleFax: (632)900-6741 to 44