Social Safeguards implication and livelihoods restoration as an integral part of infrastructure development projects funded by ADB in Tajikistan

Upload: others

Post on 16-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

Social Safeguards implication and livelihoods restoration as an

integral part of infrastructure development projects funded by

ADB in Tajikistan

Page 2: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

ADB Priority Areas Partnership in Tajikistan

o Infrastructure Investment in Transport and Energy Sectors;

o Public Sector Management;o Agriculture and Natural

Resources;

Project Categories Involuntary Resettlement

Overall 13 ProjectsA B C FI/C

1 7 4 1

Page 3: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

CAREC Corridor 3 (Dushanbe – Uzbekistan border) Road Improvement Project

Funding:ADB Grant – 120 mln. USDGovernment of Tajikistan – 34.4 mln. USD

Outputs:o 62 km Road Reconstructed and Upgraded;o Border Infrastructure and facilities Improved;o Developed Gender and Livelihoods;

Outcome:Improved connectivity and mobility along the Tajikistan section of the CAREC Corridor 3

Page 4: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

CAREC Corridor 3 (Dushanbe – Uzbekistan border) Road Improvement Project

Page 5: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

LARP ScopeProject Impact on Local Communities

Impacts DPs No. Unito Agricultural lands and orchards 387 ha 42,6o Residential / Commercial lands 392 ha 8,1o Buildings and structures 373 no. 1410o Businesses 82 no. 82o Full displacement 34o Communal / Public assets no. 15o Total number of DPs 804 per. 6338

TJS 22 190 515 (above 4 mln. USD) cash compensation provided to DPs

Page 6: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

Consultations with Government Institutions

At central level

ADB SPS Policy and National Laws requirements alignment specially on:

o Cash compensation for affected lands;o DPs with no formal legal rights on land;o Livelihoods Assistance provisions;o Assistance for severity of impact;o Allowance for vulnerable households;

Page 7: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

Consultations with Government Institutions

Page 8: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

Consultations with Government Institutions

At local level

IR procedures and practices:

o Involvement in the project design;o Establishment of LAR Commission;o Communities appeals and issues;o Agriculture patterns and livelihoods source;

Page 9: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

Consultations with Government Institutions

Page 10: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

Consultations with DPs / CommunitiesServe as a platform for DPs’ views and their inclusion

in decision making processAt local level

o Share information on project design;o Entitlements and compensations;o Infrastructure improvements (irrigation, drainage);o Relocation approach and available options;o Other livelihoods restoration options;

Page 11: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

Consultations with DPs / Communities

Page 12: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

Conclusionso LAR as a participatory process;

o Protection of socially and economic vulnerable groups;

o Synchronized construction schedules with land acquisition;

o Monitor and facilitate mechanisms for hearing communities issues and concerns.

Page 13: 03 Faizullo Kudratov - Impact Assessment...Title 03 Faizullo Kudratov.pdf Created Date 1/8/2017 10:03:35 PM

Recommendations

o Improved efficiency of LAR process;

o Advanced planning and preparation of relocation sites;

o Implementation of short term and long term livelihoods restoration strategies;