03 gbi assessment method for construction (ir looi hip peu)

Upload: edward-low

Post on 02-Jun-2018

234 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    1/51

    Kota Kinabalu16 November [email protected]

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    2/51

    CONTENT 2

    1 The Construction Process

    4 Check List Templates

    3 Affordable Green Builing

    2 The GBI Rating Tool

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    3/51

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    4/51

    THE C ONSTRUCTION P ROCEDURE 4

    16 th November 2013

    Client / Design Team Construction Team Authorities

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    5/51

    THE C ONSTRUCTION F LOW P ROCESS 5

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    6/51

    THE C ONSTRUCTION P ROCEDURE 6

    16 th November 2013

    Public Interest

    Clients Interest

    Code of Conduct

    Expert Knowledge

    4 U n i v e r s a l C o n c e p t s o fP r o f e s s i o n a l i s m

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    7/51

    THE P ROFESSIONAL IN C ONSTRUCTION 7

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    8/51

    THE P ROFESSIONAL IN C ONSTRUCTION 8

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    9/5116 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    10/5116 th November 2013

    THE B UILDING IMPACT ON THE E NVIRONMENT 10

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    11/5116 th November 2013

    THE LIFE C YCLE 11

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    12/5116 th November 2013

    T YPICAL LCA B OUNDARIES FOR UPVC PIPES 12

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    13/5116 th November 2013

    THE B UILDING IMPACT ON THE E NVIRONMENT 13

    Energywaste

    Water

    Sewage

    http://www.animationlibrary.com/animation/29835/Fire_sun/
  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    14/5116 th November 2013

    THE B UILDING IMPACT ON THE E NVIRONMENT 14

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    15/5116 th November 2013

    THE B UILDING IMPACT ON THE E NVIRONMENT 15

    The Building sector consumes approx 10% -15% of total energynationally.

    Approx10%-15%BuildingSector

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    16/51

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    17/5116 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    18/51

    GBI A SSESSMENT TOOLS 18

    1. NRNC (Non Residential New Construction)2. RNC (Residential New Construction) 2009

    3. NREB (Non Residential Existing Building)4. RNC V2 (Residential New Construction, Version 2)

    2010

    5. GBI Township (Township Development)6. IEB (Industrial Existing Building)7. INC (Industrial New Construction)

    2011

    8. NRNC Data Centre 2012

    10. NRNC Retail 2013

    11. Under Development(a) Health Care(b) Interior

    (c) Resort / Hotel

    2013 - 2014

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    19/51

    THE RNC T OOL 19

    16 th November 2013

    RESIDENTIAL NEW C O N S T R U C T I O N V E R S I O N 3 . 0

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    20/51

    THE NRNC T OOL 20

    16 th November 2013

    NON-RESIDENTIAL NEW C O N S T R U C T I O N V E R S I O N 1 . 0

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    21/51

    GBI G REEN G OALS IN C ONSTRUCTION 21

    16 th November 2013

    Measures can be Broken Down into the following

    Compliance to Minimum Legal Standards Noadditional Cost.

    Good Practice Measures No additional Cost.Best Practice Standard Some Additional Cost

    Best Available Technology Additional Cost

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    22/51

    CRITERIA R ELATING TO C ONSTRUCTOR 22

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    23/51

    CRITERIA R ELATING TO C ONSTRUCTOR 23

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    24/51

    CRITERIA R ELATING TO C ONSTRUCTOR 24

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    25/51

    CRITERIA R ELATING TO C ONSTRUCTOR 25

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    26/51

    CRITERIA R ELATING TO C ONSTRUCTOR 26

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    27/51

    CONSTRUCTOR C RITERIA 27

    16 th November 2013

    Minimum Legal & Safety Standards No Additional Cost

    1. EE1 - Minimum Energy Efficiency Standards

    OTTV

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    28/51

    16 th November 2013

    CONSTRUCTOR C RITERIA 28

    Minimum Legal & Safety Standards No Additional Cost

    5. SM4 Earthworks Construction Activity Pollution Control

    Mandatory under law. Protect site from pollution and

    6. SM6 Workers Site Amenities

    Provide proper facilities and housing to construction workers on site

    7. SM10 Storm Water DesignScore 1 out of 3 available points. Design storm water runoff to complywith technical Manual MSMA (Manual Natural Storm Water)

    1

    1

    1

    Total Score Minimum Legal & Safety Standards

    11 POINTS

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    29/51

    16 th November 2013

    CONSTRUCTOR C RITERIA 29GOOD PRACTICE Standards No Additional Cost

    1. EE6 Sustainable Maintenance & Building User Manual

    Provide space for maintenance officeEnsure maintenance staff (50%) appointed earlyProvide documented proof of maintenance plan

    2. EQ6 Sound InsulationPartitions between units and rooms with sound insulation quality(STC>45)

    3. EQ7 Post Occupancy SurveyImplement post occupany survey

    4. SM1 Sustainable SiteSelect sites not environmentally sensitive

    5. SM3 Community ConnectivityLocate site where at least 10 public amenities are available (e.g.Library, grocery, supermarket, police station etc.

    6. SM8 Public Transportation AccessCovered waiting area and public transportation score 4 out of 8

    7. SM11 Greenscape & Water Bodies

    At least 15% of land area to score 1 out of 5 points.

    2

    1

    1

    1

    4

    4

    1

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    30/51

    16 th November 2013

    CONSTRUCTOR C RITERIA 30

    GOOD PRACTICE Standards No Additional Cost 8. SM14 Composting

    Plan for composting of landscape and/or organic waste9. MR2 Recycled Content Material

    Select concrete, steel, glass with recycled content; target at least 10%of total building material cost to score 1 out of 2 points

    10. MR3 Regional Materials

    Select building material at least 75% supplied from region (500kmradius from site). Exclude M&E items.

    11. MR5 Storage & Collection of Recyclables.During construction provide recycling bins & planFor permanent design provide bins and collection centre

    12. MR6 Construction Waste Management

    Recover at least 50% of construction waste e.g. Steel, waste concrete,pile cut-off, timber waste etc to score 1 out of 2 points.

    12. WE3 Water Efficient Irrigation & LandscapeSelect native plants which do not use water to reduce irrigation needby at least 50% to score 1 out of 2 points.

    1

    1

    2

    2

    1

    Total Score GOOD Practice Standards 22 POINTS

    1

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    31/51

    16 th November 2013

    CONSTRUCTOR C RITERIA 31

    BEST PRACTICE Standards Some Additional Cost

    1. EE2 Advanced EE Performance

    OTTV < 42 and RTTV < 0.5W/mK. Score 2 out of 12 points.Additional cost for roof insulation or insulation embedded in r.c. Flatroof.

    2. EE4 External Lighting & Control

    High efficiency lighting to external lightings and photo sensors forcontrol. Some cost for LED or high efficiency fluorescent or SON lamps

    3. SM8 Public Transportation Access

    Dedicated, covered walkway to station score another 2 out of 8points

    2

    2

    2

    Minimum Legal & Safety Standards 11 POINTS

    GOOD Practice Standards 22 POINTS

    TOTAL NO COST MEASURES 33 POINTS

    Additional Point for certification 17 POINTS

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    32/51

    16 th November 2013

    CONSTRUCTOR C RITERIA 32

    BEST PRACTICE Standards Some Additional Cost

    4. SM9 Dedicated Cycling LaneProvide cycling lanes, bicycle parking baysSome small additional cost.

    5. SM11 Heat Island Effect

    At least 25% of land area (normal local authority requirements is 15%).

    This will score additional 1 out of 5 points6. SM13 Heat Island Effect - Roof

    Select roof material with good SRI at least 75% of roof area (may beno cost or some cost)

    7. MR1 Materials Reuse and Selection

    Select low impact building material at least 2% to score 2nd point.Some cost possibly

    8. MR6 Construction Waste Management

    Recover at least 75% of construction waste e.g. Steel, waste concrete,pile cut-off, timber waste etc to score the 2nd point.

    2

    1

    1

    1

    1

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    33/51

    16 th November 2013

    CONSTRUCTOR C RITERIA 33

    BEST PRACTICE Standards Some Additional Cost

    4. WE1

    Rain Water Harvesting (for common areas)RWH to reduce common area water by 30%, score 2 out of 4Some small additional cost.

    5. WE2 Waste Water Recycling

    Recycle grey water. To keep cost down use grey water only forlandscape irrigation. 10% common water reduction score 1 out of 2points.

    6. Innovation Total available 7 Points

    Design bioswale 25% of building perimeterExternal shading device for 50% of glazed area (this will also help inEE1 and EE2)

    Recycle fire system water (minimal cost)Herb and Food garden

    7. IN2 Appoint GBI Facilitator

    Some cost. The advantage is the GBIF can advice on the bestmeasures with optimal cost for adoption.

    2

    1

    4

    1

    Total Score BEST Practice Standards 20 POINTS

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    34/51

    16 th November 2013

    CONSTRUCTOR C RITERIA 34

    Code Description Total Min .Standards

    GoodPractice

    BestPractice

    EE1 Min EE Performance 1 1 0 0

    EE2 Advanced EE Performance 12 0 0 2

    EE3 Renewable Energy 5 0 0 0

    EE4 External Lighting and Control 2 0 0 2

    EE5 Internet Connectivity 1 0 0 0

    EE6 Sustainable Maintenance & Building User Manual 2 0 2 0

    EQ1 Minimum Indoor Air Quality Performance 3 3 0 0

    EQ2 Volatile Organic Compounds Minimisation 2 0 0 0

    EQ3 Formaldehyde Minimisation 1 0 0 0

    EQ4 Daylighting 3 3 0 0

    EQ5 External Views 1 1 0 0

    EQ6 Sound Insulation 1 0 1 0

    EQ7 Post Occupancy Evaluation 1 0 1 0

    Sub Total 35 8 4 4

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    35/51

    16 th November 2013

    CONSTRUCTOR C RITERIA 35Code Description Total Min .

    StandardsGood

    PracticeBest

    Practice

    SM1 Site Selection & Planning 1 1 0 0

    SM2 Rehabilitation of Brownfield OR redevelopment ofExisting Building

    1 0 0 2

    SM3 Community Connectivity 4 0 4 0

    SM4 Earthworks Construction Activity Pollution Control 1 1 0 0

    SM5 QLASSIC Quality Assessment System for BuildingConstruction Works

    1 0 0 0

    SM6 Workers Site Amenities 1 1 0 0

    SM7 IBS Industrialised Building System 2 0 0 0

    SM8 Public Transportation Access 8 0 4 2

    SM9 Dedicated Cycling Network 2 0 0 2

    SM10 Stormwater Design Quantity & Quality Control 3 1 0 0

    SM11 Heat Island Effect Greenscape & Water Bodies 5 0 1 1

    SM12 Heat Island Effect - Hardscape 2 0 0 1

    SM13 Heat Island Effect Roof 1 0 0 1

    SM14 Composting 1 0 0 1

    Sub Total (cumulative) cumulative 68 12 13 14

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    36/51

    16 th November 2013

    CONSTRUCTOR C RITERIA 36

    Code Description Total Min .Standards

    GoodPractice

    BestPractice

    MR1 Materials Reuse and Selection 2 0 0 1MR2 Recycled Content Materials 2 0 1 0

    MR3 Regional Materials 2 0 2 0

    MR4 Sustainable Timber 2 0 0 0

    MR5 Storage and Collection of Recyclables 2 0 2 0

    MR6 Construction Waste Management 2 1 1 1WE1 Rainwater Harvesting 4 0 0 2

    WE2 Waste Water Recycling 2 0 0 1

    WE3 Water Efficient Irrigation & Landscaping 2 0 1 0

    WE4 Waste Efficient Fittings 4 0 0 0

    IN1 Innovation 7

    Bioswale 25% of perimeter 0 0 1

    External shading device for 50% of glazing area 0 0 1

    Recycle fire system water 0 0 1

    Herb & Food Garden 0 0 1

    IN2 GBI Facilitator 1 0 0 1

    Sub Total 100 13 20 24

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    37/51

    16 th November 2013

    CONSTRUCTOR C RITERIA 37

    Code Description Total Min .Standards

    GoodPractice

    BestPractice

    EE Energy Efficiency 23 1 2 4EQ Indoor Environmental Quality 12 7 2 0

    SM Sustainable Site Planning & Management 33 4 9 10

    MR Material & Resources 12 1 6 2

    WE Water Efficiency 12 0 1 3

    IN Innovation 8 0 0 5Sub Total 100

    Up Minimum Safety Standard 13

    Up to Good Practice Standards 33

    Up to Best Practice Standards 57

    Certified at Minimum or NO COST.

    Or additional cost < 1% of normal construction cost.

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    38/51

    16 th November 2013

    CONSTRUCTOR C RITERIA 38

    Description Total Min .Standards

    GoodPractice

    BestPractice

    EE Energy Efficiency 23 1 3 2EQ Indoor Environmental Quality 11 6 2 2

    SM Sustainable Site Planning & Management 39 12 6 2

    MR Material & Resources 9 1 6 2

    WE Water Efficiency 12 0 0 0

    IN Innovation 6 0 0 5Sub Total 100

    Min. Safety Standard 20

    Good Practice Std. 37

    Best Practice Std. 50

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    39/51

    S UMMARY OF G OVERNMENT INCENTIVES 39

    16 th November 2013

    Wa t e r P a s s i v eD e s i g n

    ????

    WaterEfficientFittings

    Rain WaterHarvesting

    OTTVCompliance(MS1525)

    RTTVCompliance(MS1525)

    Min openingsfor

    ventilation

    Min openingsfor daylighting

    L a n ds c a p e

    25% more

    Green Space(over currentrequirements)

    E n e r g y

    EnergyCalculationsto MS1525

    G r e e nB u i l d i n gCertification

    GBI Gold orPlatinum

    GBI Certified

    Already Mandatoryunder UBBLRecently

    Mandatory

    MakeMandatory

    The above areonly beginning for

    discussions

    Mandatory onlyon sectors orvia incentives

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    40/51

    16 th November 2013

    GBI Check ListDeliverables byConsultants,Clients,

    Contractors,Owner/Developer

    ESC Plan CheckList

    CoW

    Contractors,S.O.

    CWM Plan CheckList

    Contractors,

    S.O.

    CxS Plan &Check List

    Contractors,EngineerBriefing/Training

    Material CheckList

    Recycled MaterialReUsed MaterialRegional Material

    Quality CheckList

    ContractorCIDBQLASSIC

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    41/51

    16 th November 2013

    CWMP C HECK LIST 41

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    42/51

    CHECK LIST 42

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    43/51

    CWMP C HECK LIST 43

    16 th November 2013

    Date: Waste Form No.:

    Person In Charge: Container Type:

    No. of Trips Source of Waste

    Reuse RecycleDisposal Onsite OffsitePercentage of Waste in the Container

    Concrete % Insulation %Wood % Glass %Metals % Electrical %Cardboard % %

    Gypsum % %Plastic % %Destination of waste Waste Receipt No./Photo

    No.Sub-Contractor Signature

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    44/51

    MR2 R ECYCLED C ONTENT C HECK LIST 44

    16 th November 2013

    Recycled Content Materials to be used in this project:-Post Consumer1. Galvanized iron door frame2. Aluminum frame for window3. Mild steel railing to the staircase4. Dry wall partition*5. Carpet *6. Suspended ceiling*7. Reinforcement steel bars

    8. Cement with fly-ash mixturePre Consumer1. Waste Concrete2. Pile stump cut-off

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    45/51

    ESC C HECK LIST 45

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    46/51

    ESC C HECK LIST 46

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    47/51

    ESC C HECK LIST 47

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    48/51

    ESC C HECK LIST 48

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    49/51

    ESC C HECK LIST 49

    16 th November 2013

  • 8/10/2019 03 GBI Assessment Method for Construction (Ir Looi Hip Peu)

    50/51

    GREEN PAGES MALAYSIA 50

    [email protected], 10 th October-2012

    www.greenpagesmalaysia.com