04_peg_knut-1-day seminar on grouting and deep mixing-aecom

58
Pre-Excavation Grouting in Hard Rock Tunnelling AGS (HK) 1-day Seminar on Grouting and Deep Mixing 7 June 2014 By Knut F. Garshol

Upload: sjandali1

Post on 03-Oct-2015

15 views

Category:

Documents


0 download

DESCRIPTION

Seminar on grouting

TRANSCRIPT

  • Pre-Excavation Grouting in Hard Rock Tunnelling

    AGS (HK) 1-day Seminar on Grouting and Deep Mixing

    7 June 2014

    By Knut F. Garshol

    PresenterPresentation NotesGood Morning Everybody!

    Your interest in the subject of PEG is much appreciated, so let us get started without wasting your time

  • 2

    Headlines of this Presentation:

    1. Why Ground Water Control?

    2. Selection of Grout Mix

    3. Pre-Excavation Grouting, Execution Steps

    4. Special Aspects of PEG

    5. Project Reference HATS 2A 1. Grouting Results 2. Summing Up HATS2A

    6. CONCLUSION

  • Why Ground Water Control?

  • Rock material is impermeable

    GW contained in discontinuities

    GW is migrating on conductive channels

    Groundwater Movement in Rock

    4

    Jointed Rock

    Massive Rock

    Fault Zone

    Conductivity contrast is an important factor in GW control considerations

    PresenterPresentation NotesPlease Note: Rock is different to Soil!!

    Conductive channels within joint plane or along crossing of joint planes.

  • Surface Settlement

    Underground Safety and Working Conditions

    Environmental Impact

    Effects of GW Ingress

    5

  • 6

    Water in-rush at tunnel face

    1 ton

    PresenterPresentation NotesExamples of what can happen if probe drilling and PEG has NOT been executed!

    The 1 ton is just a mental reminder that at 50 bar, if you want to hold back the water pressure in 51 mm diameter borehole, you need a force of about 1000 kp. This kind of hydrostatic pressure is not something to play with. It is seriously difficult and may be dangerous (500 m of water head!).

  • Avoid such situations

    7

    Small lake became smaller

    Back to normal

    14 km Gardermoen Tunnel, Oslo, Norway

    PresenterPresentation Notes14 km Gardermoen Tunnel, Oslo NorwayMajor media-circus Extensive Post-groutingSupplemented by permanent water re-charge

  • 1st Joint Venture: Excavated 5% of 24.5 km Stopped by Water ingress Settled in Court New tender process

    Stage 1 finished by the new Contractors, BUT. With substantial delays

    Stage 2A: Drastically changed compared with Stage 1

    Experience from HATS Stage 1

    8

  • Manual handling of drill rods & packers

    9

    HATS Stage 1

  • Avoid Post Grouting!

    10

    HATS Stage 1

  • D&B Advantage: Drill Jumbo

    11

    HATS Stage 2A Probe hole hitting 15 bar water channel

  • Risk of major water in-rush practically eliminated

    Gives basically dry working conditions in tunnels

    Substantially improved stability in poor ground

    Less water to pump to surface

    Improved conditions for permanent lining works

    Benefits of GW-Control:

    12

    PresenterPresentation NotesIF PEG has to be done to prevent surface settlement, these Benefits are free BONUS

  • Selection of Grout Mix

  • Ground water control

    Ground stability improvement

    Sometimes: A combination of the above

    Requirements for success:

    Purposes of Grouting

    14

    A suitable grout must be injected into the ground, penetrating a sufficient ground volume to achieve

    the targeted effects

  • Basic Grouting Problem in rock

    15

  • Traditionally, locally available OPC w/c-ratio 3.0 to 1.0 mostly with Bentonite Unstable grout that needs "grout to refusal Low-quality and poor durability grout

    Today, use of micro cement w/c-ratio 1.0 and lower Stable and thixotropic grouts (no bleeding) Bentonite replaced by admixtures

    Selection of Grout-Mix

    16

  • High w/c-ratio gives lots of water to pump

    High bleeding requires "pump to refusal" Gives extreme materials spreading, locally No cement enters finer cracks in first step, due to

    clogging before pressure increase

    Practically complicated (variation of w/c-ratio)

    Conclusion: Time consuming

    Traditional Technology Disadvantages

    17

  • Stable, low viscosity, fixed w/c-ratio grout Allows dual stop criteria for injection

    Maximum pressure or maximum quantity per hole

    Allows high output and pressure from start Gives simultaneous penetration of small and large cracks and openings

    Conclusion: Time saved

    New Technology Advantages

    18

  • Always the Primary grout material

    Used as a suspension in water w/c-ratio typically between 0.45 1.5 (by weight)

    Wide range of additives and admixtures

    Wide range of cement types and properties

    Permeation capability depends on: Particle size of the cement used Viscosity (and cohesion) of the suspension Pressure stability of the suspension

    Generally about Cement

    19

  • Marsh Funnel Viscosity

    20

  • Mud Balance

    21

  • W/C-ratio = 1.0 mix

    Water-Cement Ratio

    22

    Control by Mud Balance

  • Pressure Stability

    23

  • Initial and final set time

    Strength development

    Final strength of injected grout

    Stability and durability in the ground? 17 projects, 59 km of tunnel:

    Average 37% ingress reduction (during 10 years)

    Other important properties

    24

  • Pre-Excavation Grouting Execution Steps

  • Drill & Blast with PEG

    26

    Probe Ahead

    Blasting

    Temporary Support

    Scaling, Mucking and Geological Mapping

    Measure Water Inflow

    Pre-Excavation Grouting

    After every 4th blast (typically)

  • Systematic Probe Drilling PEG if triggered

    Minimum 5 m overlap (more in poor ground)

    Grouting Stop Pressure 60-80 bar If not reached Stop on Quantity

    Stable Micro Fine Cement Grout, Only

    Colloidal Silica (where needed)

    Overlap provides tight bulkhead for next probe drilling and PEG fan VERY important

    27

    Execution Steps

  • Probe Holes Grout Holes Control Holes

    Tunnel Cross-Section

    Number of holes depend on tunnel span (1-1.5 m c/c).

    Grout hole length (15 to 33 m). Lookout distance (5.5 m).

    Schematic Layout of Drilling Pattern

    Grout Hole Pattern

    28

  • 29

    Advance approx. 4 m

    29

    Construction Method Drill & Blast + PEG

  • 30

    Rod Magazine

    (EXAMPLE) Tamrock TRH rod-handling-system

    Automatic Rod Handling

    Compared with manual rod handling:

    Double drilling output

    AND

    Improved Safety

    PresenterPresentation NotesAutomatic Rod Handling will double the drilling output AND improve work safety.

    HATS2A Example: This is highly recommended when you have to drill more than 420 km of boreholes for GW control.

  • 31

    Equipment Set-up - Simplified

    Colloidal Mixer

    Agitator

    High-Pressure Grout Pump

    Packer Electronic Flow and Pressure Recording

  • 32

    Contract 23 Unigrout Atlas Copco

    Contract 24 AMV / Hny

    3 Pumps and 3 Grout Lines Each

    The Real Deal

    PresenterPresentation NotesHATS2A Example: For pumping of over 5000 tons of cement and large quantities of CS, proper equipment is crucial!

  • Microfine Cement Colloidal Silica

    0.1

    mm

    OPC 0.1mm MC 0.03 mm

    CS 0.016 m

    Grouting Stop Criteria Microfine Cement

    Pressure: 60-80 bar Volume 2000 L

    Colloidal Silica Pressure: 40 bar Volume 750 L

    Colloidal Silica

    Microfine Cement Colloidal Silica

    33

    Grouting Materials

    PresenterPresentation NotesPrimary grout material is MFC NO OPC!

    CS when further grouting is required and MFC cannot penetrate.

  • Special Aspects of PEG

  • Safety of PEG works

    35

    Disposable Packer designed for 100 bar

    Hydraulic working basket

    Packers secured by

    chain

  • Disposable Packers & Lances

    36

  • Use of Standpipes in Poor Rock

    37

  • Bag Packers in Poor Rock

    38

  • Project Reference - HATS2A

    Sub-Sea Sewage Conveyance Hong Kong

    PresenterPresentation NotesLet us start with the

  • Harbour Area Treatment Scheme Stages 1 and 2A

    40

    North Point

    Aberdeen

    Sai Ying Pun

    Stonecutters Island

    LEGEND

    Outfall Tunnels (Completed) HATS Stage 1 Sewage Tunnels (Completed) HATS Stage 2A Sewage Tunnels

    PresenterPresentation NotesSlide shows Kowloon & HK Island: Densely populated and built up!

    Stage 1 of the sewage Project consisted of 24.5 km of mostly TBM excavation and was completed over 10 years ago.

    The yellow circle shows the TKO-area: Surface settlements encountered due to high GW ingress to the tunnel

    Stage 1 experienced Several face collapses in shear zones, costing many months of delay. Primary reason: Hydraulic collapse or erosion.

    Stage 2, the yellow line consists of 20 km of D&B excavation, currently 95% excavated.

  • HATS 2A Overview

    41

    North Point

    Stonecutters Island

    Sai Ying Pun

    Vertical shafts: 13 Total Tunnel Length: 20 km

    Victoria Habour

    Contract 23

    Contract 24

    PresenterPresentation NotesStage 2 is split in 2 Contracts as shown.

    In addition to the 20 km of tunneling, there are 13 vertical shafts.

  • Settlement Sensitive Reclaimed Land

    42

    North Point

    Sai Ying Pun

    LEGEND

    Coastline of Year 2005 HATS 2A Tunnels

    Aberdeen

    HONG KONG ISLAND

    PresenterPresentation NotesA lot of reclaimed land along the N-coast of HK-Island increases the risk of surface settlement and damage by GW drawdown.

  • Depth Below Sea Level

    43

    North Point Wan Chai East Central

    Sai Ying Pun Sandy Bay

    Cyberport

    Wah Fu

    Aberdeen

    Appx. 70 msl Appx. 120 msl

    Appx. 150 msl To Stonecutters Island

    North Point to Aberdeen

    Crossing of Victoria Harbour

    LEGEND Sea Soil Rock Appx. 140 msl

    Victoria Habour

    Stonecutters Island Sai Ying Pun

    PresenterPresentation NotesWill show the rock types on next slide!

  • Major Rock Types Encountered in HATS 2A Tunnels

    44

    Granitic Rock 66% of tunnel length Medium Grained Granite 50-percentile UCS = 180 MPa

    Volcanic Rock 34% of tunnel length Predominantly Volcanic Coarse

    Ash Crystal Tuff with subordinate Fine Ash Tuff

    50-percentile UCS = 240 MPa Highly variable joint intensity

    and orientation

    Granite 66%

    Tuff 34%

    Geological Map of Hong Kong (CEDD/GEO 2006)

    Granite/Tuff Contact Zone

    Tuff

    Granite

  • 45

    Granite/Tuff Contact Zone

    T T G

    G

    G T

  • Distribution of Residual Ingress Limits

    46

    0.0

    5.0

    10.0

    15.0

    20.0

    25.0

    30.0

    35.0

    40.0

    45.0

    50.0

    5 15 30 50

    L/min/100 m tunnel

    Perc

    ent o

    f Tun

    nel L

    engt

    hIn granite In tuff

    PresenterPresentation NotesThis slide shows the 4 Residual Ingress Limits on the horizontal axisAndHow they are applied along the tunnelSPLIT on sections in Granite and Tuff

    These limites were established based on numeric modelling and the risk level of surface settlement.

    For Granite, 40% fall within the relatively relaxed limit of 50 L/min/100 m. This is because of the 4 km of low-risk (regarding settlement) tunneling crossing beneath Victoria Harbour.

    The relative tunnel lengths in Granite and Tuff are almost the same for the 15 and 30 L/min/100 m limits.

    The excavation length in Tuff within the strictest ingress limit is about 3X greater than for tunnel sections in granite.

    As a result, tunnel sections in Tuff faced more demanding PEG-Works because of 1) Higher degree of rock jointing and 2) 3X longer section within strictest ingress limit.

  • Grouting Results

  • Residual Ingress to Excavated Tunnels

    48

    Rock Type Granite Avg L/min/100 m

    Tuff Avg L/min/100 m

    Maximum Ingress Limit 30.2 16.9

    Actual Residual overall ingress 6.5 7.5

    Sections within limit (92%) 4.5 6.0

    Sections failed (8%) 45.3 21.6

    Average values Weighted against tunnel length

    PresenterPresentation NotesFirst: The Measured ingress to excavated tunnel sections!

  • In Granite: Very Wet & Very Dry Sections

    49

    LEGEND HATS 2A Alignment

    Tunnel section 413 m long: Measured ingress from all 1st stage grout holes: = 9,200 L/min/100 m tunnel Measured after excavation: About 1.0 L/min/100 m (= 99.99% reduction) Cement Consumption: 1549 kg/m (= 5.7 X the granite average)

    Tunnel section about 1500 m: Almost dry (hardly any PEG required) Cement Consumption < 50 kg/m

    PresenterPresentation NotesIllustration of the wide range of conditions encountered!

  • Probe Drilling in the Wet section

    50

    1200 L/min 15 bar pressure

    PresenterPresentation NotesNote that excavation into the same channel without grouting => Would easily produce 5X more GW ingress (6 m3/min).

  • Filled Open Joints

    51

  • Filled Open Joints - Detail

    52

    20 MPa UCS

    PresenterPresentation NotesNote the brittle fracturing of the MFC grout illustrating the high compressive strength.

    Early grout strength is Important for prevention of blow-out when excavating into treated area.

  • 13 September 2013

    Practically Dry Tunnel

    53

  • Summing Up HATS2A

  • Micro Fine Cement ONLY, supplemented by Colloidal Silica

    Verification of result by Control Holes before further excavation

    Tight face bulkhead is a Must especially in soft ground

    27% of tunnel length required < 5 L/min/100 m tunnel

    92% of excavated tunnels well below ingress limits

    The Tuff required 78% more drilling ahead AND 3.7 X more Colloidal Silica than in Granite

    Two Main Reasons for the Success: D&B excavation Modern PEG technology + Re-measurable quantities for payment

    55

    Summing Up HATS2A

    PresenterPresentation NotesBasis for Success Reasons Claim:

    Stage 1: Several face collapses and months in delay, caused by problems of drilling necessary holes and outdated grouting technology. Settlement problems on surfaceStage 2: Zero face collapse problems. Ingress limits basically satisfied. Zero settlement problems on surface.

  • CONCLUSION

  • CONCLUSION

    57

    Technology for Ground Water Control by PEG for Practically Dry Tunnels is currently available

    In Hard Rock Tunnelling:

    Very Strict Ingress Limits will require: Excavation by Drill and Blast

    Micro Fine Cement Colloidal Silica

  • [email protected]

    Pre-Excavation Grouting in Hard Rock TunnellingHeadlines of this Presentation:Why Ground Water Control?Groundwater Movement in RockEffects of GW IngressWater in-rush at tunnel face Avoid such situationsExperience from HATS Stage 1Manual handling of drill rods & packersAvoid Post Grouting!D&B Advantage: Drill JumboBenefits of GW-Control:Selection of Grout MixPurposes of GroutingBasic Grouting Problem in rockSelection of Grout-MixTraditional Technology DisadvantagesNew Technology AdvantagesGenerally about CementMarsh Funnel ViscosityMud BalanceWater-Cement RatioPressure StabilityOther important propertiesPre-Excavation Grouting Execution Steps Drill & Blast with PEGExecution StepsGrout Hole PatternSlide Number 29Automatic Rod HandlingEquipment Set-up - SimplifiedThe Real DealGrouting MaterialsSpecial Aspects of PEGSafety of PEG worksDisposable Packers & LancesUse of Standpipes in Poor RockBag Packers in Poor RockProject Reference - HATS2AHarbour Area Treatment Scheme Stages 1 and 2AHATS 2A OverviewSettlement Sensitive Reclaimed LandDepth Below Sea LevelMajor Rock Types Encountered in HATS 2A TunnelsSlide Number 45Distribution of Residual Ingress LimitsGrouting ResultsResidual Ingress to Excavated TunnelsIn Granite: Very Wet & Very Dry SectionsProbe Drilling in the Wet sectionFilled Open JointsFilled Open Joints - DetailPractically Dry Tunnel Summing Up HATS2A Summing Up HATS2ACONCLUSIONCONCLUSIONSlide Number 58