Oracle EBS WMS Implementation
Date: 18 August 2014 Page 1
Document Control Week Off: 9-June-2014
Project Name Oracle R12 WMS Implementation
Document Status Active
Reported Date 13/June/2014
Prepared By Zensar
Version 1.0
Reviewed By Philip Bench/Krishna G/Jacob C
High Level Status
Track Status Comments Overall On Track
Resources On Track
Issues / Risks On Track, Risk Reservation issue in WMSCRP instance
On Track On Track, Risk Off Track, Significant Risk
Milestone Start Date End Date Status Comment
Project Definition 27-Jan-2014 31-Jan-2014 100 % Completed usage matrix .
Setup & Configuration 03-Feb-2014 21-Feb-2014 100 % Validate onhand receipt transactions interface (81477 rec)
ARFC Design 24-Feb-2014 04-Apr-2014 60 % Functional Design & Setup in progress
ARFC CRP 14-Apr-2014 02-May-2015 100 %CRP testing completed on WMSTST instanceFrom 10-Apr-14 to 08-May-14
ARFC Development & IT Testing 17-Mar-2014 11-Jul-2014 60 % Technical development status attached
ARFC SIT 19-May-2014 30-May-2014 05 % Instance available. Transaction being cleared
Retrogression SIT 2-Jun-2014 13-Jun-2014
ARFC Training 09-Jun-2014 11-Jul-2014
ARFC UAT 14-Jul-2014 25-Jul-2014
ARFC Data migration 28-Jul-2014 01-Aug-2014
Modification & Issue Resolution 21-Jul-2014 01-Aug-2014
Cutover 04-Aug-2014 08-Aug-2014
ARFC Go Live 11-Aug-2014 --
Post go live support 11-Aug-2014 5-Sep-2014
-
8/11/2019 06 13 2014 WMS Weekly Report
2/6
Oracle EBS WMS Implementation
Date: 18 August 2014 Page 2
Progress
Current Week
Activities:
Bhaskar Wanjari1. Development T59A: Shipping : Pre-pack doc (Packing instructions, Battery
labels) for ARFC ( W105).
Harshit Verma1. MWA development T67: Carton details required for Ship confirm
i.e. value > 0 (Dims) ( W109) .
Praveen Yandagoudar1. Code Migration to SIT instance .
Tejas Pawar1. Support to SR 3-9046929981 : Uncosted Material transaction stuck with Error
- Cleared all the pending ,stuck transaction for all organization.
- Closed the SR .2. Support to SR 3-9056964921 ,PO Receiving Issue
- Worked with Oracle , Investigated the available patches. - Finalized a patch to resolve this issue,Followup with oracle on call and
received the password to download the patch
3 Analyze the oracle functionality for issue W99 T167: Capture Shipping label andPacking slip details during LPN Pack & trigger the same reports during thetransaction .
Next Week
Activities: 1. WMS Setup & configuration (WMSTST)2. WMS Setup (WMSSIT)
3. CRP issue resolution & testing4. Discuss on conversion plan activities5. Technical Development activities
Task List :
Smart sheet count: Requirements and issues logged in CRP testing
Category Count Closed
Conversion 4
Setup 7 1
-
8/11/2019 06 13 2014 WMS Weekly Report
3/6
Oracle EBS WMS Implementation
Date: 18 August 2014 Page 3
SR 4 2
Development 9
Testing 6 1
Followup 3
-
8/11/2019 06 13 2014 WMS Weekly Report
4/6
Oracle EBS WMS Implementation
: 18 August 2014 Page 4
hnical Development Status:
Gap # Deliverables MD 050 MD 070 CodeUnitTesting
Remark
1 W97To capture serial number during packing i.e. before shipconfirm. To customize the pack page.
100% 100% 100% 90% Waiting for feedback
2 W108Capture additional serial number at pack for serial controlleditems 100% 100% 90% 90%
MWA Work in Progress forAt Receipt Items
3 W16Ability to enter weight, dims into system at box level.Outbound dimensions/weight per outbound box incl type(pallet/box)
100% 100% 100% 100% Waiting for feedback
4 W57 Ability to prepare Export docs during Pack (last step in Pack) 100% 100% 100% 100% Waiting for feedback
5 W99Capture Shipping label and Packing slip details during LPNPack & trigger the same reports during the transaction
100% 100% 100% 100% Waiting for feedback
6 W72Capability to prevent Over issue and Under issue ofcomponents
On hold
7 W83 Prevent WIP move if all components are not issues for the job On hold
8 W96Serial number check before completing job. To scan part serial
number & box serial number, validate then pack100% 100% 100% 100% Waiting for feedback
9 W103 Receiving : Customization to request labels (Quantity) On hold
10 W105 Shipping : Pre-pack doc (Packing instructions, Battery labels) On hold
11 W95 Marc GT integration On hold
12 Data Migration :- On hand Conversion 100% 100% 100% 100% Done for CRP
13 W109T67: Carton details required for Ship confirm i.e. value > 0(Dims). To be profile driven (e.g. by site or by orders like dropship)
14 W70WIP Move Assembly - Provide the capability to default firstoperation and Last operation in Mobile handheld
-
8/11/2019 06 13 2014 WMS Weekly Report
5/6
Oracle EBS WMS Implementation
: 18 August 2014 Page 5
# Gap # Deliverables MD 050 MD 070 CodeUnitTesting
Remark
15 W112T147: MCS, Guad, CTO need to be able to ship by Delivery(Quick Ship) on serialized (SO issue) product)
25% 75% 90% 50%1. Modified the code2. Initial Testing In Progress
16 W110T135: Move Any LPN page - Receipt Putaway, provide LOV forsuggested drop To Locator where onhand quantity exist
17 W111 T137: Receipt page - Modify sub-I and locator field asmandatory
18 W113 T138: Misc transaction MWA form need to add reference field
19 W114 T139: Sub-i transfer MWA form need to add reference field
20T149: Script to update PO receipt routing from Direct toStandard for DAYTON DC, Trimble Corvallis, Trimble Mexico,EERSEL &
25% 25% 10% Development In Progress
21T152: Script update all open Work Orders (sub-inventorysupply, completion) for Dayton DC, Gaud.
25% 25% 10% Development In Progress
22T153: Script to update locator pick / drop seq for Dayton DC,MCS, GUAD, CTO & ERFC
25% 75% 50% Development In Progress
-