  • 8/11/2019 06 13 2014 WMS Weekly Report

    1/6

    Oracle EBS WMS Implementation

    Date: 18 August 2014 Page 1

    Document Control Week Off: 9-June-2014

    Project Name Oracle R12 WMS Implementation

    Document Status Active

    Reported Date 13/June/2014

    Prepared By Zensar

    Version 1.0

    Reviewed By Philip Bench/Krishna G/Jacob C

    High Level Status

    Track Status Comments Overall On Track

    Resources On Track

    Issues / Risks On Track, Risk Reservation issue in WMSCRP instance

    On Track On Track, Risk Off Track, Significant Risk

    Milestone Start Date End Date Status Comment

    Project Definition 27-Jan-2014 31-Jan-2014 100 % Completed usage matrix .

    Setup & Configuration 03-Feb-2014 21-Feb-2014 100 % Validate onhand receipt transactions interface (81477 rec)

    ARFC Design 24-Feb-2014 04-Apr-2014 60 % Functional Design & Setup in progress

    ARFC CRP 14-Apr-2014 02-May-2015 100 %CRP testing completed on WMSTST instanceFrom 10-Apr-14 to 08-May-14

    ARFC Development & IT Testing 17-Mar-2014 11-Jul-2014 60 % Technical development status attached

    ARFC SIT 19-May-2014 30-May-2014 05 % Instance available. Transaction being cleared

    Retrogression SIT 2-Jun-2014 13-Jun-2014

    ARFC Training 09-Jun-2014 11-Jul-2014

    ARFC UAT 14-Jul-2014 25-Jul-2014

    ARFC Data migration 28-Jul-2014 01-Aug-2014

    Modification & Issue Resolution 21-Jul-2014 01-Aug-2014

    Cutover 04-Aug-2014 08-Aug-2014

    ARFC Go Live 11-Aug-2014 --

    Post go live support 11-Aug-2014 5-Sep-2014

  • 8/11/2019 06 13 2014 WMS Weekly Report

    2/6

    Oracle EBS WMS Implementation

    Date: 18 August 2014 Page 2

    Progress

    Current Week

    Activities:

    Bhaskar Wanjari1. Development T59A: Shipping : Pre-pack doc (Packing instructions, Battery

    labels) for ARFC ( W105).

    Harshit Verma1. MWA development T67: Carton details required for Ship confirm

    i.e. value > 0 (Dims) ( W109) .

    Praveen Yandagoudar1. Code Migration to SIT instance .

    Tejas Pawar1. Support to SR 3-9046929981 : Uncosted Material transaction stuck with Error

    - Cleared all the pending ,stuck transaction for all organization.

    - Closed the SR .2. Support to SR 3-9056964921 ,PO Receiving Issue

    - Worked with Oracle , Investigated the available patches. - Finalized a patch to resolve this issue,Followup with oracle on call and

    received the password to download the patch

    3 Analyze the oracle functionality for issue W99 T167: Capture Shipping label andPacking slip details during LPN Pack & trigger the same reports during thetransaction .

    Next Week

    Activities: 1. WMS Setup & configuration (WMSTST)2. WMS Setup (WMSSIT)

    3. CRP issue resolution & testing4. Discuss on conversion plan activities5. Technical Development activities

    Task List :

    Smart sheet count: Requirements and issues logged in CRP testing

    Category Count Closed

    Conversion 4

    Setup 7 1

  • 8/11/2019 06 13 2014 WMS Weekly Report

    3/6

    Oracle EBS WMS Implementation

    Date: 18 August 2014 Page 3

    SR 4 2

    Development 9

    Testing 6 1

    Followup 3

  • 8/11/2019 06 13 2014 WMS Weekly Report

    4/6

    Oracle EBS WMS Implementation

    : 18 August 2014 Page 4

    hnical Development Status:

    Gap # Deliverables MD 050 MD 070 CodeUnitTesting

    Remark

    1 W97To capture serial number during packing i.e. before shipconfirm. To customize the pack page.

    100% 100% 100% 90% Waiting for feedback

    2 W108Capture additional serial number at pack for serial controlleditems 100% 100% 90% 90%

    MWA Work in Progress forAt Receipt Items

    3 W16Ability to enter weight, dims into system at box level.Outbound dimensions/weight per outbound box incl type(pallet/box)

    100% 100% 100% 100% Waiting for feedback

    4 W57 Ability to prepare Export docs during Pack (last step in Pack) 100% 100% 100% 100% Waiting for feedback

    5 W99Capture Shipping label and Packing slip details during LPNPack & trigger the same reports during the transaction

    100% 100% 100% 100% Waiting for feedback

    6 W72Capability to prevent Over issue and Under issue ofcomponents

    On hold

    7 W83 Prevent WIP move if all components are not issues for the job On hold

    8 W96Serial number check before completing job. To scan part serial

    number & box serial number, validate then pack100% 100% 100% 100% Waiting for feedback

    9 W103 Receiving : Customization to request labels (Quantity) On hold

    10 W105 Shipping : Pre-pack doc (Packing instructions, Battery labels) On hold

    11 W95 Marc GT integration On hold

    12 Data Migration :- On hand Conversion 100% 100% 100% 100% Done for CRP

    13 W109T67: Carton details required for Ship confirm i.e. value > 0(Dims). To be profile driven (e.g. by site or by orders like dropship)

    14 W70WIP Move Assembly - Provide the capability to default firstoperation and Last operation in Mobile handheld

  • 8/11/2019 06 13 2014 WMS Weekly Report

    5/6

    Oracle EBS WMS Implementation

    : 18 August 2014 Page 5

    # Gap # Deliverables MD 050 MD 070 CodeUnitTesting

    Remark

    15 W112T147: MCS, Guad, CTO need to be able to ship by Delivery(Quick Ship) on serialized (SO issue) product)

    25% 75% 90% 50%1. Modified the code2. Initial Testing In Progress

    16 W110T135: Move Any LPN page - Receipt Putaway, provide LOV forsuggested drop To Locator where onhand quantity exist

    17 W111 T137: Receipt page - Modify sub-I and locator field asmandatory

    18 W113 T138: Misc transaction MWA form need to add reference field

    19 W114 T139: Sub-i transfer MWA form need to add reference field

    20T149: Script to update PO receipt routing from Direct toStandard for DAYTON DC, Trimble Corvallis, Trimble Mexico,EERSEL &

    25% 25% 10% Development In Progress

    21T152: Script update all open Work Orders (sub-inventorysupply, completion) for Dayton DC, Gaud.

    25% 25% 10% Development In Progress

    22T153: Script to update locator pick / drop seq for Dayton DC,MCS, GUAD, CTO & ERFC

    25% 75% 50% Development In Progress

  • 8/11/2019 06 13 2014 WMS Weekly Report

    6/6