07-05-17 weekly construction activities - mgm springfield · 7/7/17 8:46 am page 3 of 3 zone...

4
7/7/17 8:46 AM Page 1 of 3 MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -7/5/17-7/18/17 WORK HOURS: 7:00 AM - 7:00 PM FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT: [email protected] FULL CONSTRUCTION BUILD OUT ZONE LOCATION STATUS 1 95 and 101 State Street 95 State Interior fit out is underway along with interior demolition work/cleanup and floor leveling. Window delivery and installation has begun. Exterior façade work is underway. 2 Hotel The following activities are ongoing: Above ground storm piping, spray on fireproofing, exterior framing, power distribution,and interior framing lay out. 3 Casino The following activities are ongoing: Above ground storm piping, exterior framing, overhead mechanical, electrical and plumbing (MEP) installation, roofing, interior framing, fire protection, power distribution, and casino mock up build out. 4 Da Vinci Park No work anticipated 5 Dave's Furniture No work anticipated 6 Armory No work anticipated 7 Plaza No work anticipated 8 Church No work anticipated 9 Entertainment The following activities are ongoing: spray on fireproofing, temporary power and lighting installation, exterior framing, roofing, and scaffold erection. 10 Parking Garage The following activities are ongoing: Above ground mechanical, electrical, and plumbing (MEPs) installation, waterproofing and caulking, interior masonry wall erection in electric / IDF rooms, painting and line striping, installation of storefront, and elevator construction. 11 Support Area No work anticipated 12 MGM Way Receiving deliveries and staging of material/equipment. STREET WORK State Street No work anticipated

Upload: others

Post on 11-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 07-05-17 Weekly Construction Activities - MGM Springfield · 7/7/17 8:46 AM Page 3 of 3 ZONE LOCATION STATUS York Street Lot Construction material staging is underway. Zorzi Lot Established

7/7/178:46AM Page1of3

MGM SPRINGFIELD CONSTRUCTION ACTIVITIES -7/5/17-7/18/17

WORK HOURS: 7:00 AM - 7:00 PM

FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT: [email protected]

FULL CONSTRUCTION BUILD OUT

ZONE LOCATION STATUS

1 95 and 101 State Street 95 State Interior fit out is underway along with interior demolition work/cleanup and floor leveling. Window delivery and installation has begun. Exterior façade work is underway.

2 Hotel The following activities are ongoing: Above ground storm piping, spray on fireproofing, exterior framing, power distribution,and interior framing lay out.

3 Casino The following activities are ongoing: Above ground storm piping, exterior framing, overhead mechanical, electrical and plumbing (MEP) installation, roofing, interior framing, fire protection, power distribution, and casino mock up build out.

4 Da Vinci Park No work anticipated

5 Dave's Furniture No work anticipated

6 Armory No work anticipated

7 Plaza No work anticipated

8 Church No work anticipated

9 Entertainment The following activities are ongoing: spray on fireproofing, temporary power and lighting installation, exterior framing, roofing, and scaffold erection.

10 Parking GarageThe following activities are ongoing: Above ground mechanical, electrical, and plumbing (MEPs) installation, waterproofing and caulking, interior masonry wall erection in electric / IDF rooms, painting and line striping, installation of storefront, and elevator construction.

11 Support Area No work anticipated

12 MGM Way Receiving deliveries and staging of material/equipment.

STREET WORK

State Street No work anticipated

Page 2: 07-05-17 Weekly Construction Activities - MGM Springfield · 7/7/17 8:46 AM Page 3 of 3 ZONE LOCATION STATUS York Street Lot Construction material staging is underway. Zorzi Lot Established

7/7/178:46AM Page2of3

ZONE LOCATION STATUS

Main Street

Reflectorized drums will intermittently be placed in the south bound lane to shift traffic from 6am-6pm Monday through Friday to allow for the unloading of certain materials onto the construction site. The barrels will be moved out of the road at the end of each day to allow parking during non-working hours. Two way traffic will be maintained at all times and two police details will be present. This traffic shift is currently underway.

Road work to adjust a curb box at the corner of Main Street & Stockbridge Street is anticipated to take place within the next two weeks. A police detail will be present for this work and two-way traffic will be maintained.

Union Street

Utility work is taking place at the intersections of Union, Howard West, and Bliss Street with East Columbus Ave. During this work, Union Street will be closed to through traffic from Main Street to East Columbus Avenue. Access to Pride Gas Station, the Colvest Building, and 55 State Street will be maintained at all times. Signage will be in place to direct patrons to business’ on Main Street via State Street and to provide updates and direction for drivers in the area.

East Columbus Ave will be open to through traffic throughout the project. At times, lanes will need to be reduced to accommodate utility crossings at the intersections. Police details will be present throughout the summer to help traffic flow as efficiently as possible.

East Columbus Avenue Work is underway to repair/replace portions of water main piping. A police detail is anticipated.

Bliss Street Work is underway to repair/replace portions of water main piping. A police detail is anticipated.

Howard Street Turn Around No work anticipated

Howard Street Work is underway to repair/replace portions of water main piping. A police detail is anticipated.

UTILITY ACTIVITY

UTILITY PROVIDER WORK TO BE PERFORMED

Eversource No work anticipated

Verizon No work anticipated

Comcast No work anticipated

Columbia Gas No work anticipated

Springfield Water & Sewer No work anticipated

MISCELLANEOUS ACTIVITY

LOCATION WORK TO BE PERFORMED

Page 3: 07-05-17 Weekly Construction Activities - MGM Springfield · 7/7/17 8:46 AM Page 3 of 3 ZONE LOCATION STATUS York Street Lot Construction material staging is underway. Zorzi Lot Established

7/7/178:46AM Page3of3

ZONE LOCATION STATUS

York Street Lot Construction material staging is underway.

Zorzi Lot Established as parking for craft labor foreman and superintendents.

Offsite Parking Lots Craft labor parking has been established at the Mass Mutual Center parking garage and 1870 E. Columbus Ave.

Page 4: 07-05-17 Weekly Construction Activities - MGM Springfield · 7/7/17 8:46 AM Page 3 of 3 ZONE LOCATION STATUS York Street Lot Construction material staging is underway. Zorzi Lot Established

MAIN STREET

EAST COLUMBUS AVENUE

HOW

ARD

TURN

ARO

UND

195/101 STATE

2HOTEL

3CASINO

12MGM WAY

7PLAZA

6ARMORY

8CHURCH

5DAVE’S

FURNITURE

4DA VINCI

PARK

9ENTERTAINMENT

10PARKING GARAGE

11SUPPORT

AREA

BLIS

S ST

REET

HOW

ARD

STRE

ET

TRAFFIC WILL BE INTERMITTENTLY SHIFTED FROM THE SOUTHBOUND LANE BETWEEN 6AM-6PM DURING THE WORK WEEK TO ALLOW FOR MATERIALS LOADING.

TWO WAY TRAFFIC WILL BE MAINTAINED AND A POLICE DETAIL IS ANTICIPATED.

STAT

E ST

REET

ROAD WORK TO ADJUST A CURB BOX AT THE CORNER OF MAIN ST. & STOCKBRIDGE ST. IS ANTICIPATED TO TAKE PLACE WITHIN THE NEXT TWO WEEKS.

A POLICE DETAIL WILL BE PRESENT FOR THIS WORK AND TWO-WAY TRAFFIC WILL BE MAINTAINED.

UNIO

N ST

REET

BEGINNING IN MID JUNE AND CONTINUING THROUGHOUT THE SUMMER, UTILITY WORK WILL BE TAKING PLACE AT THE INTERSECTIONS OF UNION, HOWARD WEST, AND BLISS STREET WITH EAST COLUMBUS AVE. DURING THIS WORK, UNION STREET WILL BE CLOSED TO THROUGH TRAFFIC FROM MAIN STREET TO EAST COLUMBUS AVENUE. ACCESS TO PRIDE GAS STATION, THE COLVEST BUILDING, AND 55 STATE STREET WILL BE MAINTAINED AT ALL TIMES. SIGNAGE WILL BE IN PLACE TO DIRECT PATRONS TO BUSINESSES ON MAIN STREET VIA STATE STREET AND TO PROVIDE UPDATES AND DIRECTION FOR DRIVERS IN THE AREA.

EAST COLUMBUS AVE WILL BE OPEN TO THROUGH TRAFFIC THROUGHOUT THE PROJECT. AT TIMES, LANES WILL NEED TO BE REDUCED TO ACCOMMODATE UTILITY CROSSINGS AT THE INTERSECTIONS. POLICE DETAILS WILL BE PRESENT THROUGHOUT THE SUMMER TO HELP TRAFFIC FLOW AS EFFICIENTLY AS POSSIBLE.