1 aia update on integrated project delivery lean construction institute design forum january 8 2009...

47
1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

Upload: brook-wright

Post on 11-Jan-2016

217 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

1

AIA Update on Integrated Project Delivery

Lean Construction Institute Design ForumJanuary 8 2009

Markku Allison, AIA

Page 2: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

2

position statement | 2007

Page 3: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

3

Position No. 26: Project Delivery

The AIA believes that every project delivery process must address the quality, cost-effectiveness, and sustainability of our built environment. This

can best be effected through industry-wide adoption of an integrated approach to project delivery methodologies characterized by early

involvement of owners, designers, constructors, fabricators and end user/operators in an environment of effective collaboration and open

information sharing. The AIA also believes that an architect is well qualified to serve as a leader on integrated project delivery teams. The AIA further

believes that evolving project delivery processes require integration of education and practice in design and construction, both within and across

disciplines.

Page 4: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

4

Ramifications

• Applies to all projects• Integrated, collaborative models are best

• Early involvement is important• Open information sharing is important

• Design and construction education integration should happen• Leadership may involve more than just the architect

Page 5: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

5

sea change for the Institute

Page 6: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

6

integrated project delivery guide | 2007.11.05

Page 7: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

7

ipdg | key ideas

Principles of Integrated Project Delivery(general)

Mutual Respect and TrustMutual Benefit and Reward

Collaborative Innovation and Decision MakingEarly Involvement of Key Participants

Early Goal DefinitionIntensified Planning

Open CommunicationAppropriate Technology

Organization and Leadership

Page 8: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

8

ipdg | key ideas

Page 9: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

9

ipdg | key ideas

IPD principles can be applied to a variety of contractual arrangements

Page 10: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

10

market interest (2009.01.08)

Owner Designer ConstructorSubcontractor EngineerSystems Supplier AttorneyInsurer StudentEducatorNone of the AboveGRAND TOTAL

223279711930310

1487332542114499518

199117926

12%44%11%2%8%2%3%1%3%3%

11%100%

Page 11: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

11

research

Page 12: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

12

Nearly 80% of respondents indicate they are aware of IPD; about half of respondents view themselves as knowledgeable or experienced.

Confidential

Base: Total Respondents n=2051

Page 13: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

13

Based on the definition, reduction of conflict is the IPD attribute of greatest value to project teams.

Confidential

Base: Total Respondents n=2051

Page 14: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

14

Based upon the definition, early involvement of key participants is the most important principle of IPD.

Confidential

Base: Total Respondents n=2051

Page 15: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

15

Of the potential barriers provided to respondents, lack of legal precedent and industry partner skill sets are the greatest barriers to pursuing IPD.

Confidential

Base: Knowledgeable/Experienced with IPD n=1074

Page 16: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

16

Lack of trust, lack of skills, lack of information about process and lack of appropriate technology are not significant barriers for most segments.

Confidential

Owner (n=137)

Architect (n=708)

Engineer (n=60)

Contractor (n=137)

Sub-contractor

(n=32)*

Know-ledgeable (n=583)

Experienced (n=480)

Lack of Legal Precedent 61% 67% 57% 52% 53% 76% 47%Industry Partner Support Not There 47% 58% 63% 52% 59% 62% 48%Lack of Insurance 46% 57% 45% 39% 53% 62% 41%Procurement Constraints/Limitations 56% 54% 43% 48% 44% 58% 45%Industry Partner Skill Sets 53% 64% 67% 50% 63% 67% 53%Uncertainty About Risk 48% 59% 53% 39% 38% 67% 39%Uncertainty about Compensation Structure

47% 56% 60% 38% 31% 65% 37%

Lack of Trust in Industry Partners 38% 36% 33% 24% 26% 38% 30%Lack of Necessary Skills 34% 25% 24% 10% 22% 29% 18%Lack of Info About Process 29% 28% 20% 25% 36% 32% 22%Lack Appropriate Technology 34% 21% 18% 13% 22% 26% 17%

Owners are the least likely to believe that lack of support by the industry is a barrier to IPD. The remaining segments view it as a barrier.

Page 17: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

17

Lack of trust, lack of skills, lack of information about process and lack of appropriate technology are not significant barriers for most segments.

Confidential

Owner (n=137)

Architect (n=708)

Engineer (n=60)

Contractor (n=137)

Sub-contractor

(n=32)*

Know-ledgeable (n=583)

Experienced (n=480)

Lack of Legal Precedent 61% 67% 57% 52% 53% 76% 47%Industry Partner Support Not There 47% 58% 63% 52% 59% 62% 48%Lack of Insurance 46% 57% 45% 39% 53% 62% 41%Procurement Constraints/Limitations 56% 54% 43% 48% 44% 58% 45%Industry Partner Skill Sets 53% 64% 67% 50% 63% 67% 53%Uncertainty About Risk 48% 59% 53% 39% 38% 67% 39%Uncertainty about Compensation Structure

47% 56% 60% 38% 31% 65% 37%

Lack of Trust in Industry Partners 38% 36% 33% 24% 26% 38% 30%Lack of Necessary Skills 34% 25% 24% 10% 22% 29% 18%Lack of Info About Process 29% 28% 20% 25% 36% 32% 22%Lack Appropriate Technology 34% 21% 18% 13% 22% 26% 17%

Owners are the least likely to believe that lack of support by the industry is a barrier to IPD. The remaining segments view it as a barrier.

Page 18: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

18

1052 projects: over 30% behind schedule and over budget

Source: AIA Survey 2008

Page 19: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

19

Source: AIA Survey 2008

38% of DBB projects behind schedule22% of IPD projects behind schedule

62% of DBB projects on or ahead78% of IPD projects on or ahead

Page 20: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

20

Source: AIA Survey 2008

37% of DBB projects over budget25% of IPD projects over budget

63% of DBB projects on or under budget75% of IPD projects on or under budget

Page 21: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

21

488 IPD projects: overages drop by almost 2/3

Source: AIA Survey 2008

90% of IPD projects on or ahead of schedule86% of IPD projects on or under budget

Page 22: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

22

BIM appears to be influential in the success of IPD projects.

Confidential

Base: Experienced with IPD n=488Base: Experienced/Project included BIM n=254

Page 23: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

23

Sustainability goals are common in IPD projects, and appear to be influential in achieving sustainability goals.

Confidential

Base: Experienced with IPD n=488Base: Experienced/Project included

Sustainability Goals n=336

Page 24: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

24

Source: AIA Survey 2008

11%

16%

4%

10%

14%

Page 25: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

25

Anecdotal but driving to quantitativeIPD seen as influential in accomplishing sustainability goals

Collaborative models establish stronger goalsImplementing complex sustainability strategies is best accomplished

with more stakeholders

Connections to Sustainability

Page 26: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

26

50to50 | 2007.12.12

Page 27: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

27

50 specific strategies to move toward carbon reduction.A how-to resource for practitioners and others.

Text, diagrams, and images.

50to50

Page 28: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

28

agreements

Page 29: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

29

Transitional Forms | B195, A195, A295More recognizable, familiar

Utilizes GMP contract with pre-construction services

Immediately familiar and usable within today’s environment

SPE – Full Integration | C195More provocative, unique approach

Single Purpose Entity (Limited Liability Company)

All for one and one for all

IPD Agreements – Two Approaches

Page 30: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

30

GMP Amendment

Owner Architect Agreement

Business Terms

General Conditions

All Responsibilities of Owner, Architect and Contractor for All

Phases of Design and Construction

Owner Contractor Agreement

Business Terms

A295 Transitional IPD Forms

Page 31: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

31

Owner

C

C C

C

A CM

SPE

SPE Contract Structure

1

1. SPE Agreement

2. SPE Member Services Agreement

2 2

3. SPE OwnerAgreement

3

4. Non-Member Agreement

Page 32: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

32

• Structures the SPE

• Provides for SPE management

• Includes procedure for establishing Target Cost

• Contains Dispute Resolution provision

CM

O

A

Owner

Construction ManagerArchitect

SPE

SPE Agreement – C195

Page 33: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

33

• Owner Funds SPE

• Owner Audit Rights

• Limitation of Liability, Indemnification and Waiver of Claims

• All disputes resolved under SPE dispute resolution provisionsCMA

SPE

Owner

SPE Owner Agreement – C196

Page 34: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

34

• Services at Cost

• Incentive and Goal Achievement Comp.

• SPE has Audit Rights

• Limitation of Liability, Indemnification and Waiver of Claims

• All disputes resolved under SPE dispute resolution provisions

SPE

CMA

Owner

SPE Member Services Agreement – C196

Page 35: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

35

• With Non-Member consultants and contractors

• Contracts for stipulated sum or GMP

C

C C

C

Owner

SPE

CMA

SPE Non-Member Agreements

Page 36: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

36

E202: BIM Protocol Exhibit

Page 37: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

37

Phase

UniFormat 300 Series

Level of Development

Model Element Author

Notes

Page 38: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

38

Key Definitions

Coordination

Model Standards

Ownership

Page 39: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

39

Model Management

Page 40: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

40

Levels of DevelopmentLOD 100: Massing content indicative of volume, location, and orientation.

LOD 200: Generalized systems or assemblies with approximate quantities.

LOD 300: Specific assemblies accurate in terms of quantity, size, shape, location, and orientation.

LOD 400: LOD 300 with fabrication, assembly and detailing information added.

LOD 500: “Record Model”

Page 41: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

41

Flow-down

Page 42: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

42

Traditional Delivery

Page 43: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

43

Integrated Project Delivery

Page 44: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

44

Non-UniFormat Elements

Page 45: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

45

2008

MHC SmartMarket Report2008

3xPT WhitepaperConsensus opinions about industry change

from owners, contractors, and architects

QuickTime™ and a decompressor

are needed to see this picture.

Page 46: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

46

Coming soon!

On Compensation:Considerations for Teams in a Transformed Industry

Outline•Introduction

•Motivations of Team Members: Why Do We Do This•Compensation for What: Ingredients of Compensation

•Current Compensation Models•New Value Propositions

•Appendix A: Three Sample Models•Appendix B: FAQs about Compensation

Page 47: 1 AIA Update on Integrated Project Delivery Lean Construction Institute Design Forum January 8 2009 Markku Allison, AIA

47

www.aia.org/ip

www.aia.org/sustainability