1 chapter 3: project management and the inception phase + project management up and inception phase...

57
1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Upload: evelyn-goodman

Post on 02-Jan-2016

222 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

1

Chapter 3: Project Management and the

Inception Phase+

Project Management

UP and Inception Phase

Feasibility Analysis

Page 2: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Overview: p73

“use an iterative, adaptive approach for this project”:– Developers decide on a few core processes– These become mini projects– More functionality is added via each iteration:– It consists of several different iterations (projects),

especially initially to understand the users needs and business processes that must be supported, with the last iterations making it robust and complete.

2

Page 3: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

3

Page 4: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Adaptive Project control:

Its harder to monitor the projects progress– Difficult to give a firm time schedule and project

costs– Characteristic of the adaptive approach:– Since the system is growing, the project is

somewhat open-ended, with the consequence of “scope creep”

– This must be controlled!!– See again Fig. 3-3 and 3-4

4

Page 5: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Introduction:

The development of a new software system is a difficult endeavor:– Inadequate understanding of users requirements– Lack of executive support– Inexperienced project managers, page 75

Project management processes are the activities that are directly related to managing and controlling a project

5

Page 6: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Example UP, page 65: (text focused on Agile method)

Is a formal methodology for software development:– Premise is that sw should be developed in an

iterative approach: the system grows and evolved

First iteration: inception iteration– Defining the new scope of the system

Second: elaboration– Defining the user’s requirement

6

Page 7: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

UP cont.

Construction iteration:– Building a reliable and robust system

Transition phase:– To test and deploy the system

In addition:– Development activities, called disciplines

Business modeling, Requirements ,Design Implementation, Testing, Deployment, Project Management, Configuration and change management, and environment.

7

Page 8: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Inception phase:

The focus will be to get the project started and the most prevalent business disciplines will be– Business modeling: understanding the business

needs– Environment: to configure the development tools

for the team– Project management: to plan and schedule the

rest of the project

8

Page 9: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

9

What is a project?

A group of tasks required to accomplish a goal MS Project?

– Is a sophisticated program designed to predict the outcome of a project by charting the required time and resources

– Gantt Chart– Pert Chart

Page 10: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

10

Terminology:

Project: An undertaking involving resources that have been allocated to a specific task, which are to be completed within a given time frame and budget

Task: A specific activity that is to be carried out at a specific time

A critical task: A task that, if lengthened, will delay the finish of the project

Page 11: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

11

Terminology

Duration: The length of time needed to complete a task

Dependency: A specific relationship between two tasks. You may need to finish one task before you can start another. In this case, the implementation of the second task is dependent upon the completion of the first task

Page 12: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

12

Terminology:

Resource: A specific entity used to complete a task. This includes people, equipment or any other entity used to get the task completed.

Resource conflict: This occurs when certain resources are needed for more than one task at the same time

Page 13: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

13

Terminology:

Calendar: A specific timetable that defines the working and non-working time……

for an entire project: Project Calendar.

a set of resources: Base Calendar

particular resources: Resource Calendar

Page 14: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

14

MS Project:

Time: Time Management is the schedule of the duration of tasks or how much time is needed to accomplish a task

Costs: To track cash flow for spending and income. You can also separately track resources costs, tasks costs, and income, while keeping a running total of the entire project, or even individual tasks.

Page 15: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

15

MS Project:

Reports: You can generate reports from interim analysis and presentations to various parties– Workload usage– Under/Over budgeted tasks– Actual hours vs. planned hours spent

Page 16: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

16

Four Phases:

Define the project’s objective Build the project plan Track and manage the project Close the project

Page 17: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

17

A. Objective:

You cannot hit the target if you cannot see it. Object should be measurable Define a definite END to the project Include any assumptions about the constraints

on the project Everyone affected must agrees to the definition

Page 18: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

18

Defining goals:

The project goals must be clearly defined so that you have a basis for evaluating the project’s success at a later time

Non-specific goal: Apply for an additional phone

Specific: Apply for an additional phone, to be installed before 15 September 2009, in office D100 for Ms Jones

Page 19: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

19

B. Build the plan

To figure out the best way to get there. Gather information: Task that have to be done,

time estimates of durations of tasks Enter the information in MS Project Ms Project will create a plan

Page 20: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

20

Define Requirements:

All the TASKS All the resources Time constraints that must be planned for Cost constraints that must be budgeted for

Page 21: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

21

C. Track and Management

Your team must execute the plan You keep close tabs on their progress You will encounter problems you did not expect Know the latest STATUS of the project Resolve early problems

Page 22: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

22

D. Close Project

Every project is a learning experience. No matter how well you planned at the beginning, by the end of the project, your map has changed from the original plan

Page 23: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

23

Example:

Work through the example in the book: – Page 93 - 99

Page 24: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Feasibility Analysis: p102 - 107

Project feasibility analysis is an activity that verifies that a project may be– Started and– Successfully completed

To determine if a development project has a reasonable chance of success.

24

Page 25: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Objective:

Identify all the risks of failure, and establish plans and procedures to ensure that they do not interfere with the success of the project

Activities to ensure feasibility:– Risk Management– Determine Organizational/cultural– Evaluate Technological– Determine Schedule– Resource and Economic (Cost/Benefit)

25

Page 26: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Economic Feasibility:

Two Questions:– Is the anticipated value of benefits greater than

projected costs of development– Does the organization have adequate cash flow to

fund the project

To assist in the determination of economic feasibility, people use a cost/benefit analysis.

26

Page 27: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Cost-Benefit Analysis:

Is the process of comparing the anticipated costs of an IS to the anticipated benefits.

It is performed throughout the SDLC to determine the economic feasibility of a project and to compare alternative solutions.

Techniques:– Payback analysis– Return on Investment (ROI)– Present Value analysis (NPV)

27

Page 28: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

A. Payback Analysis:

Is the process of determining how long it takes an information system to pay for itself.

The time it takes to recover the system’s costs is called the payback period.

Steps:– Determine initial development cost– Estimate annual benefits AND operating costs– Payback period: Compare the development +

operating costs TO total benefits28

Page 29: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

29

Page 30: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Table Information:

The table shows the anticipated annual costs, cumulative costs, annual benefits and cumulative benefits.

Year 0 corresponds to the year in which system development begins.

This projects development takes less than one year, so some benefits are already realized in Year 0.

See next slide for calculations:30

Page 31: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

31

Page 32: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Payback Period:

After year 4, the accumulated costs and benefits are nearly equal.

At the end of year 5 the accumulated benefits exceeds the costs, so some point in year 5, the payback period is established.

32

Page 33: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

33

Page 34: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Critique:

It places all the emphasis on early costs and benefits and ignores the benefits received after the payback period.

The further out in time that you extend your projections, the more unsure your forecast will be.

Cannot use it to compare/rank different projects, because later benefits/cost are ignored.

34

Page 35: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

B. ROI:

Is a percentage rate that measures profitability by comparing the total net benefits (return) received from a project to the total costs (investment) of the project.

= (total benefits – total costs)/total costs

35

Page 36: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Example: Use your spreadsheet!!

36

Page 37: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Critique:

Can be used to rank projects It measures the overall rate of return and

annual rates can vary considerably– Two projects with the same ROI might not be

equally desirable if the benefits of one project occur significantly earlier than the benefits of the other

– It ignores the timing of costs and benefits OR the time value of money

37

Page 38: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

C. Present Value Analysis

A commercial organization will only invest in a system if it believes it can thereby increase its profits by more than the cost of borrowing capital.

If the capital is already available, the projected increase in profits is compared with the projected income which could have been secured had the capital been used for another project.

38

Page 39: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Discounted Cash Flows:

Is a tool which enables an analyst to assess the profitability of the proposed capital outlay.

It investigates the projections of profit and loss statements.– Cost is consider as negative flows and– Anticipated profits as positive flows.– These amounts must take into considerations like

corporation tax, depreciation, investment grants, etc

39

Page 40: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

DCF:

40

Page 41: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Example:

Capital cost End of years cash flows

1 2 3

1,000 500 600 400

41

Page 42: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Example (cont.)

42

Page 43: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Quick approximation of return rate

Remember our problem is to determine a discount rate so that we will arrive at the initial outlay

Analyzing the flows, we can assume an average cash flow of R500

Use Excel function to get an approximate value:

43

Page 44: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Use RATE function:

44

Page 45: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Guessing the rate:

23% gives a PV larger than R1,000 Therefore I am searching for a rate that will give

a PV less than R1,000. Lets guess 25%, meaning

– Use Interpolation for an acceptable rate.

45

Page 46: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

PV:

We have to create ‘Discount Factors’, like on page 106 of the text book

Multiply each discount factor with the corresponding cash flow or payment and evaluate the final value.

46

Page 47: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Guessing the IRR:

47

Page 48: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Approximation with interpolation:

It is expected from you to solve the equation with ‘linear interpolation’:

48

Page 49: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Revision:

Q: Is a Rand you have today worth more than a Rand you do not receive until one year from today?

A: If you have a Rand now, you can invest it and it will grow in value to more than a Rand in the nearby future!

If you invest R100 now in a mutual fund, with an annual return of %8, it will be R108 after one year instead of R100!

49

Page 50: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Same example:

Instead of asking “How much will my R100 be worth a year from now?” one can ask:

“How much do I need to invest today, at %8, in order to have R100 a year from now?”

This concept is known as the time value of money.

It forms the basis of the technique called present value analysis.

50

Page 51: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

PV:

The PV of a future Rand is the amount that, when invested today at a certain interest rate, grows to exactly one Rand at a certain point in the future.

This interest rate is called the discount rate. In PV analysis a company uses a discount rate

that represents the rate of return if the money is put into relatively risk-free investments.

51

Page 52: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Summary:

To perform PV analysis you must time-adjust the cost and benefit figures.– MULTIPLY each of the projected benefits and costs

by the proper pv values.– SUM all these time-adjusted benefits/costs– Calculate the net present value (NPV) of the

project: Total pv of the benefits – Total pv of the costs

52

Page 53: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

A interesting Web site:

http://www.toolkit.com/small_business_guide

53

Page 54: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Example: p106, text book

Determine discount factors at 10% Determine the Value of Benefits PV benefits Determine Costs PV of costs Determine PV of net benefits and costs Determine Cumulative NPV Determine Payback period Determine ROI

54

Page 55: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

55

Page 56: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Discount Table: 10%

56

Page 57: 1 Chapter 3: Project Management and the Inception Phase + Project Management UP and Inception Phase Feasibility Analysis

Assignment 2

You can tackle assignment 3 with confidence now!

Test date? Scope?

57