1 cohesion policy 2007 - 13 adam abdulwahab evaluation network meeting brussels, 21 september 2009...
TRANSCRIPT
![Page 1: 1 Cohesion Policy 2007 - 13 Adam Abdulwahab Evaluation network meeting Brussels, 21 September 2009 Ex post evaluation of cohesion policy programmes 2000-2006](https://reader035.vdocuments.net/reader035/viewer/2022072017/56649f055503460f94c19a61/html5/thumbnails/1.jpg)
1
Cohesion Policy
2007 - 13
Adam Abdulwahab
Evaluation network meeting
Brussels, 21 September 2009
Ex post evaluation of cohesion policy programmes 2000-2006 co-financed by
the European Fund for Regional Development (Objective 1 and 2)
Work Package 10
“Efficiency: Unit Costs of
Major Projects”
![Page 2: 1 Cohesion Policy 2007 - 13 Adam Abdulwahab Evaluation network meeting Brussels, 21 September 2009 Ex post evaluation of cohesion policy programmes 2000-2006](https://reader035.vdocuments.net/reader035/viewer/2022072017/56649f055503460f94c19a61/html5/thumbnails/2.jpg)
2
Cohesion Policy
2007 - 13
Overview of ToR - 1• Scope: sample of ERDF major projects• Task 1: Literature review• Task 2: Infrastructure projects
– Definition of “units”– Estimated unit costs and completion times– Actual unit costs and completion times– Analysis of cost overruns and time delays– Role of ex ante risk assessment
![Page 3: 1 Cohesion Policy 2007 - 13 Adam Abdulwahab Evaluation network meeting Brussels, 21 September 2009 Ex post evaluation of cohesion policy programmes 2000-2006](https://reader035.vdocuments.net/reader035/viewer/2022072017/56649f055503460f94c19a61/html5/thumbnails/3.jpg)
3
Cohesion Policy
2007 - 13
Overview of ToR - 2• Task 3: Productive investment projects
– Costs of job created– Comparability of different cost per job figures– Estimated costs of jobs created– Actual costs of jobs created
• Task 4: Spreadsheet– Indicative benchmark ranges– Tool for further data input
![Page 4: 1 Cohesion Policy 2007 - 13 Adam Abdulwahab Evaluation network meeting Brussels, 21 September 2009 Ex post evaluation of cohesion policy programmes 2000-2006](https://reader035.vdocuments.net/reader035/viewer/2022072017/56649f055503460f94c19a61/html5/thumbnails/4.jpg)
4
Cohesion Policy
2007 - 13
Practical Limits• Data availability => smaller sample
(altogether 96 projects)• Data quality
– Difficulty of determining costs of components– Variations are higher than expected
• Reasons:– Modifications of projects– Projects were not necessarily monitored in same
structure as they were approved
![Page 5: 1 Cohesion Policy 2007 - 13 Adam Abdulwahab Evaluation network meeting Brussels, 21 September 2009 Ex post evaluation of cohesion policy programmes 2000-2006](https://reader035.vdocuments.net/reader035/viewer/2022072017/56649f055503460f94c19a61/html5/thumbnails/5.jpg)
5
Cohesion Policy
2007 - 13
Results of Literature Review• No public unit cost database
– One exception: ROCKS (World Bank) only roads and very limited European relevance
• No generally agreed definitions of unit costs for infrastructure projects
• Widespread “Optimism Bias”
• Job creation costs are determined only for (active) labour policy interventions
![Page 6: 1 Cohesion Policy 2007 - 13 Adam Abdulwahab Evaluation network meeting Brussels, 21 September 2009 Ex post evaluation of cohesion policy programmes 2000-2006](https://reader035.vdocuments.net/reader035/viewer/2022072017/56649f055503460f94c19a61/html5/thumbnails/6.jpg)
6
Cohesion Policy
2007 - 13
Sector snapshot - Rail• Cost range (literature): 2.8 to 8.6 mEUR/km• Sample
– Project length: 8.9 km to 1,435 km– Unit cost: 0.3 to 49 mEUR/km
• Main reasons for cost overruns: environmental issues, statutory authorities, work suspensions
• Main reasons for delays: funding and construction
![Page 7: 1 Cohesion Policy 2007 - 13 Adam Abdulwahab Evaluation network meeting Brussels, 21 September 2009 Ex post evaluation of cohesion policy programmes 2000-2006](https://reader035.vdocuments.net/reader035/viewer/2022072017/56649f055503460f94c19a61/html5/thumbnails/7.jpg)
7
Cohesion Policy
2007 - 13
Sector snapshot - Roads• Cost range (literature):
– Single carriageway: 0.7 to 2.0 mEUR/km– Dual carriageway: 2.7 to 8.7 mEUR/km– Dual carriageway, 3-lane: 36.4 to 91.3 mEUR/km
• Sample– Project length: 5.3 km to 144.2 km– Unit cost: 1 to 50 mEUR/km
• Main reasons for cost overruns: design complexity, environmental issues, statutory authorities
• Main reasons for delays: site preparation and construction
![Page 8: 1 Cohesion Policy 2007 - 13 Adam Abdulwahab Evaluation network meeting Brussels, 21 September 2009 Ex post evaluation of cohesion policy programmes 2000-2006](https://reader035.vdocuments.net/reader035/viewer/2022072017/56649f055503460f94c19a61/html5/thumbnails/8.jpg)
8
Cohesion Policy
2007 - 13
Sector snapshot – Urban transport
• Cost range (literature): – Metro: 27 to 300 mEUR/km (highest: 483 mEUR/km)– Tram: 2.5 to 64 mEUR/km
• Sample– Project length: 4 km to 22 km– Unit cost: 5 to 120 mEUR/km
• Main reasons for cost overruns: permits/consents, procurement factors
• Main reasons for delays: funding and planning
![Page 9: 1 Cohesion Policy 2007 - 13 Adam Abdulwahab Evaluation network meeting Brussels, 21 September 2009 Ex post evaluation of cohesion policy programmes 2000-2006](https://reader035.vdocuments.net/reader035/viewer/2022072017/56649f055503460f94c19a61/html5/thumbnails/9.jpg)
9
Cohesion Policy
2007 - 13
Sector snapshot – Water & Wastewater
• Sample not comparable to literature• Cost range (literature):
– Water treatment: 100 to 3800 EUR/m3/day– Water supply: 370 to 6800 EUR/m3/day
• Sample (relative homogeneity)– Project length: 85 km to 94 km– Unit cost: 0.75 to 2.11 mEUR/km
• Main reasons for cost overruns: design changes• Main reasons for delays: site preparation, funding,
permits/consents
![Page 10: 1 Cohesion Policy 2007 - 13 Adam Abdulwahab Evaluation network meeting Brussels, 21 September 2009 Ex post evaluation of cohesion policy programmes 2000-2006](https://reader035.vdocuments.net/reader035/viewer/2022072017/56649f055503460f94c19a61/html5/thumbnails/10.jpg)
10
Cohesion Policy
2007 - 13
Productive Investment Projects
• Difficulty to determine employment effects• Mainly determined by
– Capital/labour ratio of industry– Technological characteristics
• Decision based on CBA not on job creation
Measuring cost of jobs creation is futile and will be discontinued
![Page 11: 1 Cohesion Policy 2007 - 13 Adam Abdulwahab Evaluation network meeting Brussels, 21 September 2009 Ex post evaluation of cohesion policy programmes 2000-2006](https://reader035.vdocuments.net/reader035/viewer/2022072017/56649f055503460f94c19a61/html5/thumbnails/11.jpg)
11
Cohesion Policy
2007 - 13
Thank you for your attention