1 contract
TRANSCRIPT
-
8/2/2019 1 Contract
1/30
CONTRACT
DEFINITION: It is an Agreement between
Two or more parties having
Consideration and is
enforceable by law is called a
CONTRACT
-
8/2/2019 1 Contract
2/30
AGREEMENT
Promise/s to do something or not to
do something by parties is called an
AGREEMENT
-
8/2/2019 1 Contract
3/30
CONSIDERATION
It is a reciprocal promise/s or
exchange of things is called a
consideration
-
8/2/2019 1 Contract
4/30
Hence all agreements are not a
contract but all contract are
agreements.
Enforceable by Law means that it
should be a legal agreement and
contract
-
8/2/2019 1 Contract
5/30
LEGALLY ENFORCEABLECONTRACT
As per Contract Act 1872 Contract entered
by the parties are major, agreement/
promises are legal and consideration islegal than the contract is said to be an
legally enforceable
Contract not enforceable by law is called
as a Void Contract
-
8/2/2019 1 Contract
6/30
VOID CONTRACT
Entered by the party who is
Minor
Lunatic
Illegal act to do
(Agreement)
Illegal ConsiderationFraud
-
8/2/2019 1 Contract
7/30
VOIDABLE CONTRACT
Contract which has ability to become voidis called as a Voidable contract which areentered upon by
Misrepresentation
Undue Influence
Corson
-
8/2/2019 1 Contract
8/30
-
8/2/2019 1 Contract
9/30
Contract Law is to understand andinterpret the promises between the partiesto the contract.
Law are set by the Court with reference tothe Act passed by the Parliament
Act is a BARE Act and Sections of actinterpreted by court and Judgementpassed is called as Law
-
8/2/2019 1 Contract
10/30
We need to handle the situation from the
formation of the contract to administration
of contract to concluding the contract so
as to achieve successful completion of
contract and project with zero dispute
situations
-
8/2/2019 1 Contract
11/30
FORMATION OF CONTRACT
It is an invitation of proposal and receiving
offer and acceptance of offer is called as a
Contract
Hence invitation of proposal need be taken
care
Offer need be proper
And acceptance should be absolute
-
8/2/2019 1 Contract
12/30
TENDER WHEN ACCEPTED AFTERSCRUTINY IS BECOMING A CONTRACTDOCUMENT
EVERY WORD WRITTEN IN TENDERARE PROMISES AND CONTRACTUAL
OBLIGATIONS OF THE PARTIES TOTHE CONTRACT
HENCE DRAFTING OF TENDER
DOCUMENTS IS VERY IMPORTANT
-
8/2/2019 1 Contract
13/30
THE CLAUSE IN THE TENDER SHOULD BEDRAFTED KEEPING IN VIEW LAW RELATED
TO CONSTRUCTION CONTRACT
COURT HAVE STARTED CALLING CERTAIN
CLAUSES AS EXCULPATORY
AVOID AMBIGUITY IN THE DRAFTING
-
8/2/2019 1 Contract
14/30
PROJECT/CONTRACT ADMINISTRATOR
IT IS NECESSARY TO LET EVERY ONE KNOW EXACTLY HIS
SPHERE OF ACTIVITIES AND RELATED RESPONSIBILITY ANDAUTHORITY. EACH CADRE HAS TO BE TRAINED FOR THE EXACTJOB.
FOLLOWING ACTIVITIES ARE A MATTER OF CONTRACT
ADMINISTRATION
1. MEASUREMENTS, BILLS AND PAYMENTS.2. EXTRA-ITEMS AND CHANGE ORDER.3. EXTENSION OF TIME.4. MATERIALS ACCOUNTS.5. QUALITY.6. CLAIMS MANAGEMENT.7. LABOUR WELFARE.8. PUBLIC INTEREST AND ENVIRONMENTS.
-
8/2/2019 1 Contract
15/30
ADMINISTRATION AND HUMAN RELATIONS :
THE CONSTRUCTION PROCESS IS AN INTENSE INTERACTION
BETWEEN PEOPLE ON ALL SIDES. THERE MUST BE A DEGREE
OF CONFIDENCE BETWEEN THE TWO SIDES. OWNERS MUST
FEEL THEY WILL HAVE THEIR PROJECT DONE WITHIN
REASONABLE TIME AND MONEY. CONTRACTORS SHOULD
HAVE CONFIDENCE THAT THEIR LABOURS WILL NOT GO
WASTE. THIS REQUIRES A GOODS BALANCED CONTRACT
DRAFTED SO THAT ADMINISTRATION POSES LESS PROBLEMS.
-
8/2/2019 1 Contract
16/30
CONSTRUCTION PROJECT IS A PROCESS
WHICH HAS
A)SPECIFIC OBJECTIVE TO BE COMPLETED WITHINCERTAIN SPECIFICATIONS.
B) DEFINITE START AND COMPLETION DATES.
C) PRE SANCTIONED FUND WITH LIMITED CUSHION.
D) TO CONSUME RESOURCES SUCH AS MEN,MONEY, MACHINERIES
-
8/2/2019 1 Contract
17/30
SHORT COMING OF CONTRACT ADMINISTRATION:SHORT COMINGS OF CONTRACT ADMINISTRATION COULD BE TRACEDTO FOLLOWING AREAS.
1. CONFUSION ABOUT WHO IS WHO IN THE ORGANISATION FORDELEGATION OF DUTY AND EXERCISE OF POWERS.
2. UNTIMELY AND DEFECTIVE WORK ORDER.3. DELAY IN SITE HANDING OVER WITH PROPER ACCESS WITH
RESPONSIBILITY OF WATER/ POWER NOT CLEARLYUNDERSTOOD.
4. DRAWINGS MAY NOT BE READY.5. USERS HAVE NOT FROZEN THEIR REQUIREMENTS.6. TIME ESTIMATED FOR CONSTRUCTION IS WRONG.7. B.O.Q. IS NOT FAIRLY ACCURATE AND REQUIRES LOT OF
VARIATIONS.8. ALTERATIONS, EXTRAS, SUBSTITUTIONS ARE MORE OFTEN
REQUIRED.9. INADEQUATE SITE STAFF FOR SUPERVISION AND RECORD OF
BILLS.10.CLAIMS MANAGEMENT.11.PAUCITY OF FUNDS.
-
8/2/2019 1 Contract
18/30
CONTRACT ADMINISTRATION,
SHORTCOMINGS AND REMEDIES
CONTRACT IS A SET OF ENFORCEABLE PROMISES.
IN THIS CONTEXT, FOLLOWING DOCTRINES AREMOST IMPORTANT.
1. WAIVER2. ESTOPPELS
3. ELECTION4. ALTERATION
-
8/2/2019 1 Contract
19/30
WAIVER
ON BREACH OF ANY TERM OF CONTRACT, BY ONE PARTY THERE COMES
TO THE OTHER PARTY. THE OTHER PARTY NOT EXERCISING ITS RIGHT IS
CALLED A WAIVER
ESTOPPELSESTOPPELS IS A COROLLARY TO WAIVER IN THE SENSE THAT ONCE
YOU HAVE WAIVED A RIGHT, YOU ARE STOPPED FROM ENFORCING THE
RIGHT. YOUR ACTION CREATING RELIANCE FOR OTHER PARTY
CREATES AN ESTOPPELS FOR YOU. YOU CANNOT REVERSE THE
ACTION WITHOUT CREATING A LEGAL DETRIMENTS TO YOU.
-
8/2/2019 1 Contract
20/30
ALTERATION
WHEN ONE ALTERS A CONTRACT, THE OTHER PARTY HAS A RIGHT TO
REPUDIATE OR AFFIRM. IT IS THE AFFIRMATION THAT CREATES NEW
CONTRACTUAL RELATIONS AND REPUDIATION BECOMES
WAIVER.
ELECTION
FOR RELIEF OR OTHERWISE, YOU MAY HAVE A FEW OPTIONS. YOUR
OPTING FOR ONE, CREATES ESTOPPELS FOR OTHER. LIQUIDATED
DAMAGES LINKED TO EXTENSION OF TIME IS ONE SUCH SITUATION SO
YOU ARE ADVISED TO PUT THAT PHRASE WITHOUT PREJUDICE.
-
8/2/2019 1 Contract
21/30
BECAUSE WE CANNOT HANDLE THE
CONTRACT?
BECAUSE WE HAVE BECOME LITIGANT?
BECAUSE WE MEAN NO BUSINESS ANDARE NOT INTERESTED IN DEVELOPMENT?
IS IT TRUE?
-
8/2/2019 1 Contract
22/30
19TH CENTURY CONSTRUCTION SCENERIO
NAME DATE OF START DATE OF
COMPLETION
ESTIMATED
COST IN RS.
ACRUAL
COST IN RS
1. THE UNIVERSITY
LIBRARY &
RAJABAI CLOCK
TOWER
16TH JAN 1869
( 9 YEARS)
NOV.1878 6,32,451.00 6,32,120.00
2. P.W.D. BUILDING 21ST MAY 1869 1ST APRIL 1872 4,38,937.00 4,14,484.00
(3 YEARS)
3. THE GENERAL
POST OFFICE
21ST FEB.1869 11TH APRIL 1872 5,99,992.00 5,94,200.00
(3 YEARS)
4. PRESIDENCY
MAGISTRATES
COURT
3RD NOV 1871 31ST DEC. 1888 3,87,361.00 3,73,694
(4 YEARS)
5. THE LAW
COURTS
1ST APRIL 1871 NOV.1878 16,47,196.00 16,44,528.00
(7 YEARS)
6. MUNICIPAL
BUILDING
25TH APRIL
1889
31 ST JULY 1893 11,88,082.00 11,19,969.00
(4 YEARS)
-
8/2/2019 1 Contract
23/30
CAUSES:1. IRRATIONAL RISK-SHARING.
2. MULTIPLE AGENCIES AND CONFLICT OF
INTERESTS.
3. CONTINUOUS EROSION IN VALUE OF
MONEY.
-
8/2/2019 1 Contract
24/30
STRAINS NEED STRESS
MANAGEMENT:
STRESSES ARE CLAIMS IN
CONSTRUCTION:
CLAIMS BECOME DISPUTES AND
DISPUTES LEAD TO DISTRESS.
-
8/2/2019 1 Contract
25/30
SOURCE OF CLAIM
1.DOCUMENTS
2.EXECUTION
3.PAYMENTS
4.TIME
5.DEFAULT
-
8/2/2019 1 Contract
26/30
(A) EXECUTION OF CONTRACT: CHANGES/ EXTRA ITEMS/ VARIATIONS.
DIFFERING SITE CONDITIONS.
DELAYS AND ITS CONSEQUENCES .
(B) ADMINISTRATION OF CONTRACT:
PAYMENTS OF DUES.
CLOSURE OF CONTRACT /
TERMINATION LOSSES.
TYPES OF CLAIMS
-
8/2/2019 1 Contract
27/30
DEFECTS IN DOCUMENTS /DESIGN / DECISION.
INCOMPETENCE OF PARTIES
TO COPE UP WITH CHANGES.
DIFFERING SITE CONDITIONS.
ATTITUDE OF ANY ONE ORBOTH THE PARTIES.
-
8/2/2019 1 Contract
28/30
EXCUSABLE & NON EXCUSABLE DELAY
CRITICAL & NON CRITICAL DELAY
CONCURRENT & NON CONCURRENT DELAY
-
8/2/2019 1 Contract
29/30
General Rules of Interpretation:
In deciding the "Breach of Contract" the adjudicatingforum reads the terms and conditions within a
framework of certain rules. reading intentions of partiesfrom contract documents.
These rules are as follows :-
1. Words be given plain meaning - Plain Meaning Rule
Words which could have two meanings will be giventhat meanings which makes Contract valid rather thanvoid.
2. If certain things are expressly mentioned, it will excludeother things of similar nature - Expressio Unius Rule
3. General word like "etc." be narrowed down to meanonly things of same genre - Ejusdem generis Rule.
4. Words have to be construed forcibly against the drafter- Contra Profrentem Rule.
-
8/2/2019 1 Contract
30/30
An A.I based computer programme to go through Questions-Answers logic linked to data bank of relevant case laws to
appreciate likely outcome. This tool can be developed forcomputation of claims, documentations and decision-makingas well as for strategies to argue claims.
Early resolution of disputes in Construction is a must for allconcerned in view of fast erosion in value of money.
The constriction Disputes Resolution needs a rare combinationof legal and engineering talent. This being so rare that we
must develop tools of Artificial Intelligence for Computers toassist Arbitrators for expeditious disposal of the disputes.Construction industry in extensive interaction with Law-experts can help us to develop such tools. I placed before youmy modest effort at this.