1
Beach Nourishment Project
Town of Kitty Hawk, North Carolina
Coastal Planning & Engineering of North Carolina
November 3, 2014
Ken Willson
![Page 2: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/2.jpg)
2
Project Overview Map
![Page 3: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/3.jpg)
3
Kitty Hawk Project Area
![Page 4: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/4.jpg)
4
Kitty Hawk Stated Purpose:
1. Reduce the vulnerability of public infrastructure including NC 12, town roads between NC 12 and U.S. Highway 158, and utilities to storm-induced erosion;
2. Reduce flooding experienced in many non-oceanfront areas throughout the Town during ocean over wash conditions, including portions of NC Highway 12 and U.S. Highway 158; and
3. Reduce the vulnerability of homes within the Town that front the Atlantic Ocean and are exposed to wave events during nor’easters and other large storm events as well as natural trends.
![Page 5: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/5.jpg)
5
Storm Damage Reduction to Infrastructure
![Page 6: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/6.jpg)
6
Flood Damage Reduction to Non-Oceanfront Areas
![Page 7: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/7.jpg)
7
Storm Damage Reduction to Oceanfront Homes
![Page 8: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/8.jpg)
8
Storm Damage Reduction Project
![Page 9: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/9.jpg)
9
Dune
Design Beach
Berm Width6.0 ft.
NAVD88
Storm Damage Reduction Project Example
![Page 10: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/10.jpg)
10
Constructed Beach Fill
Storm Damage Reduction Project Example
![Page 11: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/11.jpg)
11
Post-ConstructionAdjustment in 1-3 years
Storm Damage Reduction Project Example
![Page 12: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/12.jpg)
12
Advance Fill
Design Beach
Storm Damage Reduction Project Example
![Page 13: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/13.jpg)
13
Dune
Loss of Advance Fill In 5-10 years
Design Beach
Berm Width6.0 ft.
NAVD88
Storm Damage Reduction Project Example
![Page 14: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/14.jpg)
14
![Page 15: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/15.jpg)
15
When structures are seaward of the dune, more sand is required toconstruct the design seaward of the structures.
Storm Damage Reduction Project Example
![Page 16: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/16.jpg)
16
When structures are seaward of the dune, more sand is required toconstruct the design seaward of the structures.
Built in front of structures
Berm Width6.0 ft.
NAVD88
Dune
+13.0 ft.
Design Beach
Storm Damage Reduction Project Example
![Page 17: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/17.jpg)
17
Design Beach
When structures are seaward of the dune, more sand is required toconstruct the design seaward of the structures.
Tie into existing dune
Berm Width6.0 ft.
NAVD88
Dune
+13.0 ft.
Storm Damage Reduction Project Example
![Page 18: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/18.jpg)
18
ALTERNATIVE VOLUME (CY) DENSITY (CY/FT)
ALTERNATIVE 1 – Dune and Berm Design (20 ft. wide, 13 ft. high dune; 50 ft. wide, 6 ft. high berm (Tie into Existing Dune)
1,583,000 81.3
ALTERNATIVE 2 – Dune and Berm Design (20 ft. wide, 13 ft. high dune; 50 ft. wide, 6 ft. high berm (Seaward of Structures)
2,872,000 147.4
81% Increase
![Page 19: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/19.jpg)
19
Berm Only Option
50’ Berm Width6.0 ft.
NAVD88
Design Beach
![Page 20: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/20.jpg)
20
Minimal Dune Design - 12
30’ Berm Width6.0 ft.
NAVD8810’ Dune
Width+12.0 ft.
Design Beach
![Page 21: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/21.jpg)
21
Storm Damage Reduction Analysis
• Minimal simulated impact to the road given existing conditions
• No impacts to the road with berm only or MDD-12 design.
1. Reduce the vulnerability of public infrastructure including NC 12, town roads between NC 12 and U.S. Highway 158, and utilities to storm-induced erosion;
• 122 structures impacted given existing conditions. 48% reduction with berm only and 64% reduction with MDD-12 design
3. Reduce the vulnerability of homes within the Town that front the Atlantic Ocean and are exposed to wave events during nor’easters and other large storm events as well as natural trends;
![Page 22: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/22.jpg)
22
Runup Evaluation
Calculated Runup Elevation
![Page 23: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/23.jpg)
23
Runup Evaluation
Calculated Runup Elevation
![Page 24: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/24.jpg)
24
Runup Evaluation
Runup Elevation
![Page 25: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/25.jpg)
25
Design Beach
Calculated Runup Elevation
With ProjectWithout Project
Design Beach
Runup Evaluation
![Page 26: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/26.jpg)
26
Design BeachDesign
Beach
Design Beach
Calculated Runup Elevation
With ProjectWithout Project
Design Beach
Runup Evaluation
![Page 27: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/27.jpg)
27
Design BeachDesign
Beach
Design Beach
Calculated Runup Elevation
With ProjectWithout Project
Design Beach
Runup Evaluation
![Page 28: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/28.jpg)
28
Runup Evaluation
Runup Elevation = Lower Than Elevation of the Road
![Page 29: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/29.jpg)
29
Annual Event Runup Analysis
• 12 ft. Dune Design and 50 Ft. Berm:
– 69.8% to 92.7 % reduction in length of shoreline exceeded by calculated runup.
![Page 30: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/30.jpg)
30
5 – Year Event• “Kill Devil Hills” Design – 15 ft. high / 20 ft. wide dune, fronted
by a 40 ft. berm
– Advances Shoreline 100 ft. (Average)
– Requires 3.19 Million CY
– 100% increase in Volume
– Additional $15 Million
• 100 – Ft. Berm Only Design
– Advances Shoreline 100 ft.
– Requires 2.93 Million CY
– 84% increase in Volume
– Additional $12.5 Million
• What could we do with another $2 Million - $3 Million
![Page 31: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/31.jpg)
31
5 – Year Event
• $ 3 Million = ~ 16 CY/Ft. More Sand
• Design: Slightly Over a 60 ft. Design Berm
– Annual Event - 73.4% to 98.7 % reduction in length of shoreline exceeded by calculated runup.
– 5-Year Event – 39.6% to 72.2% reduction in length of shoreline exceeded by calculated runup.
![Page 32: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/32.jpg)
32
Runup Elevation
Runup Evaluation
![Page 33: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/33.jpg)
33
5 – Year Event
• $ 3 Million = ~ 16 CY/Ft. More Sand
• Design: Slightly Over a 60 ft. Design Berm
– Annual Event - 73.4% to 98.7 % reduction in length of shoreline exceeded by calculated runup.
– 5-Year Event – 39.6% to 72.2% reduction in length of shoreline exceeded by calculated runup.
– With 14.0 ft. NAVD Starter Dune these numbers become 100%
![Page 34: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/34.jpg)
34
60 Ft. Berm Design
• 60 Ft. Berm; 14.0 ft. NAVD “Starter Dune”; Sand Fencing
• Main Fill Length – 18,900 ft. (3.58 miles)
• 1000 Ft. Taper on North End
• Fill Density ~ 95 cy/ft. to ~100 cy/ft.
• Total Volume = ~1.91 Million Cubic Yards
• Project Cost = ~$20.5 Million
![Page 35: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/35.jpg)
35
Task Name Projected Completion
Compatibility Analysis 10/24/2014
Kitty Hawk Design Finalized 11/3/2014
Address USACE and BOEM Comments and release EFH and BA 10/28/2014
Completion of USACE, BOEM, USFWS, and NMFS Consultation 10/28/2015
Address Comments and Release Draft EA (Duck, KH, and KDH) 11/14/2014
Submit CAMA Applications February/March 2015
BOEM Lease Agreement Issued 1/1/2016
Open Bids Anytime After 1/1/2016
Construction Beginning March 2016
Schedule
![Page 36: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/36.jpg)
36
Beach Nourishment Project
Town of Kitty Hawk, North Carolina
Questions??
Ken Willson – [email protected]
![Page 37: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/37.jpg)
37
Kill Devil Hills Project Area
![Page 38: 1 Dark Background Body Slide This background is best for on-screen presentations only—the background shows up best on-screen but uses excessive toner if](https://reader037.vdocuments.net/reader037/viewer/2022110405/56649efe5503460f94c12e53/html5/thumbnails/38.jpg)
38
Duck Project Area