Facility Construction CommitteeFacility Construction Committee
February 11, 2002 8:30 PMFebruary 11, 2002 8:30 PM
Facility Construction DepartmentFacility Construction Department
Construction Status Report Construction Status Report
PresentationPresentation to theto the
by theby the
![Page 2: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/2.jpg)
2
Projects Under ConstructionProjects Under Construction(as of February 2002)(as of February 2002)
CampusCampus Start Date Start Date
1.1. Sta. Maria Elementary School Oct. 2001Sta. Maria Elementary School Oct. 2001
2.2. Farias Elementary School Oct. 2001Farias Elementary School Oct. 2001
3.3. Sanchez/Ochoa Elem. School Oct. 2001Sanchez/Ochoa Elem. School Oct. 2001
4.4. Dovalina Elementary SchoolDovalina Elementary School Oct. 2001 Oct. 2001
5.5. Milton Elementary School Jan. 2002Milton Elementary School Jan. 2002
6.6. Nixon High SchoolNixon High School Jan. 2002 Jan. 2002
![Page 3: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/3.jpg)
3
Santa Maria Elementary SchoolSanta Maria Elementary School
Architect:Architect: Cavazos & Associates ArchitectsCavazos & Associates Architects Contractor:Contractor: Leyendecker Construction, Inc.Leyendecker Construction, Inc. Contract amount:Contract amount: $4,862,700.00$4,862,700.00 Construction Start:Construction Start: Oct. 31, 2001Oct. 31, 2001 Start of School:Start of School: Aug. 15, 2002Aug. 15, 2002 Completion Date:Completion Date: Aug. 31, 2002Aug. 31, 2002 Change Order(s):Change Order(s): Addition of Single Sex Addition of Single Sex
Restrooms at PK & K.Restrooms at PK & K.
![Page 4: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/4.jpg)
4
Financial Overview – Sta. MariaFinancial Overview – Sta. MariaLeyendecker’s ContractLeyendecker’s Contract
Balance to Finish = $ 4,320,850.
89%
Amount Paid = $ 541,850.
11%
Balance to Finish = $ 4,320,850.
89%
Amount Paid = $ 541,850.
11%
![Page 5: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/5.jpg)
5
Construction Time - Sta. MariaConstruction Time - Sta. MariaLeyendecker’s ContractLeyendecker’s Contract
Total Days Remaining in
Contract = 20166%
Days Lapsed in Contract =
10334%
Total Days Remaining in
Contract = 20166%
Days Lapsed in Contract =
10334%
![Page 6: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/6.jpg)
6
LISD:
Sta. Maria:Sta. Maria:
Foundation construction on going. Foundation construction on going. Approximately 45,000 sq. Ft. Will Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. 20,000 sf to be poured by 1-22-02. All excavations is complete, all All excavations is complete, all reinforcing is on jobsite. Masonry reinforcing is on jobsite. Masonry construction projected to commence construction projected to commence 1-23-02. Metal building delivery 1-23-02. Metal building delivery scheduled to commence 3-01-02. scheduled to commence 3-01-02.
LISD:
Sta. Maria:Sta. Maria:
Foundation construction on going. Foundation construction on going. Approximately 45,000 sq. Ft. Will Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. 20,000 sf to be poured by 1-22-02. All excavations is complete, all All excavations is complete, all reinforcing is on jobsite. Masonry reinforcing is on jobsite. Masonry construction projected to commence construction projected to commence 1-23-02. Metal building delivery 1-23-02. Metal building delivery scheduled to commence 3-01-02. scheduled to commence 3-01-02.
Santa Maria Elementary SchoolSanta Maria Elementary School
![Page 7: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/7.jpg)
7
Santa Maria Elementary SchoolSanta Maria Elementary School
![Page 8: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/8.jpg)
8
Farias Elementary SchoolFarias Elementary School
Architect:Architect: Ashley Humphries, & Sanchez Ashley Humphries, & Sanchez ArchitectsArchitects
Contractor:Contractor: Leyendecker Construction, Inc.Leyendecker Construction, Inc. Contract amount:Contract amount: $4,926,997.$4,926,997. Construction Start:Construction Start: Oct. 31, 2001Oct. 31, 2001 Days in ContractDays in Contract:: 320 Calendar Days320 Calendar Days Completion Date:Completion Date: Aug. 31, 2002Aug. 31, 2002 Change Order(s):Change Order(s): Addition of Single Sex Addition of Single Sex
Restrooms at PK & K.Restrooms at PK & K.
![Page 9: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/9.jpg)
9
Financial Overview – FariasFinancial Overview – FariasLeyendecker’s ContractLeyendecker’s Contract
Balance to Finish = $ 4,552,997.
92%
Amount Paid = $ 374,000.
8%
Balance to Finish = $ 4,552,997.
92%
Amount Paid = $ 374,000.
8%
![Page 10: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/10.jpg)
10
Construction Time - FariasConstruction Time - FariasLeyendecker’s ContractLeyendecker’s Contract
Total Days Remaining in
Contract = 21768%
Days Lapsed in Contract =
10332%
Total Days Remaining in
Contract = 21768%
Days Lapsed in Contract =
10332%
![Page 11: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/11.jpg)
11
Farias Elementary SchoolFarias Elementary School
![Page 12: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/12.jpg)
12
Farias Elementary SchoolFarias Elementary School
![Page 13: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/13.jpg)
13
Sanchez/Ochoa Elementary SchoolSanchez/Ochoa Elementary School
Architect:Architect: Sepulveda & Assoc. ArchitectsSepulveda & Assoc. Architects Contractor:Contractor: Leyendecker Construction, Inc.Leyendecker Construction, Inc. Contract amount:Contract amount: $ 5,132,719.$ 5,132,719. Construction Start:Construction Start: Oct. 31, 2001Oct. 31, 2001 Number Contract Days:Number Contract Days: 320320 Completion Date:Completion Date: Sept. 16, 2002Sept. 16, 2002 Change Order(s):Change Order(s): NoneNone
![Page 14: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/14.jpg)
14
Financial Overview – Sanchez/OchoaFinancial Overview – Sanchez/OchoaLeyendecker’s ContractLeyendecker’s Contract
Balance to Finish = $ 4,584,619.
89%
Amount Paid = $ 548,100.
11%
Balance to Finish = $ 4,584,619.
89%
Amount Paid = $ 548,100.
11%
![Page 15: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/15.jpg)
15
Construction Time – Sanchez/OchoaConstruction Time – Sanchez/OchoaLeyendecker’s ContractLeyendecker’s Contract
Total Days Remaining in
Contract = 21768%
Days Lapsed in Contract =
10332%
Total Days Remaining in
Contract = 21768%
Days Lapsed in Contract =
10332%
![Page 16: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/16.jpg)
16
LISD:
All foundation excavation is complete. All All foundation excavation is complete. All reinforcing steel is on jobsite, all beam reinforcing steel is on jobsite, all beam reinforcing steel is tied and ready for reinforcing steel is tied and ready for installation. All of zones “D” and “E” have installation. All of zones “D” and “E” have been poured, 14800 sf of zone “B” poured. been poured, 14800 sf of zone “B” poured. Zone “C” to be poured week 1-21-02 along Zone “C” to be poured week 1-21-02 along with zone “A” and pending portion of zone with zone “A” and pending portion of zone “B”.Metal building delivery scheduled to “B”.Metal building delivery scheduled to commence 2-15-02.commence 2-15-02.
LISD:
All foundation excavation is complete. All All foundation excavation is complete. All reinforcing steel is on jobsite, all beam reinforcing steel is on jobsite, all beam reinforcing steel is tied and ready for reinforcing steel is tied and ready for installation. All of zones “D” and “E” have installation. All of zones “D” and “E” have been poured, 14800 sf of zone “B” poured. been poured, 14800 sf of zone “B” poured. Zone “C” to be poured week 1-21-02 along Zone “C” to be poured week 1-21-02 along with zone “A” and pending portion of zone with zone “A” and pending portion of zone “B”.Metal building delivery scheduled to “B”.Metal building delivery scheduled to commence 2-15-02.commence 2-15-02.
Sanchez/Ochoa Elementary SchoolSanchez/Ochoa Elementary School
![Page 17: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/17.jpg)
17
Sanchez/Ochoa Elementary SchoolSanchez/Ochoa Elementary School
![Page 18: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/18.jpg)
18
Sanchez/Ochoa Elementary SchoolSanchez/Ochoa Elementary School
![Page 19: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/19.jpg)
19
Sanchez/Ochoa Elementary SchoolSanchez/Ochoa Elementary School
![Page 20: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/20.jpg)
20
Sanchez/Ochoa Elementary SchoolSanchez/Ochoa Elementary School
![Page 21: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/21.jpg)
21
Dovalina Elementary SchoolDovalina Elementary School
Architect:Architect: Design Group International, Design Group International, Inc.Inc.
Contractor:Contractor: Leyendecker Construction, Inc.Leyendecker Construction, Inc. Contract amount:Contract amount: $ 2,801,900.$ 2,801,900. Construction Start:Construction Start: Oct. 31, 2001Oct. 31, 2001 Number Contract Days:Number Contract Days: 304304 Completion Date:Completion Date: Aug. 31, 2002Aug. 31, 2002 Change Order(s):Change Order(s): NoneNone
![Page 22: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/22.jpg)
22
Financial Overview – DovalinaFinancial Overview – DovalinaLeyendecker’s ContractLeyendecker’s Contract
Balance to Finish = $ 2,413,460.
86%
Amount Paid = $ 388,440.
14%
Balance to Finish = $ 2,413,460.
86%
Amount Paid = $ 388,440.
14%
![Page 23: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/23.jpg)
23
Construction Time - DovalinaConstruction Time - DovalinaLeyendecker’s ContractLeyendecker’s Contract
Total Days Remaining in
Contract = 20166%
Days Lapsed in Contract =
10334%
Total Days Remaining in
Contract = 20166%
Days Lapsed in Contract =
10334%
![Page 24: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/24.jpg)
24
LISD:
Foundation has been poured for addition. Foundation has been poured for addition. CMU in progress and is approximately 50% CMU in progress and is approximately 50% complete. Metal building schedule for complete. Metal building schedule for delivery on 1-18-02, with metal panels and delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02.insulation delivery scheduled for 1-25-02.
LISD:
Foundation has been poured for addition. Foundation has been poured for addition. CMU in progress and is approximately 50% CMU in progress and is approximately 50% complete. Metal building schedule for complete. Metal building schedule for delivery on 1-18-02, with metal panels and delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02.insulation delivery scheduled for 1-25-02.
Dovalina Elementary SchoolDovalina Elementary School
![Page 25: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/25.jpg)
25
Dovalina Elementary SchoolDovalina Elementary School
![Page 26: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/26.jpg)
26
Dovalina Elementary SchoolDovalina Elementary School
![Page 27: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/27.jpg)
27
Milton Elementary SchoolMilton Elementary School
Architect:Architect: Turner Hickey & Assoc. Arch.Turner Hickey & Assoc. Arch. General Contractor:General Contractor: To be determinedTo be determined Asbestos/Demolition:Asbestos/Demolition: M & M Contracting, Inc.M & M Contracting, Inc. Contract amount:Contract amount: $ 183,978.$ 183,978. Construction Start:Construction Start: Jan. 27, 2002Jan. 27, 2002 Number Contract Days:Number Contract Days: 47 Days47 Days Completion Date:Completion Date: March 15, 2002March 15, 2002 Change Order(s):Change Order(s): NoneNone
![Page 28: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/28.jpg)
28
Financial Overview – MiltonFinancial Overview – MiltonM & M Contracting ContractM & M Contracting Contract
Asbestos/DemolitionAsbestos/DemolitionBalance to Finish = $ 183,978.
100%
Amount Paid = $ 0.
0%
Balance to Finish = $ 183,978.
100%
Amount Paid = $ 0.
0%
![Page 29: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/29.jpg)
29
Construction Time – MiltonConstruction Time – MiltonM & M Contracting ContractM & M Contracting Contract
Asbestos/DemolitionAsbestos/Demolition
Total Days Remaining in Contract = 32
68%
Days Lapsed in Contract =
1532%
Total Days Remaining in Contract = 32
68%
Days Lapsed in Contract =
1532%
![Page 30: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/30.jpg)
30
Milton Elementary SchoolMilton Elementary School
![Page 31: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/31.jpg)
31
Milton Elementary SchoolMilton Elementary School
![Page 32: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/32.jpg)
32
Milton Elementary SchoolMilton Elementary School
![Page 33: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/33.jpg)
33
J. W. Nixon High SchoolJ. W. Nixon High School
Architect:Architect: Cavazos & Associates Cavazos & Associates ArchitectsArchitects
Contractor:Contractor: Leyendecker Construction, Inc.Leyendecker Construction, Inc. Contract amount:Contract amount: $ 9,298,985.$ 9,298,985. Construction Start:Construction Start: Jan. 30, 2002Jan. 30, 2002 Number Contract Days:Number Contract Days: 551551 Completion Date:Completion Date: August. 15, 2003August. 15, 2003 Change Order(s):Change Order(s): NoneNone
![Page 34: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/34.jpg)
34
Financial Overview – Nixon HighFinancial Overview – Nixon HighLeyendecker’s ContractLeyendecker’s Contract
Balance to Finish = $ 9,298,985.
100%
Amount Paid = $ 0.
0%
Balance to Finish = $ 9,298,985.
100%
Amount Paid = $ 0.
0%
![Page 35: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/35.jpg)
35
Construction Time – Nixon HighConstruction Time – Nixon HighLeyendecker’s ContractLeyendecker’s Contract
Total Days Remaining in
Contract = 53998%
Days Lapsed in Contract =
122%
Total Days Remaining in
Contract = 53998%
Days Lapsed in Contract =
122%
![Page 36: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/36.jpg)
36
J. W. Nixon High SchoolJ. W. Nixon High School
![Page 37: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/37.jpg)
37
J. W. Nixon High SchoolJ. W. Nixon High School
![Page 38: 1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the](https://reader035.vdocuments.net/reader035/viewer/2022062722/56649f355503460f94c526eb/html5/thumbnails/38.jpg)
38
End of PresentationEnd of Presentation
Question & Answer SessionQuestion & Answer Session