1 installation of topside using floatover method kuliah tamu fakultas teknologi kelautan - its 2...
TRANSCRIPT
11
INSTALLATION OF TOPSIDE USING FLOATOVER METHOD
Kuliah Tamu Fakultas Teknologi Kelautan - ITS2 November 2010
By. Ir. Ice Achmad Kurniawan
22
Agenda
1.Why Floatover2.Floatover Concept3.Design Engineering4.Barge Equipment and Appurtenances 5.Floatover Sequences6. Procurement 7. Marine Spread
33
1. WHY FLOATOVER
Conventional method: LIFTING
WHY FLOATOVER - Unavailability of suitable vessel with crane
capability to install heavy topside (>2000MT)- Cost and schedule advantages of installing pre-
commissioned, integrated, single-piece topsides. - Desire to reduce increasingly expensive offshore
hook-up and commissioning time - Now more demanding due to Scarce availability of
heavy-lift crane vessels for work in shallow waters
44
2. FLOATOVER CONCEPT
- The topside module typically is placed on a barge or heavy transport vessel positioned within (internal slot of jacket) or around the legs (external) of a pre-installed jacket- The module then is settled onto the jacket legs by a combination of vessel ballasting and a mechanical lowering system. - The operation of incrementally transferring the
module loads from the barge to the jacket (MATING operation) - Undocking, sufficient clearance, vessel move out
from the jacket
55
3. FLOATOVERT&I DESIGN ENGINEERING
1. Deck Mating analysis2. Barge Strength Check (load out & transportation
condition)3. Transportation Analysis4. Mooring Analysis5. Seafastening Design6. Floatover Rapid Ballast System Design7. Jacket Structural Analysis (allowable limit during
floatover)
66
PROCESS DESIGN FLOW DIAGRAM
77
MATING ANALYSIS
•To simulate the barge’s motion characteristic and to identify the loading on the jacket using a time domain analysis.•Multiple load cases were identified from the initial stage, docking, load transfer and undocking stage to represent the floatover method•The load impact result shall be within allowable jacket design load•Installation sea states criteria shall be established at up front stage as an input for the analysis. •Software use MOSES or LIFSIM
Seastate Input (Installation Criteria)Head/stern sea Hs = 1.00 m Tz up to 7.5 sQuartering sea Hs = 0.75 m Tz up to 7.5 sBeam sea Hs = 0.50 m Tz up to 7.5 s
Output will be used to determine the flaotover workability
88
DSF-BARGE SEAFASTENING
99
TOPSIDE-DSF SEAFASTENING
1010
LMU
1111
DSU
1212
PLAN LAYOUT LOAD OUT
1313
LAY OUT FENDERING SYSTEM
1414
JACKET ALLOWABLE IMPACT
LOAD
1515
4. FLOATOVER OPT.SEQUENCES• Standby - The vessel is a safe distance from the substructure but connected
to the mooring system, preparation rapid ballast system or the hydraulic jacks are under way
• Docking - The vessel enters the substructure and alignment• Pre-Mating - When ballasting the vessel to match the leg mating units
(LMU) with receptors on top of the substructure legs and removing the remaining tie downs, it is critical that the vessel motions be limited to suit the chosen LMU geometry. No weight transfer yet occurs
• Mating - The topsides is lowered onto the substructure by either rapid ballasting of the vessel or by contracting the hydraulic jacks. The topsides weight is transferred to the jacket completely
• Post-mating - A gap is created between the deck support units (DSU) and the vessel to ensure vessel motions will not cause contact between the two
• Exit - The vessel is removed from the jacket slot.• Post Floatover
- Removal of premooring system, clean up installation aids from jacket if required- Process of welding & NDT examination between topside leg with jacket transition pieces- Final Survey
1616
ANCHOR PATTERN
1717
ELEVATION
1818
5. BARGE SYSTEM AND APPURTUNANCES
1. Rapid Ballast System: to perform the load transfer in the available 12-hour tidal sequence, with specific rate. Can be external or internal (modified from existing barge ballast system)
2. Fendering system was designed to ease the transition through the jacket with sufficient clearances, which reduced the sway impact loading upon docking.
3. The surge fenders were installed to lock the barge in its final docking position.
4. LMU (elastomer-based leg mating unit): to reduce the vertical impact forces (designed to support 50%) of the deck load during load transfer.
5. DSU (Deck Support Unit), elastomer to reduce vertical impact between DSF and topside during the deck load transfer
6. DSF (Deck Support Frame), structure to support topside during load out, transportation and floatover
7. Barge Motion Monitoring System, electronic system to monitor motion of the barge (6 degree of freedom, the motion will be compared with mating analysis)
8. Positioning System 9. Wave Rider Buoys
1919
BARGE GENERAL LAYOUT
1. S45 PREPARATION AND FENDERING SYSTEM 2. LINKBEAMs & LIGHT SKIDBEAMs FABRICATION 3. 3RD PARTY MARINE SPREADS CHARTER
(Various)4. EXTERNAL RAPID BALLAST SYSTEM 5. SURVEY AND POSITIONING 6. WEATHER FORECAST 7. CATERING SERVICE 8. INSTALLATION AIDS 9. VSAT LINK SERVICE10. AGENCY SERVICE11.ROV 13. NDT
6. PROCUREMENTS
1.1 X TRANSPORTATION BARGE (S45)2.1 X TOWING TUG 14,200BHP3.2 X AHT 10,800BHP C/W KARMFORKS 4.1 X AHT 7000BHP5.1 X AWB (Accommodation Work Barge),
120PAX CAPACITY, 120T CRANE6.1 X CREW BOAT, 80 PAX CAPACITY7.1 X ZODIAC BOAT
7. MARINE SPREAD
2222
1.Project Description
18" x 100 km
ADGF PLEM
BELANAKFPSO/ FSO
KERISI
24" x 93 km
WHP-K
KERISIPLEM
NORTH BELUT
WHP-D
WHP-C
22" x 10 km
gas phase - 16" x 37 kmliquid phase - 12" x 37 km
gas phase - 16" x 23 kmliquid phase - 12" x 23 km
DUYONG
CPP
16" x 0.5 km
MALAYSIA
INDONESIA
HIUSUBSEA
CPP Topside
The NBCPP topside is a large, complex integrated deck with a not to exceed weight of 14,000 MT. The field is located approximately 60km east-north-east of
the Belanak FPSO installed in the Belanak Field, located on the Block B of the Indonesian sector of the Natuna Field.
2323
Load out of CPPTopside on S45
Transportation of CPP TopsideSailaway
Installation of CPP Topside using Floatover method
on CPP Jacket
2.Project Phases
Location:S45 mobilize to
Topside Fabrication Yard
Location: Block B of Natuna Sea – Indonesia
The NBCPP is located in 95.2 m water depth
2424
3. Scope of Work
Main Scope of Work:
• Provision of expertise, manpower, plant, equipment, Contractor’s Spread, consumables and all other items necessary to transport CPP Topside components from the fabrication yard to the North Belut offshore Site and install them safely and efficiently.
2525
4.Project Key Milestones
Date Activity
11 June 2007 Contract Effective Date
3 Jan 2009 S45 transfer to Sintai for Fendering System and Preparation Work
1 May 2009 S45 mobilized to PTMI Yard
16 May 2009 CPP Topside loaded out onto S45 barge
1st June 2009 Sailaway of CPP Topside
6th June 2009 CPP Topside Installed using Floatover method
7th June 2009 All vessels demobilized from site
5.Interfaces with Other Company’s
ContractorNo Description PT Technip PT Mc Dermot PT Saipem
1All loadout planning,
engineering and AFC dwg R X
Review + supply barge data, check barge
strength and stability for load out
2 Load out operation X
3Structural Load out Analysis
(Reaction load) X R
4 Transportaton Analysis R X
5 Mating Analysis R X
6Installation Aids fixed by
welding to jacket structures R
Supply material, Fabricate and pre
installDesign and supply AFC
dwg and MTO
7 DSF DesignSupply material,
Fabricate R
8 CPP Topside DesignSupply material,
Fabricate
9 LMU (OKI)Design,
Fabricate Install
10 Seafastening R
Supply material, Fabricate and
installDesign and supply AFC
dwg and MTO
11External Rapid Ballast System Floatover R
R, may request to use assistance Design and install
R = ReviewX = Responsibility
Project PhotosLOAD OUT
Project PhotosTOWING
Project PhotosPRE-MATING
Project PhotosFLOATOVER
Project PhotosFLOATOVER
Project PhotosFLOATOVER
Project PhotosFLOATOVER
Project PhotosFLOATOVER
Project PhotosFLOATOVER
Project PhotosFLOATOVER