1 master production scheduling (mps) – basic techniques lecture session 6
TRANSCRIPT
1
Master Production Scheduling (MPS) – Basic Techniques
http://www.pom.edu/mpc/lectures_in_manufacturing_planning.htmlecture session 6
• MPS: Role in the MPC System• MPS Defined• MPS Approaches• Single Level MPS Time-Phased Record• Customer Order Processing• Rolling through Time (Transactions)
2
Manufacturing Planning and Control System
3
MPS Defined• Anticipated Build Schedule – a statement of production not
market demand
• The MPS is:
– Stated in terms of product specifications
– Concerned with product mix while Sales and Operations Planning is concerned with volume
• The MPS is the basis for:
– Making customer delivery promises– Utilizing plant capacity effectively– Attaining the strategic objectives in the sales and operations
plan– Resolving trade-offs between manufacturing and marketing
4
MPS Approaches
• Make – to – Stock
• Make – to – Order
• Assemble – to – Order
5
Single Level MPS Record Example• The Zero Manufacturing Company ships Product A from the firm's plant
warehouse to satisfy East Coast demand. Currently, the sales forecast for Product A at the Murphysboro plant is 30 units per period.
• Product A is considered a make-to-stock item.– Plant warehouse on hand inventory = 50 units– Safety Stock = 10 units– Lot Size = L4L– Open Order for 30 units due in period 1
• The master production scheduler has heard that an MRP record which uses the forecast for gross requirements and has a lead time of zero can be used for master production scheduling. Complete the following MRP record. How can this be used for master production scheduling?
1 2 3 4 5 6
Projected available balancePlanned order releaseQ = lot for lot; LT = 0; SS = 10
PeriodProduct AGross requirementsScheduled receipts
6
Single Level MPS Record Processing
1 2 3 4 5 630 30 30 30 30 3030
Projected available balance 50 50 20 10 10 10 1020 30 30 30Planned order release
Q = lot for lot; LT = 0; SS = 10
PeriodProduct AGross requirementsScheduled receipts
One way viewing an MPS is as the set of planned order releases and scheduled receipts in a record such as above. The problem is that any errors in forecast will be reflected in the on-hand balance. All changes will come in the planned orders. Use of firm planned orders will reduce this instability.
7
Customer Order Promising Example
The MPS planner at Murphy Motors uses MPS time-phased records for planning end item production. The planner is currently working on a schedule for the P24. The production lot size is 70 and the safety stock is 5.
1 2 3 4 5 6 7 830 30 30 40 40 40 45 4513 8 4
Available
MPS (completion)
Period
Available to promise
On hand = 20, MPS Lot Size = 70
Item: P24ForecastOrders
8
Customer Order Promising Example
a. Complete the MPS time-phased record for P24.
b. Can Murphy accept the following orders? Update the MPS time-phased record for accepted orders.
Order Amount Desired Period1 40 42 30 63 30 24 25 3
9
Customer Order Processing Procedure
Item: P24 1 2 3 4 5 6 7 8Forecast 30 30 30 40 40 40 45 45Orders 13 8 4Available 60 30 70 30 60 20 45 70Available to promise 69 66 70 70 70MPS (Completion) 70 70 70 70 70On hand = 20, MPS lot size = 70
Perioda.
b. Order Amount Desired Period1 40 42 30 63 30 24 25 3
10
Customer Order Processing Procedure
b.
• The convention of the greater of forecast or orders is used in determining the projected available balance.
Item: P24 1 2 3 4 5 6 7 8Forecast 30 30 30 40 40 40 45 45Orders 13 38 29 40 30Available 60 22 62 22 52 12 37 62Available to promise 39 1 40 70 70MPS (Completion) 70 70 70 70 70On hand = 20, MPS lot size = 70
Period
Order Amount Desired Period Accept (Y or N) 1 40 4 Y2 30 6 Y3 30 2 Y4 25 3 Y
11
Rolling Through Time – Transactions Example
The following MPS time phased record has been prepared at the start of period 1.
Item: Smell fresh 1 2 3 4 5 6 7 8Forecast 20 20 20 30 30 30 30 30Orders 5 3 2 Available 50 30 10 30 50 20 40 10Available to promise 60 50 50 50MPS (Completion) 50 50 50 50
Period
On hand = 20, MPS lot size = 50
12
Rolling Through Time – Transactions Example
The following events occurred during period 1:
• Actual demand during period 1 was 25 units.• Marketing forecasted that 40 units would be
needed for period 9.• An order for 10 in period 2 was accepted.• An order for 20 in period 4 was accepted.• An order for 6 in period 3 was accepted.• The MPS in period 1 was produced as
planned.
13
Rolling through Time -Transactions/ Processing
b. Update the record below after rolling through time.
Beginning On Hand Period 1 = 20
Period 1 Actual Demand = -25
MPS Receipt Into Stock =+50
Beginning on Hand Period 2 = 45
Smell freshPeriod 2 3 4 5 6 7 8 9Forecast 20 20 30 30 30 30 30 40Orders 13 8 20 Available 25 5 25 45 15 35 5 15Available to promise 24 30 50 50 50MPS (Completion) 50 50 50 50On Hand = 45, MPS lot size = 50