1 mrp and erp chapter 14. 2 transparency on aggregate to master plan
TRANSCRIPT
3
Independent Demand
A
B(4) C(2)
D(1) E(1) D(3) F(2)
Dependent Demand
Independent demand is uncertain. Dependent demand is certain.
4
• Dependent demand: Demand for items that are subassemblies or component parts to be used in production of finished goods.
• Once the independent demand is known, the dependent demand can be determined.
Dependant Demand
5
• Material requirements planning (MRP): Computer-based information system that translates master schedule requirements for end items into time-phased requirements for subassemblies, components, and raw materials.
MRP
6
• Master Production Schedule• Time-phased plan specifying timing and quantity of production for
each end item.• Material Requirement Planning Process
Product Structure
Tree
Lead Times
7
MRP Inputs MRP Processing MRP Outputs
Masterschedule
Bill ofmaterials
file
Inventoryrecords
file
MRP computerprograms
Changes
Order releases
Planned-orderschedules
Exception reports
Planning reports
Performance-controlreports
Inventorytransaction
Primaryreports
Secondaryreports
MRP
9
Master ScheduleMaster schedule: One of three primary inputs in MRP;
states which end items are to be produced, when these are needed, and in what quantities.
Cumulative lead time: The sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of final assembly.
Time fences: Series of time intervals during which order changes are allowed or restricted.
10
Bill-of-Materials
Bill of materials: One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product.
Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels.
11
Product Structure Tree
Chair
Seat
Legs (2)Cross
barSide
Rails (2)Cross
barBack
Supports (3)
LegAssembly
BackAssembly
Level 0
1
2
12
Inventory Records
• One of the three primary inputs in MRP• Includes information on the status of
each item by time period– Gross requirements– Scheduled receipts– Amount on hand– Lead times– Lot sizes– And more …
14
MRP Processing
• Gross requirements
• Schedule requirements
• Projected on hand
• Net requirements
• Planned-order receipts
• Planned-order releases
15
MPR Processing
• Gross requirements
– Total expected demand
• Scheduled receipts
– Open orders scheduled to arrive
• Planned on hand
– Expected inventory on hand at the beginning of each time period
16
MPR Processing
• Net requirements
– Actual amount needed in each time period
• Planned-order receipts
– Quantity expected to received at the beginning of the period in which it is shown, reflecting the lot size
• Planned-order releases
– Planned amount to order in each time period; same as Planned-order receipts offset by lead time
17
Inventory Requirements
• Net requirements:
• Available Inventory:
Net Requirements = Gross Requirements – Available Inventory
Available Inventory = Projected on hand– Safety stock – Inventory allocated to other items
18
T14-1: MRP - Example
Master Schedule Week Number 1 2 3 4 5 6 7 8 for Shutters: Quantity 100 150
Shutters: Gross requirements 0 0 0 100 0 0 0 150Scheduled receipts
Quantity = 1 Projected on hand 0 0 0 0 0 0 0 0LT = 1 Net requirements 0 0 0 100 0 0 0 150
Lot Size = 1 Planned-order receipts 0 0 0 100 0 0 0 150Planned-order releases 0 0 100 0 0 0 150 0
Frames: Gross requirements 0 0 200 0 0 0 300 0Scheduled receipts
Quantity = 2 Projected on hand 0 0 0 120 120 120 120 140LT = 2 Net requirements 0 0 200 0 0 0 180 0
Lot Size = 320 Planned-order receipts 0 0 320 0 0 0 320 0Planned-order releases 320 0 0 0 320 0 0 0
Wood sections: Gross requirements 0 0 400 0 0 0 600 0Scheduled receipts 70
Quantity = 4 Projected on hand 70 70 70 20 20 20 20 50LT = 1 Net requirements 0 0 330 0 0 0 580 0
Lot Size = 70 Planned-order receipts 0 0 350 0 0 0 630 0Planned-order releases 0 350 0 0 0 630 0 0
Note: Use Lot Size = 1 for lot-for-lot ordering.
Clear
19
A Key MRP Output
• Planned orders (referring to Planned Order Releases)- schedule indicating the amount and timing of future orders. It tells us how when to order and how much, assuring us a lower level of inventory than if we did not use MRP.
20
Other MRP Outputs (MRP Secondary Reports)
• Performance-control reports
• Planning reports
• Exception reports
21
Capacity Planning
Capacity requirements planning: The process of determining short-range capacity requirements.
Load reports: Department or work center reports that compare known and expected future capacity requirements with projected capacity availability.
22
Capacity Requirements in MRP Planning
Develop a tentativemaster production
schedule
Develop a tentativemaster production
schedule
Use MRP tosimulate material
requirements
Use MRP tosimulate material
requirements
Convert materialrequirements to
resource requirements
Firm up a portionof the MPS
Is shopcapacity
adequate?
Cancapacity be
changed to meetrequirements
Revise tentativemaster production
schedule
Changecapacity
Yes
No
Yes
No
23
Benefits of MRP
• Low levels of in-process inventories
• Ability to track material requirements
• Ability to evaluate capacity requirements
• Means of allocating production time
24
Requirements of MRP• Computer and necessary software
• Accurate and up-to-date– Master schedules
– Bills of materials
– Inventory records
• Integrity of data
25
MRP II or Manufacturing Resource Planning
• Expanded MRP with and emphasis placed on integration
– Financial planning
– Marketing
– Engineering
– Purchasing
– Manufacturing
26
MarketDemand
Productionplan
Productionplan
Problems?Problems?
Rough-cutcapacity planning
Rough-cutcapacity planning
Yes No YesNo
Finance
Marketing
Manufacturing
Adjustproduction plan
Adjustproduction plan
Masterproduction schedule
Masterproduction schedule
MRP
Capacityplanning
Problems?Requirementsschedules
Requirementsschedules
Ad
just
mas
ter
sch
edu
le
MRP II
27
• Enterprise resource planning (ERP): – Next step in an evolution that began
with MPR and evolved into MRPII– Integration of financial, manufacturing,
and human resources on a single computer system.
ERP
28
ERP Software
– ERP software provides a system to capture and make data available in real time to decision makers and other users in the organization
– Provides tools for planning and monitoring various business processes
– Includes• Production planning and scheduling
• Inventory management
• Product costing
• Distribution
29
MRP in Services
• Service applications such as:– Professional services– Postal services– Retail– Banking– Healthcare– Higher education– Engineering– Logistical services– Real estate
30
ERP Strategy Considerations
• High initial cost
• High cost to maintain
• Future upgrades
• Training
31
The following slides are from a consultant who marketsERP systems. Please review the slides. As time permits.we can go through them in class. Note the reason for these slides is to illustrate a situation you might find yourself in if you are a manager in a company makinga decision to purchase an ERP system. It can be a veryintimidating process for your company when the sellerhas all the information about a complex system, and thebuyer is at the mercy of the seller’s knowledge and technical know-how.