1 nodal update for: single entry model (sem) go-live transition ndswg may 19, 2009 matt mereness
DESCRIPTION
3 SEM updates Today’s NMMS 6 Status: –NMMS 6 was released from FAT on 4/30/09 –NMMS 6 was loaded into Nodal iTest on 5/13/09; anticipate exiting N-iTest end of month. Issue escalation to TAC/ROS/WMS –Model posting issue- disclosure of Resource data (TAC/ROS/WMS) May 7 TAC direction to work with ROS and WMS on Resource data May 14 ROS and May 18 WMS direction to: –Consider posting CIM model only to TSPs in the interim (too much zonal market left) –Long-term concern with PUN/Load Profile data being in CIM file –Consider posting “clean” CIM file without Resource data for all MPs –SEM Go-Live approval without TPTF Initial direction to have ROS replace TPTF approval TAC chair asked to defer to next month discussion –Both would be changes to SEM Go-Live Procedure Consideration if Board approval is requiredTRANSCRIPT
http://nodal.ercot.com 1
Nodal Update for:Single Entry Model (SEM)Go-Live TransitionNDSWGMay 19, 2009Matt Mereness
http://nodal.ercot.com 2
SEM Go-Live Transition Update
• SEM updates– SEM Overview moved to Appendix
• Schedule review • Communications with stakeholders• Training Update• Ownership versus Operatorship • SEM Go-Live Criteria• Metric Discussion (NOMCR training & submission)• Processes/Submissions during June-Aug’09 transition• RARF Follow-up on validation
http://nodal.ercot.com 3
SEM updates • Today’s NMMS 6 Status:
– NMMS 6 was released from FAT on 4/30/09– NMMS 6 was loaded into Nodal iTest on 5/13/09; anticipate exiting N-iTest
end of month.
• Issue escalation to TAC/ROS/WMS– Model posting issue- disclosure of Resource data (TAC/ROS/WMS)
• May 7 TAC direction to work with ROS and WMS on Resource data• May 14 ROS and May 18 WMS direction to:
– Consider posting CIM model only to TSPs in the interim (too much zonal market left)– Long-term concern with PUN/Load Profile data being in CIM file– Consider posting “clean” CIM file without Resource data for all MPs
– SEM Go-Live approval without TPTF• Initial direction to have ROS replace TPTF approval• TAC chair asked to defer to next month discussion
– Both would be changes to SEM Go-Live Procedure• Consideration if Board approval is required
http://nodal.ercot.com 4
SEM updates (continued)
• Communication– May 6th to 15th TSP outreach through Wholesale Client Services
• TDSP/TO associations sent to 23 TOs• Solicit training headcount from TOs (pre and post Go-Live)
http://nodal.ercot.com 5
SEM updates (continued)
• Communication (continued)– May 15- Market Notice sent for SEM Kick-off call to occur– May 15- SEM Update provided on regular EDS Market Call– May 28- SEM Kick-off WebEx 10:00-11:30am
• Go-Live timelines and activities for June - August 2009 • Training overview and sign-up • Dates and access methods to test submissions of NOMCRs • Readiness metrics related to training and testing • Communications mailbox and SEM market call schedule
– Question- Will Friday morning market calls work or are some folks on 4x10 or 9x80 schedules?
http://nodal.ercot.com 6
Schedule Review
Coming into critical window of final Zonal->Nodal model transformation, market training, application roll-out
http://nodal.ercot.com 7
Communications with Stakeholder Meetings (cont’d)Apr Modeling Guidelines detailed review
Training update (content outline) Jun 1 – Aug 31 SvcReq limits and process Initial discussion of high-level transitional business
processes Discuss Transition Metrics for MPs SEM Update & Go-Live Criteria discussion
Update to ROS
May Publish final “draft” Modeling Guidelines Training update/documentation Follow-up discussion of high-level transitional
business processes Escalate- Model Posting/Disclosure, no TPTF apprv Discuss Transition Metrics for MPs SEM Update & Go-Live Criteria discussion EDS Kick-off of SEM
Update to ROS/TAC/WMS
Jun Publish final Modeling Guidelines Training Begins/Update NDSWG Publish SRs not in seed model Confirm final 30-day processes (Aug 1-31) SEM Update & Go-Live Criteria discussion
Update to ROS
Jul Joint NDSWG and SSWG meeting Status of SEM-EDS activities SEM Go-Live Entry Criteria satisfied
Update to ROS
Aug Confirm Go-Live activities Sign up for 2nd round of training
Approval from ROS in late July/early August for TAC to consider at Aug meeting
http://nodal.ercot.com 8
Training Update
• TSP Submission Testing and Training environments will be the same system
- Model to be used will be snapshot from October 2008
• Submission Testing system access – Available June 8 – Aug 10– NOMCR testing system will be on-line and available to all TSPs– ERCOT has established a dedicated email and have staff available to support questions
([email protected])– Existing “NMMS Sandbox” will be replaced in coming weeks
• Training to be hosted in Taylor – Pre-SEM classes June 22 – Aug 3
• Current plans for at least six 3-day sessions • Planning for 12-18 seats for each class• Large dedicated training room
– Post-SEM classes Sept 23- Oct 20• Fewer sessions and smaller classes (tbd)• Make-up classes, not just-in-time training for all staff after go-live
http://nodal.ercot.com 9
Training Update (continued)
• Thanks for the input provided on training• Concern over enough classroom time• Concern over which equipment types will be modeled in the class
• ERCOT extended from 2 to 3-Day Class• One class per week for 6 weeks• Start 1pm Tuesday / End noon Thursday
• Trainees can stay in Lab Thursday afternoon for Q&A• If schedule fills up, ERCOT will shorten class to 2-days for the overbooked weeks
• June 23-25, June 30- July 2• July 7- 9, 14-16, 21-23, 28-30
• Next 4 slides show summary of training format and equipment• Full training outline in Appendix (no change from last month)
• Testing/Training will only include Level 1 Validation• Level 1 – Automatic by the system upon submitting.• Level 2 – Visual by the N/W Model Coordinator• Level 3 – Power flow run on the one NOMCR.• Level 4 – Power flow run on all NOMCRs for that day.• Level 5 – Power flow run on the AREVA system.
Training (continued)
Training (continued)
Training (continued)
Training (continued)
http://nodal.ercot.com 14
Ownership vs Operatorship Issues Discussion• Friday, May 15 meeting
• ERCOT, MP-Volunteers (D.Bogen, C.Crews, Ebby John, Hill Brady)
• Discussion highlights• Ask ERCOT to provide how RARF Owner/Operator will be reflected in
NMMS when entered by ERCOT• Ask ERCOT to provide downstream consumption of Owner/Operator
NMMS, Outage Scheduler, Telemetry metrics• Should ERCOT consider recognition of Owner/Operator in Protocols 3.10 as
the TO in the Operating Guides• Concern with equipment owners that are unregistered-at-ERCOT being in
conflicting with NERC standards• Whether NMMS reporting could reflect a category of unregistered Owners
for reporting• Consider if early NMMS reports are “draft”• Questioned and answer that NMMS supports:
• Multiple Owners (percentages can be assigned) and single Operator
http://nodal.ercot.com 15
SEM Go-Live Criteria• SEM Go-Live Criteria defined in the SEM Go-Live Procedure
http://nodal.ercot.com/readiness/golive/index.html• Section 4- The following entry criteria shall be met for SEM Go-Live
– TSPs & ERCOT complete EDS 2 Release 4 activities (next page)– Nodal network model validated and approved as baseline for SEM Go-Live
by ERCOT System Ops and Market Ops Directors– ERCOT publishes CIM model to be used for SEM Go-Live– ERCOT sufficiently staffed for maintenance of nodal & zonal systems– Nodal EMS is capable of consuming NMMS CIM files through the EMS CIM
importer for use in the Nodal EMS application suite– SEM Go-Live readiness approved by TPTF, TAC and ERCOT BOD
• presume ROS approval in place of TPTF
– ERCOT publishes the following documents for TSPs• ERCOT Network Operations Model validation whitepaper• ERCOT Network Operations Model validation results• NMMS Modeling Guidelines / Validation Rules document• Latest CIM data dictionary and schema
http://nodal.ercot.com 16
SEM Go-Live Criteria (cont’d)– All TSPs complete EDS 2 Release 4 activities
• MPs have enrolled and can access the ERCOT MIS portal• MPs have been trained on the NOMCR process• TSPs can electronically submit data changes utilizing the NOMCR user interface and CIM
compliant format for data exchange or via the manual MIS NOMCR process• QSEs can submit data changes utilizing the registration submission and subsequent ERCOT
NOMCR process• MPs can receive NOMCR acknowledgement of submittals, verifications, and confirmation of
data posting
– ERCOT completes EDS 2 Release 4 activities• ERCOT is ready to fully utilize the NOMCR process for all TSP/QSE data change requests• TSP MPs can successfully submit data changes via the CIM compliant electronic NOMCR
process. • QSE can successfully submit data changes through registration submissions (and updated in
the Network Operations Model via the NOMCR process)• ERCOT has processes in place to use a “single entry point” to maintain both Nodal and
Zonal network model databases when MPs submit changes via the NOMCR process• NMMS is the database of record for the Network Operations Model including the ICCP
modeling point database and operatorship / ownership information• NMMS database is under full change control by ERCOT Network Model Group• ERCOT discontinues the use of Service Requests for data changes and change control• ERCOT begins the use of the NOMCR process for data changes and change control
http://nodal.ercot.com 17
Metric Discussion
MP14 – B – MP EDS-2, Release 4 Trials Participation
Reported By: TSP
Target Completion: Single Entry Model Go-Live minus 30 Days
Category: Trials Participation
Metric Description: This metric evaluates the level of TSP market participant participation in the EDS 2, Release 4 Trials.
Background: The intent of this metric is to ensure that Market Participants are actively participating in the NOMCR process.
Criteria: The Readiness Team will review documentation that an adequate number of TSPs have submitted modifications through the NMMS tool following the NOMCR process.
# of TSP MPs Participating in Trial participating in the NOMCR process >= 95%RAG Rules - MPs
Red - Not participating in trialsAmber – Not ApplicableGreen – Meeting criteria
RAG Rules – Market SegmentRed – Not meeting criteria
Amber – within 10 percent of criteriaGreen – meeting criteria
Reporting Data Sources: Self-Reported
References TP: 5.4.1 TNP: 3.10.8, 3.3.2.1, 3.10.7
Metric inventory posted at: http://nodal.ercot.com/readiness/metrics/index.html
For MPs, two metrics will be assessed during SEM Go-Live:
http://nodal.ercot.com 18
Metric Discussion (continued)MP13 – MP Completes Nodal Operations Related TrainingReported By: QSER, QSE, TSP
Target Completion: Cyclical in preparation for the 168-Hour Test and Go-Live transition sequence
Metric Description: Market Participants complete the applicable training modules associated with nodal operations related readiness
Background: The intent of this metric is to ensure that Market Participants participating in Nodal have adequate knowledge of the Nodal Operations to participate
Criteria: The Readiness Team will review self-reporting from each Market Participant indicating their level of training necessary to assure the Market Participant’s ability to successfully operate in the Nodal Market meets the scope of activities described in the ERCOT developed Training Materials included in the following courses.Basic Training Program;Non-Opt In Entity NOIE (QSE) Operations;Generation 101;Transmission 101; Network Model Management; ERCOT 101 for Wind Generation.
For Market ParticipantsCompleted Survey with All Positive Responses = Green
Completed Survey with One or More Negative Response = AmberDid Not Complete Survey = Red
For Market SegmentOver 95% of Market Share Responded Positively to the Survey = Green
Over 5% of Market Share Did Not Respond to the Survey = RedAny Alternative Scenario = Amber
Reporting Data Sources: Self-Reported Survey
References TP: TNP: N/A
http://nodal.ercot.com 19
Processes/Submissions during June-Aug’09 transition– Does NDSWG agree with this approach, and is approval needed?
– Transition periods:• June 1- Aug 30, 2009 (objective to minimize SvcReq during this period)
– No equipment name changes (defer until after SEM Go-Live 8/31/09) – Submit changes as far in advance as possible
• Aug 15-30, 2009– Two weeks no submissions, except for emergency changes
• Aug 31, 2009 - Feb 2010 (NOMCRs for any/all network changes)– Initially the NOMCR timeline will align with zonal timeline
» NOMCRs received and translated to zonal model change » 30-day lead-time, compliant with current zonal database schedule» Status is tracked and communicated via system emails
– SRs that did not go into zonal production will be converted to NOMCRs for verification and submission by TSPs in Sept
– TSP gradually transitions to NodalProtocols(3.10) 90-day reqts
http://nodal.ercot.com 20
RARF follow-up on validation
• Follow-up from previous NDSWG regarding validation rules for RARF– Resource Asset Registration spreadsheet files are submitted by Resource
Entities via a Service Request (this will not change in Nodal)– Validation steps:
– Limited enforcement in Excel file (drop-down fields)– Submission screening process
– RARF visually reviewed by Client reps for completeness– Audit process executed to enforce 1800 business rules
– Example Low Limits <= High Limits– ERCOT has matured process and posting validation rules for
current and future Planning and Transmission submissions– Plans to go-back after current RARF activities and create
market-facing validation rules by end-of-year– If issues found, RE contacted for correction
– Submission into NMMS subject to Network Modeling Guidelines
http://nodal.ercot.com 21
Questions
• Questions or comments can be submitted to:– [email protected]– [email protected]
http://nodal.ercot.com 22
APPENDIXOverview of SEMTraining Outline
http://nodal.ercot.com 23
SEM Go-Live Overview
• Single Entry Model (SEM) Go-Live is the switchover on Aug 31, 2009 for TSP submissions of network operations model change requests– from “Service Request” submissions via TML – to “NOMCR” submissions via the NMMS – System of record for Model remains Zonal/Genesys system until Dec 2010
TSPCurrent Activity
Submit Modeling Change via Service Request
ERCOT UploadsSvc Request
into ZonalGenesys Model
ERCOT Copies/ConvertsZonal Model “seed”
Into Nodal NMMS Model
TSPAug 31, 2009
Submit Modeling Change viaNOMCR/NMMS Tool
(includes ICCP)
ERCOT IncrementallyConverts NOMCR
Into Svc Req Uploads into ZonalGenesys Model
ERCOT uploads NOMCR
Into Nodal NMMS Model to
support nodal testingData Consistency Checks are run to ensure model synchronization/fidelity
Periodic checks are run to ensure model synchronization/fidelity
Full
Copy
Incr.
NOMCR
24
Current Network Operations Model Maintenance for TSPs
ERCOT Zonal EMMS Model(system of record through 12/1/2010)
Submits Service Request to Change Model
ERCOT Nodal NMMS Model(nodal testing model- CIM file for EMS/MMS/etc)
Periodic full copy and conversion of model (zonal seed used for nodal systems)
TSP
25
After 8/31/2009: SEM Go-Live Network Operations Model Maintenance for TSP
ERCOT Zonal EMMS Model(system of record through 12/1/2010)
ERCOT Nodal NMMS Model(nodal testing model- CIM file for EMS/MMS/etc)
ERCOT enters NOMCRs into zonal model
ERCOT runs consistency checks to ensure models are aligned and maintained
Submits Model Change Request (NOMCR)
TSP
NMMS ModelSystem of Record
Nodal Go-Live 12/1/2010
26
Network Operations Model Maintenance for Resource & QSE
ERCOT Zonal EMMS Model(system of record through 12/1/2010)
ERCOT Nodal NMMS Model(nodal testing model- CIM file for EMS/MMS/etc)
ERCOT enters into zonal model
NMMS ModelSystem of Record
Nodal Go-Live 12/1/2010
Submits RARF (Resource Asset Reg Form) via Service Request
Submits ICCP Change via Service Request
ERCOT processQSE
RE
http://nodal.ercot.com 27
General Review of SEM Transition (cont’d)
• The processes and approvals leading up to this activity were outlined in the SEM Go-Live Procedure approved by TPTF and TAC in Aug/Sep 2008
– http://nodal.ercot.com/readiness/golive/index.html
• In the coming months ERCOT will continue to provide updates to NDSWG and ROS on details of the implementation and switchover activities.
• All nodal presentations to NDSWG continue to be consolidated and posted on Nodal Readiness Center:
– http://nodal.ercot.com/readiness/eds2/documents/index.html
APPENDIX TRAINING-
TRAINING OUTLINE
TRAINING-Course Objectives:
• To give course participants:
• … a working level understanding of the time-line, participants, transition tasks, roles and responsibilities associated with the SEM go-live
• … a review of the basics of the ERCOT modeling process
Cont…
TRAINING- Course Objectives cont.:
• … proficiency in the handling of the “life of a NOMCR / SAMR” – understanding the process. This involves:
– Project Tracker & Coordinator entry– NOMCR creation– Model updates
» IMM changes» Upload CIM XML
– Validations & submissions– Status notifications– Additional features (history, archive, comments, filter, name mapping)
TRAINING- Course Agenda
Section 1: Introduction – Basics Review
Section 2: SEM highlights for transition
Section 3: NOMCR Creation (PTC)
Section 4: Modeling Overview
Section 5: A day in the life of a NOMCR
Section 6: Modeling Exercises
Section 7: Wrap Up
TRAINING- Section 1: Introduction – Basics Review
• Course Openers – Welcome, Objectives, Course Structure
• ERCOT Models – General, What gets modeled, Typical Attributes, The Network Operations Model, Derivative Models (Planning & CRR)
• The Operations Model: What’s Changing & Why it’s Changing. Roles and Responsibilities. The SEM Process – basics.
• Overview of the Change Submittal Process: The NOMCR & The SAMR
• Overview of the Change Submission User Interfaces: PTC and IMM
TRAINING- Section 2: SEM highlights for transition
• What is SEM?
• SEM Transition and Schedule
• SEM Pre Go-Live – Objectives and responsibilities
• SEM Go-Live – Actions during process
• SEM Post Go-Live - Actions
TRAINING- Section 3: NOMCR Creation (PTC)
• Project Tracker & Coordinator login and interface – Log-in, NOMCRs, SAMRs, the interface, Visibility states (public or private)
• Hands-on exercise: NOMCR Creation
TRAINING- Section 4: Modeling Overview
• Background on (ERCOT CIM) Network Operations model
• Overview of Modeling
• Validation Rules/Process
• Small hands-on activity (create, validate, and submit NOMCR)
TRAINING- Section 5: A day in the life of a NOMCR
• State Diagram Introduction – What it is and how to use it
• Definition of Terms - Walk-through of terms MPs will see:
• Explanation of the Status Table
• NOMCR Timelines – Including Interim Update provisions
• Walk through State Diagram – from a TSP and ERCOT perspective
• Exercise – based on flow process
TRAINING- Section 6: Modeling Exercises
• The entry of a NOMCR using scripted scenarios
• Usage of the Modeling Guidelines document
• Additional topics, as identified by course participants
TRAINING- Section 7: Wrap Up
• Discussion of any remaining items. Closing comments