http://nodal.ercot.com 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

Upload: roger-williamson

Post on 18-Jan-2018

219 views

Category:

Documents


0 download

DESCRIPTION

3 SEM updates Today’s NMMS 6 Status: –NMMS 6 was released from FAT on 4/30/09 –NMMS 6 was loaded into Nodal iTest on 5/13/09; anticipate exiting N-iTest end of month. Issue escalation to TAC/ROS/WMS –Model posting issue- disclosure of Resource data (TAC/ROS/WMS) May 7 TAC direction to work with ROS and WMS on Resource data May 14 ROS and May 18 WMS direction to: –Consider posting CIM model only to TSPs in the interim (too much zonal market left) –Long-term concern with PUN/Load Profile data being in CIM file –Consider posting “clean” CIM file without Resource data for all MPs –SEM Go-Live approval without TPTF Initial direction to have ROS replace TPTF approval TAC chair asked to defer to next month discussion –Both would be changes to SEM Go-Live Procedure Consideration if Board approval is required

TRANSCRIPT

Page 1: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 1

Nodal Update for:Single Entry Model (SEM)Go-Live TransitionNDSWGMay 19, 2009Matt Mereness

Page 2: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 2

SEM Go-Live Transition Update

• SEM updates– SEM Overview moved to Appendix

• Schedule review • Communications with stakeholders• Training Update• Ownership versus Operatorship • SEM Go-Live Criteria• Metric Discussion (NOMCR training & submission)• Processes/Submissions during June-Aug’09 transition• RARF Follow-up on validation

Page 3: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 3

SEM updates • Today’s NMMS 6 Status:

– NMMS 6 was released from FAT on 4/30/09– NMMS 6 was loaded into Nodal iTest on 5/13/09; anticipate exiting N-iTest

end of month.

• Issue escalation to TAC/ROS/WMS– Model posting issue- disclosure of Resource data (TAC/ROS/WMS)

• May 7 TAC direction to work with ROS and WMS on Resource data• May 14 ROS and May 18 WMS direction to:

– Consider posting CIM model only to TSPs in the interim (too much zonal market left)– Long-term concern with PUN/Load Profile data being in CIM file– Consider posting “clean” CIM file without Resource data for all MPs

– SEM Go-Live approval without TPTF• Initial direction to have ROS replace TPTF approval• TAC chair asked to defer to next month discussion

– Both would be changes to SEM Go-Live Procedure• Consideration if Board approval is required

Page 4: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 4

SEM updates (continued)

• Communication– May 6th to 15th TSP outreach through Wholesale Client Services

• TDSP/TO associations sent to 23 TOs• Solicit training headcount from TOs (pre and post Go-Live)

Page 5: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 5

SEM updates (continued)

• Communication (continued)– May 15- Market Notice sent for SEM Kick-off call to occur– May 15- SEM Update provided on regular EDS Market Call– May 28- SEM Kick-off WebEx 10:00-11:30am

• Go-Live timelines and activities for June - August 2009 • Training overview and sign-up • Dates and access methods to test submissions of NOMCRs • Readiness metrics related to training and testing • Communications mailbox and SEM market call schedule

– Question- Will Friday morning market calls work or are some folks on 4x10 or 9x80 schedules?

Page 6: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 6

Schedule Review

Coming into critical window of final Zonal->Nodal model transformation, market training, application roll-out

Page 7: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 7

Communications with Stakeholder Meetings (cont’d)Apr Modeling Guidelines detailed review

Training update (content outline) Jun 1 – Aug 31 SvcReq limits and process Initial discussion of high-level transitional business

processes Discuss Transition Metrics for MPs SEM Update & Go-Live Criteria discussion

Update to ROS

May Publish final “draft” Modeling Guidelines Training update/documentation Follow-up discussion of high-level transitional

business processes Escalate- Model Posting/Disclosure, no TPTF apprv Discuss Transition Metrics for MPs SEM Update & Go-Live Criteria discussion EDS Kick-off of SEM

Update to ROS/TAC/WMS

Jun Publish final Modeling Guidelines Training Begins/Update NDSWG Publish SRs not in seed model Confirm final 30-day processes (Aug 1-31) SEM Update & Go-Live Criteria discussion

Update to ROS

Jul Joint NDSWG and SSWG meeting Status of SEM-EDS activities SEM Go-Live Entry Criteria satisfied

Update to ROS

Aug Confirm Go-Live activities Sign up for 2nd round of training

Approval from ROS in late July/early August for TAC to consider at Aug meeting

Page 8: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 8

Training Update

• TSP Submission Testing and Training environments will be the same system

- Model to be used will be snapshot from October 2008

• Submission Testing system access – Available June 8 – Aug 10– NOMCR testing system will be on-line and available to all TSPs– ERCOT has established a dedicated email and have staff available to support questions

([email protected])– Existing “NMMS Sandbox” will be replaced in coming weeks

• Training to be hosted in Taylor – Pre-SEM classes June 22 – Aug 3

• Current plans for at least six 3-day sessions • Planning for 12-18 seats for each class• Large dedicated training room

– Post-SEM classes Sept 23- Oct 20• Fewer sessions and smaller classes (tbd)• Make-up classes, not just-in-time training for all staff after go-live

Page 9: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 9

Training Update (continued)

• Thanks for the input provided on training• Concern over enough classroom time• Concern over which equipment types will be modeled in the class

• ERCOT extended from 2 to 3-Day Class• One class per week for 6 weeks• Start 1pm Tuesday / End noon Thursday

• Trainees can stay in Lab Thursday afternoon for Q&A• If schedule fills up, ERCOT will shorten class to 2-days for the overbooked weeks

• June 23-25, June 30- July 2• July 7- 9, 14-16, 21-23, 28-30

• Next 4 slides show summary of training format and equipment• Full training outline in Appendix (no change from last month)

• Testing/Training will only include Level 1 Validation• Level 1 – Automatic by the system upon submitting.• Level 2 – Visual by the N/W Model Coordinator• Level 3 – Power flow run on the one NOMCR.• Level 4 – Power flow run on all NOMCRs for that day.• Level 5 – Power flow run on the AREVA system.

Page 10: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

Training (continued)

Page 11: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

Training (continued)

Page 12: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

Training (continued)

Page 13: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

Training (continued)

Page 14: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 14

Ownership vs Operatorship Issues Discussion• Friday, May 15 meeting

• ERCOT, MP-Volunteers (D.Bogen, C.Crews, Ebby John, Hill Brady)

• Discussion highlights• Ask ERCOT to provide how RARF Owner/Operator will be reflected in

NMMS when entered by ERCOT• Ask ERCOT to provide downstream consumption of Owner/Operator

NMMS, Outage Scheduler, Telemetry metrics• Should ERCOT consider recognition of Owner/Operator in Protocols 3.10 as

the TO in the Operating Guides• Concern with equipment owners that are unregistered-at-ERCOT being in

conflicting with NERC standards• Whether NMMS reporting could reflect a category of unregistered Owners

for reporting• Consider if early NMMS reports are “draft”• Questioned and answer that NMMS supports:

• Multiple Owners (percentages can be assigned) and single Operator

Page 15: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 15

SEM Go-Live Criteria• SEM Go-Live Criteria defined in the SEM Go-Live Procedure

http://nodal.ercot.com/readiness/golive/index.html• Section 4- The following entry criteria shall be met for SEM Go-Live

– TSPs & ERCOT complete EDS 2 Release 4 activities (next page)– Nodal network model validated and approved as baseline for SEM Go-Live

by ERCOT System Ops and Market Ops Directors– ERCOT publishes CIM model to be used for SEM Go-Live– ERCOT sufficiently staffed for maintenance of nodal & zonal systems– Nodal EMS is capable of consuming NMMS CIM files through the EMS CIM

importer for use in the Nodal EMS application suite– SEM Go-Live readiness approved by TPTF, TAC and ERCOT BOD

• presume ROS approval in place of TPTF

– ERCOT publishes the following documents for TSPs• ERCOT Network Operations Model validation whitepaper• ERCOT Network Operations Model validation results• NMMS Modeling Guidelines / Validation Rules document• Latest CIM data dictionary and schema

Page 16: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 16

SEM Go-Live Criteria (cont’d)– All TSPs complete EDS 2 Release 4 activities

• MPs have enrolled and can access the ERCOT MIS portal• MPs have been trained on the NOMCR process• TSPs can electronically submit data changes utilizing the NOMCR user interface and CIM

compliant format for data exchange or via the manual MIS NOMCR process• QSEs can submit data changes utilizing the registration submission and subsequent ERCOT

NOMCR process• MPs can receive NOMCR acknowledgement of submittals, verifications, and confirmation of

data posting

– ERCOT completes EDS 2 Release 4 activities• ERCOT is ready to fully utilize the NOMCR process for all TSP/QSE data change requests• TSP MPs can successfully submit data changes via the CIM compliant electronic NOMCR

process. • QSE can successfully submit data changes through registration submissions (and updated in

the Network Operations Model via the NOMCR process)• ERCOT has processes in place to use a “single entry point” to maintain both Nodal and

Zonal network model databases when MPs submit changes via the NOMCR process• NMMS is the database of record for the Network Operations Model including the ICCP

modeling point database and operatorship / ownership information• NMMS database is under full change control by ERCOT Network Model Group• ERCOT discontinues the use of Service Requests for data changes and change control• ERCOT begins the use of the NOMCR process for data changes and change control

Page 17: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 17

Metric Discussion

MP14 – B – MP EDS-2, Release 4 Trials Participation

Reported By: TSP

Target Completion: Single Entry Model Go-Live minus 30 Days

Category: Trials Participation

Metric Description: This metric evaluates the level of TSP market participant participation in the EDS 2, Release 4 Trials.

Background: The intent of this metric is to ensure that Market Participants are actively participating in the NOMCR process.

Criteria: The Readiness Team will review documentation that an adequate number of TSPs have submitted modifications through the NMMS tool following the NOMCR process.

# of TSP MPs Participating in Trial participating in the NOMCR process >= 95%RAG Rules - MPs

Red - Not participating in trialsAmber – Not ApplicableGreen – Meeting criteria

RAG Rules – Market SegmentRed – Not meeting criteria

Amber – within 10 percent of criteriaGreen – meeting criteria

Reporting Data Sources: Self-Reported

References TP: 5.4.1 TNP: 3.10.8, 3.3.2.1, 3.10.7

Metric inventory posted at: http://nodal.ercot.com/readiness/metrics/index.html

For MPs, two metrics will be assessed during SEM Go-Live:

Page 18: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 18

Metric Discussion (continued)MP13 – MP Completes Nodal Operations Related TrainingReported By: QSER, QSE, TSP

Target Completion: Cyclical in preparation for the 168-Hour Test and Go-Live transition sequence

Metric Description: Market Participants complete the applicable training modules associated with nodal operations related readiness

Background: The intent of this metric is to ensure that Market Participants participating in Nodal have adequate knowledge of the Nodal Operations to participate

Criteria: The Readiness Team will review self-reporting from each Market Participant indicating their level of training necessary to assure the Market Participant’s ability to successfully operate in the Nodal Market meets the scope of activities described in the ERCOT developed Training Materials included in the following courses.Basic Training Program;Non-Opt In Entity NOIE (QSE) Operations;Generation 101;Transmission 101; Network Model Management; ERCOT 101 for Wind Generation.

For Market ParticipantsCompleted Survey with All Positive Responses = Green

Completed Survey with One or More Negative Response = AmberDid Not Complete Survey = Red

For Market SegmentOver 95% of Market Share Responded Positively to the Survey = Green

Over 5% of Market Share Did Not Respond to the Survey = RedAny Alternative Scenario = Amber

Reporting Data Sources: Self-Reported Survey

References TP: TNP: N/A

Page 19: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 19

Processes/Submissions during June-Aug’09 transition– Does NDSWG agree with this approach, and is approval needed?

– Transition periods:• June 1- Aug 30, 2009 (objective to minimize SvcReq during this period)

– No equipment name changes (defer until after SEM Go-Live 8/31/09) – Submit changes as far in advance as possible

• Aug 15-30, 2009– Two weeks no submissions, except for emergency changes

• Aug 31, 2009 - Feb 2010 (NOMCRs for any/all network changes)– Initially the NOMCR timeline will align with zonal timeline

» NOMCRs received and translated to zonal model change » 30-day lead-time, compliant with current zonal database schedule» Status is tracked and communicated via system emails

– SRs that did not go into zonal production will be converted to NOMCRs for verification and submission by TSPs in Sept

– TSP gradually transitions to NodalProtocols(3.10) 90-day reqts

Page 20: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 20

RARF follow-up on validation

• Follow-up from previous NDSWG regarding validation rules for RARF– Resource Asset Registration spreadsheet files are submitted by Resource

Entities via a Service Request (this will not change in Nodal)– Validation steps:

– Limited enforcement in Excel file (drop-down fields)– Submission screening process

– RARF visually reviewed by Client reps for completeness– Audit process executed to enforce 1800 business rules

– Example Low Limits <= High Limits– ERCOT has matured process and posting validation rules for

current and future Planning and Transmission submissions– Plans to go-back after current RARF activities and create

market-facing validation rules by end-of-year– If issues found, RE contacted for correction

– Submission into NMMS subject to Network Modeling Guidelines

Page 21: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 21

Questions

• Questions or comments can be submitted to:– [email protected][email protected]

Page 22: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 22

APPENDIXOverview of SEMTraining Outline

Page 23: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 23

SEM Go-Live Overview

• Single Entry Model (SEM) Go-Live is the switchover on Aug 31, 2009 for TSP submissions of network operations model change requests– from “Service Request” submissions via TML – to “NOMCR” submissions via the NMMS – System of record for Model remains Zonal/Genesys system until Dec 2010

TSPCurrent Activity

Submit Modeling Change via Service Request

ERCOT UploadsSvc Request

into ZonalGenesys Model

ERCOT Copies/ConvertsZonal Model “seed”

Into Nodal NMMS Model

TSPAug 31, 2009

Submit Modeling Change viaNOMCR/NMMS Tool

(includes ICCP)

ERCOT IncrementallyConverts NOMCR

Into Svc Req Uploads into ZonalGenesys Model

ERCOT uploads NOMCR

Into Nodal NMMS Model to

support nodal testingData Consistency Checks are run to ensure model synchronization/fidelity

Periodic checks are run to ensure model synchronization/fidelity

Full

Copy

Incr.

NOMCR

Page 24: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

24

Current Network Operations Model Maintenance for TSPs

ERCOT Zonal EMMS Model(system of record through 12/1/2010)

Submits Service Request to Change Model

ERCOT Nodal NMMS Model(nodal testing model- CIM file for EMS/MMS/etc)

Periodic full copy and conversion of model (zonal seed used for nodal systems)

TSP

Page 25: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

25

After 8/31/2009: SEM Go-Live Network Operations Model Maintenance for TSP

ERCOT Zonal EMMS Model(system of record through 12/1/2010)

ERCOT Nodal NMMS Model(nodal testing model- CIM file for EMS/MMS/etc)

ERCOT enters NOMCRs into zonal model

ERCOT runs consistency checks to ensure models are aligned and maintained

Submits Model Change Request (NOMCR)

TSP

NMMS ModelSystem of Record

Nodal Go-Live 12/1/2010

Page 26: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

26

Network Operations Model Maintenance for Resource & QSE

ERCOT Zonal EMMS Model(system of record through 12/1/2010)

ERCOT Nodal NMMS Model(nodal testing model- CIM file for EMS/MMS/etc)

ERCOT enters into zonal model

NMMS ModelSystem of Record

Nodal Go-Live 12/1/2010

Submits RARF (Resource Asset Reg Form) via Service Request

Submits ICCP Change via Service Request

ERCOT processQSE

RE

Page 27: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

http://nodal.ercot.com 27

General Review of SEM Transition (cont’d)

• The processes and approvals leading up to this activity were outlined in the SEM Go-Live Procedure approved by TPTF and TAC in Aug/Sep 2008

– http://nodal.ercot.com/readiness/golive/index.html

• In the coming months ERCOT will continue to provide updates to NDSWG and ROS on details of the implementation and switchover activities.

• All nodal presentations to NDSWG continue to be consolidated and posted on Nodal Readiness Center:

– http://nodal.ercot.com/readiness/eds2/documents/index.html

Page 28: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

APPENDIX TRAINING-

TRAINING OUTLINE

Page 29: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

TRAINING-Course Objectives:

• To give course participants:

• … a working level understanding of the time-line, participants, transition tasks, roles and responsibilities associated with the SEM go-live

• … a review of the basics of the ERCOT modeling process

Cont…

Page 30: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

TRAINING- Course Objectives cont.:

• … proficiency in the handling of the “life of a NOMCR / SAMR” – understanding the process. This involves:

– Project Tracker & Coordinator entry– NOMCR creation– Model updates

» IMM changes» Upload CIM XML

– Validations & submissions– Status notifications– Additional features (history, archive, comments, filter, name mapping)

Page 31: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

TRAINING- Course Agenda

Section 1: Introduction – Basics Review

Section 2: SEM highlights for transition

Section 3: NOMCR Creation (PTC)

Section 4: Modeling Overview

Section 5: A day in the life of a NOMCR

Section 6: Modeling Exercises

Section 7: Wrap Up

Page 32: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

TRAINING- Section 1: Introduction – Basics Review

• Course Openers – Welcome, Objectives, Course Structure

• ERCOT Models – General, What gets modeled, Typical Attributes, The Network Operations Model, Derivative Models (Planning & CRR)

• The Operations Model: What’s Changing & Why it’s Changing. Roles and Responsibilities. The SEM Process – basics.

• Overview of the Change Submittal Process: The NOMCR & The SAMR

• Overview of the Change Submission User Interfaces: PTC and IMM

Page 33: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

TRAINING- Section 2: SEM highlights for transition

• What is SEM?

• SEM Transition and Schedule

• SEM Pre Go-Live – Objectives and responsibilities

• SEM Go-Live – Actions during process

• SEM Post Go-Live - Actions

Page 34: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

TRAINING- Section 3: NOMCR Creation (PTC)

• Project Tracker & Coordinator login and interface – Log-in, NOMCRs, SAMRs, the interface, Visibility states (public or private)

• Hands-on exercise: NOMCR Creation

Page 35: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

TRAINING- Section 4: Modeling Overview

• Background on (ERCOT CIM) Network Operations model

• Overview of Modeling

• Validation Rules/Process

• Small hands-on activity (create, validate, and submit NOMCR)

Page 36: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

TRAINING- Section 5: A day in the life of a NOMCR

• State Diagram Introduction – What it is and how to use it

• Definition of Terms - Walk-through of terms MPs will see:

• Explanation of the Status Table

• NOMCR Timelines – Including Interim Update provisions

• Walk through State Diagram – from a TSP and ERCOT perspective

• Exercise – based on flow process

Page 37: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

TRAINING- Section 6: Modeling Exercises

• The entry of a NOMCR using scripted scenarios

• Usage of the Modeling Guidelines document

• Additional topics, as identified by course participants

Page 38: 1 Nodal Update for: Single Entry Model (SEM) Go-Live Transition NDSWG May 19, 2009 Matt Mereness

TRAINING- Section 7: Wrap Up

• Discussion of any remaining items. Closing comments