Page 1: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

1

Purchasing and Procurement Processes

Module FourRevision Date: 2/06/2015

Page 2: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

2

COURSE INTRODUCTION

Course Overview & Learning Objectives

Course Expectations

Training Approach & Participation Protocol

Page 3: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

3© WA Department of Enterprise Services

Mutual Respect

General guidelines for online meetings:

Interact

Engage

Participate

Page 4: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

4© WA Department of Enterprise Services

Training Credit

To complete the module and receive credit, you will be expected to achieve a 80% on

the module assessment . Employees should log into LMS to complete each module

assessment. Use of the participant workbook is encouraged in the assessment!

Page 5: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

5© WA Department of Enterprise Services

Course Overview

Course will be delivered in four modules: Module 1: Purchasing & Procurement

Overview Module 2: Choosing a Route for Purchases of

Goods and Procurement of Services Module 3: Competitive Procurements,

Amendments, and Exemptions Module 4: Purchasing & Procurement

Processes

Page 6: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

6© WA Department of Enterprise Services

Module Overview

Section One

The Planning Process

Section Two

Solicitation and Selection

Section Three

Post-Procurement

Page 7: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

7© WA Department of Enterprise Services

Learning Objectives

As a result of this training participants will be able to:

Identify purchasing and procurement needs and outcomes

Describe the importance of communicating need within the agency

Identify scope, timeline, requirements and vendors as part of the planning process

Discuss how to evaluate and select a vendor Apply the purchasing and procurement planning phases

Page 8: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

8

THE PLANNING PROCESS

Identify the Need and Outcomes

Communicate Need Within Agency

Identify Scope, Timeline and Requirements

Identify Vendors

Define Scope and/or Statement of Work

Page 9: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

9© WA Department of Enterprise Services

Procurement Steps1. Identify the Need and Outcomes

2. Communicate Need Within Agency

3. Identify Scope, Timeline and Requirements

4. Identify Vendors

5. Define Scope and/or Statement of Work

6. Communicate Formal Need With Vendors

7. Evaluate Vendors

8. Select Vendor

9. Negotiate Contract

10. Contract Execution and Management

Pla

nni

ng P

hase

Sol

icita

tion

& S

ele

ctio

nP

ost

Pro

cure

men

t

Page 10: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

10© WA Department of Enterprise Services

Collaboration and Planning

Collaboration is important – Work with Business Owners, Subject Matter Experts

and Stakeholders

Page 11: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

11© WA Department of Enterprise Services

Identify the Need and OutcomesStep 1

Why does your agency purchase goods and services?

Page 12: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

12© WA Department of Enterprise Services

Identify the Need and OutcomesStep 1

Critical Thinking & Outcomes of a Purchase or Procurement

Identify Need

Identify Alternatives

Available

Evaluate & Analyze

Identify Outcomes

Page 13: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

13© WA Department of Enterprise Services

Communicate Agency Need Step 2

1. Initiate planning process

2. Engage SMEs,

business owner and

other stakeholders

3. Conduct independent

research

4. Determine checkpoints

and delegated authority

Page 14: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

14© WA Department of Enterprise Services

Purchasing vs. Procurement

Purchasing - the process of obtaining goods and services for the State of Washington.

Procurement - the combined functions of identifying needs, initiating a procurement project, selecting a vendor, contracting with a vendor, purchasing of the goods or services, managing the resulting contract.

Page 15: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

15© WA Department of Enterprise Services

Identify Scope, Requirements and Timeline

Step 3

Identify and define the scope and overall contract timeline

Page 16: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

16© WA Department of Enterprise Services

Identify Scope, Requirements and TimelineStep 3

Contract Purpose

High-level Functional

Areas

Contractor Responsibilities

Contract Phases & Timeline

What is NOT in Scope?

Page 17: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

17© WA Department of Enterprise Services

Identify Scope, Requirements and TimelineStep 3

Common Pitfalls in Scope of Work/Requirements Writing

• Too strict and rigid• Not enough details• Written to a certain vendor or solution• Outdated or obsolete requirements

Page 18: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

18© WA Department of Enterprise Services

Identify VendorsStep 4

1. DES Vendor Lists

2. Knowledge of Vendor

Marketplace

3. Vendor Pre-Bid

Communication

4. Other Sources

Page 19: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

19© WA Department of Enterprise Services

Define Scope and/or Statement of WorkStep 5

Scope or Work vs. Statement of Work

Page 20: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

20© WA Department of Enterprise Services

Define Statement of WorkStep 5

Statement of Work

Requirements &

Specifications

Project History &

Objectives

Deliverables

MilestonesSchedule

Reporting Requirements

Performance Standards

Page 21: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

21

SOLICITATION AND SELECTION

Communicate Formal Need With Vendors

Evaluate Vendors

Select Vendor

Page 22: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

22© WA Department of Enterprise Services

Procurement Steps1. Identify the Need and Outcomes

2. Communicate Need Within Agency

3. Identify Scope, Timeline and Requirements

4. Identify Vendors

5. Define Scope and/or Statement of Work

6. Communicate Formal Need With Vendors

7. Evaluate Vendors

8. Select Vendor

9. Negotiate Contract

10. Contract Execution and Management

Pla

nni

ng P

hase

Sol

icita

tion

& S

ele

ctio

nP

ost

Pro

cure

men

t

Page 23: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

23© WA Department of Enterprise Services

Communicate Formal Need to VendorsStep 6

Request For Quote

/Quotation

OR Qualifications

(RFQ)

Request For Proposal

(RFP)/Request for Bids (RFB)

Request For Qualifications

and Quotation (RFQQ)

Communicate

Page 24: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

24© WA Department of Enterprise Services

Communicate Formal Need with VendorsStep 6

Solicitation Need RFQ RFQQ RFP/RFB

Standard, Ongoing Purchase X X

Many Vendors Offer This X X

Cost is the Most Important Factor X

Vendor Qualifications and Performance Important in Addition to Cost

X X

Vendor Specialization / Few Offer This X

Complex Project Needs X

Solution Required to Meet Need X

Page 25: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

25© WA Department of Enterprise Services

Communicate Formal Need with Vendors

Step 6

Assign Procurement Coordinator

•Define list of potential vendors

•Encourage WEBS registration

Draft Solicitation Content

•Requirements tailored to level of complexity

Issue Solicitation

•Use WEBS•Post Amendments on WEBS

Receive Bids

•Document date/time

•Maintain confidentiality

Page 26: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

26© WA Department of Enterprise Services

Communicate Formal Need with VendorsStep 6

Evaluate Costs /Rates

• Rank based on lowest cost or rate

Award

• Lowest cost, responsive bidder

Post Results

• WEBS• Notify

successful & unsuccessful Bidders

Negotiate & Award Contract

• Conduct Debriefings

• Negotiate & award the contract

Page 27: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

27© WA Department of Enterprise Services

Communicate Formal Need with Vendors - Step 6

Select Team

•Establish Team Roles

•Write Specifications

• Identify RFP/RFB Coordinator for the project

•Score and rank Bids

Draft RFP/RFB Content

•Project approach and methodology

•Finalize Scope of Work

•Outcomes and Performance Measures

•Deliverables and milestones

•Management and staffing plan

•Bidder responses format

•Cost response format

Finalize and Release RFP/RFB

•Stakeholders review draft RFP

•Finalize RFP for release

•Post and publish RFP

Post Release Activities

•Respond to Bidder questions

•Draft amendments or addendums

Evaluation Process (Step 7)

Page 28: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

28© WA Department of Enterprise Services

Communicate Formal Need w/ Vendors - Cost Sheets Step 6

Vendor Name Cost

Time

Materials

Total:

Vendor Name Deliverable Cost

Deliverable A

Deliverable B

Deliverable C

Total:

Vendor Name

Hourly Rate

Hours Total

Staff level

Total:

Page 29: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

29© WA Department of Enterprise Services

Evaluate VendorsStep 7

Evaluation Objectives

Provide clear direction and guidance Ensure integrity of fair evaluation process Create a documented process Recommend for contract award

Page 30: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

30© WA Department of Enterprise Services

Evaluate VendorsStep 7

Evaluation Step Considerations

Confidentiality and Security Conflict of Interest Evaluation Milestones Evaluator Availability?

Page 31: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

31© WA Department of Enterprise Services

Evaluate VendorsStep 7

Procurement

Coordinator

• Ensure Adherence

• Prepare & Distribute

Evaluation Committee

• Evaluate• Score

Executive Sponsorship

• Supports & Authorizes

• Controls Expenditures

Evaluation Roles include ….

Page 32: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

32© WA Department of Enterprise Services

Evaluate VendorsStep 7

Phase 1• Initial Screening

Phase 2

• Evaluation of Technical and Management Response

Phase 3

• Oral Presentations (if applicable)

Phase 4

• Evaluation of Cost Proposals

Phase 5

• Best and Final Offers (BAFO)

Phase 6

• Ranking of Proposals

Page 33: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

33© WA Department of Enterprise Services

Evaluate VendorsStep 7

Technical Evaluation

Technical Evaluation CriteriaPoints

(Weighted Score)

1 Executive Summary (75 points max) and Vendor Identifying Information (25 points max)

100

2 Qualifications of Firm (300 points max) 300

3 Approach to Scope of Work (300 points max)

300

4 Qualifications of Proposed Key Personnel (200 points max)

200

5 Corporate References (100 points max) 100

6 Total Weighted Score 1000

Page 34: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

34© WA Department of Enterprise Services

Evaluate VendorsStep 7

Cost Evaluations

Vendor Name CostVendor A $150,000

Vendor B $175,000

Vendor C $180,000

Page 35: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

35© WA Department of Enterprise Services

Evaluate VendorsStep 7

Cost Evaluation

Cost Component

Vendor A Vendor B Vendor C

Supplies $50,000 $60,000 $70,000

Staff $50,000 $90,000 $90,000

Administrative Expenses

$20,000 $5,000 $5,000

Profit/Overhead $30,000 $20,000 $15,000

Total $150,000 $175,000 $180,000

Page 36: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

36© WA Department of Enterprise Services

Select VendorStep 8

Once the evaluation is complete

Award to Highest Scoring Bidder

OR

Reject all Bids or Re-Issue the Solicitation

Page 37: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

37© WA Department of Enterprise Services

Select VendorStep 8

Once all bidders have been notified, conduct debriefings if requested.

Following the award, as you get ready to negotiate and establish a contract make sure the solicitation files are complete.

Page 38: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

38

POST-PROCUREMENT

Negotiate Contract

Contract Execution and Management

Page 39: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

39© WA Department of Enterprise Services

Procurement Steps1. Identify the Need and Outcomes

2. Communicate Need Within Agency

3. Identify Scope, Timeline and Requirements

4. Identify Vendors

5. Define Scope and/or Statement of Work

6. Communicate Formal Need With Vendors

7. Evaluate Vendors

8. Select Vendor

9. Negotiate Contract

10. Contract Execution and Management

Pla

nni

ng P

hase

Sol

icita

tion

& S

ele

ctio

nP

ost

Pro

cure

men

t

Page 40: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

40© WA Department of Enterprise Services

Negotiate ContractStep 9

Conduct Baseline Contract Review

Edit contract based on proposal

Finalize and Route

for Signatures

Contract Starts

Page 41: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

41© WA Department of Enterprise Services

Contract Execution and Management Transition Step 10

Contract Execution

Initial Kick-off Meeting

Contract Management Framework

Project

Management

Page 42: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

42© WA Department of Enterprise Services

Ongoing Contract Management

Schedule Monitoring

Risk Mitigation

Compliance with T&C Approve

Contractor Invoices

Contract Execution and Management Transition Step 10

Page 43: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

43© WA Department of Enterprise Services

Summary & Key Points

Identified purchasing and procurement needs and outcomes

Described the importance of communicating need within the agency

Identified scope, requirements and timeline, and vendors as part of the planning process

Discussed how to evaluate and select a vendor Applied the purchasing and procurement planning

phases

Page 44: 1 Purchasing and Procurement Processes Module Four Revision Date: 2/06/2015

44© WA Department of Enterprise Services

Next Steps

Complete test and achieve 80% or higher Complete evaluation form