Target Costing

If you cannot find the time to do it right, how will you find the time to do it over?

Page 2: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

2

General Concept

Target cost is the cost that can be incurred while still earning the desired profit

Selling price – desired profit = target cost

The customer sets the price

Profit must be achieved through cost control

Page 3: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

3

Target Costing Characteristics

Contradicts the traditional approach: design product, determine cost, set price

Intense customer focus

What do they want?

How much will they pay for it?

Can we make a profit on it?

Want answers to these questions before committing to the project

Page 4: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

4

Target Costing Characteristics

Cost control from the beginning

70-90% of costs are committed to at the design stage

Focus on product and process design to engineer out costs from the beginning

Saves costly changes later on

Page 5: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

5

Target Costing Characteristics

Product, manufacturing process, delivery process designed simultaneously

Ensures features customers demand, but within acceptable cost parameters

Eliminates the temptation to add costly features

Customers may not value the added features

Forces consideration of manufacturability

Reduces the need for subsequent changes

Page 6: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

6

Target Costing Characteristics

Cost control at all phases of the product life cycle

Design

Production

Delivery/setup

Customer’s cost of ownership

Emphasizes future sales instead of current cost savings

Service and repair

Disposal and recycling

Page 7: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

7

Cross-Functional Team

Marketing

Design/engineering

Manufacturing

Purchasing

Including suppliers

Distribution

Service/support

Cost accounting

Finance

Legal

Page 8: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

8

Target Costing Process

Two stage process

Establish the target cost

Market research

Product planning, concept development stages

Achieve the target cost

Value engineering, continuous improvement

Design stage

Continuous improvement in later stages

Page 9: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

9

Establishing the Target Cost

Determine the product and its market

Who is the target market?

What do they want?

What do competitors offer?

Introduce concept or prototype

Evolutionary or revolutionary?

Refine until it meets customer needs

Page 10: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

10

Establishing the Target Cost

Determine the selling price

Must be acceptable to the customer

Must be able to withstand competition

Techniques

Existing price +/- value of features added or deleted

Consensus of focus group

Price predicted to achieve a desired market share

Page 11: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

11

Establishing the Target Cost

Determine the required profit

Return on sales

Desired return

Historical return for similar products

Industry average for similar products

Return on sales will fluctuate over the life of the product

Price and costs fluctuate

Page 12: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

12

Establishing the Target Cost

Product Life Stage

Uni

t Sel

ling

Pric

e

Page 13: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

13

Establishing the Target Cost

Product Life Stage

Uni

t Cos

t

Gradual decline as volume increases

Competitors enter market, straining supply of resources

Unexpected events affect cost of resources

Page 14: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

14

Establishing the Target Cost

Unit price, cost and profit are almost meaningless because they fluctuate

Life cycle totals are more meaningful

Total expected revenue throughout product life

- Total desired profit throughout product life

Total target cost

Page 15: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

15

Achieving the Target Cost

Must include the features the customer wants while maintaining cost at or below target

Want to meet the customers needs, but not exceed them

Eliminating desired features will result in an undesirable product

Adding unwanted features will increase cost

Failing to keep cost at or below target will result in unacceptable profits

Page 16: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

16

Achieving the Target Cost

Rank customer requirements (exhibit 1)

What does the customer want?

How important is each function to the customer?

What do we and our competitors currently offer? Competitive evaluation (exhibit 1)

Do our current product features meet the customer needs?

Are the customers’ needs met, unmet or exceeded?

What can we learn from our competitors’ products?

Page 17: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

17

Achieving the Target Cost

EXHIBIT 1CUSTOMER REQUIREMENT RANKINGS

Less More Raw % of Total

Customer Requirement Important Score Raw Score

1 2 3 4 5 1 2 3 4 5

Multiple speeds 4 4 14.8%

Horizontal oscillation 3 3 11.1%

Vertical oscillation 1 1 3.7%

Light weight 4 4 14.8%

Adjustable height 1 1 3.7%

Airflow capacity 4 4 14.8%

Quietness 5 5 18.5%

Compact size 3 3 11.1%

Looks nice 2 2 7.4%

Total 27 100%

Us

Competitor

Both

Important

Competitive

Comparison

Ranking

Page 18: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

18

Achieving the Target Cost

Determine the cost gap between current cost and allowable cost

Current cost is based on

Currently used components

Current suppliers

Current manufacturing processes

Current distribution network

Etc.

Page 19: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

19

Achieving the Target Cost

Decompose the cost gap (exhibit 2)

Life cycle decomposition Cost reduction goals are divided among the functions in

the product’s life cycle

Design/engineering

Manufacturing

Sales/distribution

Service/support

General administration

Etc.

Page 20: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

20

Achieving the Target Cost

Value chain decomposition

Cost reduction targets are divided among internal and external activities

Internal costs

Labor, overhead, selling and administrative costs, etc.

External costs

Components and services acquired from suppliers, etc.

Often represent a large proportion of total cost

Page 21: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

21

Achieving the Target Cost

EXHIBIT 2COST GAP BREAKDOWN BY LIFE CYCLE AND VALUE CHAIN

Life Cycle

Target Current Gap Target Current Gap Target Current Gap

Research and development 0.30$ 0.50$ 0.20$ 0.30$ 0.50$ 0.20$

Manufacturing 4.00 5.00 1.00 13.00$ 15.00$ 2.00$ 17.00 20.00 3.00

Marketing and distribution 1.50 2.00 0.50 4.50 5.00 0.50 6.00 7.00 1.00

Service and support 0.25 0.50 0.25 0.25 0.50 0.25

General administration 0.75 1.00 0.25 0.75 1.00 0.25

Total 6.80$ 9.00$ 2.20$ 17.50$ 20.00$ 2.50$ 24.30$ 29.00$ 4.70$

Internal Costs External Costs Total Costs

Value Chain

Page 22: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

22

Achieving the Target Cost

Perform value engineering to design out costs without sacrificing needed features

Perform a cost analysis of major components and activities

List components or activities and their functions

Calculate a cost breakdown (exhibit 3)

Determine the current cost of each component or activity and convert to percentage of total cost

Costs include materials, labor, overhead, etc.

Page 23: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

23

Achieving the Target Cost

EXHIBIT 3COMPONENT COST BREAKDOWN

Percent of

Component Function Cost total cost

Motor Turns blade 8$ 40%

Transmission Provides oscillation capabilities 4 20%

Speed control/switch Controls blade speed 3 15%

Body Houses motor, transmission, speed control 2 10%

Blade Moves air 1 5%

Blade guard Protects blade from contacting objects 2 10%

Total 20$ 100%

Page 24: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

24

Achieving the Target Cost

Relate the components to customer requirements (exhibit 4)

Develop Quality-Function-Deployment matrix

Indicates which components have the greatest impact on customer requirements

Develop a functional ranking (exhibit 5)

Indicates the importance of each component to the customer

Based on the component’s contribution to providing the desired functions

Page 25: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

25

Achieving the Target Cost

EXHIBIT 4QUALITY-FUNCTION-DEPLOYMENT (QFD) MATRIX

Speed Blade

Motor Transmission control Body Blade guard

Multiple speeds

Horizontal oscillation

Vertical oscillation

Light weight

Adjustable height

Airflow capacity

Quietness

Compact size

Looks nice

Strong correlationModerate correlationWeak correlation

Components

Customer Requirements

Page 26: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

26

Achieving the Target Cost

EXHIBIT 5COMPONENT CONTRIBUTION TO CUSTOMER REQUIREMENTS

Customer Requirements Speed Blade

Motor Transmission control Body Blade guard

Multiple speeds 40 X 14.8 = 5.92 60 X 14.8 = 8.88

Horizontal oscillation 80 X 11.1 = 8.88 20 X 11.1 = 2.22

Vertical oscillation 80 X 3.7 = 2.96 20 X 3.7 = 0.74

Light weight 70 X 14.8 = 10.36 10 X 14.8 = 1.48 20 X 14.8 = 2.96

Adjustable height 100 X 3.7 = 3.70

Airflow capacity 50 X 14.8 = 7.40 50 X 14.8 = 7.40

Quietness 40 X 18.5 = 7.40 60 X 18.5 = 11.10

Compact size 5 X 11.1 =0.56 5 X 11.1 =0.56 30 X 11.1 =3.33 30 X 11.1 =3.33 30 X 11.1 =3.33

Looks nice 50 X 7.4 = 3.70 50 X 7.4 = 3.70

Total contribution percentage 31.64% 13.88% 8.88% 16.65% 21.83% 7.03%

Components

Contribution weight assigned to the component * importance to the customer (exhibit 1)

Page 27: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

27

Achieving the Target Cost

Identify components for cost reduction Calculate a value index for each major component

(exhibit 6)

Component cost as a percentage of total cost divided by the component’s relative importance to the customer

Index greater than 1

Disproportionately high cost in relation to its importance

Implies cost reduction should be considered

Do not manage by the numbers alone

Page 28: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

28

Achieving the Target Cost

EXHIBIT 6CALCULATION OF VALUE INDICES FOR COMPONENTS

Percent of ContributionComponent Total Cost Percentage Value Action

(Exhibit 3) (Exhibit 5) Index ImpliedMotor 40% 31.64% 1.26 Reduce costTransmission 20% 13.88% 1.44 Reduce costSpeed control 15% 8.88% 1.69 Reduce costBody 10% 16.65% 0.60 ImproveBlade 5% 21.83% 0.23 Improveblade guard 10% 7.03% 1.42 Reduce cost

Page 29: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

29

Achieving the Target Cost

Generate cost reduction ideas

Eliminate over-engineering

Eliminate, replace, combine, rearrange

Seek ways to accomplish the goal at less cost

Consider the process as well as the product

More efficient manufacturing processes

Better logistics

Etc.

Page 30: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

30

Achieving the Target Cost

Test the ideas

Will they be effective?

Are they technologically feasible?

Is there a domino effect?

Construct a component interaction matrix (exhibit 7)

Do activities interact?

Estimate the achievable costs

Use activity-based costing, cost tables, etc.

Page 31: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

31

Achieving the Target Cost

EXHIBIT 7COMPONENT INTERACTION MATRIX

Speed BladeComponent Motor Transmission control Body Blade guard

Motor X XTransmission X XSpeed control XBody X X X XBlade XBlade guard X X

Page 32: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

32

Make the Decision

Achievetargetcost?

Closeenough?

Release designfor production

Abortproject

Repeatvalueengr.?

Value engineering

Yes

No

Yes

No

No

Yes

Begin

Page 33: 1 Target Costing If you cannot find the time to do it right, how will you find the time to do it over?

33

Organizational Impact

Positives

Customer focus

Cross-functional integration

Open sharing of information

Better process understanding

Negatives

Too much customer focus

Potential organizational conflict

Too much pressure to attain targets

Longer development times