1 tss report pcc meeting salt lake city, ut october 26-27, 2006
TRANSCRIPT
1
TSS Report
PCC Meeting
Salt Lake City, UT
October 26-27, 2006
2
Approval Item
Generation Testing Implementation Plan
3
Status Reports
MVWG WECC Dynamic Modeling Procedure Load Model Wind Generation Model
Wind Generation Task Force Reactive Reserve Work Group Progress Reports Projects Progressing in Three-Phase Rating
Process SRWG (David Franklin – Chair)
4
Generation Testing Implementation Plan Responding to a PCC assignment of
TSS/MVWG, Generator Testing Task Force (GTTF) prepared a Generation Testing Implementation Plan (GTIP)
GTIP includes: transition plan for the new Generation Testing
Policy Clarification on the treatment of identical units
within the same power plnt
5
Generation Testing Implementation Plan – Issue 1 Issue 1: Generator Owners who did not perform
baseline testing in accordance with the original requirements are non-compliant with the Policy.
Issue 1 Response/Implementation: Generator Owners that are non-compliant with the
baseline test requirement (as defined in section B.1.2 of the Policy) shall provide to WECC staff, by December 31, 2006, a schedule to perform baseline testing and model validation.
The Generator Owner should coordinate the schedule with the appropriate Transmission Planner (s).
The Generator Owner will be considered non-compliant with the Policy until the baseline testing and model validation is completed.
6
Generation Testing Implementation Plan – Issue 2 Issue 2: A large number of Generator
Owners, who complied with the original baseline test requirement, are required to perform model re-validation. Spread generator re-validation over a five-year
period. Coordinate the re-validation efforts with the
respective replacement programs, as well as maintenance cycles.
WECC should have the authority to accept or reject the re-validation schedule proposed by the Generator Owners.
7
Generation Testing Implementation Plan – Issue 2 (continued) Issue 2 Response/Implementation :
Generator Owners that have complied with the baseline test requirements (as defined in section B.1.2 of the Policy) shall provide to WECC staff, by December 31, 2006, a schedule to perform model re-validation (as defined in section B.1.3 of the Policy).
The Generator Owner should coordinate the schedule with its the appropriate Transmission Planner(s).
The Generator Owner will be considered compliant with the Policy as long as the initial model re-validation is completed within 5 years from December 31, 2006. or from when the baseline test and model validation was first completed; whichever comes first.
Subsequent model re-validation should be done every 5 years.
8
Generation Testing Implementation Plan – Issue 3 Issue 3: Baseline testing and model
validation of the “sister” units in the same Generating Facility.
Issue 3 Response/Implementation: In case of multiple “identical” generating units
at the same Generating Facility, baseline testing (as defined in section B.1.2 of the Policy) shall be performed on at least one of the representative units.
Model data validation (as defined in section B.1.3 of the Policy) shall be performed for all generating units.
9
Generation Testing Implementation Plan – Issue 4 Issue 4: Wind Farm Model Validation Issue 4 Response/Implementation:
The technical guidelines developed in conjunction with the Policy, as well as existing WECC generator testing guidelines, apply to conventional generating units.
Similar guidelines will be developed to address model data and model validation requirements for wind power plants.
Those guidelines will go through the WECC approval process.
10
Proposed Motion
TSS Requests PCC Approval of the Generation Testing Implementation Plan
11
WECC Dynamic Modeling Procedure
Purpose Establish procedure for development and
maintenance of models, and for the submittal of data to WECC.
Improve the quality of the WECC Master Dynamic Data File
Assist WECC staff in managing submittals of models
Clarify modeling procedure for WECC members Improve interaction with program developers
Identify need for new models and improvement to existing models
Identify and report compatibility and conversion issues
12
WECC Dynamic Modeling Procedure (continued)
MVWG is the WECC group responsible for assuring the model database is kept up to date.
Any models added to the WECC master dynamic model library require acceptance from MVWG.
This Procedure will formalize the process for MVWG acceptance.
The Dynamic Model library will be posted on WECC website.
13
Load Modeling Development
Status WECC-CIEE/PIER MOU approved by BOD
Air-conditioner testing and modeling Load composition analysis (component data base) Load monitoring (white paper) Load data uncertainty analysis
Finalized specification for Composite Load Model Architecture and Prototype Load Model Data Tool
under development Going Forward
Implement composite load model in PSLF Version 1.0 (without single phase motor model)
Solicit bids and contract for load model data tool Load model validation (some validation base cases
created)
14
1. Basic Research
2. Load Model Prototype
3. Sensitivity Studies
4. Fill in Research Gaps
5. Composite Load Model Structure
6. Load Model Data Tool
7. Load Model Databases
8. Load Model Validation / Sensitivity Studies
9. Load Monitoring
10.System Performance Studies
11.Advanced - Load Composition Model
Now
FY07
Done
FY08
Load Modeling Development
15
Wind Generator Model Development
Status Nearing completion standard Type 3 model implementation
in PSLF and PSSE Obtained additional $45K from WECC for implementation of
three remaining models Collaboration with wide range of stakeholders continues
Going Forward Continue development of Type 1, 2 and 4 standard models Prepare guide on steady-state modeling of wind power
plants Independent of dynamic models Target date: December 2006
Draft Proposal to CIEE/PIER for follow-up work NREL leading effort; WGTF, WGMG will be “technical advisors” Scope of work includes near-term needs such as monitoring,
dynamic model validation, wind power plant “equivalencing”, best practices for modeling wind power plants in WECC
16
2006 Modeling Workshop
Logistics November 14-15 (Tue-Wed) 2006, Las Vegas, NV Coordinated with annual SRWG workshop per TSS
request Major Topics
NERC/WECC Modeling Standards Generator Testing and Model Validation Wind Modeling Load Modeling System Monitoring and Applications
17
Wind Generation Task Force
Working with RS on development of a Voltage Ride-through Standard Cover low voltage and high voltage periods after
clearing a system fault Going Forward
Coordination with existing NERC/FERC/IEEE/IEC requirements
FERC power factor range (+/- 0.95, only if TP can demonstrate the need through technical studies) may conflict with WECC MORC voltage control requirement
Reactive and Voltage Control Reactive capability at low generation levels Dynamic performance for voltage control and or/reactive
compensation Off-Nominal Frequency
Verification of wind turbine frequency trip settings with the WECC Off-Nominal Frequency Standard.
18
Reactive Reserve Work Group
Distributed a Survey Implementation of Planning Standards I.D:
Voltage Support and Reactive Power Directed to use the “Guide to WECC/NERC
Planning Standards I.D: Voltage Support and Reactive Power” to help you complete survey
Completed survey due to WECC Staff by November 17, 2006.
19
Progress Reports
Member Systems reporting significant facilities in the 2006 Annual Progress reports to WECC from which, as of October 13, 2006 no report has been received: None
Member Systems reporting significant facilities in the WECC Transmission Database from which, as of October 13, 2006, no report has been received: None
20
Significant facilities reported in the WECC Transmission Database as of October 17, 2006, which were not included in Annual Progress Reports submitted:
CFE Xochimilco – Mexicali 230 kV Xochimilco – Wisteria 230 kV
Metropoli – Tijuanan MX 230 kV La Jovita – Presidente Juarz 230 kV
La Jovita – El Cipres 230 kV La Jovita – Lomas 230 kV
Mexicali – Tecnologico 230 kV El Centenario – La Rosita 230 kV
El Centenario – Sanchez Taboada 230 kV Ejodo Michoacan de Ocampo – Mexicali 230 kV Ejido Michoacan de Ocampo – Sanchez 230 kV
La Jovita – La Herradura 230 kV El Canon – El Cipres 230 kV
NEVP VARS Project 230 kV
Equestrian North 500 KV Project Pecos – Brooks 230 kV
Centennial II Project PNM
San Juan – West Mesa SPR
Equestrian North 500 kV Emma – Mira Lome 345 kV
DPA Navajo Transmission Project Segment 2 Navajo Transmission Project Segment 3
21
Three Phase Rating Status – Phase 1
* Initiated Regional Planning Process. Has not yet requested a Project Review Group or submitted a Comprehensive Progress Report
Project Name Sponsor Proposed Rating Date Entered
Ely* SPPC 2,000 MW (N-S)
1,000 MW (S-N)
10/10/06
Path 27 Upgrade LADWP 2400 MW 8/23/06
BC to Northern California Project *
PG&E 1500 to 2000 MW 8/16/06
Path 51 – Southern Navajo*
APS 3100 MW 6/15/06
LEAPS* Nevada Hydro 1000 MW 3/1/06
Harry Allen-Robinson Summit
Great Basin Transmission
2,000 MW 2/9/06
Desert Rock APS for Dine Power Authority
1,500 MW 11/21/05
Sea Breeze* Sea Breeze Pacific Regional Transmission System
1000 MW 10/26/04
22
Three Phase Rating Status – Phase 2
Project Name Sponsor Proposed Rating Date Entered
Path 46 Rating Increase
CAISO
10,623 MW
(505 MW Increase)
10/11/06
Sunrise Project SDG&E 1,000 MW 5/2/06
IV-San Felipe Green Path Project
IID 1,000 MW 5/2/06
Path 36 Rating Increase
Western 1,680 MW
(75 MW Increase)
4/7/06
DPV2_EOR9300 SCE/SRP 10,500 MW
(2,445 MW Increase)
3/14/06
Indian Hills-Upland Green Path Project
LADWP 1,000 MW 2/23/06
Montana Alberta Tie MATL 300 MW 2/2/06
MPSL PacifiCorp 600 MW
(200 MW Increase)
2002
23
Three Phase Rating Status – Phase 3
Project Name Sponsor Proposed Rating Date Entered
Path 46 Rating Increase
CAISO
10,623 MW
(505 MW Increase)
10/13/06
DPV2 Path 46 SCE 11,823 MW
(1,200 MW Increase)
5/17/06
Path 48 Colorado-New Mexico Interconnection Project (CNMIP)
PNM 1,849 MW (simultaneous) to
1,970 MW (non simultaneous)
5/5/06
Path 26 Upgrade III CAISO 4,000 MW
(300 MW Increase)
5/5/06
EOR 9000+ Project SRP 9,300 MW
(1,245 MW increase)
9/12/05
DPV2 Path 49 SCE 9,255 MW
(1200 MW Increase)
8/30/05
Path 49 Upgrade CAISO 8,055 MW
(505 MW Increase)
1/18/05
24
Three Phase Rating Status – Expedited
Project Name Sponsor Proposed Rating Date Entered Path 51 Redefinition
SRP
No change
10-6-06
25
SRWG Report – WECC Base Case Data Preparation Process
David Franklin, SRWG Chair to present