1 virgo commissioning progress post vsr1 plans e. tournefier stac meeting june 26 th,2007
TRANSCRIPT
![Page 1: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/1.jpg)
1
Virgo commissioning progress
Post VSR1 plans
E. Tournefier
STAC meeting June 26th ,2007
![Page 2: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/2.jpg)
2carrierSidebands
15 minutes
Status at last STAC
• Thermal effects => fine tuning of parameters during lock acquisition + slow lock acquisition
• ITF stably locked (Weekend Science Runs) but• Controls needed to be improved (longitudinal, angular, suspension):
=> stability, noise re-introduction, stationarity, duty cycle• Control noises had to be reduced and environmental noises to be understood
WSR5 (Nov 2006)
![Page 3: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/3.jpg)
3
Status now• Thermal effects still with us (waiting for thermal compensation)
=> still need fine tuning of parameters during lock acquisition + slow lock acquisition
• ITF control well improved: – reliable and more stable controls (long locks), good stationarity, – control noise subtraction (no impact above 40 Hz), – duty cycle improved against environmental conditions
• Noise well reduced (both controls and environmental)but…• Still noises to understand
![Page 4: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/4.jpg)
4
Next steps – Diffused light
Install as soon as possible acoustic isolation
Detection lab
End benches
Perform diffused light mitigation
Detection lab
End benches
Understand better a solution for the Brewster noise
Replacement with a bigger one
Remove it ?
Understand possible clipping/spurious beam in vacuum
Modeling of all the beams
Mitigation – conservative approach
OK
OK
DoneShall we?
OK (to be continued)
Last STAC
![Page 5: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/5.jpg)
5
Next steps – Control noise
Frequency noise improvements
Install Better SSFS (common mode servo ) electronics (under design)
Understand sensing noise (diffused light?)
Longitudinal control noise reduction
More aggressive filtering
Alpha technique frequency dependent
Understand sensing noise (diffused light?) and couplings in the auxiliary d.o.f. error signal (thermal lensing?)
Angular degrees of freedom
Mirror/beam centering – coils balancing ongoing
More aggressive filtering on going
OK
OK
started
OK
OK (improved error signal)
Last STAC
![Page 6: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/6.jpg)
6
Next steps – Control improvements
Increase gain of the automatic alignment loops
Improve suspension control
Global inverted pendulum control
Vertical inertial damping
OK
OK (and more)
Last STAC
![Page 7: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/7.jpg)
7
Activities since last STAC
• December 2006 – April 2007: 5 more WSRs– Improvements of controls (longitudinal, angular, suspensions)– Environmental noise (diffused light, magnetic) investigations and reduction
• April 6th – 18th electrical shutdown:Infrastructure works:– Electrical works, Computing (UPS, civil work, re-organisation,..)Detector improvements- Acoustic enclosure around external detection bench- Replacement of Brewster window with a larger oneRestart went ok: ITF relocked within ~2days
• April 18th –May 18th :– Acoustic enclosures at end benches– Scattered light investigations (Brewster) + other environmental noises– Improvements of controls (longitudinal, angular, suspensions)– Change of naming convention (V1:channel_name)for easier data exchange with
LSC
• May 18th: start VSR1– Continue noise investigations + small control improvements
![Page 8: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/8.jpg)
8
Interferometer controls
• Thermal side-effects
• Longitudinal and angular controls
• Mirror suspension control
![Page 9: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/9.jpg)
9
Lock acquisition: thermal transient
• Fine tuning needed for lock acquisition: – demodulation phases, engagement of loops, gains, offsets on error signals,
…Plus:• Variations in the thermal transient:
seem related to activities in laser lab but not understood
Some lengthy relocks
![Page 10: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/10.jpg)
10
Thermal effects on sidebands: first studies
• Image of the sidebands (first step of phase camera):scanning system on B5 beam: - the beam is scanned on a pin-hole + photodiode - demodulated signal is used to reconstruct the sidebands shape
Clear defocusing effect
Need thermal compensation system + complete phase camera (see Michele’s talk)
![Page 11: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/11.jpg)
11
Mirror longitudinal controls: noise reductionPRCL control noise => sensed by B5 => MICH control noise => sensed by dark
fringe (B1)1/ Built a signal as stable AND less noisy than B2_3f (mixing B2 and B2_3f) 2/ online noise subtraction:
- include frequency dependence (f) - add a servo to tune the time dependance of the global gain
PRCL
MICH
B2_ACpmix
(f)
(f) => MICH noise impact reduced by ~ 50
- with =0 - with measured (f)
![Page 12: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/12.jpg)
12
Frequency stabilization and frequency noise
• New electronics designed and installed: – Better layout– Improved filter => frequency noise reduced at high
frequencies+ new functionality (switch between input signals)
• Alignment stability improved coupling of frequency noise also well reduced
![Page 13: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/13.jpg)
13
Mirror actuator noise
BS actuator noise reduced in May
The arm mirrors actuators need to be improved: to be done during VSR1 (will we find the Eddy currents noise?)
Next: new coil drivers + new DACs (see Michele’s talk)
DAC
DSPCoilDriverG
Emphasis DeEmphasis DeEmphasis
![Page 14: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/14.jpg)
14
Longitudinal control noises: summary
WSR5 (Nov 2006)
VSR1 (now)MICH noise
PRCL noise
frequency noise
![Page 15: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/15.jpg)
15
Mirror angular controls
• Control loops improved:– Add a second modulation (8 MHz) to control the common end motion– Optimized filters with more gain => robustness and stability
• Global control upgrade: more flexibility, noise injection,…
Alignment signals
DF and recycled powers
8MHz
-> Drift control (10mHz)
-> Drift control
![Page 16: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/16.jpg)
16
Angular control noise
• Beam centering on the mirrors:– Now within ~ 1mm => reduced coupling– Now automated
• More aggressive filters less noise reintroduction
Angular noise budget
The angular noise is not limiting the current Virgo sensitivity
This noise can be further reduced:- More power on B1p quadrant- Electronic noise reduction: new
electronics (see Michele’s talk)
Should be compliant with Virgo design above 20-30 Hz
B7
B8_q2
B8
WE
WINI NE
BS
![Page 17: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/17.jpg)
17
Suspension control: bottom stage
Compensation of non-linear z -> coupling:Large seismic activity large correction sent to the marionette (zM) y recoil of F7 (and payload) Side effects on alignment
Solution: compensate for z -> y coupling
Need a quadratic compensation:
Dark fringe: alignment and total power
- No compensation- With compensation
y=a*zM +b*zM2 (payload: b=a/25)
Correction signals
zM
ycorr
y
Under similar seismic activity:
![Page 18: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/18.jpg)
18
Suspension control: top stageOld problem: environmental noise reintroduced by Lvdt (seism) and Acc (wind) used for top stage control
Several strategies developed:1/ Panoply of error-signal blending depending on environmental conditions (‘onfly tuning’)2/ Use the ITF longitudinal error signal instead (Global Inverted Pendulum Control)=> z correction to the mirror well reduced
GC (reconstructed z)
LVDT
LVDTLVDTLVDT
VSR1: enabled only for NE-WE
No GIPCWith GIPC
old new
Other improvements: • Vertical damping on long suspensions• Local controls: optimized filters
![Page 19: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/19.jpg)
19
Sensitivity versus wind and sea activity
Illustration of the improvements of angular control and suspension control
Empirical formula: Horizon = H0(1 - a x seism – b x wind)
WSR1 (Sept 2006): a= 0.37, b= 0.37 VSR1 (May-Jun 2007):a= 0.07, b= 0.04
Sensitivity to bad weather conditions is well reduced The lock can be kept in bad weather conditions
- Measured horizon- Sea activity- Wind activity- Predicted horizon
![Page 20: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/20.jpg)
20
Environmental noises
• magnetic noise
• scattered light- optical benches- Brewster windows
![Page 21: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/21.jpg)
21
Magnetic noise
• Before WSR10 magnetic noise was limiting the sensitivity between 50 and 110 Hz
• Investigations: track the sources of magnetic field close to the input mirrors (more sensitive due to wrong polarity of the magnets)=> found noisy power supplies=> power supplies displaced
Home made portable magnetometer
Dark fringe
• Still some evidence for magnetic noise: under investigation
![Page 22: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/22.jpg)
22
Scattered light
Environmental noise acting on in air components +Scattered light from in air components =-------------------------------------------------------------Phase noise in the interferometer (with the typical environmental-like noise structures)
Laser
Brewsterwindows
End benches
External bench
Injection bench
Detectionsuspended bench
Actions:- reduce diffused light on benches- acoustic isolations- large Brewster windows
![Page 23: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/23.jpg)
23
Scattered light at end benches
Evidence for diffused light by the optics of the end benches (Jan 2007)Actions: 1/ use more rigid mounts for critical optics and dump secondary beams (Feb 2007)
WSR7WSR9: after 1/
Acoustic injections => acoustic noise still very close to the sensitivity floor
2/ install acoustic enclosures
Tentative acoustic noise projection
![Page 24: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/24.jpg)
24
Acoustic enclosures
• External detection bench:– Displace bench from the tower (~50cm)– Install acoustic panels (a room into the room)
• End benches:– Simpler: build a room around the benches
DetectionEnd buildings
![Page 25: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/25.jpg)
25
Scattered light and acoustic isolation
Tentative acoustic noise projection with acoustic enclosureSeismic noise on the optical bench
- No acoustic enclosure- With acoustic enclosure
After acoustic enclosure installation:
Impact of acoustic noise wellreduced above 100 Hz
Tentative acoustic noise projection before
![Page 26: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/26.jpg)
26
Brewster window + detection tower
Brewster link
Detection tower
Tentative projection of ‘Brewster noise’
Observations:- Brewster+detection tower = area very sensitive to acoustic noise- Tentative noise projections: Brewster could be a limiting factor
But: very difficult to make the difference between the Brewster and the detection tower
Damp all spurious beams inside the detection tower
Replace Brewster with a larger one (to fulfill: diameter > 5 x beam waist)
![Page 27: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/27.jpg)
27
Detection tower scattered light
Dump the secondary beams with black glass baffles:- Reflection by output port windows- Secondary beams (from second face of optics) on the suspended bench
B1sB1
B1p
B5
L3 /2OMC
M1
M5
L7
![Page 28: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/28.jpg)
28
New Brewster windowApril shutdown:
Detection Brewster replaced with a larger one: 16cm -> 19.6 cm
Result: the noise is increased…After testing several hypothesis,found the culprit: aluminium baffle
=> Protect it from light the retro-diffused by the detection bench
Detection
![Page 29: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/29.jpg)
29
New Brewster window ‘patched’
• After protecting the aluminium baffle: recovered the pre-shutdown sensitivity
• Additionnal small improvements: - ‘damp’ the Brewster link (weight+rubber)- smaller vacuum pump on SR tower improve sensitivity from 100 to 200Hz
The path of the noise in this area still has to be understood
Old BrewsterNew Brewster‘improved’ New Brewster
![Page 30: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/30.jpg)
30
Sensitivity and noise budget
![Page 31: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/31.jpg)
31
Sensitivity measurement: actuators calibration
Found a frequency dependence of the actuators response (could be due to Eddy current effects)
“Improves” sensitivity by 20% at high frequencies
10%
![Page 32: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/32.jpg)
32
VSR1 noise budget
Magnetic noise: under investigation
Not yet understood:hints for jitter/Pnoise from the injectionsystem
Environmental noise(laser lab)
Actuator noise=> shaping filters to
be installed
Laser powerOMC matching
![Page 33: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/33.jpg)
33
Environmental noises: some hints
• Below 30 Hz: beam jitter due to acoustic noise on laser bench ? some improvements obtained with better air conditioning flux
• Structures from 200 to 800Hz: input beam jitter, power noise?
Investigations ongoing during the run
Input beam jitter Acoustic noise on laser bench
Beam jitter vs acoustic noiseBeam jitter vs dark fringe
dark fringedark fringe IMC reflection
![Page 34: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/34.jpg)
34
Detector operation –
Few words on VSR1
![Page 35: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/35.jpg)
35
Detector monitoring/automation
• Detector monitoring, automation: the essential every day’s life tools, regularly upgraded
• Logbook: regular additions depending on user needs (more with the run!)
![Page 36: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/36.jpg)
36
VSR1 : some statistics
• Good stability, long locks ( up to 59 hours)• Gaussianity of the data is good, low trigger rate, low SNR• NS-NS horizon (averaged) ~ 3.5 Mpc• Science mode duty cycle ~ 85%• Unlocks:
– Technical: IMC fast unlock, Gc crash– Earthquakes, (bad weather)– Maintenance, commissioning breaks
Horizon NS-NS (averaged value)
1 month
![Page 37: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/37.jpg)
37
Commissioning activities during VSR1
Alignment drifts observed during long locks: related to the mis-centering of one end quadrant (used for BS control)
=> spoils error signal (AC) Improvement: include quadrant asymmetry in the error signal for BS control
Small drifts still there Try to use another error signal (B1p?)Longer term: Install galvanometer to keep centering
in science mode Reshuffle the end benches to have cleaner signals
realignment
Dark fringe
Q81 asymmetry IMC fast unlocks
- adjustement of IMC gain loop - repair electronics (loose connections)
=> rate smaller
Suspension controls: some improvements /test of configurations / try to keep lock during earthquakes
Environmental noise investigations: magnetic, acoustic, seismic
![Page 38: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/38.jpg)
38
Long term observations: Etalon effect!• Etalon effect:
small FP cavity inside input mirrors (due to AR face) effective reflectivity modulated with mirror thickness (temperature) … and so the finesse
AR HR HR
r1 r2 r3LA
LB
AR HR HR
r1 r2 r3LA
LB
B7/B8 phd
-FP transmitted power-Input mirror temperature
Temperature variation
FP
Tra
nsm
itte
d po
wer
No clear effect on sensitivity now… but to take into account for Virgo+
F/F = ± 3.5%
![Page 39: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/39.jpg)
39
Post VSR1 plans
• Noises: Environmental noise investigations are going on during VSR1,simple actions will be done during the run– Magnetic noise close to the mirrors: identify sources and ‘remove’ them – Acoustic, seismic noise in the laser lab:
find noise sources, reduce coupling to ITF– Acoustic noise at detection port:
understand the path => remove Brewster?- Reduce the mirror actuator noise: shaping filters (to be done during VSR1)- Angular noise reduction (not urgent)
• Controls:– Rearrange the end benches: better error signals from quadrants– Install better centering system for quadrants (‘science mode’ compatible)– Improve the control of the short suspensions (now the limiting ones)– Revise the longitudinal control using the 8MHz modulation? (cleaner signals)
• Thermal effects: (see Michele’s talk)– Clean the input mirrors ? (if not too risky) – Install and commission the thermal compensation system when ready (Jan
2008?)+ phase camera
![Page 40: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/40.jpg)
40
![Page 41: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/41.jpg)
41
Conclusion
• A lot of progress on the interferometer controls (still suffering from thermal effects): – Stability, robustness, duty cycle ok for science data taking– Noise re-introduction only a limitation below 40 Hz– Control scheme can still be improved:
• Quadrants / use 8MHz for longitudinal / short suspensions
• Good progress on the environmental noise:– Magnetic noise: well reduced still under investigation– Scattered light:
• Benches: improvement of benches setup + acoustic enclosures End benches and detection bench are safe now
• Brewster: larger one installed + investigations on noise path To be better understood (remove Brewster?)
– Remaining environmental noise under investigation (ISYS) Actions to be defined when we have clearer ideas
![Page 42: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/42.jpg)
42
Backup slides
![Page 43: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/43.jpg)
43
Discussion
• ITF noise larger because of new Brewster• Brewster link vibrating more than before? No.• Sensitivity to Brewster vibrations larger than before? Yes• Why?• What is the mechanisms ?
BEAMSPLITTER DETECTION
1) Scattering of spurious light coming from the ITF
2) Scattering of spurious lightgenerated in the Brewster
3) Scattering of spurious light coming from the detection
![Page 44: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/44.jpg)
44
• With new larger Brewster new light visible on the detection bench- Light visible at ~10 cm from the axis of the main beam- This light is missing the first detection lens (L1, diameter 12 cm)- This light is diffused on a couple of supports on the detection bench
New observations (III)
B1s
B1
B1p
B5
L3/2OMC
M1
M5
L7
![Page 45: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/45.jpg)
45
• Julien Marque (2004)
Old prediction: spurious beams
Bd3
Bd4
Bi1
![Page 46: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/46.jpg)
46
• Julien Marque (2004)
Old prediction: spurious beams
Bd3 and 4
![Page 47: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/47.jpg)
47
• With the old brewster
One of the predicted spurious beams
Diaphragms Brewster
B1
B5
Brewster link axis
Distance from BS (m)
Dis
tanc
e fr
om w
est a
xis
(cm
)
One spurious beam
![Page 48: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/48.jpg)
48
• With the new brewster
One of the predicted spurious beams
Diaphragms Brewster
B1
B5
Brewster link axis
Distance from BS (m)
Dis
tanc
e fr
om w
est a
xis
(cm
)
One spurious beam
![Page 49: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/49.jpg)
49
• With the new brewster
• Considering beam diameter defined as 2 w0
One of the predicted spurious beams
Diaphragms Brewster
B1
B5
Brewster link axis
Distance from BS (m)
Dis
tanc
e fr
om w
est a
xis
(cm
)
One spurious beam
![Page 50: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/50.jpg)
50
• Additional diaphragm before the Brewster
Added from SR tower
A possible mitigation
Diaphragms Brewster
B1
B5
Brewster link axis
Distance from BS (m)
Dis
tanc
e fr
om w
est a
xis
(cm
)
One spurious beam
![Page 51: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/51.jpg)
51
Scattering of spurious light from the ITF ?
• Yes, but ….
• …… no difference in the ITF noise
![Page 52: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/52.jpg)
52
Damping the Brewster
![Page 53: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/53.jpg)
53
• Injection with shaker: comparison with old Brewster
Noise injections (May 9th)
![Page 54: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/54.jpg)
54
• Injection with loudspeaker: comparison with old Brewster
Noise injections (May 9th)
![Page 55: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/55.jpg)
55
• Tapping tests on injection Brewster, injection tower, injection table- Small effects on ITF sensitivity- No excitation of ITF noise structures/resonances- Much less sensitive than detection tower and Brewster
• Tapping tests on injection Brewster, injection tower, injection table- Very small effects on ITF sensitivity- No excitation of ITF noise structures/resonances
• Tapping test attempted on NI- failed due to unlock
• Need to study sensitivity to all towers vibration- need to learn how to excite towers without unlock- place seismometers in more useful positions (now measuring verticalseismic noise near tower base)
More investigations (IV)
![Page 56: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/56.jpg)
56
“Mystery noise”
![Page 57: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/57.jpg)
57
“Mystery noise”
![Page 58: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/58.jpg)
58
“Mystery noise”
![Page 59: 1 Virgo commissioning progress Post VSR1 plans E. Tournefier STAC meeting June 26 th,2007](https://reader035.vdocuments.net/reader035/viewer/2022062621/551bea76550346b4588b62bb/html5/thumbnails/59.jpg)
59
“Mystery noise”