1 wyoming infrastructure authority november 10, 2009 superconductor electricity pipelines
TRANSCRIPT
1
Wyoming Infrastructure AuthorityNovember 10, 2009
Superconductor Electricity Pipelines
The challenge of moving renewable power long distances needs another option
2
Today’s Key Energy Challenge: Carrying 100’s of Gigawatts of Green Power to Market
Many Issues• Multiple Sources• Multiple Destinations• Cost Allocation• Siting• Transmission Across
Interconnections• Losses
Many Issues• Multiple Sources• Multiple Destinations• Cost Allocation• Siting• Transmission Across
Interconnections• Losses
A New Transmission Option
Combine:• Conventional underground pipeline construction
With two power system technologies:• Superconductor cables• Reduced voltage multi-terminal DC power transmission
The result:• A high capacity electric transmission “pipeline” that offers
a new option for connecting diffuse sources of renewable power to remote load centers in a controlled mannerUnderground and easy to siteHighly efficientCost competitive with currently available options Offers underground security and siting advantages
Superconductor Advantages with DC Power
• When carrying DC current, superconductors themselves are perfectly lossless- Regardless of length - Regardless of power rating
• Benefits- No power limitations based on current-based losses- Allows lower voltage, higher current transmission- Allows underground construction
Superconductors drive the economics of this transmission option
5
Superconductor Cables Projects Around the World
2001 2002199919981997 2010 2011 201320122000 2009200820072006200520042003
US/Nat. Grid – 34.5kV (400m)
US/DTE – 24kV (120m)
JAPAN – 77kV (500m)
US/EPRI – 115kV (50m)
SPAIN – 10kV (30m)
US/AEP – 13.8 kV (200m)
DENMARK – 36kV (30m)
CHINA – 35kV (30m)
JAPAN – 66kV (30M)
CHINA – 10.5kV (75m)
US/Southwire – 12.5kV (30m)
US/LIPA Phase I – 138kV (600m)
KOREA – 22.9kV (100m)
MEXICO – 15kV (30m)
CHINA – 110 kV (30m)
KOREA – 22.9kV (100m)
RUSSIA – 35 kV (30m)
KOREA – 22.9kV (30m)
US/ENTERGY – 13.8 kV (1,600m)
JAPAN – 66kV (250m)
CHINA – 35 kV (30m)
US/ConEd – 13.8 kV (220m)
US/LIPA Phase II – 138 kV (600m)
KOREA/KEPCO – 154 kV (500m)
AMSTERDAM – NUON (6,000m)
SPAIN – 20kV (30m)
RUSSIA – 35kV (100m)
Superconductor wire and cables are available from a variety of manufacturers around the world
Transmission Level Superconductor Cable
6
Application of established AC superconductor cable technology to DC is straightforward
• Location; Holbrook, NY (Long Island)
• 138kV, 2400A, 600m, 575MVA, single phase cables
• In service since April 2008
Figures courtesy Nexans
VSC HVDC Terminals
• Voltage Source Converter (VSC) based HVDC terminals available from multiple manufacturers
• Advantages of VSC converter topology:- Allows incorporation of multiple DC terminals on a
line- Greater control and flexibility- Allows the DC line to be envisioned as a DC bus
• VSC converter available only at lower voltages requiring higher currents- Voltage drop- Losses
7
AC Overhead Transmission
• Higher power and longer distances require higher voltages
• Losses
• Limited power flow control
• Power transmission characteristics
• Public opposition
8
0.0
1.0
2.0
3.0
4.0
5.0
0 200 400 600 800 1000
Po
wer
Tra
nsf
er C
apab
ility
, G
W
Line Length in Miles
Transfer Capability Versus Distance of a 765 kV Overhead Line
0%
2%
4%
6%
8%
10%
12%
14%
16%
100 200 300 400 500 600 700 800 900 1000
% L
os
se
s (E
st.
)
Miles
5GW of Renewable Energy Transmission
Range of Losses for Various 765kV Overhead Line Designs
Courtesy Argonne National Lab
Dominant form of transmission, but many challenges
DC Superconductor Cable
10,000MW in a <1m Gas Pipe
Courtesy of Electric Power Research Institute
Superconductor ampacity has little to no impact on cable dimensions
Operational Opportunities for DC Superconductor Cables: ELECTRICAL EFFICIENCY
• Overall losses 2.75% for 5GW @1000 miles (2.4% for 10GW)
10
0%
2%
4%
6%
8%
10%
12%
14%
0 100 200 300 400 500 600 700 800 900 1000
Lo
ss
es
(% o
f 5
GW
)
Length (miles)
Losses for 5GW Transmission
765kV OH, 2 Lines
765kV OH, 3 Lines
+/-300kV Underground DC [6]
Overhead +/-800kV DC [7]
+/-200kV Superconductor Pipeline
Optimized 765kV, 3 Lines [8]
Loss advantage increases with distance and MW rating
Operational Opportunities for DC Superconductor Cables: SIMPLIFIED SITING AND ROW
11
• Underground installation addresses public and environmental concerns
• One pipeline can replace many overhead lines
12
Operational Opportunities for DC Superconductor Cables: SIMPLIFIED SITING AND ROW
Co-location along existing right-of-way may simplify costly and complex siting procedures
Operational Opportunities for DC Superconductor Cables: GRID OPERATIONS
Enhanced Grid Operation and Market Dynamics- Networked DC terminals allow aggregation of
renewable sources (wind/solar) reducing variability- Opportunity for ancillary services including regulation,
spinning reserve, etc
Reduced Impact on Underlying Grid- Largely decoupled from underlying AC grid- Control over DC system interaction with AC grid during
faults- Provides long distance wheeling without impacting
regional grids
13
Operational Opportunities for DC Superconductor Cables: Redundancy
• Redundant cables can provide single line redundancy
• Loop networks, like EHV overlays, provide inherent redundancy 14
Cost Analysis
• 5GW, 1000mile Superconductor DC Cable System- US$8 M/mile- Costs include DC terminals, refrigeration, installation- Doubling capacity to 10GW line increases cost by less
than 1/3
• Cost Competitive with EHV AC- US$2.5 - $5.5 Million/mile per line- 2 to 3 lines needed for same capacity
15
Long distance, high power superconductor DC cables are cost competitive with EHV AC lines
Tres Amigas SuperStation Project
Western Interconnection
Eastern Interconnection
Texas Interconnection
14,400 square acres (22.5 sq. miles) of land in Clovis , New Mexico already allocated for project
Tres Amigas Project to Use Superconductor Electricity Pipeline
18
Lots of Power, Out of Sight and Easy to Site