![Page 1: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/1.jpg)
1
All Committee MeetingOctober 04, 2017
SALTON SEA MANAGEMENT PROGRAMPHASE I: 10-YEAR PLAN
WORK PLAN
![Page 2: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/2.jpg)
2
I. Goals & Objectives
II. Overarching ProjectDevelopment &Management Needs
III. Action Plan for PriorityAreas
IV. Conclusions
WORK PLAN ORGANIZATION
![Page 3: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/3.jpg)
3
Bridges SSMP concepts to design/constructionof Phase I actions
Outlines SSMP objectives
Identifies key factors, information and tasks tocontinue to move forward with Phase I actions
Provides insights to stakeholders on designprogress
Describes advisory committees & roles
I. GOALS & OBJECTIVES
![Page 4: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/4.jpg)
4
Chapters
Hydrology for Project Implementation
Water Quality for New Habitat Creation
Habitat Planning & Design Tool
Air Quality Management
Environmental Compliance
Compatibility with Other Regional Plans & Projects
Additional Projects for Evaluation
II. OVERARCHING PROJECT DEVELOPMENT &MANAGEMENT NEEDS
![Page 5: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/5.jpg)
5
Task in Work Plan Time Frame
Overarching Project Development TasksHydrology for Project Implementation Ongoing-Mar 2018
Water Quality for New Habitat Creation Ongoing-Mar 2018
Habitat Planning and Design Tool Dec 2017-Jun 2018
Air Quality Management Plan Dec 2017-Mar 2018
Environmental Compliance Requirements Ongoing
Evaluate Compatibility with Other Regional Planning Docs Dec 2017-Jun 2018
Near-term Priority Area Planning & DesignNew River West Restoration Design Jul 2017-Dec 2018
Alamo River North Restoration Design Jan 2018-Dec 2018
Whitewater River Area Restoration Design Jan 2018-Dec 2018
TIMELINE OF WORK PLAN TASKS
![Page 6: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/6.jpg)
6
HYDROLOGY FOR PROJECT IMPLEMENTATION
On-going Mar 2018On-going Mar 2018Timeline
![Page 7: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/7.jpg)
7
WATER QUALITY FOR NEW HABITATS
On-going Mar 2018On-going Mar 2018Timeline
![Page 8: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/8.jpg)
8
Phase 1 project areas have been established
Next steps will involve refined conceptual designs
Develop ecological targets
Detailed topo including
LIDAR surveys
Water supply analyses
Soil & geotechnical analysis
Accommodate geothermal access
HABITAT ASSESSMENT
Dec 2017 Jun 2018Dec 2017 Jun 2018Timeline
![Page 9: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/9.jpg)
9
Design Considerations
Habitat functional values
Water use / gravity vs pumping
Salinity
Water quality in constructed
habitat
Selenium management
Invasive plant management
Mosquito abatement
HABITAT LOCATIONS & TYPES
Habitat Types
Permanent wetlands withvegetation
Dry playa
Mudflat, sandflat, & beach
Mid- & deep-water
Shallow water
Existing habitat
![Page 10: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/10.jpg)
10
1. Assessment: Select project five areas (2016)
2. Prioritization of project areas (2017)
3. Define and apply design criteria/targets (2017/2018)
HABITAT SELECTION PROCESS
![Page 11: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/11.jpg)
11
Ecological function and performance
Consistency with Audubon’s guidelines forintegrating ecological function/bird usage
Water budgets (hydrology)
Water quality
Air quality performance of other playa treatments
HABITAT PLANNING & DESIGN TOOLS
![Page 12: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/12.jpg)
12
Modeled after Salton Sea Air Quality MitigationProgram (IID, July 2016)
Evaluate Dust SuppressionMethods
Water dependent
Waterless
Coordination with IID,ICAPCD, & affectedagencies
AIR QUALITY MANAGEMENT
Dec 2017 Mar 2018Dec 2017 Mar 2018Timeline
![Page 13: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/13.jpg)
13
Environmental documents & permitting completed forcurrent projects
Species Conservation Habitat - New River East & West
Red Hill Bay
Torres Martinez Wetlands
Additional areas available within SCH 3,770-ac footprint
Environmental compliance for other areas is beingevaluated & coordinated with regulatory agencies
ENVIRONMENTAL COMPLIANCE
Jul 2017 On-goingJul 2017 On-goingTimeline
![Page 14: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/14.jpg)
14
Phase I: 10-Year Plan will be compared to existingRegional Plans
IID Water Conservation & Transfer Project HCP/NCCP
Coachella Valley Multiple
Species Habitat
Conservation Plan
Check for compatibility,continuity, & consistency
COMPATIBILITY WITH OTHER REGIONALPLANS/PROJECTS
Dec 2017 Jun 2018Dec 2017 Jun 2018Timeline
![Page 15: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/15.jpg)
15
Evaluate potential to reconnect, inundate, ortreat harbors & boat docks along east & westshores
Reduce odors Reduce vectors Dust suppression Recreation opportunities
Water import options
ADDITIONAL PROJECTS FOR EVALUATION
![Page 16: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/16.jpg)
16
Project Implementation/Construction Strategy
Focuses on key components & locations
New River East & West
Alamo River North & South
Whitewater River
Phase I project sequencing determined by
Proximity to water sources
Status of environmental clearance/permits
Availability of access to property
Other shoreline areas will be developed later
III. ACTION PLAN FOR PHASE I AREAS
![Page 17: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/17.jpg)
17
PHASE I AREAS
![Page 18: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/18.jpg)
18
TYPICAL CONCEPT2018 – 20232023 – 2028
![Page 19: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/19.jpg)
19
Currently being updated to conform to theWater Board’s Stipulated Order
Currently moving forward with design for NewRiver West
Planning stages for Alamo North &Whitewater
CONSTRUCTION SCHEDULE
![Page 20: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/20.jpg)
20
STIPULATED WATER BOARD DRAFT ORDER
ExposedArea
DustSuppression
0
10,000
20,000
30,000
40,000
50,000
2018 2020 2022 2024 2026 2028
Are
a(a
cres
)
Exposed Area Habitat Area Dust Suppression
Habitat
![Page 21: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/21.jpg)
21
Provides path forward for implementingPhase 1 of 10-Yr Plan
Final section of document includes:
Timeline of Work Plan tasks References
IV. CONCLUSIONS
![Page 22: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/22.jpg)
22
WORK PLAN REVIEW TIMELINE
Activity Timeframe
Draft Work Plan to Committees Sep 26, 2017
Review Comments from Committees Due Oct 27, 2017
Release to Public Early Nov 2017
Living Document / Updated as Needed
Work commencing in multiple areas while Work Plan is finalized
![Page 23: 10-YR Plan Work Plan 10-04-17 Draft 5 [Read-Only]resources.ca.gov/CNRALegacyFiles/wp-content/uploads/2017/... · 2017-10-03 · e a (a c r e s) Exposed Area Habitat Area Dust Suppression](https://reader034.vdocuments.net/reader034/viewer/2022050114/5f4b867d91fcb5401e41df7c/html5/thumbnails/23.jpg)
23
QUESTIONS / DISCUSSION