10004e00.pdf
TRANSCRIPT
-
7/28/2019 10004E00.pdf
1/93
Eni S.p.A. Exploration & Production Division
BEST PRACTICE
UNIT 230
RELIEF AND BLOWDOWN SYSTEM
10004.HTP.PRC.PRG
Rev. 0 January 2008
-
7/28/2019 10004E00.pdf
2/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 2 of 93
INDEX
ACRONYMS 5
RELIEF AND BLOWDOWN SYSTEM UNIT 230 6
1.1 General ..................................................................................................................................6 1.2 Systems Description .............................................................................................................. 6 1.3 Relief System Design............................................................................................................. 7
1.3.1 Overpressure Protection Philosophy ........................................................................7 1.3.2 Upset Conditions.......................................................................................................8
1.3.2.1 Blocked Discharge..................................................................................... 8 1.3.2.2 Inadvertent Valve Opening ........................................................................9 1.3.2.3 Control Valve Failure ................................................................................. 9 1.3.2.4 Utility Failure .............................................................................................. 9 1.3.2.5 Fire Exposure .......................................................................................... 10 1.3.2.6 Jet Fire ..................................................................................................... 10 1.3.2.7 Entrance of volatile material into the system........................................... 11 1.3.2.8 Thermal Expansion..................................................................................11 1.3.2.9 Tube Rupture........................................................................................... 11 1.3.2.10 Internal Explosion ....................................................................................12 1.3.2.11 Chemical Reaction...................................................................................12 1.3.2.12 Hydraulic Expansion................................................................................ 12
1.3.3 Additional Consideration .........................................................................................14 1.3.3.1 Pumps......................................................................................................14 1.3.3.2 Compressors ........................................................................................... 15 1.3.3.3 Turbines................................................................................................... 15 1.3.3.4 Fired Heaters ........................................................................................... 15 1.3.3.5 PSV Operating in Liquid Service ............................................................. 15 1.3.3.6 Atmospheric and Low Pressure Storage Tanks ...................................... 18
1.3.4 Relief Devices .........................................................................................................18 1.3.4.1 Spring loaded relief valves....................................................................... 18 1.3.4.2 Pilot-operated relief valves ......................................................................19 1.3.4.3 Rupture disks........................................................................................... 20
1.3.5 Relief Valves Location.............................................................................................20 1.3.6 Piping Upstream of a Relief Device ........................................................................21
1.4 Blowdown System Design ................................................................................................... 23 1.4.1 Determination of Blowdown Requirements............................................................. 24 1.4.2 Sectioning of the Process Systems ........................................................................26 1.4.3 Depressuring Device Location ................................................................................27
1.5 Layout of Downstream Piping Systems ...............................................................................28 1.5.1 Common Discharge Systems..................................................................................28 1.5.2 Blockage Due to Hydrate Formation in Downstream Piping System......................29
1.6 Isolation Valves in Pressure Relief Piping ...........................................................................29 1.6.1 Isolation Valves Requirements................................................................................30 1.6.2 Interlocking Systems ............................................................................................... 33
1.6.2.1 Discharge to Atmosphere ........................................................................34 1.6.2.2 Discharge to Closed System ...................................................................34
1.7 Disposal System .................................................................................................................. 36 1.7.1 General....................................................................................................................36 1.7.2
Atmospheric discharge............................................................................................37
1.7.3 Disposal by Flaring..................................................................................................37 1.7.4 Flaring Versus Venting............................................................................................37
-
7/28/2019 10004E00.pdf
3/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 3 of 93
1.7.5 Flare and Vent Structure.........................................................................................39 1.7.5.1 Self-supported ......................................................................................... 39 1.7.5.2 Guy-wire supported .................................................................................40 1.7.5.3 Derrick supported ....................................................................................40
1.8
Flare System Design............................................................................................................40 1.8.1 Flare Type ...............................................................................................................41
1.8.1.1 Exothermic Flares.................................................................................... 41 1.8.1.2 Endothermic Flares..................................................................................43 1.8.1.3 Enclosed Ground Flares..........................................................................44
1.8.2 Flare Sizing .............................................................................................................45 1.8.2.1 Evaluation of Flare Diameter ...................................................................45 1.8.2.2 Evaluation of Flare Height .......................................................................45
1.8.3 Segregated flare systems .......................................................................................46 1.8.4 Flare Disposal of Hydrogen Sulphide .....................................................................47
1.9 Other Flaring Equipment......................................................................................................48 1.9.1 K.O. Drum ...............................................................................................................48
1.9.1.1 K.O. Drum Pump and Instrumentation ....................................................49 1.9.1.2 K.O. Drum Sizing .....................................................................................49
1.9.2 Liquid Seals.............................................................................................................51 1.9.3 Purge System..........................................................................................................51
1.10 Vent System Design ............................................................................................................ 52 1.10.1 Vent Sizing ..............................................................................................................52 1.10.2 Individual vent outlets..............................................................................................53
1.11 Flare Radiation Study .......................................................................................................... 54 1.12 Relief and Blowdown System Highlights .............................................................................61
APPENDIX 1 - SIZING OF RELIEF DEVICES ..............................................................................65 Design Considerations ............................................................................................ 65 Sizing for Gas or Vapour Relief...............................................................................67 Sizing for Steam Relief............................................................................................ 71 Sizing for Liquid Relief ............................................................................................ 72 Sizing for Two Phase Liquid-Vapour Relief ............................................................ 74 Sizing for Thermal Relief......................................................................................... 74
APPENDIX 2 HIGH INTEGRITY PROTECTION SYSTEM (HIPS) ............................................ 76 Reference Documents ............................................................................................ 76 HIPS Justification.................................................................................................... 78 HIPS Design............................................................................................................79
Advantages and Disadvantages of HIPS................................................................ 84 GLOSSARY 87
REFERENCE 92
-
7/28/2019 10004E00.pdf
4/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 4 of 93
For Main Utilities Best Practice reference shall be made to Eni E&P
internal document No. 10002.HTP.PRC.PRG .
-
7/28/2019 10004E00.pdf
5/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 5 of 93
ACRONYMS
BDV Blowdown valve
CCF Common cause failure
DIERS Design institute for emergency relief system
ESD Emergency shutdown
HIPS High integrity protection system
LHV Lower heating value
PES Programmable electronic system
PRV Pressure relief valve
PSV Pressure safety valve
SIL Safety integrity level
SIS Safety instrumented system
SRS Safety requirement specification
S/R VALVE Safety / Relief valve
TSV Thermal safety valve
-
7/28/2019 10004E00.pdf
6/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 6 of 93
RELIEF AND BLOWDOWN SYSTEM UNIT 230
1.1 General
This document sets out the general guidelines for sizing and designing a
relief and blowdown system, for both on-shore and off-shore production
facilities, with particular attention to the flare sizing.
The principal elements of pressure relief systems are the individual
pressure relief devices, the flare piping system, the flare separator drum,
and the flare including sealing devices, purge and steam injection for
smokeless burning.
Design of relief systems must comply with applicable state and federal
codes and laws as well as the requirements of the insurance covering the
plant or installation. State and federal regulations not only cover safety
but also environmental considerations such as air and water pollution and
noise abatement.
This section presents a convenient summary of relief, depressuring and
disposal systems information obtained from API 520 / 521 / 526 / 537 and
other sources.
1.2 Systems Descr ipt ion
Pressure relieving devices have to be installed to ensure that a process
system or any of its components are not subjected to pressures that
exceed the design pressure. API 521 recommends a depressurization
time (to 7 barg) of 15 minutes (see Paragraph 1.4) ; therefore, relieving
flowrates can be considered to be continuous rates of limited duration 10
- 15 min. The relieving rate will cease once the source of overpressure is
isolated.
Blow-down depressuring valves are intended to provide for a rapid
reduction of pressure in equipment by releasing vapours, as pressure
safety valves cannot provide depressuring and merely limit the pressure
rise under emergency conditions.
-
7/28/2019 10004E00.pdf
7/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 7 of 93
1.3 Relief System Design
The flowrates to the system can be caused by various operating and
upset conditions not all of which are of emergency type.
Even though the determination of relieving rates for each upset condition
and sizing of the relevant relief device is out of the scope of the work, in
the following is given a brief description of the most common
overpressure causes; moreover, Appendix 1 contains some relief devices
sizing methods. However, for a more rigorous determination of individual
relieving rates and relief devices sizing reference should be made
respectively to Section 5 of API 521 and to API 520.
1.3.1 Overpressure Protection Philosophy
Overpressure is due to a deviation of the normal operating conditions and
it is the result of an unbalance or disruption of the normal flows of
material and energy that causes the material or energy, or both, to build
up in some part of the system. Analysis of the causes and magnitudes of
overpressure is, therefore, a special and complex study of material and
energy balances in a process system.
Overpressure may result from:
(a) heat input, which is indirect pressure input through vaporization
or thermal expansion
(b) direct pressure input from higher pressure sources.
The causes of overpressure are considered to be unrelated if no process
or mechanical or electrical linkages exist among them, or if the length of
time that elapses between possible successive occurrences of these
causes is sufficient to make their classification unrelated.
The simultaneous occurrence of two or more unrelated causes of
overpressure (also known as double or multiple jeopardy) is not a basis
for design. Example double jeopardy scenarios might be: fire exposure
simultaneous with exchanger internal tube failure, fire exposure
simultaneous with failure of administrative controls to drain and
depressure isolated equipment, or operator error that leads to a blocked
-
7/28/2019 10004E00.pdf
8/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 8 of 93
outlet coincidental with a power failure. On the other hand, instrument air
failure during fire exposure may be considered single jeopardy if the fire
exposure causes local air line failures.
1.3.2 Upset Conditions
Pressure vessels, heat exchangers, operating equipment, and piping are
designed to contain the system pressure. The equipment design is based
on the normal operating pressure at operating temperatures, the effect of
any combination of process upsets that are likely to occur and the
differential between the operating and set pressures of the pressure-
relieving device.
The process systems designer must define the minimum pressure relief
capacity required to prevent the pressure in any piece of equipment from
exceeding the maximum allowable accumulated pressure.
In the following is given a brief description of some common occurrences
that may require overpressure protection. This summary is not intended
to be all inclusive; it is merely recommended as a guide.
1.3.2.1 Blocked Discharge
The inadvertent closure of a block valve on the outlet of a pressure
vessel while the plant is on stream may expose the vessel to a pressure
that exceeds the maximum allowable working pressure.
If closure of an outlet block valve can result in overpressure, a pressure
relief device is required unless administrative procedures to control valveclosure, such as car seals or locks, are in place. In this case, the relief
load is usually the maximum flow which the pump, compressor, or other
flow source produces at relief conditions. The quantity of material to be
relieved should be determined at conditions that correspond to the set
pressure plus overpressure instead of at normal operating conditions.
Instantaneously, the flowrate to be discharged should be higher than the
normal operating flow (e.g. compressor). Moreover, the presence of a
liquid outlet on the vessel (LV) could decrease the flowrate to be
-
7/28/2019 10004E00.pdf
9/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 9 of 93
discharged. However, during design operation the worst case shall be
considered; therefore, only the higher flowrate case (absence of liquid
outlet or closed LV) shall be deeply analyzed for relief device sizing.
1.3.2.2 Inadvertent Valve Opening
The inadvertent opening of any valve from a source of higher pressure,
such as high-pressure steam or process fluids, should be considered.
This action may require pressure-relieving capacity unless provisions are
made for locking or sealing the valve closed.
This overpressure scenario can be due to operator error, who can
operate the valve in the wrong position, or to valve leakage. In these
cases, the relief valve shall be sized considering the maximum valve C v
declared by the manufacturer and the maximum p across the valve
(valve set pressure protected equipment design pressure).
1.3.2.3 Control Valve Failure
The failure positions of instruments and control valves must be carefullyevaluated. A valve may stick in the wrong position, or a control loop may
fail. If one or more of the inlet valves are opened by the same failure that
caused the outlet valve to close, pressure-relieving devices may be
required to prevent overpressure. The required relief capacity is the
difference between the maximum inlet and maximum outlet flows.
1.3.2.4 Utility Failure
The consequences that may develop from any utility service loss,
whether local or plantwide, must be carefully evaluated. The normal utility
services that could fail and a partial listing of affected equipment that
could cause overpressure are given in Table 1.3.1.
-
7/28/2019 10004E00.pdf
10/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 10 of 93
Utility Failure Equipment Affected
Pumps for cooling water circulation or any other service such as boiler feed, reflux, etc.
Air cooler fans, cooling tower
Compressors (for air, vacuum, refrigeration, etc.)Instrumentation
Electric
Motor-operated valvesCondensers and coolersCooling Water Jackets on rotating equipmentTransmitters / Controllers / AlarmsInstrument Air Regulating valvesTurbine driversReboilersReciprocating pumps
Steam
Direct steam injection equipmentBoilers
Engine driversCompressorsFuelGas TurbinesSealsInert Gas Purge System
Table 1.3.1 Possible utility failure and relevant equipment affected.
1.3.2.5 Fire Exposure
Even if fire is not usually the condition that may create the greatest
relieving requirements, it is the most common case.
Various empirical equations have been developed to determine relief
loads from vessels exposed to fire. Formula selection varies with the
system and fluid considered (see API 521, Section 5).
1.3.2.6 Jet Fire
Jet fire is a fire created when a leak from a pressurized system ignites
and forms a burning jet. Jet fires can occur when almost any combustible
/ flammable fluid under pressure is released to atmosphere. Equipment
failure during a jet-fire is due to a localized and instantaneous
overheating without a significant pressure increase in the equipment (the
relief device set point isnt often reached). This is due to the localized
nature of heating whereby the bulk fluid temperature might not increase
appreciably. Hence, a relief device might not prevent vessel failure from
jet fire impingement.
-
7/28/2019 10004E00.pdf
11/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 11 of 93
Instead of a pressure-relief system, protection against jet fires focuses on
prevention of leaks through proper maintenance and/or mitigation
systems such as fireproofing, depressuring systems, isolation of leaks,
equipment and/or flange orientation and minimization and emergency
response.
1.3.2.7 Entrance of volatile material into the system
Entrance of water or light hydrocarbons into hot oil, causing a great and
instantaneous expansion in volume, can cause system overpressure.
Normally, a pressure relieving device is not provided for this contingency.
Proper design and operation of the process system are essential in
attempts to eliminate this possibility.
1.3.2.8 Thermal Expansion
If isolation of a process line on the cold side of an exchanger can result in
excess pressure due to heat input from the warm side, then the line or
cold side of the exchanger should be protected by a pressure safetyvalve (PSV). If any equipment, item or line can be isolated while full of
liquid, a PSV should be provided for thermal expansion of the contained
liquid.
1.3.2.9 Tube Rupture
When a large difference exists between the design pressure of the shell
and tube sides of an exchanger, provisions is required for relieving the
low pressure side (it could be required either on shell side or on tube
side). Because the test pressure is normally about 150% of the design
pressure, a 2/3 rule is established from it. The rule is this: pressure relief
for tube rupture is not required where the low pressure exchanger side
(including upstream and downstream systems) is designed at or above
the 2/3 criteria. Because ASME changed the hydrostatic test pressure for
pressure vessels from the 150% design pressure to a new standard of 130% design pressure, the existing 2/3 rule changed to a 10/13 rule.
-
7/28/2019 10004E00.pdf
12/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 12 of 93
As a general rule, the required relief capacity is based on twice the tube
cross section area, and the assumption that high pressure fluid can flow
through both the tube stub and the other end of the tube.
1.3.2.10 Internal Explosion
Where overpressure protection against internal explosions (excluding
detonation) caused by ignition of vapour-air mixtures is to be provided,
rupture discs or explosion vent panels, not relief valves, should be used.
Relief valves cannot be used in this case because they react too slowly to
protect the vessel against the extremely rapid pressure build-up caused
by internal flame propagation.
1.3.2.11 Chemical Reaction
The rapid evolution of an exothermic reaction (runaway) or the
degradation reaction which generates gas products can cause the vessel
rupture. Exothermic reactions become dangerous only when the
produced heat is greater than the removed heat and the temperatureincrease causes a reaction rate increase.
Protection against reaction runaway or gases generation should be
provided. The methodology for determining the appropriate size of an
emergency vent system for chemical reactions was established by DIERS
(Design Institute for Emergency Relief Systems).
1.3.2.12 Hydraulic Expansion
Hydraulic expansion is the increase in liquid volume caused by an
increase in temperature. It can result from:
(a) Piping or vessels are blocked-in while they are filled with cold
liquid and are subsequently heated.
(b) An exchanger is blocked-in on the cold side with flow in the hot
side.
-
7/28/2019 10004E00.pdf
13/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 13 of 93
(c) Piping or vessels are blocked-in while they are filled with liquid at
near-ambient temperatures and are heated by direct solar
radiation.
Provisions are required for relieving the equipment. The capacity
requirement is not easy to determine. Since every application will be
relieving liquid, the required capacity of the thermal safety valve (TSV)
will be small; specifying an oversized device is, therefore, reasonable. A
3 4 1 nominal pipe size (NPS 3 4 NPS 1) relief valve is commonly
used.
Proper selection of the set pressure for these relieving devices should
include a study of the design rating of all items included in the blocked-insystem. The TSV pressure setting should never be above the maximum
pressure permitted by the weakest component in the system being
protected.
3 4 1 size is not adequate for long pipelines of large diameter in
uninsulated aboveground installations and large vessels or exchangers
operating liquid-full; in these cases, in order to evaluate the relief device
proper size, the following equation must be applied:
cdq V
=
1000
(1)
Where:
q volume flowrate at flowing temperature [m/s]
V cubic expansion coefficient for the liquid at the expected
temperature [1/C]
total heat transfer rate [W]
d relative density referred to water ( d = 1.00 @15.6C)
c specific heat capacity of trapped fluid [J/kgK]
For aboveground pipelines protection, a system with multiple TSVs shall
be provided. The distance from one TSV to the other is specified on
mechanical standard documents.
-
7/28/2019 10004E00.pdf
14/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 14 of 93
If the liquid being relieved is expected to flash or form solids while it
passes through the relieving device, the procedure described in API 520
is recommended.
1.3.3 Additional Consideration
In the following is given a short summary for sizing the relief devices for
those equipment, such as pumps, compressors, atmospheric and low
pressure storage tanks, etc., which are not included in the API 520 and
API 521. This paragraph is also intended to give a brief description about
pressure safety valve operating in liquid service.
1.3.3.1 Pumps
Alternative pumps, in order to avoid the motor pump overheating and to
protect the piping downstream from pressures greater than design
pressure, require a safety valve on the discharge. Therefore, because of
the double function of the relief valve (protection against overpressure
and overheating), this devices shall be sized for both overpressure andoverheating. For overheating considerations, the pump manufacturer
shall be consulted.
Normally, these devices are piped back to the vessel or piping upstream
of the pump rather than to the flare system.
For a preliminary estimation of the valve set pressure, the following
equation shall be applied. The valve set pressure is calculated using both
equations; the chosen value is the greater between the two results.
deliveryset pp = 1.1 (2)
deliveryset pp += 7.1 (3)
Where:
pset Valve set pressure [bar]pdelivery Pump delivery pressure [bar]
-
7/28/2019 10004E00.pdf
15/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 15 of 93
For valves sizing a flowrate value equal to the pump flowrate (or pump
maximum flowrate in case of pumps with variable motor) must be taken
into consideration.
Lines and equipment downstream a centrifugal pump have always a
design pressure equal to the pump shut-off pressure. Wherever this rule
is not applied, the piping and / or equipment downstream the pump shall
be protected with a relief device.
1.3.3.2 Compressors
In order to protect rotary compressors and lines, a relief valve upstream
of the block and check valves shall be provided on the compressor
delivery and, if foreseen, on each of the intermediate stages.
1.3.3.3 Turbines
A special pressure relief valve shall be foreseen at the turbine outlet in
order to prevent overpressure phenomena at the condenser in case of cooling water loss or other system failure.
This kind of valve, without spring, acts against atmospheric back-
pressure and requires water for seals.
1.3.3.4 Fired Heaters
If there is a possibility that the process side of a fired heater may be
blocked-in, then a relief valve should be provided to protect the heater.
1.3.3.5 PSV Operating in Liquid Service
For those relief valves protecting equipment operating in liquid service,
the set pressure shall be evaluated taking into consideration the liquid
head and the elevation of the valve itself.
During the first engineering phase, the valve elevation could be uncertain;
in these cases, the designer shall evaluate the valve set pressure
-
7/28/2019 10004E00.pdf
16/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 16 of 93
supposing a reasonable valve height. For valve elevation preliminary
estimate the following method shall be applied:
a) Considering a relief header laying on the pipe-rack at an
elevation of 10 m and equipment with an upper tangent line lower
than 10.5 m, the safety valve set pressure shall be evaluated
supposing a PSV elevation of at least 10.5 m aboveground.
Figure 1.3.1 PSV in l iquid serv ice.
b) For all the equipments whose upper tangent line is higher than10.5 m (or above the relief header upper tangent line), the
following considerations shall be applied:
b.1) If the equipment is inside a structure, the PSV shall be
positioned 1.5 m above the first level over the equipment upper
tangent line. This level is 3 m above the upper tangent line.
-
7/28/2019 10004E00.pdf
17/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 17 of 93
Figure 1.3.2 - PSV in liquid service.
b.2) If there isnt a level over the equipment, the PSV shall have a
minimum elevation above the upper tangent line.
Figure 1.3.3 - PSV in liquid service.
-
7/28/2019 10004E00.pdf
18/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 18 of 93
1.3.3.6 Atmospheric and Low Pressure Storage Tanks
In this paragraph is given a short description of relief devices required for
storage tanks designed for operation at pressure from vacuum to 15 psig
(103.4 kPag) overpressure protection. For more rigorous information
about atmospheric and low pressure overpressure protection, reference
shall be made to API 2000.
Common overpressure causes for this kind of storage tank (with or
without weak roof-to-shell attachment) are listed in the following:
Liquid movement into or out of the tank;
Tank breathing due to weather changes;
Fire exposure
Other circumstances such as equipment failure or operating
errors.
In case of tanks with fixed roof, the PSV to be installed shall be sized
considering the most severe overpressure condition.
Tanks with weak roof-to-shell attachment, as better specified in API 650,
are designed with a roof-to-shell connection which fails in case of fire and
protect the equipment itself. Hence, for a tank built to these
specifications, a relief device for protecting the equipment exposed to fire
is not required. However, an overpressure protection for the most severe
condition identified among the remaining overpressure causes is
required. The PSV to be installed shall be sized for the most severe
condition and assuming the blanketing valve fully opened.
1.3.4 Relief Devices
1.3.4.1 Spring loaded relief valves
A conventional pressure relief valve is a self-actuated spring-loaded
pressure relief valve which is designed to open at a predetermined
pressure and protect a vessel or system from excess pressure by
removing or relieving fluid from that vessel or system.
-
7/28/2019 10004E00.pdf
19/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 19 of 93
Conventional spring-loaded relief valves shall be installed where back-
pressure does not exceed 10% of the set pressure (see API 520, Section
3, Paragraph 3.3.3.1)
A balanced pressure relief valve is a spring loaded pressure relief valve
which incorporates a bellows or other means of balancing the valve disc
to minimize the effects of back pressure on the performance
characteristics of the valve.
Balanced pressure relief valves should be considered where the built-up
back pressure (back pressure caused by flow through the downstream
piping after the relief valve lifts) is too high for a conventional pressure
relief (see API 520, Section 3, Paragraph 3.3.3.1).In general, balanced pressure relief valves are suitable for back-
pressures ranging from 10% to 50% of the set pressure. They can be of
two main types: balanced piston and balanced bellows. Balanced bellows
shall be given preference where the fluid is corrosive or fouling.
1.3.4.2 Pilot-operated relief valves
A pilot-operated pressure relief valve consists of the main valve, which
normally encloses a floating unbalanced piston assembly, and an
external pilot.
Pilot-operated relief valves shall be selected rather than conventional
spring-loaded relief valves when any of the requirements listed
hereinafter is present: low accumulation rates, calibration without
removing the valve, handling of large flows, higher pressure in the
downstream piping is required etc.
It shall be ensured, before selecting a pilot-operated relief valve, that
there is no possibility of blockage of the pilot valve or sensing line due to
hydrates, ice, wax or solids. There shall be no low points in the sensing
line or its take off, and all fine bore elements exposed to process fluids
shall be heat-traced and insulated if non-blockage cannot be guaranteed.
Filters shall not be used in the sensing line to the pilot valve because they
can increase the risk of blockage.
-
7/28/2019 10004E00.pdf
20/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 20 of 93
1.3.4.3 Rupture disks
Rupture disk devices are non-reclosing pressure relief devices used to
protect vessels, piping and other pressure containing components from
excessive pressure and/or vacuum. Rupture disks are used in single and
multiple relief device installations. They are also used as redundant
pressure relief devices.
With no moving parts, rupture disks are simple, reliable and faster acting
than other pressure relief devices. Because of these, rupture disks are
used in any application requiring overpressure protection where a non-
reclosing device is suitable.
Moreover, because of their light weight, rupture disks can be made from
high alloy and corrosion-resistant materials that are not practical in
pressure relief valves.
These devices can be specified for systems with vapour or liquid
pressure relief requirements. Also, rupture disk designs are available for
highly viscous fluids. The use of rupture disk devices in liquid service
should be carefully evaluated to ensure that the design of the disk is
suitable for liquid service. The user should consult the manufacturer for
information regarding liquid service applications.
Rupture disks can be of various types; for more details see API 520.
1.3.5 Relief Valves Location
To ensure protection of the whole system, the relief assembly should be
located, where practical, in the upstream part, i.e. where the highest
pressure occurs, and as close as possible to the source of overpressure.
Relief valves shall be connected to the protected equipment in the vapour
space above any contained liquid or to piping connected to the vapour
space. An exception can be made if the vessel is fitted with a demister
mat. In this case the relief connection shall be upstream of the mat,
unless the relieving capacity is of the same order of magnitude as the
normal operating flow through the demister mat.
-
7/28/2019 10004E00.pdf
21/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 21 of 93
The pressure drop of the piping between protected equipment and its
relief valve shall not exceed 3% of the set pressure.
The inlet and outlet piping shall be installed without pockets to ensure
that liquid does not accumulate at the relief valve outlet or inlet.
Relief valves discharging to atmosphere should be located at the
maximum practical elevation to keep discharge piping (to safe location)
as short as possible. In case of multiple relief valves (including one
spare), each relief valve shall have an individual discharge pipe (see also
API 521).
Relief valves connected to a closed relief system shall be located above
the relief header. Relief valve outlet lines should be connected to the topof the header, or at least so that the header cannot drain back into outlet
lines even with the header full of liquid. If the valves cannot be put above
the header, they shall be lined up to discharge into a local drain vessel.
Alternatively, if the problem of elevation is confined to a few valves, outlet
lines to the header shall be heat-traced from the relief valve to the highest
point of the line. Heat tracing isnt permitted for relief valves which
discharge a medium which can leave a deposit.Relief valve systems require periodic inspection and maintenance and
hence they should be easily accessible.
1.3.6 Piping Upstream of a Relief Device
In order to ensure safe disposal of flared and vented streams, certain
factors shall be taken into consideration when designing the pipework
upstream of the relief device.Piping upstream of a relief device should be designed with as few
restrictions to flow as possible and should not be pocketed.
The flow area through all pipe and fittings between a pressure vessel and
its relief valve shall be at least the same as that of the valve inlet (e.g.
isolation valves shall be full bore).
Depending on the actual relief valve capacity, the pressure drop of the
inlet piping and fittings shall not exceed 3% of the valve set pressure (thisis to avoid chatter, which will result in significant seat damage and loss of
-
7/28/2019 10004E00.pdf
22/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 22 of 93
capacity). Exceptions to this requirement are only allowed in the case of a
pilot-operated valve with a suitably arranged remote pilot connection
close to the source of overpressure.
The above is especially applicable to relief valves handling gas or vapour.
Relief valves in pure liquid service require special attention, since in this
case chatter may also be caused by the acceleration of the (non
expandable) liquid in the inlet piping: a change in pressure amounting to
more than 3% of the set pressure will readily occur and cause valve
chatter. In this case the likelihood of chatter can be limited by installing a
relief valve with a special liquid trim (linear flow characteristic) thereby
avoiding the need to take the relief valve capacity to determine thepressure drop of the inlet piping. For PSV sizing in liquid service see
paragraph 1.3.3.5.
When two or more relief valves (spares not counted) are fitted on one
connection, the cross-sectional area of this connection shall be at least
equal to the combined inlet areas of the valves, and the above pressure
drop requirement shall apply for the combined flow of the valves.
Relief valves on cold process streams shall have an uninsulated inlet lineof sufficient length to prevent icing of the relief valve, in particular the disk
and spring. Alternatively, heat tracing may be required. Special attention
shall be paid in this respect to valves which discharge into the
atmosphere, i.e. in those having open outlets which may become blocked
with ice.
To avoid the need for special high temperature materials, relief valves on
hot process streams may be installed using an uninsulated length of inletline, creating a cold dead ended leg between the process stream and the
relief valve.
A pressure safety valve typical scheme is shown in Figure 1.3.4.
-
7/28/2019 10004E00.pdf
23/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 23 of 93
Figure 1.3.4 PSV typical s cheme.
1.4 Blowdown System Design
Because of a relief valve cannot depressurize a system but can only limit
the pressure rise to the set point during upset conditions, a dedicated
depressuring system is required to mitigate the consequences of a vessel
leak by reducing the leakage rate or to reduce the failure potential for
scenarios involving overheating (e.g. fire).
When metal temperature is increased due to fire or exothermic or
runaway process reactions, the metal temperature may reach a level at
which stress rupture could occur. This may be possible even though the
system pressure does not exceed the maximum allowable accumulation.
In this case, depressuring reduces the internal stress thereby extending
the life of the vessel at a given temperature.
In order to be effective, the depressuring system must depressure the
vessel such that the reduced internal pressure keeps the stresses below
the rupture stress. API 521 suggests depressurizing to 6.9 barg or 50% of
-
7/28/2019 10004E00.pdf
24/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 24 of 93
vessel design pressure, whichever is the lower, within 15 minutes.
Moreover, Eni E&P internal standard, see doc. no. 20199.VON.SAF.SDS,
suggests reaching the 50% of vessel operating pressure within 5 minutes
and then depressurizing to 7 barg within the next 10 minutes. Even
though API 521 suggests this criterion for carbon steel vessels with a wall
thickness of approximately 1 or more, the above described depressuring
criterion is also applied for vessels with thinner walls.
Depressuring is assumed to continue for the duration of the emergency.
The valves should remain operable for the duration of the emergency or
should fail in a full open position. Fireproofing of the control signal and
valve actuator may be required in a fire zone. As per API 521, emergency depressuring for the fire scenario should be
considered for large equipment operating at or above 250 psig (aprrox.
1700 kPag). Depressuring criteria other than those given above can be
used depending upon the specific circumstances and user-defined
requirements. For example, if there is a reactive hazard or other
exceptional hazard that can cause loss of containment due to over-
temperature, emergency depressuring can be appropriate for equipmentdesigned for a wider range of pressures than that noted above.
1.4.1 Determination of Blowdown Requirements
As mentioned above, blowdown systems are principally required to
reduce the risk of loss of equipment integrity during a fire or to reduce a
local loss of containment arising from a leak when such an occurrence
could create an unacceptable safety hazard.
In assessing whether or not blowdown valves (BDV) are required,
particular attention should be paid to equipment location with respect to
other equipment, buildings and personnel, and the contents of the
equipment in terms of quantity and composition. Figure 1.4.1 shows a
typical BDV scheme.
-
7/28/2019 10004E00.pdf
25/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 25 of 93
Figure 1.4.1 Typical BDV scheme.
In performing the depressuring analysis it shall be ensured that
throughout depressuring the system pressure never exceeds the load
bearing capacity of the equipment. Account shall therefore be taken of
the reduction of strength with increasing temperature.
As per API 521, the depressuring system shall reduce the pressure of the
equipment within a fire zone to 50% of the design pressure or 6.9 barg
within 15 minutes. This does not imply that the depressuring stops after
15 minutes. Rotating equipment represent an exception because, due to
the loss of seal pressure, depressuring may be required in much less
than 15 minutes.
The depressuring calculation shall take into account the following:
Vaporization of the liquid due to the reduction in pressure;
Change in density of the vapour in the equipment due to the
pressure reduction and temperature increase;
Vaporization due to heat input from the external fire.
-
7/28/2019 10004E00.pdf
26/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 26 of 93
In general, for depressuring system sizing, an initial pressure equal to
safety relief valve set pressure shall be taken into account. Compressor
systems have instead an initial depressuring pressure equal to
compressor settle out pressure. In order to evaluate compressor settle
out pressure, the following equations shall be applied:
psettle out =tot
edischedischsuctionsuction
VVpVp argarg + (4)
and for a preliminary estimate
p settle out = edischsuction pp arg3/13/2 + (5)
Sizing of depressuring valves shall be based on the assumption that,
during a fire, all input and output streams to and from the system are
stopped and all internal heat sources within the process have ceased. It
shall also be assumed when calculating the vapour load generated that
fire is in progress throughout the depressuring period.
To determine the vapour depressuring flowrates it is necessary to
establish a liquid inventory and the vapour volume of the system. This
shall include all facilities located in the fire area and all equipment outside
the fire area which, under normal operating conditions, are in open
connection with the facilities located within the fire area.
1.4.2 Sectioning of the Process Systems
In large plants, in order to reduce the design blowdown flow rate, process
sectionalizing may be considered.
Process sectionalizing is a philosophy applied to split an installation into a
number of smaller fire zones. Potential fire areas shall be identified and
clearly shown on a plot plan. For process units, depending on the
drainage design of the plot, a typical fire area of 300 m should be
assumed.
-
7/28/2019 10004E00.pdf
27/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 27 of 93
Each zone shall be isolated by emergency shutdown (ESD) valves. Each
zone shall be provided with its own depressurizing facilities, such that
each zone can be depressurized sequentially, thereby reducing the
design peak rate.
After initiating depressurisation of the first zone, that of other zones may
be initiated as soon as the flowrate of the first zone has decayed such
that a second zone may be initiated without exceeding the design
capacity of the flare/vent system. This strategy requires equipment in an
adjacent fire zone to be adequately protected by a combination of
appropriate layout, fire walls, fire proof insulation, such that the risk of a
loss of integrity of equipment in a fire zone adjacent to the first affectedzone is insignificant.
This approach is not usually practical on an integrated offshore
production platform or in small plants; in these cases, during an ESD, all
blowdown valves open simultaneously and sequenced depressurization
using time delays is not used. Moreover, the sectioning of the process
system and time delays shall not be applied in those plants where a
single event can cause the simultaneous opening of the entire systemblowdown valve.
1.4.3 Depressuring Device Location
The location of depressuring valves shall be governed by the same
considerations as relief valves and they may discharge into the same
disposal system as the relief valves on the equipment under
consideration.
Particular attention should also be paid to the position of non-return
valves when locating depressuring valves, to ensure that equipment
downstream of the non-return valve cannot be isolated from the
depressuring valve.
Depressuring devices require periodic testing and hence the
depressuring device should be located to allow easy access.
-
7/28/2019 10004E00.pdf
28/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 28 of 93
1.5 Layout of Downstream Piping Systems
1.5.1 Common Discharge Systems
It is usually simpler and more economic to combine discharges from anumber of facilities into a common discharge system served by a central
vent or flare.
In the normal configuration of a common discharge system designed for
venting or flaring gas at an elevated height, a knock-out drum situated
close to the stack is required to recover liquid hydrocarbon or slugs. The
relief valves or depressuring valves will discharge via plant sub-headers
with connections into a main header running outside the battery limits. If this is not possible the flare/vent piping should at least be routed through
areas where there is little possibility of a dangerous situation due to local
failure of the flare/vent piping (i.e. where possible all piping should be
welded).
The flow area through all pipe and fittings downstream a relief valve, shall
be at least the same as that of the valve outlet. The disposal piping shall
be self-draining towards the knock-out drum. In general, in order to avoid
liquid accumulation, all the relief headers shall slope continuously
towards the vent or flare K.O. drum.
If possible, connecting sub-headers shall be connected to the top of the
header; in any case, they shall drain into the headers. The sub-headers
shall be connected in such a way that there are no welds in the lower one
third of the circumference of the header.
As per API 521, the discharge piping system should be designed so that
the built-up back pressure, caused by the flow through the valve, does
not reduce the capacity below that required of any pressure-relief valve
that can be relieving simultaneously. Where conventional pressure relief
valves are used, the relief manifold system should be sized to limit the
built-up back pressure to approximately 10% of the set pressure of each
pressure-relief valve that can be relieving concurrently.
With pilot-operated valves, higher manifold pressures can be used. The
capacity of these balanced valves begins to decrease when the back
-
7/28/2019 10004E00.pdf
29/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 29 of 93
pressure exceeds 30% to 50% of the set pressure due to subsonic flow
and/or physical responses to the high back pressure. Refer to API 520-I
for the effects of this back pressure.
1.5.2 Blockage Due to Hydrate Formation in Downstream Piping System
The blockage of discharge piping downstream of a relief or emergency
depressuring valve is not a problem under relieving or depressuring
conditions if the discharge is correctly designed.
The correct design of the discharge system should include:
sufficiently large diameter pipework (velocity < 0.7 Mach);
short length tail pipes;
the avoidance of restrictions.
To prevent hydrate or ice formation due to small leaks across the valve or
low ambient temperatures, heat tracing shall be installed.
1.6 Isolation Valves in Pressure Relief Piping
Where possible, the approach should be to use a relief valve
arrangement which does not utilise any isolation valves. This approach
eliminates the possibility of a relief valve being isolated in error. However,
for those relief devices which could have problem of plugging or other
severe problems which affect their performance, isolation and sparing of
the relief devices may be provided.
Block valves may be used to isolate a pressure relief device from the
equipment it protects or from its downstream disposal system and tofacilitate PSV / BDV inspection and maintenance without shutting down
the whole system (blowdown system included).
Since improper use of a block valve may render a pressure relief device
inoperative, the design, installation, and management of these isolation
block valves should be carefully evaluated. The ASME Boiler and
Pressure Vessel Code, Section VIII, Appendix M, discusses proper
application of these valves and the administrative controls which must be
-
7/28/2019 10004E00.pdf
30/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 30 of 93
in place when isolation block valves are used. Local jurisdictions may
have other requirements.
1.6.1 Isolation Valves Requirements
As per API 520 Part II, all the isolation valves located in relief system
piping shall meet the following requirements:
a) Valves shall be full bore.
b) Valves shall be suitable for the line service classification.
c) Valves shall have the capability of being locked or car sealed
open.
d) When gate valves are used, they should be installed with stems
oriented horizontally or, if this is not feasible, the stem could be
oriented downward to a maximum of 45 from the horizontal to
keep the gate from falling off and blocking the flow.
An isolation valve can be used either to isolate the individual relief valve
or to isolate a complete plant section. If isolation valves are used to
isolate relief valves, there is a basic difference between the need for an
inlet valve or for an outlet valve. An inlet valve is needed if the process
cannot be shut down, whereas an outlet valve is needed if the relief
header cannot be taken out of service. Thus a single relief valve (without
a spare) connected to a relief header which cannot be shut down will
have only an outlet isolation valve.
When isolation valves are installed in pressure relief valve discharge
piping, a means to prevent pressure build-up between the pressure relief
valve and the isolation valve should be provided (for example, a bleeder
valve), see Figure 1.6.1.
-
7/28/2019 10004E00.pdf
31/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 31 of 93
Figure 1.6.1 Typical pressure relief valve installation with an isolation valve.
A multiple relief valve arrangement with a 100% design relieving capacity
(including a spare relief valve), as the ones shown in Figure 1.6.2 and
Figure 1.6.3, will have an inlet isolation valve and outlet isolation valve.
-
7/28/2019 10004E00.pdf
32/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 32 of 93
Figure 1.6.2 Typical pressure relief valve installation with 100% spare relievingcapacity and a three-way valve.
-
7/28/2019 10004E00.pdf
33/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 33 of 93
Figure 1.6.3 Typical pressure relief valve installation with 100% spare relievingcapacity.
Periodic inspections of isolation valves located in relief piping should be
made which verify the position of valves and the condition of the locking
or sealing device.
1.6.2 Interlocking Systems
Where block valves are fitted upstream and/or downstream of relief
valves a system shall be in place to ensure that the required relief
capacity is always available. One method of achieving this consists in
installing of an interlocking system which makes it impossible to block off
the operating S/R valve until other similar relief capacity has been
connected to the system.
-
7/28/2019 10004E00.pdf
34/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 34 of 93
Two situations, discharge to atmosphere or discharge to a closed system,
can occur. The following paragraphs describe correct operation to allow a
safe removal of an S/R valve for maintenance.
1.6.2.1 Discharge to Atmosphere
Spared relief valves discharging directly to atmosphere (via individual
pipes) require block valves only in the inlet pipes of the valves. These
block valves shall each be provided with a single lock, but with only one
key in total. During operation the key shall be trapped in the lock of the
closed block valve of the installed spare S/R valve. The key shall be
retractable from the lock only by locking open the block valve. Hence only
one block valve can be in the closed position at any time. The piping
between the upstream block valve and the relief valve shall be fitted with
a vent connection in order to allow depressuring before the removal of
the relief valve.
Figure 1.6.4 Typical interlocking System for pr essure relief valves w ith atmosphericdischarge.
1.6.2.2 Discharge to Closed System
Spared relief valves discharging to a closed system require block valves
in both the inlet and outlet pipes. The outlet block valves shall be
-
7/28/2019 10004E00.pdf
35/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 35 of 93
provided with single locks, while the inlet block valves shall have double
locks. As per atmospheric discharge, the piping between the upstream
block valve and the relief valve shall be fitted with a vent connection in
order to allow depressuring before the removal of the relief valve.
Each relief valve shall be provided with a unique key which fits Lock 1 of
its inlet block valve and the lock of its outlet block valve. The key of the
outlet block valve shall be retractable only when the outlet block valve is
locked open. The key of Lock 1 of the inlet block valve shall be
retractable only when the switch key is inserted in Lock 2 of the same
inlet block valve.
Each relief valve shall be provided with a single switch key which fitsLock 2 of all inlet block valves. The switch key shall be retractable only
when the inlet block valve is locked open. This shall only be possible
when the key of Lock 1 is inserted in the lock. During operation, only the
inlet block valve of the installed spare S/R valve will be in the locked
closed position. All other block valves will be locked open. Locking open
the outlet block valve of the installed spare S/R valve (or its replacement
spool piece) prevents pressure build-up in case the inlet block valveshould leak.
The keys of the locks of the block valves of the relief valves in operation
will be trapped in Lock 1 of the inlet block valves. The switch key will be
trapped in Lock 2 of the closed inlet block valve of the spare valve. Since
the switch key is needed to unlock and close an inlet block valve, only
one block valve can be in the closed position at any time.
The key of Lock 1 of the inlet block valve of the spare valve shall bestored in the control room which shall only be accessible to authorized
personnel.
-
7/28/2019 10004E00.pdf
36/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 36 of 93
Figure 1.6.5 Typical i nterlocking System for pressure relief valves with discharge toa closed system.
Notice that also outlet valve could be subjected to a key interlock system:
in this case the key system could avoid to close outlet valve if the inlet
valve is open (that means that outlet valve could be closed only if the inlet
valve is closed; i.e. PSV in maintenance and an other PSV in service).
1.7 Disposal System
1.7.1 General
Streams requiring disposal are:
Relief vapour and/or liquids;
Depressuring vapours;
Any operational waste streams that do not have a more suitable
outlet.
The selection of a disposal method is subject to many factors that may be
specific to a particular location or an individual unit. Disposal systems
generally consist of piping and vessels. All components should be
suitable in size, pressure rating, and material for the service conditions
intended.
-
7/28/2019 10004E00.pdf
37/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 37 of 93
In selecting a means of disposal for these streams it is important to find a
solution in which all streams are handled with the smallest number and
diversity of systems and individual outlets.
Wherever possible disposal streams shall be collected in a closed system
and directed to a flare or vent system.
1.7.2 Atmospheric discharge
In many situations, pressure-relief vapour streams may be safely
discharged directly to the atmosphere if environmental regulations permit
such discharges.
Where feasible, this arrangement (atmospheric safe discharge) offers
significant advantages over alternative methods of disposal because of
its inherent simplicity, dependability, and economy.
1.7.3 Disposal by Flaring
The primary function of a flare is to use combustion to convert flammable,
toxic, or corrosive vapours to less objectionable compounds. Selection of the type of flare and the special design features required will be
influenced by several factors, including the availability of space; the
characteristics of the flare gas, namely, composition, quantity, and
pressure level; economics, including both the initial investment and
operating costs; and public relations. Public relations may be a factor if
the flare can be seen or heard from residential areas or navigable
waterways.
1.7.4 Flaring Versus Venting
Considerations to be made in deciding whether to vent or flare the
disposal streams are:
Impact on the environment;
-
7/28/2019 10004E00.pdf
38/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 38 of 93
Safety and integrity of the disposal system, taking into account
that disposal streams could contain products which are not
combustible;
Local regulations;
Economic evaluations.
Considerations indicating whether venting is allowed are:
If the vapours temperature is below the auto-ignition temperature
and if they are lighter than air. Gases shall be considered to be
lighter than air if the actual density of the gas after release, taking
into account the cooling associated with expansion, is less than
0.9 times the density of the air in the area at 15 C.
If the vapours are heavier than air because of low temperature
but are in locations where the installation of a flare is
impracticable (e.g. product storage areas, marketing depots) or
where potential ignition sources are remote. In these cases the
vapours discharge velocity shall be at least 152 m/s. However,
discharge velocity shall not exceed the 80% of the sonic velocity.
If concentrations of toxic and/or corrosive components in thedispersed vapour cloud do not reach harmful or irritating levels on
nearby work levels (platforms) and outside property limits. In
order to evaluate environmental impact, calculations of effluent
emissions are required.
If the risks and consequences of accidental plume ignition (e.g.
generation of shock waves) are acceptable.
In addition to the above, streams which are not foreign to the atmospheremay be vented without environmental reservations. However, safety near
the point of discharge shall be considered, i.e. factors such as
temperature, noise, local concentrations of carbon dioxide and nitrogen,
etc.
-
7/28/2019 10004E00.pdf
39/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 39 of 93
1.7.5 Flare and Vent Structure
The type and height of the structures supporting flare or vent stacks
depend on the following operational and environmental aspects:
Required availability of the flare and relief system;
Acceptable heat radiation levels;
Acceptable dispersion levels;
Acceptable noise levels;
Wind velocity.
There are three common stack support methods as shown in Figure
1.7.1.
The type selection is based on economical and operational grounds. A
brief structure description is given in the following.
Figure 1.7.1 Flare structures.
1.7.5.1 Self-supported
Self-supported stacks are normally the most desirable. However, they are
also the most expensive because of greater material requirements
needed to ensure structural integrity. They are normally limited
-
7/28/2019 10004E00.pdf
40/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 40 of 93
(economically versus alternatives) to a stack height of 200 to 300 feet
(60-90 m).
1.7.5.2 Guy-wire supported
These are the least expensive but require the largest land area due to the
guy-wire radius requirements. Typical guy-wire radius is equal to one-half
the overall stack height.
1.7.5.3 Derrick supported
Used only on larger stacks where self-supported is not practical, or available land area excludes a guy-wire design.
1.8 Flare System Design
Disposal of combustible gases, vapours, and liquids by burning is
generally accomplished in flares. Flares are used for environmental
control of continuous flows of excess gases and for large surges of gases
in an emergency.
The flare is usually required to be smokeless for the gas flows that are
expected to occur from normal day-to-day operations. This is usually a
fraction of the maximum gas flow, but some environmentally sensitive
areas require 100% smokeless or even a fully enclosed flare.
Various techniques are available for producing smokeless operation,
most of which are based on the premise that smoke is the result of a fuel-
rich condition and is eliminated by promoting uniform air distribution
throughout the flames.
To promote air distribution throughout the flames, energy is required to
create turbulence and mixing of the combustion air within the flare gas as
it is being ignited. This energy may be present in the gases, in the form of
pressure, or it may be exerted on the system through another medium
such as injecting high-pressure steam, compressed air, or low-pressure
blower air into the gases as they exit the flare tip.
-
7/28/2019 10004E00.pdf
41/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 41 of 93
1.8.1 Flare Type
1.8.1.1 Exothermic Flares
The following descriptions are for flare equipment to dispose of exothermic
flare gases; that is, gases that have a high enough heating value (usually
greater than 200 Btu/Scf (7370 kJ/Sm) for unassisted flares and 300
Btu/Scf (11050 kJ/Sm) for assisted flares) to sustain combustion on their
own without any auxiliary fuel additions.
Utility / Pipe Flare: This is the simplest flare tip; this plain design has no
special features to prevent smoke formation, and consequently should
not be used in applications where smokeless operation is required unless
the gases being flared are not prone to smoking.
Flare tips of this style, as a minimum, should include a flame retention
device (to increase flame stability at high flowrates) and one or more
pilots (depending upon the diameter of the tip).
Smokeless Flare:
Steam Injection : Flare tips which use steam to control smoking are the
most common form of smokeless flare tip. The steam can be injected
through a single pipe nozzle located in the centre of the flare, through
a series of steam/air injectors, through a manifold located around the
periphery of the flare tip, or a combination of all three. The steam is
injected into the flame zone to create turbulence and/or aspirate air
into the flame zone via the steam jets. The amount of steam required
(see API 521, 5 th Edition, Table 11) is primarily a function of the gas
composition, flowrate, and steam pressure and flare tip design.
Although steam is normally provided from a 100 to 150 psi (690-1034
kPa) supply header, special designs are available for utilizing steam
pressure in the range of 30 psi (2.07 kPa). The major impact of lower
steam pressure is a reduction in steam efficiency during smokeless
turndown conditions.
-
7/28/2019 10004E00.pdf
42/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 42 of 93
HP Air Injection: HP air injection can also be used to prevent smoke
formation. This approach is less common because compressed air is
usually more expensive than steam. However, in some situations, it
may seem preferable, for example, in arctic or low-temperature
applications where steam could freeze and plug the flare tip/stack.
Also, other applications include desert or island installations where
there is a shortage of water for steam, or where the waste flare gas
stream would react with water. The same injection methods described
for steam are used with compressed air. The air is usually provided at
100 psi (690 kPa) and the mass quantity required is approximately200% greater than required by steam since the compressed air does
not produce the water-gas shift reaction that occurs with steam.
HP Water Injection: High-pressure water is also used to control
smoking, especially for horizontal flare applications and when large
quantities of waste water or brine are to be eliminated. One pound of
water (at 345 to 690 kPa) is usually required for each pound of gasflared.
LP Forced Air: A low-pressure forced air system is usually the first
alternative evaluated if insufficient on-site utilities are available to aid in
producing smokeless operation. The system creates turbulence in the
flame zone by injecting low-pressure air supplied from a blower across
the flare tip as the gases are being ignited, thus promoting even air distribution throughout the flames. Usually air at 0.5 to 5 kPa pressure
flows coaxially with the flare gas to the flare tip where the two are
mixed. This system has a higher initial cost due to the requirement for
a dual stack and an air blower. However, this system has much lower
operating costs than a steam-assisted design (requiring only power for
a blower). The additional quantity of air supplied by the blower for
smokeless operation is normally 10% to 30% of the stoichiometric air
-
7/28/2019 10004E00.pdf
43/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 43 of 93
required for saturated hydrocarbons and 30% to 40% of the
stoichiometric air required for unsaturated hydrocarbons.
HP Flare: A high-pressure system does not require any utilities such
as steam or air to promote smokeless flaring. Instead, these systems
utilize pressure energy available within the flare gas itself (typically 35
to 140 kPa minimum at the flare tip) to eliminate fuel rich conditions
and resulting smoke within the flames. By injecting the flare gas into
the atmosphere at a high pressure, turbulence is created in the flame
zone, which promotes even air distribution throughout the flames.
Since no external utilities are required, these systems are normallyadvantageous for disposing of very large gas releases, both from the
economics of smokeless operation and the control of flame shape.
Maintaining sufficient tip pressure during turndown conditions is critical
and often requires that a staging system be employed to
proportionately control the number of flare tips in service with
relationship to the gas flowing.
1.8.1.2 Endothermic Flares
Endothermic gases may be disposed of in thermal incineration systems;
however, there are situations where the preferred approach is to use a
special flare design. These flares utilize auxiliary fuel gas to burn the flare
gases. With small gas flow rates, simple enrichment of the flare gases by
adding fuel gas in the flare header to raise the net heating value of the
mixture may be sufficient.
In other situations, such as gases with high CO 2 content and small
amounts of H 2S, it may be necessary to add a fuel gas injection manifold
around the flare tip (similar to a steam manifold) and build a fire around
the exit end of the flare tip that the gases must flow through.
-
7/28/2019 10004E00.pdf
44/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 44 of 93
1.8.1.3 Enclosed Ground Flares
In general, any of the flare tips or systems discussed above may be
mounted atop an elevated stack or mounted at grade. In general, ground
flares are primarily designed for low release rates and are not effective
for emergency releases.
With increasingly strict requirements regarding flame visibility, emissions,
and noise, enclosed ground flares (see Figure 1.8.1) can offer the
advantages of hiding flames, monitoring emissions, and lowering noise.
However, the initial cost often makes them undesirable for large releases
when compared to elevated systems.
A significant disadvantage with a ground flare is the potential
accumulation of a vapour cloud in the event of a flare malfunction; special
safety dispersion systems are usually included in the ground flare
system. For this reason, instrumentation for monitoring and controlling
ground flares is typically more stringent than with an elevated system.
These flares are typically the most expensive because of the size of the
shell or fence and the additional instrumentation which may be required
to monitor these key parameters. Another significant limitation is that
enclosed ground flares have significantly less capacity than elevated
flares.
Figure 1.8.1 Enclosed ground flare.
-
7/28/2019 10004E00.pdf
45/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 45 of 93
1.8.2 Flare Sizing
1.8.2.1 Evaluation of Flare Diameter
Flare stack diameter is generally sized on a velocity basis, althoughpressure drop should be checked.
Generally, for design proposal, a velocity of 0.5 Mach for a peak, short-
term, infrequent flow, with 0.2 Mach maintained for the more normal and
possibly more frequent conditions for low-pressure flares, is chosen.
However, sonic velocity operation may be appropriate for high-pressure
flares. Moreover, experience has shown that a properly designed and
applied flare burner can have an exit velocity of more than Mach 0,5, if pressure drop, noise and other factors permit. Many pipe flares, assisted,
unassisted or air-assisted flares have been in service for many years with
Mach numbers ranging from Mach 0,8 and higher.
The Mach number is determined as follows:
MWk
Tz
dP
WMach
f atm
=
251023.3 (6)
Where:
W Flow [kg/h]
Z Compressibility factor at flowing condition
T Temperature at vapour outlet [K]
df Flare diameter [m]
k Specific heat ratio, C p/C v
1.8.2.2 Evaluation of Flare Height
The flare stack height is generally based on the radiant heat intensity
generated by the flame. For flare radiation study, reference shall be made
to paragraph 1.11.
-
7/28/2019 10004E00.pdf
46/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 46 of 93
1.8.3 Segregated flare systems
Depending on various factors such as plot plan, equipment design
pressures, etc., it may prove desirable to provide two or more flare
systems, such as separation of high pressure and low pressure headers.
Multiple flare system arrangements may offer significant advantages or
prove mandatory on analysis of the streams that require disposal.
Segregated flare systems may be required in order to:
Segregate sources of release into high and low pressure
systems. This may be required to enable a high pressure low
radiation tip to be used with a consequent saving on flare
structural requirements. This may also mean that only the low
pressure gas requires assistance in order to burn cleanly. As a
general rule, all pressure relief devices with an operating
pressure lower than 10 barg are collected and disposed in an LP
flare system.
Segregate sources with widely differing potentials for liquid
release.
Segregate sources of cold, dry gas from significant quantities of
warm, moist gas and thereby avoid the possibility of freezing and
hydrate formation. A relief header after passing a cold stream will
be cold. If a warm, moist gas then passes, hydrates could be
formed and block the relief header.
Segregate corrosive or potentially corrosive fluids (e.g. CO 2 and
H2S) from non-corrosive or moist fluids.
The selected design should use the minimum practicable number of
separate systems but remain operable and safe under all foreseeable
conditions. The systems installed may be totally independent, or may
share common facilities such as flare knock-out drums and flare tips in
certain circumstances.
When considering the requirement for a high and low pressure disposal
system it is necessary to consider the relief valve set pressures present in
the system. If there are a large number of high pressure sources withlarge gas volumes and a relatively few low pressure sources, then
-
7/28/2019 10004E00.pdf
47/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 47 of 93
generally it would be more economical to install one high pressure relief
header and one low pressure relief header. An economical analysis is
usually required to ascertain the optimum number of flare systems, and to
which system each relief device should discharge.
1.8.4 Flare Disposal of Hydrogen Sulphide
Streams which are rich in hydrogen sulphide shall not be discharged into
a common HC flare or vent system unless it has been designed for this
purpose. This prevents the spreading of sour gas throughout the entire
main flare system and also avoids corrosion attack by hydrogen sulphide
and the subsequent accumulation of deposits of (pyrophoric) ferrous
sulphide.
These streams shall have a separate line-up, preferably a separate flare
stack equipped with a tip of the air pre-mix type. Alternatively, the gas
may be lined up to the bottom (downstream of the water seal) of the
hydrocarbon flare stack, but this should only be done if the hydrogen
sulphide rich flow constitutes a minor additional load.
The installation of a separate sour gas flare relief system implies
additional capital expenditure. From this point of view it is always better to
exclude such a system.
For a preliminary evaluation, the following factors should be considered
before deciding that a separate H 2S flare relief system need to be
installed or not. Sour gas release can be tied into the HC flare system in
case of:
1) continuous HC release with an H 2S content < 2% by volume;
2) intermittent HC release (only during startup and shutdown) with
an H 2S content < 20% by volume, provided this stream is less
than 10% by volume of the total continuous HC release rate;
3) emergency HC release (e.g. PSV, emergency depressuring) with
an H 2S content < 50% by volume.
When hydrogen sulphide rich gas has to be flared, incomplete
combustion can cause a hydrogen sulphide smell resulting in complaints
-
7/28/2019 10004E00.pdf
48/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 48 of 93
by people in the vicinity. Moreover, the presence of un-combusted
hydrogen sulphide shall be dangerous for human being in the proximity of
the plant.
At a low exit velocity back burning will occur, causing sulphide stress
corrosion, especially below the refractory. This means that when H 2S rich
gas has to be released into the HC flare system more purge gas has to
be injected as well on account of the larger size of the flare, which could
offset the saving on capital expenditure.
If a hydrogen sulphide flare relief system is used, this shall be heat-traced
up to 4 m below the top of the stack. Header materials shall be carbon
steel, except for the top 4 metres of the hydrogen sulphide stack, whichshall be of AISI 310 S or equivalent.
Since no water seal vessel has to be installed, the design pressure of the
knock-out drum shall be 7 barg. To prevent flashback and consequential
detonation purge gas shall be used.
1.9 Other Flaring Equipment
1.9.1 K.O. Drum
Gas streams from relief headers are frequently at or near their dewpoint,
where condensation may occur.
A knockout drum is usually provided near the flare/vent base, and serves
to recover liquid hydrocarbons, prevent liquid slugs, and remove liquid
particles. The knockout drum reduces hazards caused by burning liquid
that could escape from the flare stack. As mentioned above, all lines downstream a relief/blowdown device
should be sloped toward the knockout drum to permit condensed liquid to
drain into the drum for removal. The locating of the flare/vent knockout
drum also needs to take into account radiation effect from the burning
flare/accidental ignition of the vent.
The economics of drum design may influence the choice between a
horizontal and a vertical drum. When a large liquid storage capacity isdesired and the vapour flow is high, a horizontal drum is often more
-
7/28/2019 10004E00.pdf
49/93
Eni S.p.A. Exploration & Production Division
10004.HTP.PRC.PRGRev. 0 January 2008
Sh. 49 of 93
economical. Also, the pressure drop across horizontal drums is generally
the lowest of all the designs. Vertical knock out drums are typically used
where the liquid load is low or limited plot space is available. They are
well suited for incorporating into the base of the stack.
1.9.1.1 K.O. Drum Pump and Instrumentation
As just mentioned, knockout drums may be of the horizontal or vertical
type; and they should be provided with a pump or draining facilities and
instrumentation to remove the accumulated liquids to a tank, sewer, or
other location. The actual type of disposal used will depend on the
characteristics and hazards associated with the liquids removed.
In the simplest system, the vessel may have only a manually operated
drain valve and a liquid-level sight glass for reference. Moreover, a liquid-
removal pump is frequently used on knock-out drums.
More elaborate arrangements may foresee high-