10004e00.pdf

Upload: barcellona6

Post on 03-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 10004E00.pdf

    1/93

    Eni S.p.A. Exploration & Production Division

    BEST PRACTICE

    UNIT 230

    RELIEF AND BLOWDOWN SYSTEM

    10004.HTP.PRC.PRG

    Rev. 0 January 2008

  • 7/28/2019 10004E00.pdf

    2/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 2 of 93

    INDEX

    ACRONYMS 5

    RELIEF AND BLOWDOWN SYSTEM UNIT 230 6

    1.1 General ..................................................................................................................................6 1.2 Systems Description .............................................................................................................. 6 1.3 Relief System Design............................................................................................................. 7

    1.3.1 Overpressure Protection Philosophy ........................................................................7 1.3.2 Upset Conditions.......................................................................................................8

    1.3.2.1 Blocked Discharge..................................................................................... 8 1.3.2.2 Inadvertent Valve Opening ........................................................................9 1.3.2.3 Control Valve Failure ................................................................................. 9 1.3.2.4 Utility Failure .............................................................................................. 9 1.3.2.5 Fire Exposure .......................................................................................... 10 1.3.2.6 Jet Fire ..................................................................................................... 10 1.3.2.7 Entrance of volatile material into the system........................................... 11 1.3.2.8 Thermal Expansion..................................................................................11 1.3.2.9 Tube Rupture........................................................................................... 11 1.3.2.10 Internal Explosion ....................................................................................12 1.3.2.11 Chemical Reaction...................................................................................12 1.3.2.12 Hydraulic Expansion................................................................................ 12

    1.3.3 Additional Consideration .........................................................................................14 1.3.3.1 Pumps......................................................................................................14 1.3.3.2 Compressors ........................................................................................... 15 1.3.3.3 Turbines................................................................................................... 15 1.3.3.4 Fired Heaters ........................................................................................... 15 1.3.3.5 PSV Operating in Liquid Service ............................................................. 15 1.3.3.6 Atmospheric and Low Pressure Storage Tanks ...................................... 18

    1.3.4 Relief Devices .........................................................................................................18 1.3.4.1 Spring loaded relief valves....................................................................... 18 1.3.4.2 Pilot-operated relief valves ......................................................................19 1.3.4.3 Rupture disks........................................................................................... 20

    1.3.5 Relief Valves Location.............................................................................................20 1.3.6 Piping Upstream of a Relief Device ........................................................................21

    1.4 Blowdown System Design ................................................................................................... 23 1.4.1 Determination of Blowdown Requirements............................................................. 24 1.4.2 Sectioning of the Process Systems ........................................................................26 1.4.3 Depressuring Device Location ................................................................................27

    1.5 Layout of Downstream Piping Systems ...............................................................................28 1.5.1 Common Discharge Systems..................................................................................28 1.5.2 Blockage Due to Hydrate Formation in Downstream Piping System......................29

    1.6 Isolation Valves in Pressure Relief Piping ...........................................................................29 1.6.1 Isolation Valves Requirements................................................................................30 1.6.2 Interlocking Systems ............................................................................................... 33

    1.6.2.1 Discharge to Atmosphere ........................................................................34 1.6.2.2 Discharge to Closed System ...................................................................34

    1.7 Disposal System .................................................................................................................. 36 1.7.1 General....................................................................................................................36 1.7.2

    Atmospheric discharge............................................................................................37

    1.7.3 Disposal by Flaring..................................................................................................37 1.7.4 Flaring Versus Venting............................................................................................37

  • 7/28/2019 10004E00.pdf

    3/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 3 of 93

    1.7.5 Flare and Vent Structure.........................................................................................39 1.7.5.1 Self-supported ......................................................................................... 39 1.7.5.2 Guy-wire supported .................................................................................40 1.7.5.3 Derrick supported ....................................................................................40

    1.8

    Flare System Design............................................................................................................40 1.8.1 Flare Type ...............................................................................................................41

    1.8.1.1 Exothermic Flares.................................................................................... 41 1.8.1.2 Endothermic Flares..................................................................................43 1.8.1.3 Enclosed Ground Flares..........................................................................44

    1.8.2 Flare Sizing .............................................................................................................45 1.8.2.1 Evaluation of Flare Diameter ...................................................................45 1.8.2.2 Evaluation of Flare Height .......................................................................45

    1.8.3 Segregated flare systems .......................................................................................46 1.8.4 Flare Disposal of Hydrogen Sulphide .....................................................................47

    1.9 Other Flaring Equipment......................................................................................................48 1.9.1 K.O. Drum ...............................................................................................................48

    1.9.1.1 K.O. Drum Pump and Instrumentation ....................................................49 1.9.1.2 K.O. Drum Sizing .....................................................................................49

    1.9.2 Liquid Seals.............................................................................................................51 1.9.3 Purge System..........................................................................................................51

    1.10 Vent System Design ............................................................................................................ 52 1.10.1 Vent Sizing ..............................................................................................................52 1.10.2 Individual vent outlets..............................................................................................53

    1.11 Flare Radiation Study .......................................................................................................... 54 1.12 Relief and Blowdown System Highlights .............................................................................61

    APPENDIX 1 - SIZING OF RELIEF DEVICES ..............................................................................65 Design Considerations ............................................................................................ 65 Sizing for Gas or Vapour Relief...............................................................................67 Sizing for Steam Relief............................................................................................ 71 Sizing for Liquid Relief ............................................................................................ 72 Sizing for Two Phase Liquid-Vapour Relief ............................................................ 74 Sizing for Thermal Relief......................................................................................... 74

    APPENDIX 2 HIGH INTEGRITY PROTECTION SYSTEM (HIPS) ............................................ 76 Reference Documents ............................................................................................ 76 HIPS Justification.................................................................................................... 78 HIPS Design............................................................................................................79

    Advantages and Disadvantages of HIPS................................................................ 84 GLOSSARY 87

    REFERENCE 92

  • 7/28/2019 10004E00.pdf

    4/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 4 of 93

    For Main Utilities Best Practice reference shall be made to Eni E&P

    internal document No. 10002.HTP.PRC.PRG .

  • 7/28/2019 10004E00.pdf

    5/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 5 of 93

    ACRONYMS

    BDV Blowdown valve

    CCF Common cause failure

    DIERS Design institute for emergency relief system

    ESD Emergency shutdown

    HIPS High integrity protection system

    LHV Lower heating value

    PES Programmable electronic system

    PRV Pressure relief valve

    PSV Pressure safety valve

    SIL Safety integrity level

    SIS Safety instrumented system

    SRS Safety requirement specification

    S/R VALVE Safety / Relief valve

    TSV Thermal safety valve

  • 7/28/2019 10004E00.pdf

    6/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 6 of 93

    RELIEF AND BLOWDOWN SYSTEM UNIT 230

    1.1 General

    This document sets out the general guidelines for sizing and designing a

    relief and blowdown system, for both on-shore and off-shore production

    facilities, with particular attention to the flare sizing.

    The principal elements of pressure relief systems are the individual

    pressure relief devices, the flare piping system, the flare separator drum,

    and the flare including sealing devices, purge and steam injection for

    smokeless burning.

    Design of relief systems must comply with applicable state and federal

    codes and laws as well as the requirements of the insurance covering the

    plant or installation. State and federal regulations not only cover safety

    but also environmental considerations such as air and water pollution and

    noise abatement.

    This section presents a convenient summary of relief, depressuring and

    disposal systems information obtained from API 520 / 521 / 526 / 537 and

    other sources.

    1.2 Systems Descr ipt ion

    Pressure relieving devices have to be installed to ensure that a process

    system or any of its components are not subjected to pressures that

    exceed the design pressure. API 521 recommends a depressurization

    time (to 7 barg) of 15 minutes (see Paragraph 1.4) ; therefore, relieving

    flowrates can be considered to be continuous rates of limited duration 10

    - 15 min. The relieving rate will cease once the source of overpressure is

    isolated.

    Blow-down depressuring valves are intended to provide for a rapid

    reduction of pressure in equipment by releasing vapours, as pressure

    safety valves cannot provide depressuring and merely limit the pressure

    rise under emergency conditions.

  • 7/28/2019 10004E00.pdf

    7/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 7 of 93

    1.3 Relief System Design

    The flowrates to the system can be caused by various operating and

    upset conditions not all of which are of emergency type.

    Even though the determination of relieving rates for each upset condition

    and sizing of the relevant relief device is out of the scope of the work, in

    the following is given a brief description of the most common

    overpressure causes; moreover, Appendix 1 contains some relief devices

    sizing methods. However, for a more rigorous determination of individual

    relieving rates and relief devices sizing reference should be made

    respectively to Section 5 of API 521 and to API 520.

    1.3.1 Overpressure Protection Philosophy

    Overpressure is due to a deviation of the normal operating conditions and

    it is the result of an unbalance or disruption of the normal flows of

    material and energy that causes the material or energy, or both, to build

    up in some part of the system. Analysis of the causes and magnitudes of

    overpressure is, therefore, a special and complex study of material and

    energy balances in a process system.

    Overpressure may result from:

    (a) heat input, which is indirect pressure input through vaporization

    or thermal expansion

    (b) direct pressure input from higher pressure sources.

    The causes of overpressure are considered to be unrelated if no process

    or mechanical or electrical linkages exist among them, or if the length of

    time that elapses between possible successive occurrences of these

    causes is sufficient to make their classification unrelated.

    The simultaneous occurrence of two or more unrelated causes of

    overpressure (also known as double or multiple jeopardy) is not a basis

    for design. Example double jeopardy scenarios might be: fire exposure

    simultaneous with exchanger internal tube failure, fire exposure

    simultaneous with failure of administrative controls to drain and

    depressure isolated equipment, or operator error that leads to a blocked

  • 7/28/2019 10004E00.pdf

    8/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 8 of 93

    outlet coincidental with a power failure. On the other hand, instrument air

    failure during fire exposure may be considered single jeopardy if the fire

    exposure causes local air line failures.

    1.3.2 Upset Conditions

    Pressure vessels, heat exchangers, operating equipment, and piping are

    designed to contain the system pressure. The equipment design is based

    on the normal operating pressure at operating temperatures, the effect of

    any combination of process upsets that are likely to occur and the

    differential between the operating and set pressures of the pressure-

    relieving device.

    The process systems designer must define the minimum pressure relief

    capacity required to prevent the pressure in any piece of equipment from

    exceeding the maximum allowable accumulated pressure.

    In the following is given a brief description of some common occurrences

    that may require overpressure protection. This summary is not intended

    to be all inclusive; it is merely recommended as a guide.

    1.3.2.1 Blocked Discharge

    The inadvertent closure of a block valve on the outlet of a pressure

    vessel while the plant is on stream may expose the vessel to a pressure

    that exceeds the maximum allowable working pressure.

    If closure of an outlet block valve can result in overpressure, a pressure

    relief device is required unless administrative procedures to control valveclosure, such as car seals or locks, are in place. In this case, the relief

    load is usually the maximum flow which the pump, compressor, or other

    flow source produces at relief conditions. The quantity of material to be

    relieved should be determined at conditions that correspond to the set

    pressure plus overpressure instead of at normal operating conditions.

    Instantaneously, the flowrate to be discharged should be higher than the

    normal operating flow (e.g. compressor). Moreover, the presence of a

    liquid outlet on the vessel (LV) could decrease the flowrate to be

  • 7/28/2019 10004E00.pdf

    9/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 9 of 93

    discharged. However, during design operation the worst case shall be

    considered; therefore, only the higher flowrate case (absence of liquid

    outlet or closed LV) shall be deeply analyzed for relief device sizing.

    1.3.2.2 Inadvertent Valve Opening

    The inadvertent opening of any valve from a source of higher pressure,

    such as high-pressure steam or process fluids, should be considered.

    This action may require pressure-relieving capacity unless provisions are

    made for locking or sealing the valve closed.

    This overpressure scenario can be due to operator error, who can

    operate the valve in the wrong position, or to valve leakage. In these

    cases, the relief valve shall be sized considering the maximum valve C v

    declared by the manufacturer and the maximum p across the valve

    (valve set pressure protected equipment design pressure).

    1.3.2.3 Control Valve Failure

    The failure positions of instruments and control valves must be carefullyevaluated. A valve may stick in the wrong position, or a control loop may

    fail. If one or more of the inlet valves are opened by the same failure that

    caused the outlet valve to close, pressure-relieving devices may be

    required to prevent overpressure. The required relief capacity is the

    difference between the maximum inlet and maximum outlet flows.

    1.3.2.4 Utility Failure

    The consequences that may develop from any utility service loss,

    whether local or plantwide, must be carefully evaluated. The normal utility

    services that could fail and a partial listing of affected equipment that

    could cause overpressure are given in Table 1.3.1.

  • 7/28/2019 10004E00.pdf

    10/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 10 of 93

    Utility Failure Equipment Affected

    Pumps for cooling water circulation or any other service such as boiler feed, reflux, etc.

    Air cooler fans, cooling tower

    Compressors (for air, vacuum, refrigeration, etc.)Instrumentation

    Electric

    Motor-operated valvesCondensers and coolersCooling Water Jackets on rotating equipmentTransmitters / Controllers / AlarmsInstrument Air Regulating valvesTurbine driversReboilersReciprocating pumps

    Steam

    Direct steam injection equipmentBoilers

    Engine driversCompressorsFuelGas TurbinesSealsInert Gas Purge System

    Table 1.3.1 Possible utility failure and relevant equipment affected.

    1.3.2.5 Fire Exposure

    Even if fire is not usually the condition that may create the greatest

    relieving requirements, it is the most common case.

    Various empirical equations have been developed to determine relief

    loads from vessels exposed to fire. Formula selection varies with the

    system and fluid considered (see API 521, Section 5).

    1.3.2.6 Jet Fire

    Jet fire is a fire created when a leak from a pressurized system ignites

    and forms a burning jet. Jet fires can occur when almost any combustible

    / flammable fluid under pressure is released to atmosphere. Equipment

    failure during a jet-fire is due to a localized and instantaneous

    overheating without a significant pressure increase in the equipment (the

    relief device set point isnt often reached). This is due to the localized

    nature of heating whereby the bulk fluid temperature might not increase

    appreciably. Hence, a relief device might not prevent vessel failure from

    jet fire impingement.

  • 7/28/2019 10004E00.pdf

    11/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 11 of 93

    Instead of a pressure-relief system, protection against jet fires focuses on

    prevention of leaks through proper maintenance and/or mitigation

    systems such as fireproofing, depressuring systems, isolation of leaks,

    equipment and/or flange orientation and minimization and emergency

    response.

    1.3.2.7 Entrance of volatile material into the system

    Entrance of water or light hydrocarbons into hot oil, causing a great and

    instantaneous expansion in volume, can cause system overpressure.

    Normally, a pressure relieving device is not provided for this contingency.

    Proper design and operation of the process system are essential in

    attempts to eliminate this possibility.

    1.3.2.8 Thermal Expansion

    If isolation of a process line on the cold side of an exchanger can result in

    excess pressure due to heat input from the warm side, then the line or

    cold side of the exchanger should be protected by a pressure safetyvalve (PSV). If any equipment, item or line can be isolated while full of

    liquid, a PSV should be provided for thermal expansion of the contained

    liquid.

    1.3.2.9 Tube Rupture

    When a large difference exists between the design pressure of the shell

    and tube sides of an exchanger, provisions is required for relieving the

    low pressure side (it could be required either on shell side or on tube

    side). Because the test pressure is normally about 150% of the design

    pressure, a 2/3 rule is established from it. The rule is this: pressure relief

    for tube rupture is not required where the low pressure exchanger side

    (including upstream and downstream systems) is designed at or above

    the 2/3 criteria. Because ASME changed the hydrostatic test pressure for

    pressure vessels from the 150% design pressure to a new standard of 130% design pressure, the existing 2/3 rule changed to a 10/13 rule.

  • 7/28/2019 10004E00.pdf

    12/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 12 of 93

    As a general rule, the required relief capacity is based on twice the tube

    cross section area, and the assumption that high pressure fluid can flow

    through both the tube stub and the other end of the tube.

    1.3.2.10 Internal Explosion

    Where overpressure protection against internal explosions (excluding

    detonation) caused by ignition of vapour-air mixtures is to be provided,

    rupture discs or explosion vent panels, not relief valves, should be used.

    Relief valves cannot be used in this case because they react too slowly to

    protect the vessel against the extremely rapid pressure build-up caused

    by internal flame propagation.

    1.3.2.11 Chemical Reaction

    The rapid evolution of an exothermic reaction (runaway) or the

    degradation reaction which generates gas products can cause the vessel

    rupture. Exothermic reactions become dangerous only when the

    produced heat is greater than the removed heat and the temperatureincrease causes a reaction rate increase.

    Protection against reaction runaway or gases generation should be

    provided. The methodology for determining the appropriate size of an

    emergency vent system for chemical reactions was established by DIERS

    (Design Institute for Emergency Relief Systems).

    1.3.2.12 Hydraulic Expansion

    Hydraulic expansion is the increase in liquid volume caused by an

    increase in temperature. It can result from:

    (a) Piping or vessels are blocked-in while they are filled with cold

    liquid and are subsequently heated.

    (b) An exchanger is blocked-in on the cold side with flow in the hot

    side.

  • 7/28/2019 10004E00.pdf

    13/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 13 of 93

    (c) Piping or vessels are blocked-in while they are filled with liquid at

    near-ambient temperatures and are heated by direct solar

    radiation.

    Provisions are required for relieving the equipment. The capacity

    requirement is not easy to determine. Since every application will be

    relieving liquid, the required capacity of the thermal safety valve (TSV)

    will be small; specifying an oversized device is, therefore, reasonable. A

    3 4 1 nominal pipe size (NPS 3 4 NPS 1) relief valve is commonly

    used.

    Proper selection of the set pressure for these relieving devices should

    include a study of the design rating of all items included in the blocked-insystem. The TSV pressure setting should never be above the maximum

    pressure permitted by the weakest component in the system being

    protected.

    3 4 1 size is not adequate for long pipelines of large diameter in

    uninsulated aboveground installations and large vessels or exchangers

    operating liquid-full; in these cases, in order to evaluate the relief device

    proper size, the following equation must be applied:

    cdq V

    =

    1000

    (1)

    Where:

    q volume flowrate at flowing temperature [m/s]

    V cubic expansion coefficient for the liquid at the expected

    temperature [1/C]

    total heat transfer rate [W]

    d relative density referred to water ( d = 1.00 @15.6C)

    c specific heat capacity of trapped fluid [J/kgK]

    For aboveground pipelines protection, a system with multiple TSVs shall

    be provided. The distance from one TSV to the other is specified on

    mechanical standard documents.

  • 7/28/2019 10004E00.pdf

    14/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 14 of 93

    If the liquid being relieved is expected to flash or form solids while it

    passes through the relieving device, the procedure described in API 520

    is recommended.

    1.3.3 Additional Consideration

    In the following is given a short summary for sizing the relief devices for

    those equipment, such as pumps, compressors, atmospheric and low

    pressure storage tanks, etc., which are not included in the API 520 and

    API 521. This paragraph is also intended to give a brief description about

    pressure safety valve operating in liquid service.

    1.3.3.1 Pumps

    Alternative pumps, in order to avoid the motor pump overheating and to

    protect the piping downstream from pressures greater than design

    pressure, require a safety valve on the discharge. Therefore, because of

    the double function of the relief valve (protection against overpressure

    and overheating), this devices shall be sized for both overpressure andoverheating. For overheating considerations, the pump manufacturer

    shall be consulted.

    Normally, these devices are piped back to the vessel or piping upstream

    of the pump rather than to the flare system.

    For a preliminary estimation of the valve set pressure, the following

    equation shall be applied. The valve set pressure is calculated using both

    equations; the chosen value is the greater between the two results.

    deliveryset pp = 1.1 (2)

    deliveryset pp += 7.1 (3)

    Where:

    pset Valve set pressure [bar]pdelivery Pump delivery pressure [bar]

  • 7/28/2019 10004E00.pdf

    15/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 15 of 93

    For valves sizing a flowrate value equal to the pump flowrate (or pump

    maximum flowrate in case of pumps with variable motor) must be taken

    into consideration.

    Lines and equipment downstream a centrifugal pump have always a

    design pressure equal to the pump shut-off pressure. Wherever this rule

    is not applied, the piping and / or equipment downstream the pump shall

    be protected with a relief device.

    1.3.3.2 Compressors

    In order to protect rotary compressors and lines, a relief valve upstream

    of the block and check valves shall be provided on the compressor

    delivery and, if foreseen, on each of the intermediate stages.

    1.3.3.3 Turbines

    A special pressure relief valve shall be foreseen at the turbine outlet in

    order to prevent overpressure phenomena at the condenser in case of cooling water loss or other system failure.

    This kind of valve, without spring, acts against atmospheric back-

    pressure and requires water for seals.

    1.3.3.4 Fired Heaters

    If there is a possibility that the process side of a fired heater may be

    blocked-in, then a relief valve should be provided to protect the heater.

    1.3.3.5 PSV Operating in Liquid Service

    For those relief valves protecting equipment operating in liquid service,

    the set pressure shall be evaluated taking into consideration the liquid

    head and the elevation of the valve itself.

    During the first engineering phase, the valve elevation could be uncertain;

    in these cases, the designer shall evaluate the valve set pressure

  • 7/28/2019 10004E00.pdf

    16/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 16 of 93

    supposing a reasonable valve height. For valve elevation preliminary

    estimate the following method shall be applied:

    a) Considering a relief header laying on the pipe-rack at an

    elevation of 10 m and equipment with an upper tangent line lower

    than 10.5 m, the safety valve set pressure shall be evaluated

    supposing a PSV elevation of at least 10.5 m aboveground.

    Figure 1.3.1 PSV in l iquid serv ice.

    b) For all the equipments whose upper tangent line is higher than10.5 m (or above the relief header upper tangent line), the

    following considerations shall be applied:

    b.1) If the equipment is inside a structure, the PSV shall be

    positioned 1.5 m above the first level over the equipment upper

    tangent line. This level is 3 m above the upper tangent line.

  • 7/28/2019 10004E00.pdf

    17/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 17 of 93

    Figure 1.3.2 - PSV in liquid service.

    b.2) If there isnt a level over the equipment, the PSV shall have a

    minimum elevation above the upper tangent line.

    Figure 1.3.3 - PSV in liquid service.

  • 7/28/2019 10004E00.pdf

    18/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 18 of 93

    1.3.3.6 Atmospheric and Low Pressure Storage Tanks

    In this paragraph is given a short description of relief devices required for

    storage tanks designed for operation at pressure from vacuum to 15 psig

    (103.4 kPag) overpressure protection. For more rigorous information

    about atmospheric and low pressure overpressure protection, reference

    shall be made to API 2000.

    Common overpressure causes for this kind of storage tank (with or

    without weak roof-to-shell attachment) are listed in the following:

    Liquid movement into or out of the tank;

    Tank breathing due to weather changes;

    Fire exposure

    Other circumstances such as equipment failure or operating

    errors.

    In case of tanks with fixed roof, the PSV to be installed shall be sized

    considering the most severe overpressure condition.

    Tanks with weak roof-to-shell attachment, as better specified in API 650,

    are designed with a roof-to-shell connection which fails in case of fire and

    protect the equipment itself. Hence, for a tank built to these

    specifications, a relief device for protecting the equipment exposed to fire

    is not required. However, an overpressure protection for the most severe

    condition identified among the remaining overpressure causes is

    required. The PSV to be installed shall be sized for the most severe

    condition and assuming the blanketing valve fully opened.

    1.3.4 Relief Devices

    1.3.4.1 Spring loaded relief valves

    A conventional pressure relief valve is a self-actuated spring-loaded

    pressure relief valve which is designed to open at a predetermined

    pressure and protect a vessel or system from excess pressure by

    removing or relieving fluid from that vessel or system.

  • 7/28/2019 10004E00.pdf

    19/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 19 of 93

    Conventional spring-loaded relief valves shall be installed where back-

    pressure does not exceed 10% of the set pressure (see API 520, Section

    3, Paragraph 3.3.3.1)

    A balanced pressure relief valve is a spring loaded pressure relief valve

    which incorporates a bellows or other means of balancing the valve disc

    to minimize the effects of back pressure on the performance

    characteristics of the valve.

    Balanced pressure relief valves should be considered where the built-up

    back pressure (back pressure caused by flow through the downstream

    piping after the relief valve lifts) is too high for a conventional pressure

    relief (see API 520, Section 3, Paragraph 3.3.3.1).In general, balanced pressure relief valves are suitable for back-

    pressures ranging from 10% to 50% of the set pressure. They can be of

    two main types: balanced piston and balanced bellows. Balanced bellows

    shall be given preference where the fluid is corrosive or fouling.

    1.3.4.2 Pilot-operated relief valves

    A pilot-operated pressure relief valve consists of the main valve, which

    normally encloses a floating unbalanced piston assembly, and an

    external pilot.

    Pilot-operated relief valves shall be selected rather than conventional

    spring-loaded relief valves when any of the requirements listed

    hereinafter is present: low accumulation rates, calibration without

    removing the valve, handling of large flows, higher pressure in the

    downstream piping is required etc.

    It shall be ensured, before selecting a pilot-operated relief valve, that

    there is no possibility of blockage of the pilot valve or sensing line due to

    hydrates, ice, wax or solids. There shall be no low points in the sensing

    line or its take off, and all fine bore elements exposed to process fluids

    shall be heat-traced and insulated if non-blockage cannot be guaranteed.

    Filters shall not be used in the sensing line to the pilot valve because they

    can increase the risk of blockage.

  • 7/28/2019 10004E00.pdf

    20/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 20 of 93

    1.3.4.3 Rupture disks

    Rupture disk devices are non-reclosing pressure relief devices used to

    protect vessels, piping and other pressure containing components from

    excessive pressure and/or vacuum. Rupture disks are used in single and

    multiple relief device installations. They are also used as redundant

    pressure relief devices.

    With no moving parts, rupture disks are simple, reliable and faster acting

    than other pressure relief devices. Because of these, rupture disks are

    used in any application requiring overpressure protection where a non-

    reclosing device is suitable.

    Moreover, because of their light weight, rupture disks can be made from

    high alloy and corrosion-resistant materials that are not practical in

    pressure relief valves.

    These devices can be specified for systems with vapour or liquid

    pressure relief requirements. Also, rupture disk designs are available for

    highly viscous fluids. The use of rupture disk devices in liquid service

    should be carefully evaluated to ensure that the design of the disk is

    suitable for liquid service. The user should consult the manufacturer for

    information regarding liquid service applications.

    Rupture disks can be of various types; for more details see API 520.

    1.3.5 Relief Valves Location

    To ensure protection of the whole system, the relief assembly should be

    located, where practical, in the upstream part, i.e. where the highest

    pressure occurs, and as close as possible to the source of overpressure.

    Relief valves shall be connected to the protected equipment in the vapour

    space above any contained liquid or to piping connected to the vapour

    space. An exception can be made if the vessel is fitted with a demister

    mat. In this case the relief connection shall be upstream of the mat,

    unless the relieving capacity is of the same order of magnitude as the

    normal operating flow through the demister mat.

  • 7/28/2019 10004E00.pdf

    21/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 21 of 93

    The pressure drop of the piping between protected equipment and its

    relief valve shall not exceed 3% of the set pressure.

    The inlet and outlet piping shall be installed without pockets to ensure

    that liquid does not accumulate at the relief valve outlet or inlet.

    Relief valves discharging to atmosphere should be located at the

    maximum practical elevation to keep discharge piping (to safe location)

    as short as possible. In case of multiple relief valves (including one

    spare), each relief valve shall have an individual discharge pipe (see also

    API 521).

    Relief valves connected to a closed relief system shall be located above

    the relief header. Relief valve outlet lines should be connected to the topof the header, or at least so that the header cannot drain back into outlet

    lines even with the header full of liquid. If the valves cannot be put above

    the header, they shall be lined up to discharge into a local drain vessel.

    Alternatively, if the problem of elevation is confined to a few valves, outlet

    lines to the header shall be heat-traced from the relief valve to the highest

    point of the line. Heat tracing isnt permitted for relief valves which

    discharge a medium which can leave a deposit.Relief valve systems require periodic inspection and maintenance and

    hence they should be easily accessible.

    1.3.6 Piping Upstream of a Relief Device

    In order to ensure safe disposal of flared and vented streams, certain

    factors shall be taken into consideration when designing the pipework

    upstream of the relief device.Piping upstream of a relief device should be designed with as few

    restrictions to flow as possible and should not be pocketed.

    The flow area through all pipe and fittings between a pressure vessel and

    its relief valve shall be at least the same as that of the valve inlet (e.g.

    isolation valves shall be full bore).

    Depending on the actual relief valve capacity, the pressure drop of the

    inlet piping and fittings shall not exceed 3% of the valve set pressure (thisis to avoid chatter, which will result in significant seat damage and loss of

  • 7/28/2019 10004E00.pdf

    22/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 22 of 93

    capacity). Exceptions to this requirement are only allowed in the case of a

    pilot-operated valve with a suitably arranged remote pilot connection

    close to the source of overpressure.

    The above is especially applicable to relief valves handling gas or vapour.

    Relief valves in pure liquid service require special attention, since in this

    case chatter may also be caused by the acceleration of the (non

    expandable) liquid in the inlet piping: a change in pressure amounting to

    more than 3% of the set pressure will readily occur and cause valve

    chatter. In this case the likelihood of chatter can be limited by installing a

    relief valve with a special liquid trim (linear flow characteristic) thereby

    avoiding the need to take the relief valve capacity to determine thepressure drop of the inlet piping. For PSV sizing in liquid service see

    paragraph 1.3.3.5.

    When two or more relief valves (spares not counted) are fitted on one

    connection, the cross-sectional area of this connection shall be at least

    equal to the combined inlet areas of the valves, and the above pressure

    drop requirement shall apply for the combined flow of the valves.

    Relief valves on cold process streams shall have an uninsulated inlet lineof sufficient length to prevent icing of the relief valve, in particular the disk

    and spring. Alternatively, heat tracing may be required. Special attention

    shall be paid in this respect to valves which discharge into the

    atmosphere, i.e. in those having open outlets which may become blocked

    with ice.

    To avoid the need for special high temperature materials, relief valves on

    hot process streams may be installed using an uninsulated length of inletline, creating a cold dead ended leg between the process stream and the

    relief valve.

    A pressure safety valve typical scheme is shown in Figure 1.3.4.

  • 7/28/2019 10004E00.pdf

    23/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 23 of 93

    Figure 1.3.4 PSV typical s cheme.

    1.4 Blowdown System Design

    Because of a relief valve cannot depressurize a system but can only limit

    the pressure rise to the set point during upset conditions, a dedicated

    depressuring system is required to mitigate the consequences of a vessel

    leak by reducing the leakage rate or to reduce the failure potential for

    scenarios involving overheating (e.g. fire).

    When metal temperature is increased due to fire or exothermic or

    runaway process reactions, the metal temperature may reach a level at

    which stress rupture could occur. This may be possible even though the

    system pressure does not exceed the maximum allowable accumulation.

    In this case, depressuring reduces the internal stress thereby extending

    the life of the vessel at a given temperature.

    In order to be effective, the depressuring system must depressure the

    vessel such that the reduced internal pressure keeps the stresses below

    the rupture stress. API 521 suggests depressurizing to 6.9 barg or 50% of

  • 7/28/2019 10004E00.pdf

    24/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 24 of 93

    vessel design pressure, whichever is the lower, within 15 minutes.

    Moreover, Eni E&P internal standard, see doc. no. 20199.VON.SAF.SDS,

    suggests reaching the 50% of vessel operating pressure within 5 minutes

    and then depressurizing to 7 barg within the next 10 minutes. Even

    though API 521 suggests this criterion for carbon steel vessels with a wall

    thickness of approximately 1 or more, the above described depressuring

    criterion is also applied for vessels with thinner walls.

    Depressuring is assumed to continue for the duration of the emergency.

    The valves should remain operable for the duration of the emergency or

    should fail in a full open position. Fireproofing of the control signal and

    valve actuator may be required in a fire zone. As per API 521, emergency depressuring for the fire scenario should be

    considered for large equipment operating at or above 250 psig (aprrox.

    1700 kPag). Depressuring criteria other than those given above can be

    used depending upon the specific circumstances and user-defined

    requirements. For example, if there is a reactive hazard or other

    exceptional hazard that can cause loss of containment due to over-

    temperature, emergency depressuring can be appropriate for equipmentdesigned for a wider range of pressures than that noted above.

    1.4.1 Determination of Blowdown Requirements

    As mentioned above, blowdown systems are principally required to

    reduce the risk of loss of equipment integrity during a fire or to reduce a

    local loss of containment arising from a leak when such an occurrence

    could create an unacceptable safety hazard.

    In assessing whether or not blowdown valves (BDV) are required,

    particular attention should be paid to equipment location with respect to

    other equipment, buildings and personnel, and the contents of the

    equipment in terms of quantity and composition. Figure 1.4.1 shows a

    typical BDV scheme.

  • 7/28/2019 10004E00.pdf

    25/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 25 of 93

    Figure 1.4.1 Typical BDV scheme.

    In performing the depressuring analysis it shall be ensured that

    throughout depressuring the system pressure never exceeds the load

    bearing capacity of the equipment. Account shall therefore be taken of

    the reduction of strength with increasing temperature.

    As per API 521, the depressuring system shall reduce the pressure of the

    equipment within a fire zone to 50% of the design pressure or 6.9 barg

    within 15 minutes. This does not imply that the depressuring stops after

    15 minutes. Rotating equipment represent an exception because, due to

    the loss of seal pressure, depressuring may be required in much less

    than 15 minutes.

    The depressuring calculation shall take into account the following:

    Vaporization of the liquid due to the reduction in pressure;

    Change in density of the vapour in the equipment due to the

    pressure reduction and temperature increase;

    Vaporization due to heat input from the external fire.

  • 7/28/2019 10004E00.pdf

    26/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 26 of 93

    In general, for depressuring system sizing, an initial pressure equal to

    safety relief valve set pressure shall be taken into account. Compressor

    systems have instead an initial depressuring pressure equal to

    compressor settle out pressure. In order to evaluate compressor settle

    out pressure, the following equations shall be applied:

    psettle out =tot

    edischedischsuctionsuction

    VVpVp argarg + (4)

    and for a preliminary estimate

    p settle out = edischsuction pp arg3/13/2 + (5)

    Sizing of depressuring valves shall be based on the assumption that,

    during a fire, all input and output streams to and from the system are

    stopped and all internal heat sources within the process have ceased. It

    shall also be assumed when calculating the vapour load generated that

    fire is in progress throughout the depressuring period.

    To determine the vapour depressuring flowrates it is necessary to

    establish a liquid inventory and the vapour volume of the system. This

    shall include all facilities located in the fire area and all equipment outside

    the fire area which, under normal operating conditions, are in open

    connection with the facilities located within the fire area.

    1.4.2 Sectioning of the Process Systems

    In large plants, in order to reduce the design blowdown flow rate, process

    sectionalizing may be considered.

    Process sectionalizing is a philosophy applied to split an installation into a

    number of smaller fire zones. Potential fire areas shall be identified and

    clearly shown on a plot plan. For process units, depending on the

    drainage design of the plot, a typical fire area of 300 m should be

    assumed.

  • 7/28/2019 10004E00.pdf

    27/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 27 of 93

    Each zone shall be isolated by emergency shutdown (ESD) valves. Each

    zone shall be provided with its own depressurizing facilities, such that

    each zone can be depressurized sequentially, thereby reducing the

    design peak rate.

    After initiating depressurisation of the first zone, that of other zones may

    be initiated as soon as the flowrate of the first zone has decayed such

    that a second zone may be initiated without exceeding the design

    capacity of the flare/vent system. This strategy requires equipment in an

    adjacent fire zone to be adequately protected by a combination of

    appropriate layout, fire walls, fire proof insulation, such that the risk of a

    loss of integrity of equipment in a fire zone adjacent to the first affectedzone is insignificant.

    This approach is not usually practical on an integrated offshore

    production platform or in small plants; in these cases, during an ESD, all

    blowdown valves open simultaneously and sequenced depressurization

    using time delays is not used. Moreover, the sectioning of the process

    system and time delays shall not be applied in those plants where a

    single event can cause the simultaneous opening of the entire systemblowdown valve.

    1.4.3 Depressuring Device Location

    The location of depressuring valves shall be governed by the same

    considerations as relief valves and they may discharge into the same

    disposal system as the relief valves on the equipment under

    consideration.

    Particular attention should also be paid to the position of non-return

    valves when locating depressuring valves, to ensure that equipment

    downstream of the non-return valve cannot be isolated from the

    depressuring valve.

    Depressuring devices require periodic testing and hence the

    depressuring device should be located to allow easy access.

  • 7/28/2019 10004E00.pdf

    28/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 28 of 93

    1.5 Layout of Downstream Piping Systems

    1.5.1 Common Discharge Systems

    It is usually simpler and more economic to combine discharges from anumber of facilities into a common discharge system served by a central

    vent or flare.

    In the normal configuration of a common discharge system designed for

    venting or flaring gas at an elevated height, a knock-out drum situated

    close to the stack is required to recover liquid hydrocarbon or slugs. The

    relief valves or depressuring valves will discharge via plant sub-headers

    with connections into a main header running outside the battery limits. If this is not possible the flare/vent piping should at least be routed through

    areas where there is little possibility of a dangerous situation due to local

    failure of the flare/vent piping (i.e. where possible all piping should be

    welded).

    The flow area through all pipe and fittings downstream a relief valve, shall

    be at least the same as that of the valve outlet. The disposal piping shall

    be self-draining towards the knock-out drum. In general, in order to avoid

    liquid accumulation, all the relief headers shall slope continuously

    towards the vent or flare K.O. drum.

    If possible, connecting sub-headers shall be connected to the top of the

    header; in any case, they shall drain into the headers. The sub-headers

    shall be connected in such a way that there are no welds in the lower one

    third of the circumference of the header.

    As per API 521, the discharge piping system should be designed so that

    the built-up back pressure, caused by the flow through the valve, does

    not reduce the capacity below that required of any pressure-relief valve

    that can be relieving simultaneously. Where conventional pressure relief

    valves are used, the relief manifold system should be sized to limit the

    built-up back pressure to approximately 10% of the set pressure of each

    pressure-relief valve that can be relieving concurrently.

    With pilot-operated valves, higher manifold pressures can be used. The

    capacity of these balanced valves begins to decrease when the back

  • 7/28/2019 10004E00.pdf

    29/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 29 of 93

    pressure exceeds 30% to 50% of the set pressure due to subsonic flow

    and/or physical responses to the high back pressure. Refer to API 520-I

    for the effects of this back pressure.

    1.5.2 Blockage Due to Hydrate Formation in Downstream Piping System

    The blockage of discharge piping downstream of a relief or emergency

    depressuring valve is not a problem under relieving or depressuring

    conditions if the discharge is correctly designed.

    The correct design of the discharge system should include:

    sufficiently large diameter pipework (velocity < 0.7 Mach);

    short length tail pipes;

    the avoidance of restrictions.

    To prevent hydrate or ice formation due to small leaks across the valve or

    low ambient temperatures, heat tracing shall be installed.

    1.6 Isolation Valves in Pressure Relief Piping

    Where possible, the approach should be to use a relief valve

    arrangement which does not utilise any isolation valves. This approach

    eliminates the possibility of a relief valve being isolated in error. However,

    for those relief devices which could have problem of plugging or other

    severe problems which affect their performance, isolation and sparing of

    the relief devices may be provided.

    Block valves may be used to isolate a pressure relief device from the

    equipment it protects or from its downstream disposal system and tofacilitate PSV / BDV inspection and maintenance without shutting down

    the whole system (blowdown system included).

    Since improper use of a block valve may render a pressure relief device

    inoperative, the design, installation, and management of these isolation

    block valves should be carefully evaluated. The ASME Boiler and

    Pressure Vessel Code, Section VIII, Appendix M, discusses proper

    application of these valves and the administrative controls which must be

  • 7/28/2019 10004E00.pdf

    30/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 30 of 93

    in place when isolation block valves are used. Local jurisdictions may

    have other requirements.

    1.6.1 Isolation Valves Requirements

    As per API 520 Part II, all the isolation valves located in relief system

    piping shall meet the following requirements:

    a) Valves shall be full bore.

    b) Valves shall be suitable for the line service classification.

    c) Valves shall have the capability of being locked or car sealed

    open.

    d) When gate valves are used, they should be installed with stems

    oriented horizontally or, if this is not feasible, the stem could be

    oriented downward to a maximum of 45 from the horizontal to

    keep the gate from falling off and blocking the flow.

    An isolation valve can be used either to isolate the individual relief valve

    or to isolate a complete plant section. If isolation valves are used to

    isolate relief valves, there is a basic difference between the need for an

    inlet valve or for an outlet valve. An inlet valve is needed if the process

    cannot be shut down, whereas an outlet valve is needed if the relief

    header cannot be taken out of service. Thus a single relief valve (without

    a spare) connected to a relief header which cannot be shut down will

    have only an outlet isolation valve.

    When isolation valves are installed in pressure relief valve discharge

    piping, a means to prevent pressure build-up between the pressure relief

    valve and the isolation valve should be provided (for example, a bleeder

    valve), see Figure 1.6.1.

  • 7/28/2019 10004E00.pdf

    31/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 31 of 93

    Figure 1.6.1 Typical pressure relief valve installation with an isolation valve.

    A multiple relief valve arrangement with a 100% design relieving capacity

    (including a spare relief valve), as the ones shown in Figure 1.6.2 and

    Figure 1.6.3, will have an inlet isolation valve and outlet isolation valve.

  • 7/28/2019 10004E00.pdf

    32/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 32 of 93

    Figure 1.6.2 Typical pressure relief valve installation with 100% spare relievingcapacity and a three-way valve.

  • 7/28/2019 10004E00.pdf

    33/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 33 of 93

    Figure 1.6.3 Typical pressure relief valve installation with 100% spare relievingcapacity.

    Periodic inspections of isolation valves located in relief piping should be

    made which verify the position of valves and the condition of the locking

    or sealing device.

    1.6.2 Interlocking Systems

    Where block valves are fitted upstream and/or downstream of relief

    valves a system shall be in place to ensure that the required relief

    capacity is always available. One method of achieving this consists in

    installing of an interlocking system which makes it impossible to block off

    the operating S/R valve until other similar relief capacity has been

    connected to the system.

  • 7/28/2019 10004E00.pdf

    34/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 34 of 93

    Two situations, discharge to atmosphere or discharge to a closed system,

    can occur. The following paragraphs describe correct operation to allow a

    safe removal of an S/R valve for maintenance.

    1.6.2.1 Discharge to Atmosphere

    Spared relief valves discharging directly to atmosphere (via individual

    pipes) require block valves only in the inlet pipes of the valves. These

    block valves shall each be provided with a single lock, but with only one

    key in total. During operation the key shall be trapped in the lock of the

    closed block valve of the installed spare S/R valve. The key shall be

    retractable from the lock only by locking open the block valve. Hence only

    one block valve can be in the closed position at any time. The piping

    between the upstream block valve and the relief valve shall be fitted with

    a vent connection in order to allow depressuring before the removal of

    the relief valve.

    Figure 1.6.4 Typical interlocking System for pr essure relief valves w ith atmosphericdischarge.

    1.6.2.2 Discharge to Closed System

    Spared relief valves discharging to a closed system require block valves

    in both the inlet and outlet pipes. The outlet block valves shall be

  • 7/28/2019 10004E00.pdf

    35/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 35 of 93

    provided with single locks, while the inlet block valves shall have double

    locks. As per atmospheric discharge, the piping between the upstream

    block valve and the relief valve shall be fitted with a vent connection in

    order to allow depressuring before the removal of the relief valve.

    Each relief valve shall be provided with a unique key which fits Lock 1 of

    its inlet block valve and the lock of its outlet block valve. The key of the

    outlet block valve shall be retractable only when the outlet block valve is

    locked open. The key of Lock 1 of the inlet block valve shall be

    retractable only when the switch key is inserted in Lock 2 of the same

    inlet block valve.

    Each relief valve shall be provided with a single switch key which fitsLock 2 of all inlet block valves. The switch key shall be retractable only

    when the inlet block valve is locked open. This shall only be possible

    when the key of Lock 1 is inserted in the lock. During operation, only the

    inlet block valve of the installed spare S/R valve will be in the locked

    closed position. All other block valves will be locked open. Locking open

    the outlet block valve of the installed spare S/R valve (or its replacement

    spool piece) prevents pressure build-up in case the inlet block valveshould leak.

    The keys of the locks of the block valves of the relief valves in operation

    will be trapped in Lock 1 of the inlet block valves. The switch key will be

    trapped in Lock 2 of the closed inlet block valve of the spare valve. Since

    the switch key is needed to unlock and close an inlet block valve, only

    one block valve can be in the closed position at any time.

    The key of Lock 1 of the inlet block valve of the spare valve shall bestored in the control room which shall only be accessible to authorized

    personnel.

  • 7/28/2019 10004E00.pdf

    36/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 36 of 93

    Figure 1.6.5 Typical i nterlocking System for pressure relief valves with discharge toa closed system.

    Notice that also outlet valve could be subjected to a key interlock system:

    in this case the key system could avoid to close outlet valve if the inlet

    valve is open (that means that outlet valve could be closed only if the inlet

    valve is closed; i.e. PSV in maintenance and an other PSV in service).

    1.7 Disposal System

    1.7.1 General

    Streams requiring disposal are:

    Relief vapour and/or liquids;

    Depressuring vapours;

    Any operational waste streams that do not have a more suitable

    outlet.

    The selection of a disposal method is subject to many factors that may be

    specific to a particular location or an individual unit. Disposal systems

    generally consist of piping and vessels. All components should be

    suitable in size, pressure rating, and material for the service conditions

    intended.

  • 7/28/2019 10004E00.pdf

    37/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 37 of 93

    In selecting a means of disposal for these streams it is important to find a

    solution in which all streams are handled with the smallest number and

    diversity of systems and individual outlets.

    Wherever possible disposal streams shall be collected in a closed system

    and directed to a flare or vent system.

    1.7.2 Atmospheric discharge

    In many situations, pressure-relief vapour streams may be safely

    discharged directly to the atmosphere if environmental regulations permit

    such discharges.

    Where feasible, this arrangement (atmospheric safe discharge) offers

    significant advantages over alternative methods of disposal because of

    its inherent simplicity, dependability, and economy.

    1.7.3 Disposal by Flaring

    The primary function of a flare is to use combustion to convert flammable,

    toxic, or corrosive vapours to less objectionable compounds. Selection of the type of flare and the special design features required will be

    influenced by several factors, including the availability of space; the

    characteristics of the flare gas, namely, composition, quantity, and

    pressure level; economics, including both the initial investment and

    operating costs; and public relations. Public relations may be a factor if

    the flare can be seen or heard from residential areas or navigable

    waterways.

    1.7.4 Flaring Versus Venting

    Considerations to be made in deciding whether to vent or flare the

    disposal streams are:

    Impact on the environment;

  • 7/28/2019 10004E00.pdf

    38/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 38 of 93

    Safety and integrity of the disposal system, taking into account

    that disposal streams could contain products which are not

    combustible;

    Local regulations;

    Economic evaluations.

    Considerations indicating whether venting is allowed are:

    If the vapours temperature is below the auto-ignition temperature

    and if they are lighter than air. Gases shall be considered to be

    lighter than air if the actual density of the gas after release, taking

    into account the cooling associated with expansion, is less than

    0.9 times the density of the air in the area at 15 C.

    If the vapours are heavier than air because of low temperature

    but are in locations where the installation of a flare is

    impracticable (e.g. product storage areas, marketing depots) or

    where potential ignition sources are remote. In these cases the

    vapours discharge velocity shall be at least 152 m/s. However,

    discharge velocity shall not exceed the 80% of the sonic velocity.

    If concentrations of toxic and/or corrosive components in thedispersed vapour cloud do not reach harmful or irritating levels on

    nearby work levels (platforms) and outside property limits. In

    order to evaluate environmental impact, calculations of effluent

    emissions are required.

    If the risks and consequences of accidental plume ignition (e.g.

    generation of shock waves) are acceptable.

    In addition to the above, streams which are not foreign to the atmospheremay be vented without environmental reservations. However, safety near

    the point of discharge shall be considered, i.e. factors such as

    temperature, noise, local concentrations of carbon dioxide and nitrogen,

    etc.

  • 7/28/2019 10004E00.pdf

    39/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 39 of 93

    1.7.5 Flare and Vent Structure

    The type and height of the structures supporting flare or vent stacks

    depend on the following operational and environmental aspects:

    Required availability of the flare and relief system;

    Acceptable heat radiation levels;

    Acceptable dispersion levels;

    Acceptable noise levels;

    Wind velocity.

    There are three common stack support methods as shown in Figure

    1.7.1.

    The type selection is based on economical and operational grounds. A

    brief structure description is given in the following.

    Figure 1.7.1 Flare structures.

    1.7.5.1 Self-supported

    Self-supported stacks are normally the most desirable. However, they are

    also the most expensive because of greater material requirements

    needed to ensure structural integrity. They are normally limited

  • 7/28/2019 10004E00.pdf

    40/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 40 of 93

    (economically versus alternatives) to a stack height of 200 to 300 feet

    (60-90 m).

    1.7.5.2 Guy-wire supported

    These are the least expensive but require the largest land area due to the

    guy-wire radius requirements. Typical guy-wire radius is equal to one-half

    the overall stack height.

    1.7.5.3 Derrick supported

    Used only on larger stacks where self-supported is not practical, or available land area excludes a guy-wire design.

    1.8 Flare System Design

    Disposal of combustible gases, vapours, and liquids by burning is

    generally accomplished in flares. Flares are used for environmental

    control of continuous flows of excess gases and for large surges of gases

    in an emergency.

    The flare is usually required to be smokeless for the gas flows that are

    expected to occur from normal day-to-day operations. This is usually a

    fraction of the maximum gas flow, but some environmentally sensitive

    areas require 100% smokeless or even a fully enclosed flare.

    Various techniques are available for producing smokeless operation,

    most of which are based on the premise that smoke is the result of a fuel-

    rich condition and is eliminated by promoting uniform air distribution

    throughout the flames.

    To promote air distribution throughout the flames, energy is required to

    create turbulence and mixing of the combustion air within the flare gas as

    it is being ignited. This energy may be present in the gases, in the form of

    pressure, or it may be exerted on the system through another medium

    such as injecting high-pressure steam, compressed air, or low-pressure

    blower air into the gases as they exit the flare tip.

  • 7/28/2019 10004E00.pdf

    41/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 41 of 93

    1.8.1 Flare Type

    1.8.1.1 Exothermic Flares

    The following descriptions are for flare equipment to dispose of exothermic

    flare gases; that is, gases that have a high enough heating value (usually

    greater than 200 Btu/Scf (7370 kJ/Sm) for unassisted flares and 300

    Btu/Scf (11050 kJ/Sm) for assisted flares) to sustain combustion on their

    own without any auxiliary fuel additions.

    Utility / Pipe Flare: This is the simplest flare tip; this plain design has no

    special features to prevent smoke formation, and consequently should

    not be used in applications where smokeless operation is required unless

    the gases being flared are not prone to smoking.

    Flare tips of this style, as a minimum, should include a flame retention

    device (to increase flame stability at high flowrates) and one or more

    pilots (depending upon the diameter of the tip).

    Smokeless Flare:

    Steam Injection : Flare tips which use steam to control smoking are the

    most common form of smokeless flare tip. The steam can be injected

    through a single pipe nozzle located in the centre of the flare, through

    a series of steam/air injectors, through a manifold located around the

    periphery of the flare tip, or a combination of all three. The steam is

    injected into the flame zone to create turbulence and/or aspirate air

    into the flame zone via the steam jets. The amount of steam required

    (see API 521, 5 th Edition, Table 11) is primarily a function of the gas

    composition, flowrate, and steam pressure and flare tip design.

    Although steam is normally provided from a 100 to 150 psi (690-1034

    kPa) supply header, special designs are available for utilizing steam

    pressure in the range of 30 psi (2.07 kPa). The major impact of lower

    steam pressure is a reduction in steam efficiency during smokeless

    turndown conditions.

  • 7/28/2019 10004E00.pdf

    42/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 42 of 93

    HP Air Injection: HP air injection can also be used to prevent smoke

    formation. This approach is less common because compressed air is

    usually more expensive than steam. However, in some situations, it

    may seem preferable, for example, in arctic or low-temperature

    applications where steam could freeze and plug the flare tip/stack.

    Also, other applications include desert or island installations where

    there is a shortage of water for steam, or where the waste flare gas

    stream would react with water. The same injection methods described

    for steam are used with compressed air. The air is usually provided at

    100 psi (690 kPa) and the mass quantity required is approximately200% greater than required by steam since the compressed air does

    not produce the water-gas shift reaction that occurs with steam.

    HP Water Injection: High-pressure water is also used to control

    smoking, especially for horizontal flare applications and when large

    quantities of waste water or brine are to be eliminated. One pound of

    water (at 345 to 690 kPa) is usually required for each pound of gasflared.

    LP Forced Air: A low-pressure forced air system is usually the first

    alternative evaluated if insufficient on-site utilities are available to aid in

    producing smokeless operation. The system creates turbulence in the

    flame zone by injecting low-pressure air supplied from a blower across

    the flare tip as the gases are being ignited, thus promoting even air distribution throughout the flames. Usually air at 0.5 to 5 kPa pressure

    flows coaxially with the flare gas to the flare tip where the two are

    mixed. This system has a higher initial cost due to the requirement for

    a dual stack and an air blower. However, this system has much lower

    operating costs than a steam-assisted design (requiring only power for

    a blower). The additional quantity of air supplied by the blower for

    smokeless operation is normally 10% to 30% of the stoichiometric air

  • 7/28/2019 10004E00.pdf

    43/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 43 of 93

    required for saturated hydrocarbons and 30% to 40% of the

    stoichiometric air required for unsaturated hydrocarbons.

    HP Flare: A high-pressure system does not require any utilities such

    as steam or air to promote smokeless flaring. Instead, these systems

    utilize pressure energy available within the flare gas itself (typically 35

    to 140 kPa minimum at the flare tip) to eliminate fuel rich conditions

    and resulting smoke within the flames. By injecting the flare gas into

    the atmosphere at a high pressure, turbulence is created in the flame

    zone, which promotes even air distribution throughout the flames.

    Since no external utilities are required, these systems are normallyadvantageous for disposing of very large gas releases, both from the

    economics of smokeless operation and the control of flame shape.

    Maintaining sufficient tip pressure during turndown conditions is critical

    and often requires that a staging system be employed to

    proportionately control the number of flare tips in service with

    relationship to the gas flowing.

    1.8.1.2 Endothermic Flares

    Endothermic gases may be disposed of in thermal incineration systems;

    however, there are situations where the preferred approach is to use a

    special flare design. These flares utilize auxiliary fuel gas to burn the flare

    gases. With small gas flow rates, simple enrichment of the flare gases by

    adding fuel gas in the flare header to raise the net heating value of the

    mixture may be sufficient.

    In other situations, such as gases with high CO 2 content and small

    amounts of H 2S, it may be necessary to add a fuel gas injection manifold

    around the flare tip (similar to a steam manifold) and build a fire around

    the exit end of the flare tip that the gases must flow through.

  • 7/28/2019 10004E00.pdf

    44/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 44 of 93

    1.8.1.3 Enclosed Ground Flares

    In general, any of the flare tips or systems discussed above may be

    mounted atop an elevated stack or mounted at grade. In general, ground

    flares are primarily designed for low release rates and are not effective

    for emergency releases.

    With increasingly strict requirements regarding flame visibility, emissions,

    and noise, enclosed ground flares (see Figure 1.8.1) can offer the

    advantages of hiding flames, monitoring emissions, and lowering noise.

    However, the initial cost often makes them undesirable for large releases

    when compared to elevated systems.

    A significant disadvantage with a ground flare is the potential

    accumulation of a vapour cloud in the event of a flare malfunction; special

    safety dispersion systems are usually included in the ground flare

    system. For this reason, instrumentation for monitoring and controlling

    ground flares is typically more stringent than with an elevated system.

    These flares are typically the most expensive because of the size of the

    shell or fence and the additional instrumentation which may be required

    to monitor these key parameters. Another significant limitation is that

    enclosed ground flares have significantly less capacity than elevated

    flares.

    Figure 1.8.1 Enclosed ground flare.

  • 7/28/2019 10004E00.pdf

    45/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 45 of 93

    1.8.2 Flare Sizing

    1.8.2.1 Evaluation of Flare Diameter

    Flare stack diameter is generally sized on a velocity basis, althoughpressure drop should be checked.

    Generally, for design proposal, a velocity of 0.5 Mach for a peak, short-

    term, infrequent flow, with 0.2 Mach maintained for the more normal and

    possibly more frequent conditions for low-pressure flares, is chosen.

    However, sonic velocity operation may be appropriate for high-pressure

    flares. Moreover, experience has shown that a properly designed and

    applied flare burner can have an exit velocity of more than Mach 0,5, if pressure drop, noise and other factors permit. Many pipe flares, assisted,

    unassisted or air-assisted flares have been in service for many years with

    Mach numbers ranging from Mach 0,8 and higher.

    The Mach number is determined as follows:

    MWk

    Tz

    dP

    WMach

    f atm

    =

    251023.3 (6)

    Where:

    W Flow [kg/h]

    Z Compressibility factor at flowing condition

    T Temperature at vapour outlet [K]

    df Flare diameter [m]

    k Specific heat ratio, C p/C v

    1.8.2.2 Evaluation of Flare Height

    The flare stack height is generally based on the radiant heat intensity

    generated by the flame. For flare radiation study, reference shall be made

    to paragraph 1.11.

  • 7/28/2019 10004E00.pdf

    46/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 46 of 93

    1.8.3 Segregated flare systems

    Depending on various factors such as plot plan, equipment design

    pressures, etc., it may prove desirable to provide two or more flare

    systems, such as separation of high pressure and low pressure headers.

    Multiple flare system arrangements may offer significant advantages or

    prove mandatory on analysis of the streams that require disposal.

    Segregated flare systems may be required in order to:

    Segregate sources of release into high and low pressure

    systems. This may be required to enable a high pressure low

    radiation tip to be used with a consequent saving on flare

    structural requirements. This may also mean that only the low

    pressure gas requires assistance in order to burn cleanly. As a

    general rule, all pressure relief devices with an operating

    pressure lower than 10 barg are collected and disposed in an LP

    flare system.

    Segregate sources with widely differing potentials for liquid

    release.

    Segregate sources of cold, dry gas from significant quantities of

    warm, moist gas and thereby avoid the possibility of freezing and

    hydrate formation. A relief header after passing a cold stream will

    be cold. If a warm, moist gas then passes, hydrates could be

    formed and block the relief header.

    Segregate corrosive or potentially corrosive fluids (e.g. CO 2 and

    H2S) from non-corrosive or moist fluids.

    The selected design should use the minimum practicable number of

    separate systems but remain operable and safe under all foreseeable

    conditions. The systems installed may be totally independent, or may

    share common facilities such as flare knock-out drums and flare tips in

    certain circumstances.

    When considering the requirement for a high and low pressure disposal

    system it is necessary to consider the relief valve set pressures present in

    the system. If there are a large number of high pressure sources withlarge gas volumes and a relatively few low pressure sources, then

  • 7/28/2019 10004E00.pdf

    47/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 47 of 93

    generally it would be more economical to install one high pressure relief

    header and one low pressure relief header. An economical analysis is

    usually required to ascertain the optimum number of flare systems, and to

    which system each relief device should discharge.

    1.8.4 Flare Disposal of Hydrogen Sulphide

    Streams which are rich in hydrogen sulphide shall not be discharged into

    a common HC flare or vent system unless it has been designed for this

    purpose. This prevents the spreading of sour gas throughout the entire

    main flare system and also avoids corrosion attack by hydrogen sulphide

    and the subsequent accumulation of deposits of (pyrophoric) ferrous

    sulphide.

    These streams shall have a separate line-up, preferably a separate flare

    stack equipped with a tip of the air pre-mix type. Alternatively, the gas

    may be lined up to the bottom (downstream of the water seal) of the

    hydrocarbon flare stack, but this should only be done if the hydrogen

    sulphide rich flow constitutes a minor additional load.

    The installation of a separate sour gas flare relief system implies

    additional capital expenditure. From this point of view it is always better to

    exclude such a system.

    For a preliminary evaluation, the following factors should be considered

    before deciding that a separate H 2S flare relief system need to be

    installed or not. Sour gas release can be tied into the HC flare system in

    case of:

    1) continuous HC release with an H 2S content < 2% by volume;

    2) intermittent HC release (only during startup and shutdown) with

    an H 2S content < 20% by volume, provided this stream is less

    than 10% by volume of the total continuous HC release rate;

    3) emergency HC release (e.g. PSV, emergency depressuring) with

    an H 2S content < 50% by volume.

    When hydrogen sulphide rich gas has to be flared, incomplete

    combustion can cause a hydrogen sulphide smell resulting in complaints

  • 7/28/2019 10004E00.pdf

    48/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 48 of 93

    by people in the vicinity. Moreover, the presence of un-combusted

    hydrogen sulphide shall be dangerous for human being in the proximity of

    the plant.

    At a low exit velocity back burning will occur, causing sulphide stress

    corrosion, especially below the refractory. This means that when H 2S rich

    gas has to be released into the HC flare system more purge gas has to

    be injected as well on account of the larger size of the flare, which could

    offset the saving on capital expenditure.

    If a hydrogen sulphide flare relief system is used, this shall be heat-traced

    up to 4 m below the top of the stack. Header materials shall be carbon

    steel, except for the top 4 metres of the hydrogen sulphide stack, whichshall be of AISI 310 S or equivalent.

    Since no water seal vessel has to be installed, the design pressure of the

    knock-out drum shall be 7 barg. To prevent flashback and consequential

    detonation purge gas shall be used.

    1.9 Other Flaring Equipment

    1.9.1 K.O. Drum

    Gas streams from relief headers are frequently at or near their dewpoint,

    where condensation may occur.

    A knockout drum is usually provided near the flare/vent base, and serves

    to recover liquid hydrocarbons, prevent liquid slugs, and remove liquid

    particles. The knockout drum reduces hazards caused by burning liquid

    that could escape from the flare stack. As mentioned above, all lines downstream a relief/blowdown device

    should be sloped toward the knockout drum to permit condensed liquid to

    drain into the drum for removal. The locating of the flare/vent knockout

    drum also needs to take into account radiation effect from the burning

    flare/accidental ignition of the vent.

    The economics of drum design may influence the choice between a

    horizontal and a vertical drum. When a large liquid storage capacity isdesired and the vapour flow is high, a horizontal drum is often more

  • 7/28/2019 10004E00.pdf

    49/93

    Eni S.p.A. Exploration & Production Division

    10004.HTP.PRC.PRGRev. 0 January 2008

    Sh. 49 of 93

    economical. Also, the pressure drop across horizontal drums is generally

    the lowest of all the designs. Vertical knock out drums are typically used

    where the liquid load is low or limited plot space is available. They are

    well suited for incorporating into the base of the stack.

    1.9.1.1 K.O. Drum Pump and Instrumentation

    As just mentioned, knockout drums may be of the horizontal or vertical

    type; and they should be provided with a pump or draining facilities and

    instrumentation to remove the accumulated liquids to a tank, sewer, or

    other location. The actual type of disposal used will depend on the

    characteristics and hazards associated with the liquids removed.

    In the simplest system, the vessel may have only a manually operated

    drain valve and a liquid-level sight glass for reference. Moreover, a liquid-

    removal pump is frequently used on knock-out drums.

    More elaborate arrangements may foresee high-