10589 asset management the key to weathering the facility ... · installing air curtain door system...
TRANSCRIPT
![Page 1: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/1.jpg)
APWA 2016 PWX 8/29/2016
1
ASSET MANAGEMENTThe Guide to Weathering the
Facility and Energy Management Storm?Perspectives of 3 Local MN Governments
![Page 2: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/2.jpg)
APWA 2016 PWX 8/29/2016
2
MONEY
![Page 3: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/3.jpg)
APWA 2016 PWX 8/29/2016
3
POLITICS
ENERGY
![Page 4: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/4.jpg)
APWA 2016 PWX 8/29/2016
4
REPORTS
AGINGBUILDINGS
![Page 5: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/5.jpg)
APWA 2016 PWX 8/29/2016
5
AFLOAT?
Asset Management
for All
CapitalPlanning
+ Outcomes
ProcessCapital + Energy
Erik Birkeland
City of Duluth, MN
Tony Mancuso
St. Louis County, MN
Deb Williams
City of Bloomington, MN
![Page 6: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/6.jpg)
APWA 2016 PWX 8/29/2016
6
Laura MalwitzCR‐Building Performance Specialistslmalwitz@cr‐bps.comFind us on LinkedIn
Nancy SchultzCR‐Building Performance Specialists
nschultz@cr‐bps.comFind us on LinkedIn
LOTS TO MANAGE
![Page 7: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/7.jpg)
APWA 2016 PWX 8/29/2016
7
DATA COLLECTION
![Page 8: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/8.jpg)
APWA 2016 PWX 8/29/2016
8
SYSTEMS APPROACH
DOCUMENTATION
![Page 9: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/9.jpg)
APWA 2016 PWX 8/29/2016
9
DOCUMENTATION
DOCUMENTATION
![Page 10: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/10.jpg)
APWA 2016 PWX 8/29/2016
10
UTILITIES – VITAL SIGNS
ASSET & ENERGY MANAGEMENT TOOL
![Page 11: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/11.jpg)
APWA 2016 PWX 8/29/2016
11
![Page 12: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/12.jpg)
APWA 2016 PWX 8/29/2016
12
METRICSBASELINE
Current Replacement Value CRV
CONDITION
Facility Condition Index FCIRequirement Index RI
Energy
Energy Use Intensity EUI
ESTABLISH METRICS
![Page 13: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/13.jpg)
APWA 2016 PWX 8/29/2016
13
![Page 14: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/14.jpg)
APWA 2016 PWX 8/29/2016
14
AVOID DEFERRED MAINTENANCE
CurrentReplacement
Value (Millions $)ON
BORROWED TIME
FAIR
GOOD
POOR
MULTI‐BLDG PORTFOLIO
FCIRI
FCI & RIBENCHMARK
.64 .63 .60 .60 .56
.38.28 .25 .22 .22 .20
.14.14 .12 .09
.08 .08 .05 .031.15 1.15 .62 .60 .96 .38 .29 .31 .25 .33 .32 .20 .14 .12 .15 .13 .14 .06 .03
0
10
20
30
40
50
60
0
0.2
0.4
0.6
0.8
1
1.2
1.4
![Page 15: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/15.jpg)
APWA 2016 PWX 8/29/2016
15
137.30 142.60 146.20
0
50
100
150
200
250
2013
2014
2015
9,500
10,000
10,500
11,000
11,500
12,000
EUIkBTU/sf/yr
HeatingDegree Days
Higher Energy Use/ SF
Lower Energy Use/ SF
EUI TRENDING
MUNICIPAL SERVICES BUILDING 5 YR FUNDING NEEDS(includes inflation)
$3,947,039
$98,955 $26,685 $111,185
$1,776,947
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
2017
2018
2019
2020
2021
$5,960,811
$ TO FIX
(millions)
![Page 16: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/16.jpg)
APWA 2016 PWX 8/29/2016
16
MUNICIPAL SERVICES BUILDING June 28, 2017DEFICIENCIES IN FCI
Improvement Year 2017Total: $3,947,039
(includes inflation)
$286,958
$194,942
$40,028
$40,028
$2,125,240
$1,115,775
$144,068
$0
$500,000
$1,000,000
$1,500,000
$2,000,000
$2,500,000
Exhaust System ‐ Garage ‐ 1975 Renewal
Fire Alarm and Security: No Systems
Gas MAU #1 ‐ Parts ‐ 1975 Renewal
Gas MAU #2 ‐ Vehicle Storage ‐ 1975 Renewal
Superstructure: Roof and Bulk Water Repair
Superstructure: Structural Damage and OverhangReplacement
~Public Works Equipment ‐ In Floor Lift ‐ 1990Renewal
2017
MUNICIPAL SERVICES BUILDING UTILITY USAGE2013
Electricity, 2,183,307
Natural Gas, 4,539,700
Electricity, $51,029
Natural Gas, $31,438
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
$0
$1,000
$2,000
$3,000
$4,000
$5,000
$6,000
$7,000
$8,000
$9,000
$10,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Total kBTU’s – Energy Consumption = 6,723,007 Total Cost = $82,467
![Page 17: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/17.jpg)
APWA 2016 PWX 8/29/2016
17
CITY OF DULUTH, MNErik Birkeland• 150 BLDGS• 405,000 SF
City of Duluth Initiatives
• Implement asset management system for all City facilities
• Develop a method to benchmark, track and integrate energy data with our asset management data
• Create a project management system
• Develop the groundwork with administration and council to use the asset management approach to inform and justify capital expenditures, the development of a strategic facility plan, and flexible GO bond funding to meet emerging facility needs with CIP funding
• Develop a path forward that can be followed by subsequent City leaders
![Page 18: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/18.jpg)
APWA 2016 PWX 8/29/2016
18
Asset Management Telling the story with data – giving the decision‐makers the information they need to understand the short and long term impacts of their decisions while building consensus around the efficacy of the asset management system and approach.
2016 Capital Facility Improvements
Total Number of CIP Buildings 27 of 148 buildings
Total Square Feet CIP Buildings 404,955
Investment by Square Foot $3.09 (23% decrease from 2015)
Buildings City‐Wide $580,000
Maintenance Buildings $525,000
Fire/Police $145,000
TOTAL CAPITAL IMPROVEMENT BONDS FOR ELIGIBLE CIP FACILITIES
$1,250,000
36
CIP Book pg. 7
![Page 19: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/19.jpg)
APWA 2016 PWX 8/29/2016
19
2013‐2016 CIP Funding Levels & Facility Capital Needs
37
CIP Book pg. 7
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2013 2014 2015 2016
Total Requirements
CIP Investment
2013‐2016 CIP Funding Levels
38
CIP Book pg. 7
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
1,800,000
2,000,000
CIP Funding
2013
2014
2015
2016
$
![Page 20: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/20.jpg)
APWA 2016 PWX 8/29/2016
20
2015 Project Detail – Capital Improvement Bond
Priority Facility CIP Project Project Rationale 2016 CIP
Critical City WideVFA Requirements – ADA, Security, Mechanical,
Electrical, Envelope, Energy, Project Contingencies, etc.
End of Life Cycle, Function, Code, Asset Integrity, Life Safety, Accessibility, Energy
$430,000
Critical Facilities Bldg. Tuck‐Pointing – Severe Asset Deterioration Asset Integrity $75,000
Critical Fleet Ventilation Life Safety $200,000
Recommended Tree Farm Vehicle Storage Garage Operations $250,000
NecessaryDTA Multi‐Modal
New Police Sub‐Station Function $75,000
Necessary Fire Hall #8 Interior Flooring/Kitchen UpgradesEnd of Life
Cycle/Function/Operations
$75,000
Necessary Main Library Front Desk Reconfiguration Operations/Function $25,000
NecessaryMt. Royal Branch
New Carpet/Exterior Signage Operations/Function $125,000
TOTAL $1,250,000
39CIP Book pg. 8-10
Energy EfficiencyIntegrating energy conservation into all of our capital plans and making it happen in each project.
![Page 21: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/21.jpg)
APWA 2016 PWX 8/29/2016
21
Project Name
Type of ECO(Energy
Conservation Opportunity) Description
Cost Saved Annually
kWh Saved Annually
kW Saved
Therms Saved
Estimated Total Project
Cost Simple Payback
IncrementalPayback
Medical District Ramp ECO & LED Lighting Conversion Project
Lighting New LED lighting in ramp $17,547 58,050 NA $112,875 6.43 6.43
Tech Center Ramp ECO & LED Lighting Conversion Project Lighting New LED lighting in ramp $22,431 95,625 NA $109,375 4.88 0.04
Lake Walk LED Lighting Conversion Project LightingReplace exisitng light fixtures with new LED
fixtures on Lakewalk$17,399 18,450 NA $35,000 2.01 0.03
Lake Walk LED Lighting Conversion Project LightingReplace exisitng light fixtures with new LED
fixtures in Lake Place Plaza Park$6,141 8,775 NA $17,550 2.86 0.11
Lief Erickson LED Lighting Conversion Project LightingReplace exisitng light fixtures with new LED
fixtures + Poles in Lief Erickson Park$6,112 8,550 NA $35,192 5.76 (0.30)
Rose Garden LED Lighting Conversion Project LightingReplace exisitng light fixtures with new LED
fixtures in Rose Garden Park$6,144 8,798 NA $14,400 2.34 0.09
Channel Walk LED Lighting Conversion Project LightingReplace exisitng light fixtures with new LED fixtures on both sides of the Channel at Aerial
Bridge$5,303 2,330 NA $14,000 2.64 0.03
Corner of the Lake/Carriage Walk/Sister Cities Garden LED Lighting Conversion Project
LightingReplace exisitng light fixtures with new LED fixtures in Corner of the Lake Park/Sister
Cities/Carriage Walk$7,165 16,650 NA $33,300 4.65 0.18
Bayfront LED light Conversion LightingReplace existing light fixtures with new LED
fixturesNA $88,000 8.03 8.03
Demand Control System Demand CostInstall Peak Demand Controllers on 4‐5 high
Demand Charge Bldgs$8,000 NA $25,000
Fire Station #4 Air Curtain at Overhead Doors InnovationInstalling air curtain door system at (4) overhead
doors (12 x 14) (PoweredAire.com)$6,000 6,000 $32,000 5.33 5.3
Totals $102K 217K $517K 5.05 2.54
Strategies and Results• Mayor awarded $500,000 to invest in outdoor LED lighting conversions
• 100% of energy savings achieved ‐> energy efficiency upgrades for 5 years
• Created administrative buy‐in
• Continuously perfecting energy tracking
• Align energy use and meters with buildings
• Align work order system and maintenance strategy with our long‐term
capital program
![Page 22: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/22.jpg)
APWA 2016 PWX 8/29/2016
22
ST. LOUIS COUNTY, MNTony Mancuso
![Page 23: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/23.jpg)
APWA 2016 PWX 8/29/2016
23
![Page 24: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/24.jpg)
APWA 2016 PWX 8/29/2016
24
![Page 25: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/25.jpg)
APWA 2016 PWX 8/29/2016
25
![Page 26: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/26.jpg)
APWA 2016 PWX 8/29/2016
26
CITY OF BLOOMINGTON, MNDeb Williams• 65 BLDGS• 835,000 SF
![Page 27: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/27.jpg)
APWA 2016 PWX 8/29/2016
27
0.000.040.060.070.080.09
0.110.16
0.180.190.190.21
0.290.31
0.510.510.52
0.550.550.560.570.570.580.600.61
0.720.77
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90
W e s t e r n M a i n t e n a n c e ‐ P i s t o l R a n g e
S a l t B u i l d i n g
P u b l i c W o r k s I I N o r t h
D w a n G o l f C o u r s e ‐ M a i n t e n a n c e
O l d T o w n H a l l
W e s t e r n M a i n t e n a n c e ‐ E a s t
W a t e r T r e a t m e n t P l a n t
C i v i c P l a z a
H y l a n d G o l f C o u r s e ‐ M a i n t e n a n c e
P u b l i c W o r k s
C e m e t e r y ‐ N o r t h
B l o o m i n g t o n I c e G a r d e n
C e m e t e r y ‐ S o u t h
F i r e S t a t i o n # 1
C e n t r a l M a i n t e n a n c e ‐ S o u t h
F i r e S t a t i o n # 2
W e s t e r n M a i n t e n a n c e ‐ W e s t
R o b i n s o n B u i l d i n g
H e a l t h B u i l d i n g
F i r e S t a t i o n # 5
F i r e S t a t i o n # 6
D w a n G o l f C o u r s e ‐ C l u b H o u s e
C e n t r a l M a i n t e n a n c e ‐ N o r t h
C r e e k s i d e C o m m u n i t y C e n t e r
H y l a n d G o l f C o u r s e ‐ C l u b H o u s e
F i r e S t a t i o n # 3
F i r e S t a t i o n # 4
FCI ‐ ALL BUILDINGS MAIN, FIRE STATIONS, REC, WATER TREATMENT (NO PARKS)
FCI
GOOD FAIR POOR UNSATISFACTORY
CURRENT REALITY // Bloomington City‐Wide Level
54
FUND ING NEEDS BY YEAR‐A L L BU I L D I NG S ‐
MA IN , F I R E S TAT I ON S , R EC , WAT E R T R EATMEN T, PA R K S
$61,524,608
CURRENT REALITY // Bloomington City‐Wide Level
$4.0m$5.0m
$7.0m
$2.6m$3.9m
$8.2m
$5.5m
$18.3m
$1.3m
$5.6m
0
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
16,000,000
18,000,000
20,000,000
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
COST USD
![Page 28: 10589 Asset Management The Key to Weathering the Facility ... · Installing air curtain door system at (4) overhead doors (12 x 14) (PoweredAire.com) $6,000 6,000 $32,000 5.33 5.3](https://reader034.vdocuments.net/reader034/viewer/2022052014/602beadc6e9a84653803ae69/html5/thumbnails/28.jpg)
APWA 2016 PWX 8/29/2016
28
$1.2m
$149k
$862k
$385k
$137k$167k
$1.5m
$45k
$505k
$147k
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
2016 2017 2018 2019 2020 2021 2023 2024 2025 2026
COST USD
F I R E STAT IONSFUND ING NEEDS BY YEAR
10 YEAR OVERV I EW
CURRENT REALITY // Fire Stations
Cheers! To Surviving the Storm
Laura MalwitzBusiness Director
CR‐Building Performance Specialistslmalwitz@cr‐bps.com
Find us on LinkedIn