11.1 POWER DEVELOPMENT The Power sector is faced with a number of challenges and problems. In order to overcome the poor financial stability, to off-set power shortage in the State, particularly during peak hours and to eliminate poor reliability and to maintain quality of power, the Government of Tamil Nadu took series of policy measures and implemented effective power sector reform in the State. The power sector reforms/strategies were formulated under the guidance/ policy framework put forwarded by the Ministry Power, Government of India which aimed at the following well defined objectives, namely - (i) sustained power supply to economic growth and development in the State, (ii) production of power at optimum cost, (iii) to supply reliable / quality power supply, (iv) appropriate financial stability to Tamil Nadu Electricity Board and (v) to find out suitable partnership for installation of new Independent Power Projects (I.P.Ps.) in the State. During Ninth Plan period, the State Government had mainly attributed to the following twin objectives, viz., - (1) Electricity must be supplied under the most efficient condition in the State in terms of quality/ cost in order to support economic development and (2) the power sector should be self-supporting and there should be a net generation of financial resources for the State. To achieve the above objectives, efforts were made to increase the Plant Load Factor (P.L.F.) of Thermal Stations in the State with the object of raising the Revenue component of the State Government and thereby increase the financial status of the Tamil Nadu Electricity Board (TNEB). High priority was given for Renovation and Modernisation of power plants. Measures were also taken to reduce T & D losses by providing adequate outlay/support to power sector / TNEB apart from Research and Development techniques in the State. The financial achievement registered at the end of the Ninth Plan period was 75.82 per cent. Tenth Plan Period - Approach and Strategies for Power Development Since Tamil Nadu State had exhausted most of its viable Hydel Power potential for power development at the beginning of the Sixth Plan itself, the State had left with no option but to go in for large scale Thermal/ Nuclear Power in order to meet/cope up with the demand/supply of power required during the subsequent Plan Periods. The share from Central Sector Projects like,- Madras Atomioc Power Station(MAPS), Kaiga Atomic Power Station(KAPS), Super Power Thermal Station (SPTS) at Ramagundam etc., have played a supportive/vital role besides I.P.Ps and Non-conventional sources of Energy in the State. Based upon the past experience and setbacks that was experienced, the approach and strategies for the Tenth Plan was formulated. The main objectives of the Power Development Sector during Tenth Plan are as furnished below: To bring Energy Security in the State by completing all the ongoing projects and the schemes, which could not be commissioned during previous, plan periods. To achieve 100 per cent electrification of households both in urban and rural areas. To select suitable circles to implement the improvement of sub- transmission schemes under Accelerated Power and Reforms Development Programme.

Upload: buitram

Post on 04-May-2018

220 views

Category:

Documents


1 download

TRANSCRIPT

11.1 POWER DEVELOPMENT

The Power sector is faced with a number of challenges and problems. In order to overcome the poor financial stability, to off-set power shortage in the State, particularly during peak hours and to eliminate poor reliability and to maintain quality of power, the Government of Tamil Nadu took series of policy measures and implemented effective power sector reform in the State. The power sector reforms/strategies were formulated under the guidance/ policy framework put forwarded by the Ministry Power, Government of India which aimed at the following well defined objectives, namely - (i) sustained power supply to economic growth and development in the State, (ii) production of power at optimum cost, (iii) to supply reliable / quality power supply, (iv) appropriate financial stability to Tamil Nadu Electricity Board and (v) to find out suitable partnership for installation of new Independent Power Projects (I.P.Ps.) in the State. During Ninth Plan period, the State Government had mainly attributed to the following twin objectives, viz., - (1) Electricity must be supplied under the most efficient condition in the State in terms of quality/ cost in order to support economic development and (2) the power sector should be self-supporting and there should be a net generation of financial resources for the State. To achieve the above objectives, efforts were made to increase the Plant Load Factor (P.L.F.) of Thermal Stations in the State with the object of raising the Revenue component of the State Government and thereby increase the financial status of the Tamil Nadu Electricity Board (TNEB). High priority was given for Renovation and Modernisation of power plants. Measures were also taken to reduce T & D losses by providing adequate outlay/support to power sector / TNEB apart from Research and Development techniques in the State. The financial achievement registered at the end of the Ninth Plan period was 75.82 per cent.

Tenth Plan Period - Approach and Strategies for Power Development

Since Tamil Nadu State had exhausted most of its viable Hydel Power potential for power development at the beginning of the Sixth Plan itself, the State had left with no option but to go in for large scale Thermal/ Nuclear Power in order to meet/cope up with the demand/supply of power required during the subsequent Plan Periods. The share from Central Sector Projects like,- Madras Atomioc Power Station(MAPS), Kaiga Atomic Power Station(KAPS), Super Power Thermal Station (SPTS) at Ramagundam etc., have played a supportive/vital role besides I.P.Ps and Non-conventional sources of Energy in the State. Based upon the past experience and setbacks that was experienced, the approach and strategies for the Tenth Plan was formulated.

The main objectives of the Power Development Sector during Tenth Plan

are as furnished below:

• To bring Energy Security in the State by completing all the ongoing projects and the schemes, which could not be commissioned during previous, plan periods.

• To achieve 100 per cent electrification of households both in urban and rural areas.

• To select suitable circles to implement the improvement of sub-transmission schemes under Accelerated Power and Reforms Development Programme.

11.1 Power Development

428

• To formulate long-range master plan to bring down the line losses from the present level of 16.5 per cent to 12 per cent.

• To create necessary policy and regulatory measures through TNERC.

• To focus/ concentrate on Energy Accounting and Auditing/ Demand Side Management and

• To increase the Plant Load Factor of Thermal Power and Hydel Power Stations in the State by undertaking Renovation and Modernisation Programmes and through R & D projects.

A Memorandum of Understanding (MoU) was signed on 9th January 2002 with

the Ministry of Power (MoP), Government of India by the Government of Tamil Nadu in order to bring Energy Security in the State. Following the agreement, a series of policy measures have been taken up to improve the functioning /financial condition of the TNEB apart from implementing the reform measures in the State pointed out by the Ministry of Power, Government of India. In recognition of Tamil Nadu being a Reforming State, the Power Finance Corporation (PFC), Rural Electrification Corporation (REC) etc., have been extending financial assistance/investment needs to TNEB in relaxation to normal conditionalities relating to the following factors viz.,- exposure limit, Rate of Returns (ROR), DSCR on development, reduce T & D losses, control of theft, 100 percent metering, restructuring of tariff rates etc. As per the guideline of Ministry of Power, Government of India, the private entrepreneurs are also permitted to install Independent Power Projects (I.P.Ps.) in the State in order to create/generate additional capacity to meet the ever-growing demand in the State in the following categories viz.,-Industry, Agriculture, Commercial, Domestic, Rural Electrification etc.

Performance of the Power sector during the first three years of the Tenth

Plan Period - (2002-03 - 2003-04) are shown in the tables below: Annual

Plan Period

Installed Capacity at the disposal of the State

(MW)

Peak demand(Sustained)

(MW)

Annual Gross

Generation (MU)

Per capita Consumption

(Kwh)

2001-02 7924 6687 43920 708

10th Plan Period (2002-07) 2002-03 8268 6957 46389 740 2003-04 9319 7228 49712 780 2004-05 (As on 30.12.04)

9394 7468 (As on

23.02.05)

43920 780 *

* provisional Source: TNEB – Statistics at a Glance 2003-04

11.1 Power Development

429

Power Development – Physical Achievements

Annual Plan period

No. of Sub- stations

Extra Transmission Line (ETL) (ckt. kms.)

Distribution HT (Kms)

Lines L.T. (Kms)

Agricultural Pumpsets energized (Nos.)

Huts Electrified (Nos.)

2001-02

948 21729 118512 432259 40,307 40,000

2002-03

984 16474 123588 456633 29,863 37,280

2003-04

1044 17372 126680 467847 27,484 24,906

2004-05

1076 # 144052 # 465000 34707 @ 25080 @

# Including ETL @ Anticipated Source::TNEB – Statistics at a Glance 2003-04

The Power Position in the Tamil Nadu State as on 31.11.2004 is as follows: The Installed Capacity of Tamil Nadu Electricity Board is 9394 MW. -

I (a) TNEB Grid(Mw) 5381 Thermal 2970 Gas 424 Hydro 1987 (b) Share from Central Power Stations 2587 (c) Independent Power Projects (I.P.P.) 988 (d) Others 438 II. Gross energy generated (Mu.) * 43920 a) Energy generated (TNEB) (Mu.)* 25562 b) Energy purchased/ imported * 18358 c) Energy Exported * 96 III. Energy consumed (Mu.) * 43824 IV. Peak demand (Mw. ) - As in March 2004

7247

Source: TNEB * Provisional

Physical Achievement made by the Tamil Nadu Eletricity Board

The TNEB occupies third rank in the list of top three SEBs in the country, along with Maharashtra and Gujarat, in terms of the size of its operation gauged by the generating capacity at its command/ the amount of energy sold/ and the number of consumers serviced. Tamil Nadu ranks sixth in terms of per capita electricity consumption among the other States. The technical performance/efficiencies of TNEB measured by the plant load factor and the transmission and distribution losses have normally been above the All-India average and among the top five to six SEBs. TNEB has been in the forefront of rural electrification too. Extending electricity to rural and promoting electrification of agricultural pumps have also been accorded top most priority in the TNEB's agenda. As early as 1992, TNEB had reached electricity to all the inhabited villages in Tamil Nadu and the number of electrified agricultural pump sets in the State has registered a phenomenal growth. The Power position/Number of consumers/Number of units consumed by various categories in Tamil Nadu State may be seen in the following graphical presentation.

11.1 Power Development

430

Power Position in Tamilnadu as on 30-11-04 (in MW)Total Installed Capacity 9394 MW

Gas 424IPP 988

Hydro 1987

Central Share 2587

Thermal 2970

Others 438

Source:Statistics at a Glance-TNEB, 2003-2004

Power Consumption Pattern (in MU)Total 38550 MU

Domestic 989526%

Industry 1299934%

Agriculture 939124%

Commercial 390110%

Others 23646%

Source: Statistics at a Glance-TNEB , 2003-2004

11.1 Power Development

431

Number of Consumers - Power Sector -TN as on 31-03-04 (In "000")

TOTAL 16338

Commercial 1866

Huts 973

Industry(HT/LT) - 395

Agriculture 1702

Others 422

Domestic 10980

Source: Statistic at a Glance-TNEB , 2003-2004

Physical Targets/programmes of Power Sector in Tamil Nadu State

* TNEB has been programmed to create an additional capacity of about 30% by March 2007, i.e., 2631 MW (436 MW from State sector projects, 406 MW from Private sector projects, 1289 MW as share from Central sector projects and 500 MW from Joint sector) during the Tenth Plan period (2002-2007).

* Two mega projects have been proposed by Government of Tamilnadu to

the National Thermal Power Corporation (NTPC) and the Neyveli Lignite Corporation (NLC) which are likely to take off in the XI Plan period (2007- '12). In July 2002, the Tamil Nadu Electricity Board (TNEB) signed a Memorandum of Understanding with the NTPC for a 1000- MW plant at Ennore and a year ago, another with the NLC for a similar capacity plant at Tuticorin. The capacity of Tuticorin Plant has been fixed at 1000 MW now.

* The daily average Grid consumption during April to March 2003-04 was

135.133 MU as against 127.093 MU during the same period in 2002-03. The maximum daily consumption reached during April-March 2003-04 was 146.973 MU as on 31.03.2004 as against 139.778 MU as on 21.02.2003 during the same period last year. The maximum instantaneous Peak Demand reached on 16.03.2004 was 7247 MW as against 6960 MW on 21.02.2003.

The Plant Load Factor (PLF) is an important metric of the operational

efficiency of thermal power plants. The Plant load factor of TNEB's Thermal Stations for the period from April 2003- March 2004 vis-a-vis previous year is as follows:

11.1 Power Development

432

Station Installed

Cap. in MW as on March 2003

Generation in MU (April'02 - March '03)

PLF in %

Installed Cap. in MW as on March 2004

Generation in MU (From April 2003 -March 2004)

PLF in %

Ennore 450 17421.198 44.20 450 1263.738 31.97Tuticorin 1050 8193.010 89.07 1050 8083.330 87.64Mettur 840 6737.770 91.57 840 6735.423 91.28North Chennai 630 4406.814 79.85 630 4348.069 78.57Total 2970 21079.792 81.02 2970 20430.56 78.31

Source:TNEB * The Thermal power stations of TNEB continued to perform well.

Hence,the State Government proposes to facilitate establishment of new power generation projects in order to meet the growing energy demand.

* In Transmission also, there has been a phenomenal expansion of the

network. From just 56 substations during pre-plan period (31.3.'51), the number has increased to 984 at the end of 2002-03 and transmission lines (ckt. kms.) from 1,819 to 16,474 during the same period. The Distribution network has also been expanded enormously, that is, from 5,117 HT ckt. kms., and 5,728 LT ckt. kms., in Pre-plan period (31.3.'51) to 1,23,588 HT ckt. kms & 4,56,633 HT ckt. kms respectively by the end of 2002-03. The number of Distribution Transformers has gone up from 1,591 to 1,48,752. By end of 2002-03, 26,764 AD colonies had been electrified, 13,11,173 huts electrified and 16,76,113 agricultural pumpsets energised. Further, concerted effort is being made to reduce T & D losses, reduce outages and interruptions and loss of power due to theft etc., and for upgradation and modernisation of sub-transmission and distribution segments.

* The ultimate aim of the TNEB is to bring down the line losses from the

present level of over 16% to 12% by a series of policy measures apart from the R&D activities for reactive power compensation, improvements in the designs of T&D factors, energy conservation/savings measures etc.

* The Tamil Nadu Electricity Board has also posed improvement schemes to

Rural Electrification Corporation and PFC for sanction towards reducing T & D losses over a period of five years. The TNEB has proposed to implement the above plan in a phased manner by availing loan assistance from APDRP, NABARD, REC and PFC in the State. At present, the T & D losses in Tamil Nadu are estimated at 16.25%.

* At present, there are 169.10 lakhs of service connections (as on

31.12.2004) .1069 substations , 1.46 lakh Kms of EHT/HT lines, 4.75 lakhs of Low Tension (LT) lines and 1.59 lakhs of Distribution Transformers available in the State.

Annual Plan 2005-2006

For Generation schemes, ‘no outlay’ has been provided in the Plan-Budget Link for the year 2005-2006. However, the TNEB continue to implement/incur expenditure on generation schemes/projects out of its own revenue resources apart from subsidy in the form of tariff compensation/loans/assistance/grants etc., by the State/Central Government support/and Other Agencies.

11.1 Power Development

433

The Ongoing programmes by the Tamil Nadu Electricity Board are described in the following paragraphs:

i. Generation

A. Completed Schemes as on 1.4.2004

1. North Chennai Thermal Power Project Stage-I (3 x 210 MW/3300MU)

(Tiruvallur Dist.)

a. Original Sanctioned Cost Rs. 547.79 Crs. b. Latest Estimated Cost Rs. 1864.41 Crs. c. Cumulative expenditure upto 31.3.2004 Rs. 1783.18 Crs. d. Budget Estimate for 2004-05 Rs. 18.00 Crs e. Revised Estimate for 2004-05 Rs. 13.00 Crs. f. Proposed Budget Estimate for 2005-06 Rs. 5.00 Crs. Units I, II, III have been commissioned on 25.10.94, 27.3.95 and 24.2.96 respectively. The requirement for 2004-05 (RE) for the main work in NCTPS is the pipeline construction of RCC channel for drawal of cooling water from the Ennore Port Basin being executed by M/s. L & T. The work in Reach – I & II has been completed. In Reach – III will be completed by June ’05.

The proposed outlay for 2005-06 is mainly towards retention payments to M/s.BHEL for supply and erection of Steam Generator and Turbo Generator and its auxiliaries and works for provision of Diaphragm wall at NCTPS. 2. Thirumakottai (Kovilkalappal) GTPP (Thiruvarur Dist.- 107.88 MW/630 MU) a. Latest Estimated Cost Rs. 300.00 Crs. b. Cumulative expenditure upto 31.3.2004 Rs. 231.96 Crs. c. Budget Estimate for 2004-05 Rs. 26.00 Crs. d. Revised Estimate for 2004-05 Rs. 20.00 Crs. e. Proposed Budget Estimate for 2005-06 Rs. 5.00 Crs. The project has been commissioned during 02/2001. The provision of Rs.20.00 Crs. for 2004-05 (RE) has been given for the Hot Gas Path Inspection and provision of Rs. 5 Crs. for 2005-06 (BE) is given for the pending final payments. 3. Valuthur (Perungulam) Gas Turbine Power Project (Ramanathapuram District-

95 MW/630 MU) a. Latest Estimated Cost Rs. 346.00 Crs. b. Cumulative expenditure upto 31.3.2004 Rs. 248.95 Crs. c. Budget Estimate for 2004-05 Rs. 18.00 Crs. d. Revised Estimate for 2004-05 Rs. 15.00 Crs. e. Proposed Budget Estimate for 2005-06 Rs. 5.00 Crs.

11.1 Power Development

434

The 60 MW Gas Turbine Generator has been synchronized with Tamil Nadu

Grid on 24.12.2002 and combined cycle with 95MW commissioned on 13.03.2003. Rs.15 Crs. for 2004-05 (RE) is essentially required for making the balance payments for EPC contractor and Rs.5 Crs. is essentially required for the final payments and for combustion inspection for 2005-06. 4. Kuttalam GTPP (Nagapattinam District-101 MW) a. Estimated Cost Rs. 345.00 Crs. b. Cumulative expenditure upto 31.3.2004 Rs. 259.93 Crs. c. Budget Estimate for 2004-05 Rs. 33.00 Crs. d. Revised Estimate for 2004-05 Rs. 30.00 Crs. e. Proposed Budget Estimate for 2005-06 Rs. 10.00 Crs.

The 64 MW Gas Turbine Generator has been synchronized with Tamil Nadu Grid on 27.11.2003 and combined cycle with 101MW commissioned on 24.03.2004. Rs.30 Crs. is required for making the balance payments for EPC contractor and Rs.10 Crs. is essentially required for the final payments and combustion inspection during the year 2005-06.

B. Ongoing Schemes as on 1.4.2004

1. Pykara Ultimate Stage HEP (3 x 50 MW/Peaking Station) (Nilgiris Dist.) a. Original Estimated Cost Rs. 136.32 Crs. b. Latest Estimated Cost Rs. 382.81 Crs. c. Cumulative expenditure upto 31.3.2004 Rs. 257.81 Crs. d. Budget Estimate for 2004-05 Rs. 20.00 Crs. e. Revised Estimate for 2004-05 Rs. 25.00 Crs. f. Proposed Budget Estimate for 2005-06 Rs. 5.00 Crs.

The Pykara Ultimate Stage HEP envisages power generation utilizing the Head available between the Full Reservoir Level (FRL) of the existing Glenmorgan Forebay and the F.R.L. of the existing Maravakandi Dam. This project is conceived to provide additional installed capacity on the basis of lowering the load factor of Pykara P.H. machines for meeting more peak demand by utilizing the same flows as at present intercepted at Glenmorgan.

Erection of generating machinery for Unit-I & II completed. For Unit – III, it is nearing completion. Pressure shaft lining works completed. Tower erection works have been completed. Transmission line stringing works completed for a Route Length of 55.23 Kms. out of 58.23 Kms.

The I & II units have been put on mechanical run satisfactorily on 11.10.04

and 08.11.04. The 3rd unit is likely to be put on mechanical run by March 2005.

2. Perunchani Mini HEP (2x0.65 MW, 4.0 MU ( Kanyakumari Dist.) a. Estimated Cost Rs. 9.61 Crs. b. Cumulative expenditure upto 31.3.2004 Rs. 8.13 Crs.

11.1 Power Development

435

c. Budget Estimate for 2004-05 Rs. 0.00 Cr. d. Revised Estimate for 2004-05 Rs. 0.35 Cr. e. Proposed Budget Estimate for 2005-06 Rs. Nil The Materials have been received and units are expected to be commissioned during this year. Balance payment is expected to be made during this year. 3. Amaravathi Dam Small HEP (2 x 2 MW, 10.47 MU, Coimbatore (District) a. Estimated Cost Rs. 12.46 Crs. b. Cumulative expenditure upto 31.3.2004 Rs. 5.23 Crs. c. Budget Estimate for 2004-05 Rs. 0.00 Cr. d. Revised Estimate for 2004-05 Rs. 8.00 Crs. e. Proposed Budget Estimate for 2005-06 Rs. 3.00 Crs.

The materials have been received. The erection is under progress. Payment

towards materials and erection is expected during this year and remaining payment during next year.Hence, provision has been made in RE for 2004-05 and BE 2005-06. The project is programmed for commissioning during 2004-05. 4. Bhavani – Kattalai Barrage-I HEP (2 x 15 MW/86 MU) (Erode Dist.) a. Estimated Cost Rs. 194.53 Crs. b. Cumulative expenditure upto 31.3.2004 Rs. 123.65 Crs. c. Budget Estimate for 2004-05 Rs. 35.00 Crs. d. Revised Estimate for 2004-05 Rs. 35.00 Crs. e. Proposed Budget Estimate for 2005-06 Rs. 5.00 Crs. The Bhavani – Kattalai Barrage-I HEP is proposed for utilizing the tail waters of Lower Mettur Barrage PHs. and also the flow in Bhavani river after its confluence with river Cauvery at Bhavani. The outlay is for civil, mechanical and electrical activities. The Barrage and Barrage gate works are completed. The power house substructure major civil works completed except second stage concreting. The same is proposed to be taken up in co-ordination with machine erection works. The fabrication of intake gate and Draft Tube gates works completed. The erection of draft tube gates is to be taken up. The power house super structure will be completed by June 2005. The project is programmed for commissioning during 2005-06. 5. Bhavani Kattalai Barrage II, Odapalli (2x15 mw) a. Estimated Cost Rs. 156.67 Crs. b. Cumulative expenditure up to 31.03.2004 Rs. 1.11 Crs. b. Budget Estimate for 2004-05 Rs. 20.00 Crs. c. Revised Estimate for 2004-05 Rs. 1.00 Crs. d. Proposed Budget Estimate for 2005-06 Rs 10.00 Crs.

11.1 Power Development

436

The Bhavani Kattalai Barrage II is located down stream of Bhavani Kattalai

Barrage – I at Odapalli/Vendipallayam village of Namakkal/Erode District. It is to utilize irrigation discharge let out from Bhavani Kattalai Barrage-I. The expenditure is towards forming of approach road, storage shed, land acquisition, preliminary infrastructure civil works, Barrage and Barrage Gates works.

The project is programmed for commissioning during 2006-07. 6. Augmentation of Ash Dyke and provision of clarifiers at MTPS (Salem Dist.) a. Estimated Cost Rs. 98.15 Crs. b. Cumulative expenditure upto 31.3.2004 Rs. 42.17 Crs. c. Budget Estimate for 2004-05 Rs. 10.00 Crs. d. Revised Estimate for 2004-05 Rs. 2.50 Crs. e. Proposed Budget Estimate for 2005-06 Rs. 2.00 Crs. This scheme has been envisaged with a view to augment the askdyke to suit the requirement of the two 210 MW units commissioned under Phase-II at Mettur Thermal Power Station in 1989 and 1990. The Civil/Mechanical/Electrical works connected with construction of upper ash dyke are in progress. The provision in R.E 2004-05 is towards construction of compound wall around upper Ash Dyke and construction of Ash Slurry supports with approach road in UAD. Provision for the year 2005-06 is for pending civil works relating to the Augmentation of Ash Dyke at MTPS.

C. New Projects

1. Bhavani Kattalai Barrage III, Cholasiramani ( 2X15 MW / 78.77 MU ) a. Estimated Cost Rs. 158.33 Crs. b. Cumulative expenditure upto 31.3.2004 Rs. 0.67 Crs. c. Budget Estimate for 2004-05 Rs. 20.00 Crs. d. Anticipated Expenditure during 2004-05 Rs. 0.75 Crs. e. Proposed Budget Estimate for 2005-06 Rs. 5.00 Crs. The Bhavani Kattalai Barrage III HEP is proposed for utilizing the tail waters of Bhavani Kattalai Barrage II. The initial expenditure is towards land acquisition, survey works, preliminary infrastructure civil works, barrage & barrage gate works, power house and civil works. The project is likely to be commissioned by 2006-07. 2. Bhavani Barrage I HEP (2x5MW) a. Estimated Cost : Rs.35.34 Crs b. Budget Estimate for 2004-05 : Rs. 5.00 Crs. c. Revised Estimate for 2004-05 Rs. 0.25 Cr. d. Proposed Budget Estimate for 2005-06 Rs. 1.00 Cr.

11.1 Power Development

437

All the statutory clearances have been obtained. For the development of

Infrastructure preliminary works such as Land acquisition, formation of camp etc, a provision of Rs. 0.25 Crs. have been made in the Revised estimate for the year 2004-05 and 1 Cr. for the year 2005-06.

Anticipated date of commissioning is 12/2007.

3. Bhavani Barrage – II HEP (2 x 5 MW) a. Estimated Cost Rs. 35.34 Crs. b. Budget Estimate for 2004-05 Rs. 3.00 Crs. c. Revised Estimate for 2004-05 Rs. 0.25 Crs. d. Proposed Budget Estimate for 2005-06 Rs. 1.00 Crs. All the statutory clearance have been obtained. Expert Committee has given clearance to this scheme on techno-economical aspects. A provision of Rs.1 Cr. has been made for the year 2005-06 towards the cost of infrastructure works such as drilling of bore holes, pre-construction survey works, construction of barrage and allied works, sub-structure works of Power House.

Anticipated date of commissioning is during 2007-08. 4. Periyar Vaigai 1 Small HEP (2x2MW) a. Estimated Cost : Rs.18.83 Crs b. Budget Estimate for 2004-05 : Rs. 5.00 Crs. c. Revised Estimate for 2004-05 : Rs. 0.50 Crs. d. Proposed Budget Estimate for 2005-06 : Rs. 2.00 Crs.

The project enabling works such as acquisition of land, formation of access roads and construction of temporary camps have been taken up. A provision of Rs. 0.50 Crs. has been made in the revised estimate for the year 2004-05. A provision of Rs. 2 Crs. has been made for the year 2005-06 towards construction of weir and allied works, power house excavation and cost of Electrical and Mechanical equipments.

Anticipated date of commissioning is 12/2006.

5. Kollimalai Hydro Electric Project (1x20MW) a. Estimated Cost Rs.60.91 Crs. b. Budget Estimate for 2004-05 Rs. 2.00 Crs. c. Revised Estimate for 2004-05 Rs. 0.50 Cr. d. Proposed Budget Estimate for 2005-06 Rs. 2.00 Crs.

The project enabling works such as afforestation, Catchment Area treatment etc. are to be carried out. Nett Present value to be paid to the Forest Department. Identification of revenue lands for carrying out afforestation has been taken up. The State forest department has requested TNEB to obtain orders of central empowered committee constituted by Hon’ble Supreme Court for the felling of trees. Action is

11.1 Power Development

438

being taken to obtain the same. A provision of Rs.0.50 Crs. has been made in the Revised estimate for the year 2004-05. A provision of Rs. 2 Crs. has been made for the year 2005-06 towards forming approach roads, temporary camps and excavation works for Dam, Tunnels and Penstock.

Anticipated date of commissioning is 12/2009.

6. Thirumurthy Contour Canal HEP (1x1.25MW) a. Estimated Cost : Rs.5.92 Crs. b. Budget Estimate for 2004-05 : Rs. 2.00 Crs. c. Revised Estimate for 2004-05 : Rs. 0.25 Cr. d. Proposed Budget Estimate for 2005-06 : Rs. 1.00 Cr.

All statutory clearances have been obtained. A provision of Rs.0.25 Crs. has been made in the Revised Estimate for the year 2004-05 for carrying out preconstruction survey works, infrastructure facilities such as formation of approach roads, acquisition of lands etc. Objections have been raised by Govt. of Kerala for the establishment of this project, due to submergence (anticipated) of existing Interstate Measuring Gauge to calibrate flows in the Canal.

Action is being taken to resolve the above Interstate Issues and execution of

this project works will be taken up on receipt of clearance from Govt. of Kerala.

7. Mukkuruchihalla Pumping Scheme (Augmentation) a. Estimated Cost Rs. 9.40 Crs. b. Budget Estimate for 2004-05 Rs. 6.00 Crs. c. Revised Estimate for 2004-05 Rs. 0.50 Cr. d. Proposed Budget Estimate for 2005-06 Rs. 3.00 Crs.

The Mukkurichihalla Pumping Scheme (MPS) envisages interception of Mukkurichihalla Stream water by constructing a diversion weir across the stream. The Mukkurichihalla Stream is a tributary of Pykara river. The intercepted water is to be pumped over a gross head of 173.47m and delivered into the Naduvattam diversion flume so as to reach the Glenmorgan forebay dam. This will be utilised to augment power generation to an extent of 18.15 MU in the Pykara, Maravakandy and Moyar Power Stations. The various works involved in the Scheme are:

Construction of Diversion Weir

Construction of Pump House Construction of Pumping Main and Construction of outfall arrangements

The present status of the Project is that the Collector/Nilgirs District has been requested to permit TNEB to enter their land to take up execution of the Project, pending finalisation of land alienation proposals. The permission is awaited. Tender specification is under preparation for the execution of weir pumping main and pump house.

11.1 Power Development

439

8. Valuthur GTPP (Additional) (Ramanathapuram District- 95 MW/630 MU) a) Estimated cost Rs.350.00 Crs. b) Cumulative expenditure upto 31.3.04 NIL c) Budget Estimate for 2004-05 NIL d) Revised Budget Estimate for 2004-05 Rs. 5.00 Crs. e) Proposed Budget Estimate for 2005-06 Rs. 40.00 Crs.

Considering the surplus Natural Gas available from the gas field at Perungulam, Ramanathapuram District, M/s.GAIL have allocated 4,38,000 SCMD of natural gas per day to TNEB, to establish an additional 95 MW unit of Gas Turbine Station at Valuthur, within the premises of the existing plant at an estimated cost of Rs.350 Crs. Global tender has been called for awarding the contract on EPC basis . Pre-bid meeting has been held with tenders on 07.02.2005. M/s.GAIL has allocated the Gas to TNEB for this project. An amount of Rs.5 Crs. during 2004-05 and another amount of Rs.40.00 Crs. in 2005-06 are proposed to be spent on this project. 9. Narimanam GTPP (10 MW) a) Estimated cost Rs.40.00 Crs. b) Cumulative expenditure upto 31.3.04 NIL c) Budget Estimate for 2004-05 NIL d) Revised Budget Estimate for 2004-05 Rs. 3.00 Crs. e) Proposed Budget Estimate for 2005-06 Rs.10.00 Crs.

Ministry of Petroleum and Natural Gas, New Delhi have allocated 63,000 SCMD of natural gas for the Narimanam GTPP. In Narimanam GTPP the aero derivation machines are to be replaced by Industrial type Gas Turbine, for making the project viable one. The estimated cost of the project is around Rs.40.00 Crs. In this regard Global tenders were called for and M/s.BHEL/Bangalore happens to be the lowest tenderer and the work is to be awarded to M/s.BHEL, Bangalore. An amount of Rs.3 Crs. during the year 2004-05 and another amount of Rs.10.00 Crs. is to be spent during the year 2005-06 for making the balance payment.

II. Renovation & Modernisation Schemes A. Hydro Schemes 1. Renovation & Modernisation of Units at Pykara Power House a. Original Sanctioned Cost Rs. 17.46 Crs. b. Latest Estimated Cost Rs. 19.38 Crs. c. Cumulative expenditure upto 31.3.2004 Rs. 11.13 Crs. (Plan) Rs. 9.09 Crs. (PFC) d. Budget Estimate for 2004-05 Rs. 0.25 Cr. e. Revised Estimate for 2004-05 Rs. 0.75 Cr. f. Proposed Budget Estimate for 2005-06 Rs. 0.15 Cr.

Many of the works have been completed. Remaining are the works such as erection and commissioning of AVR, Control & Relay Panels for generators and Bus

11.1 Power Development

440

bar protection. The materials required for the above works have been received. The work is in progress. To carryout the above works and to make payment, upward revision in RE is required. The proposed outlay for the year 2005-06 is Rs.95 lakhs for this scheme.

2. Renovation, Modernisation & Uprating of Mettur Dam Power House (Benefits –

10.98 MU) a. Original Sanctioned Cost Rs. 16.33 Crs. b. Latest Estimated Cost Rs. 78.80 Crs. c. Cumulative expenditure upto 31.3.2004 Rs. 9.22 Crs. d. Budget Estimate for 2004-05 Rs. 10.00 Crs. e. Revised Estimate during 2004-05 Rs. 15.00 Crs. f. Proposed Budget Estimate for 2005-06 Rs. 10.00 Crs.

Renovation, Modernisation & Uprating works in two of the four units were completed and synchronized to grid. Works will be taken in remaining two units and expected to be completed during 2005-06. Since materials supply for all units is expected, the budget estimate for the year 2004 -05 is retained as such for 2005-‘06. 3. Renovation, Modernisation & Uprating of Papanasam Power House (benefits –

5.60 MU) a. Original Sanctioned Cost Rs. 21.77 Crs. b. Latest Estimated Cost Rs. 59.08 Crs. c. Cumulative expenditure upto 31.3.2004 Rs. 10.63 Crs. d. Budget Estimate for 2004-05 Rs. 10.00 Crs. e. Revised Estimate for 2004-05 Rs. 10.00 Crs. f. Proposed Budget Estimate for 2005-06 Rs. 6.00 Crs.

Two units have been recommissioned after Renovation, Modernisation & Uprating works. R,M &U works are in progress in the remaining two units. These units are expected to be recommissioned shortly. The budget estimate for 2005-06 is Rs. 6 Crores.

4. Renovation, Modernisation & Uprating of Sholayar Power House-I a. Estimated Cost Rs. 40.68 Crs. b. Budget Estimate for 2004-05 Rs. 0.25 Cr. c. Revised Estimate for 2004-05 Rs. 0.25 Cr. d. Proposed Budget Estimate for 2005-06 Rs. 3.00 Crs.

The Tender for Renovation, Modernisation & Uprating works of Sholayar Power House I is being processed. The material supply is expected after six months from the date of finalization of order. Hence, expenditure is likely to be incurred and during second half of the financial year 2005-06. The exact requirement can be furnished only after finalization of tender. Hence, a token provision has been made for this project towards advance payment. The Proposed outlay for 2005-06 is Rs.3 Crores.

11.1 Power Development

441

5. Renovation, Modernisation & Uprating of Periyar Power House a. Estimated Cost Rs. 73.88 Crs. b. Budget Estimate for 2004-05 Rs. 0.25 Cr. c. Revised Estimate for 2004-05 Rs. 0.25 Cr. d. Proposed Budget Estimate for 2005-06 Nil.

Tender for Renovation, Modernisation & Uprating works of this Power House is yet to be floated. Since, it will take about one year for finalization of tender no expenditure is likely for 2005-06.

6. Renovation & Modernisation of Kadamparai Dam a. Estimated Cost Rs. 14.96 Crs. b. Budget Estimate for 2004-05 Rs. 0.00 Cr. c. Revised Estimate for 2004-05 Rs. 6.00 Crs. d. Proposed Budget Estimate for 2005-06 Rs. 4.00 Crs.

It is proposed to renovate and modernize Kadamparai Dam to arrest water leak. Administrative approval for Rs.14.96 Crs. has been obtained. Contract has been awarded and the work is under execution and to be expected by May 2005. Hence, Budget provision is required for 2004-05 and 2005-2006.

B. Thermal Schemes

1) R & M work at ETPS Stage-II (Phase – I) a) Original sanctioned cost : Rs. 25.65 Crs. b) Latest estimated cost : Rs. 105.07 Crs. c) Cumulative expenditure upto 31.03.2004: Rs. 86.74 Crs. d) Budget Estimate for 2004-2005 : Rs. 12.00 Crs. e) Revised Estimate for 2004-2005 : Rs. 1.00 Cr. f) Proposed budget estimate for 2005-06 : Rs. 5.00 Crs.

The specification for completing balance works in Additional Coal Handling

System at a cost of Rs.12 Crs. is being put up for approval.

2) Additional R & M at MTPS a) Estimated Cost : Rs.51.66 Crs. b) Cumulative expenditure upto 31.03.2004: Nil c) Budget Estimate for 2004-2005 : Rs.10.00 Crs. d) Revised Estimate for 2004-2005 : Rs. 1.00 Cr. e) Proposed budget estimate for 2005-06 : Rs. 8.00 Crs.

Proposal for getting Administrative approval for Augmentation of ESP is under process. 3. Additional R&M works at ETPS a) Estimated Cost Rs.259.58 Crs.

11.1 Power Development

442

b) Cumulative expenditure upto 31.03.2004 Rs.185.26 Crs. c) Budget Estimate for 2004-2005 : Rs. 16.00 Crs. d) Revised Estimate for 2004-2005 : Rs. 8.00 Crs. e) Proposed budget estimate for 2005-06 : Rs. 10.00 Crs.

R & M works in Unit – II was commenced in 03/04 and R & M works in Unit- I will be commenced by 08/2005. Entire R & M works in units I & II will be completed by 07/2006. 4. Additional R&M works at TTPS a) Original Estimated cost : Rs.31.38 Crs. b) Latest cost : Rs.94.29 Crs. c) Cumulative expenditure upto 31.03.2004: Rs.64.87 Crs. d) Budget estimate for 2004-2005 : Rs.18.00 Crs. e) Revised Estimate for 2004-2005 : Rs. 8.00 Crs. f) Budget estimate for 2005-2006 : Rs. 8.00 Crs.

Additional R & M works of Unit – I were completed during January 2004. Proposal for getting Administrative approval for Augmentation of ESP is being put up for approval. 5. Ash Dyke at ETPS a) Estimated Cost : Rs.77.04 Crs. b) Cumulative expenditure upto 31.03.2004: Rs. 64.29 Crs. c) Budget Estimate for 2004-2005 : Rs. 15.00 Crs. d) Revised Estimate for 2004-2005 : Rs. 0.25 Cr. e) Proposed budget estimate for 2005-06 : Rs. 3.00 Crs.

Ash Dyke works were completed by M/s. L & T and M/ s. Thermax Ltd. Provision of Rs. 3 Crs. for 2005-06 (BE) is given for the pending final payments to M/s. L & T.

6. R & M at MTPS DCS in Unit I a) Estimated Cost : Rs. 2.41 Crs. b) Cumulative expenditure upto 31.03.2004: Nil. c) Budget Estimate for 2004-2005 : Rs. 1.20 Crs. d) Revised Estimate for 2004-2005 : Rs. 0.25 Cr. e) Proposed budget estimate for 2005-06 : Rs. 3.00 Crs.

DCS (Distributed Control System) works for Unit-II was completed.

Approval for DCS Unit-I was obtained and tender has been floated. Commercial bid was opened on 16.08.04. The above tender was lodged and new tender will be called for after obtaining technical clarification.

7. Residual Life Assessment study at TTPS a) Estimated Cost Rs. 2.35 Crs. b) Cumulative expenditure upto 31.03.2004 Rs.18.43 Crs.

11.1 Power Development

443

c) Budget Estimate for 2004-2005 Rs. 1.50 Crs. d) Revised Estimate for 2004-2005 : Rs. 0.25 Cr. e) Proposed budget estimate for 2005-06 : Rs. 1.50 Crs. RLA study of Unit-I was completed during January 2004. RLA study of Unit – II will be completed during September 2006. RLA study of Unit – III will be completed during December 2005.

III. Transmission & Distribution

a. Budget Estimate for 2004-05 Rs. 1105.46 Crs. b. Revised Estimate for 2004-05 Rs. 712.11 Crs. c. Proposed Budget Estimate for 2005-06 Rs. 1003.87 Crs.

The transmission and distribution system has been expanding rapidly to evacuate and distribute the power from new generating stations. Establishing of new sub stations, upgrading of sub stations, Improvements at HT & LT net works to reduce line losses, providing of capacitor banks etc. and other activities to improve operational stability are also being taken up.

During 2005-06, it has been proposed to establish 60 Nos. new sub stations and 800 Kms. of EHT lines.

Sub-Transmission and Distribution Improvements

The following schemes have been contemplated for execution during 2005-06 and subsequent years for improvement of sub-transmission and distribution networks so as to bring down T & D losses and to improve quality of power.

1. Accelerated Power Development And Reforms Programme (APDRP) Ministry of Power, Government of India have sanctioned 25 Nos. Sub-transmission and Distribution Improvement Schemes under Accelerated Power Development and Reform Programme (APDRP) covering Chennai Metropolitan area, five distribution circles and 19 Urban areas to the tune of Rs.977 Crs. The expenditure incurred for all the above 25 Nos. upto February 2005 is Rs.523.14 Crs. have been spent. An amount of Rs.224 Crs. is expected to be spent for sub-transmission and distribution schemes by the end of March 2005. An outlay of Rs.58.36 crores has been proposed for 2005-06 for this programme. 2. Prime Ministers Grama Yojana Schemes (PMGYS) a. Ongoing schemes (2003-05)

The four schemes viz. Namakkal District Phase – I, Namakkal District Phase – II, Salem District and Villupuram District at a total cost of Rs.675.68 lakhs were sanctioned, vide G.O.No.18, dt.1.3.2004 under PMGY for the electrification of 60 tribal hamlets. Against this, Rs.608.20 lakhs have been received and credited into Board’s account as grant cum loan (30% grant +70% loan) on 20.03.04. The works are under progress. The expenditure incurred upto 31.01.05 is Rs.608.20 lakhs and the habitations electrified is 60 Nos. All the above four schemes have been programmed to be completed by 31.03.05. In the scheme sanctioned during 2003-04, an additional amount of Rs.28.58 lakhs is required to be sanctioned to Namakkal

11.1 Power Development

444

District Phase-I scheme for way leave charges to Forest Department for erection of H.T. line in Namakkal District. Rs.61.46 lakhs excess amount spent on Vellore District Scheme is to be adjusted for the short fall amount incurred in Nilgiris District Scheme and Kodaikkanal area scheme in Dindigul District. The financial progress to be achieved during 2004-05 is Rs.157.52 lakhs.

b. New proposal

Apart from the above four schemes, another scheme for Dharmapuri District covering electrification of 55 hamlets at a cost of Rs.114.257 lakhs has been sanctioned vide G.O.Ms.No.160 Dt.8.12.04. A revised proposal at a cost of Rs.124.39 Lakhs included in Lind tap SS was sent to Govt. of Tamil Nadu and approval for the same is awaited. The works have been taken up by SE/ Dharmapuri EDC and 54 out of 55 hamlets have been electrified till date. One hamlet requires forest clearance. The financial progress achieved during 2004-05 is Rs.123.233 lakhs.

3. National Agricultural Bank For Rural Development (NABARD) Schemes

NABARD has sanctioned 20 schemes under (Rural Infrastructure Development Fund) RIDF-VII, VIII and IX for loan assistance for an amount of Rs.185.75 Crs. under reimbursement basis.

RIDF – VII: Four EDCs covered are Ramnad, Tuticorin, Thanjavur and

Dharmapuri under this scheme. An amount of Rs.38.24 Crs. has been sanctioned by NABARD. The financial progress achieved upto January 2005 is Rs.37.81 Crs.

RIDF – VIII: Ten EDCs are covered under this scheme. An amount of Rs.84.02 Crs. has been sanctioned by NABARD. The financial progress achieved upto Jan 2005 is Rs.74.93 Crs. The balance financial progress to be achieved during 2004-05 is Rs.12.09 Crs. The EDCs covered are Ramnad Phase-III, Kanyakumari, Thiruvannamalai, Sivaganga, Nagapattinam, Karur, Virudhunagar, Gobi, Theni, and Thirupathur.

RIDF – IX: Six EDCs covered under this schemes are Dharmapuri,

Thirunelveli Phase-I, Kanyakumari, Thirunelveli Phase-II, Tuticorin and Karur An amount of Rs.63.48 Crs has been sanctioned by Nabard. The financial progress achieved upto January 2005 is Rs.16.98 Crs. Balance to be achieved during 2004-05 and 2005-06 is Rs.46.5 Crs. An outlay of Rs.50.26 crores has been proposed for the year 2005-06.

IV. Rural Electrification a. Budget Estimate for 2004-05 Rs. 92.63 Crs. b. Revised Estimate for 2004-05 Rs. 119.65 Crs. c. Proposed Budget Estimate for 2005-06 Rs. 100.50 Crs.

Under Rural Electrification Scheme 45,000 Agriculture services and 40,000 hut services will be connected during 2004-05. During 2005-06 the target of 40,000 new Agriculture services and 40,000 hut services will be achieved.

11.1 Power Development

445

V. Survey, Investigation, Research, Computerisation and Training a. Budget estimate for 2004-05 Rs. 2.50 Crs. b. Revised estimate for 2004-05 Rs. 3.50 Crs. c. Proposed budget estimate for 2005-06 Rs. 2.50 Crs. a) Survey & Investigation TNEB is conducting survey and carrying out investigation works to find out the feasibility of establishing major/medium/mini hydro electric schemes and coal/ diesel / gas based thermal stations. b) Research and Development

The research wing in TNEB , is setting up a transformer oil testing lab facility at Trichy, Up gradation of Chennai transformer oil lab, Up gradation of Chennai HV lab and procurement of materials for study purpose. c) Computerisation

Computerisation at circle offices and Head Office at Chennai along with L.T. Bill accounting and L.T. Bill collection implementations are being carried out. d) Training

For improving the quality of training at four training centres of the Board it is proposed to provide LCD Multimedia Projector with accessories for improving the facility for various training programmes for TNEB staff. e) Environmental Cell

Issue connected with environmental aspects of power projects are dealt by this circle. During 2004-05 it will be equipped with Pollution Monitoring Equipments and accessories.

Tenth Five Year Plan Perspectives:

The Projects programmed for the Tenth Five Year Plan Period ( 2002-2007), Projects already commissioned during the first two years of the Tenth Plan(2002-04), and Projects expected to be commissioned during balance three years of Tenth Plan are shown in the following three Statements.

11.1 Power Development

446

Projects Programmed for Tenth Plan Period - (2002-07) Statement- I

Sl. No.

Name of the Project Capacity( M.W.)

Target

State Sector 1. Valuthur GTPP 95 Commissioned on 13.3.2003 2. Aliyar Small HEP 2.5 Commissioned on 23.9.02 3. Perunchani & Amaravathy HEP 5.3 The projects likely to be

commissioned on 31.03.05 4. Bhavani Kattalai Barrange-I Hydro

Project 30 The project likely to be commissioned

on 30.06.05 5. Pykara Ultimate Stage Hydro Electric

Project 150 The Unit – I & II have been put on

mechanical run on 11.10.2004 and 08.11.2004. The 3rd unit is likely to be put on mechanical run by 03/2005.

6. Kuttalam GTPP 101 Commissioned on 24.03.2004. 7. Bhavani Kattalai Barrage-II & III

Hydro Projects 60 The projects likely to be

commissioned on 31.03.2007 8. Valuthur GTPP (Additional) 95 The project likely to be commissioned

on 31.03.2007 Total (State Sector) 538.8 Private Sector 1. Neyveli Zero Unit 250 Commissioned on 16.12.02. 2. M/s.Arkay Energy Ltd. 53 Power Purchase Agreement (PPA)

signed on 25.08.2004. Financial Closure (FCD) achieved. Work nearing completion.

3. M/s.Aban Power Company 103 Synchronized with TNEB grid on Feb’2005. Testing under progress.

Total (Private Sector)

406

Central Sector 1. Neyveli Thermal Power Station-I,

Stage 1, Expansion (2x210 MW) 240 COD

Unit 1: 6.5.2003 (Share availed 120 MW) Unit 2: 5.9.2003 (Share availed 120 MW)

2. Ramagundam Super Power Thermal Station Stage.2 (500 MW)

118

2004-05

3. Talcher Super Thermal Power Project Stage 2 (4x500 MW)

540 Unit 1 - COD : 1.8.2003 (Share availed 135 MW) Unit 2 – COD : 1.3.2004 (Share availed 135 MW) Unit 3 – CDO : 01.11.2004 (Share availed 135 MW) Unit-4 – 2004-05 (Share to be availed 135 MW)

4. Kaiga Atomic Power Project Stg.II 103 2006-07 5. Kudankulam Atomic Power Project 463 2006-07 Total (Share From Central Sector 1464 Total (State+ Private +Central Share) 2408.8

11.1 Power Development

447

Projects already Commissioned during first two years of Tenth Plan Period.

Statement- II Sl. No.

Name of the Project Capacity( M.W)

Target

State Sector 1. Valuthur GTPP 95 Commissioned on 13.3.2003 2. Aliyar Small HEP 2.5 Commissioned on 23.9.02 3. Kuttalam GTPP 101 Commissioned on

24.03.2004. Total (State Sector) 198.5 Private Sector 1. Neyveli Zero Unit 250 Commissioned on 16.12.02. Total (Private Sector) 250 Central Sector 1. Neyveli Thermal Power Station-I,

Stage 1, Expansion (2x210 MW) 240 Unit 1: COD : 6.5.2003

(Share availed 120 MW) Unit 2: COD : 5.9.2003 (Share availed 120 MW)

2. Talcher Super Thermal Power Project Stage 2 (4x500 MW)

270 Unit 1 - COD : 1.8.2003 (Share availed 135 MW) Unit 2 – COD : 1.3.2004 (Share availed 135 MW)

Total (Share From Central Sector 510 Total (State+Private +Central Share) 958.5

Projects Expected to be commissioned During balance three years of Tenth Plan Period.

Statement - III

Sl. No.

Name of the Project Capacity( M.W)

Target

State Sector 1. Bhavani Kattalai Barrage-I

Hydro Project 30 The project likely to be commissioned on

30.06.05 2. Perunchani & Amaravathy

HEP 5.3 The projects likely to be commissioned on

31.03.05 3 Pykara Ultimate Stage Hydro

Electric Project 150 The Unit – I & II have been put on

mechanical run on 11.10.2004 and 08.11.2004. The 3rd unit is likely to be put on mechanical run by 03/2005.

4. Bhavani Kattalai Barrage-II & III Hydro Projects

60 The projects likely to be commissioned on 31.03.2007

5. Valuthur GTPP (Additional) 95 The project likely to be commissioned on 31.03.2007

Total (State Sector) 340.3

11.1 Power Development

448

Sl. No.

Name of the Project Capacity( M.W)

Target

Private Sector 1. M/s. Arkay Energy Ltd. 53 Power Purchase Agreement (PPA) signed on

25.08.2004. Financial Closure (FCD) achieved. Work nearing completion

2. M/s. Aban Power Company 103 Synchronized with TNEB grid on Feb,2005. Testing under progress.

Total (Private Sector) 156

Central Sector 1. Ramagundam Super Power

Thermal Station Stage.2 (500 MW)

118

2004-05

2. Talcher Super Thermal Power Project Stage 2 (4x500 MW)

270 COD Unit-3 – 01.11.04. (Share availed 135 MW) Unit-4 – 2004-05 (Share to be availed 135 MW)

3. Kaiga Atomic Power Project Stg.II

103 2006-07

4 Kudankulam Atomic Power Project

463 2006-07

Total (Share From Central Sector

954

Total (State + Private + Central Share)

1450.3

Annual Plan Outlay 2005-2006

Power Development - Annual Plan 2005-06 Outlay

(Rs. in lakhs)

Schemes Actual Exp. 2002-03

Actual Exp. 2003-04

Anticipated Exp.

2004-05

Proposed Outlay for 2005-06

I. Generation -- -- -- -- II. Renovation & Modernisation 4516.50 23800.88 5508.57 10861.80

III. Transmission & Distribution 107626.67 68753.84 55509.70 52932.60

IV. Survey & Investigation -- -- -- -- V. Rural Electrification 7634.70 32342.04 10705.53 8348.17 VI. Special Component Plan -- 804.60 0.02 0.02 Total 119777.87 125701.36 71723.82 72142.59

Source: Plan- Budget Link (Yellow Book), 2004-05 & 2005-2006