11kv test report
TRANSCRIPT
REPORT NO.:
PAGE: 1 OF 2
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
Digital Micro Ohm meter
Circuit Breaker Analizer
11kV SWGR VACUUM CIRCUIT BREAKER TEST
1. General Data
Type
Rated Voltage
Rated Current
Rated Breaking Capacity
Duty Cycle
Serial No.
Aux. Voltage
Motor Voltage
2. Visual Check
Description OK
Visual Check for External Damage
Visual Check of operation mechanism components: operation mechanism
3. Insulation Resistance Test
Breaker Closed Breaker Open
R-E R-R
S-E S-S
T-E T-T
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
Not Accepted
Visual Check of operation mechanism components: control switch, position indicator
REPORT NO.:
PAGE: 2 OF 2
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
Digital Micro Ohm meter
Circuit Breaker Analizer
11kV SWGR VACUUM CIRCUIT BREAKER TEST
4. CB Close / Open Timing Test
Phase Main Contacts
Closing Time msec Opening Time msec
R
S
T
5. Contact Resistance Measurement
Phase Current injected A Contact Resistance µΩ
R
S
T
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
REPORT NO.:
PAGE: 1 OF 5
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
DC mA Ammeter
CT Injection kit
11kV SWGR CURRENT TRANSFORMER TEST
1. Data
Phase R S T
Serial No.
CT No. Purpose Ratio Class
T2-1
5P20
CL PX
T2-2
2. Insulation Resistance Test: 500V DC for 1 min
CTSec to all other core & Primary Earth Primary to Sec. Earth
R S T R S T
3. Polarity Test:
CT No.S1-S2
R S T
T2-1
5P20
CL PX
T2-2
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
Winding Resistance @ 75 °C
REPORT NO.:
PAGE: 2 OF 5
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
DC mA Ammeter
Single Phase Variac
CT Injection kit
11kV SWGR CURRENT TRANSFORMER TEST
4. Winding Resistance in ohms @ 75 °C (room temperature °C)
CTS1-S2 Ohms S1-S2 @ 75 °C
R S T R S T
T2-1
5P20
CL PX
T2-2
ZCT
5. Magnetizing Curve Test
T2-1
R S T
Current (mA) Voltage (V) Current (mA) Voltage (V) Current (mA) Voltage (V)
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
REPORT NO.:
PAGE: 3 OF 5
11kV MV SWGR TEST REPORT
DATE:
Ref No.: _____________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
MAKE / MODEL
Meg Ohm Meter
DC mA Ammeter
Single Phase Variac
CT Injection kit
11kV SWGR CURRENT TRANSFORMER TEST5P20
R S T
Current (mA) Voltage (V) Current (mA) Voltage (V) Current (mA) Voltage (V)
CL PX
R S T
Current (mA) Voltage (V) Current (mA) Voltage (V) Current (mA) Voltage (V)
T2-2
R S T
Current (mA) Voltage (V) Current (mA) Voltage (V) Current (mA) Voltage (V)
COMMENTS:
Accepted by Name Signature Date
HHIDOOSANFICHTNERDEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
SERIAL NUMBER
CALIBRATION DATE
REPORT NO.:
PAGE: 4 OF 5
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
DC mA Ammeter
CT Injection kit
11kV SWGR CURRENT TRANSFORMER TEST
6. Ratio Test
PhaseCurrent Measured at Secondary A
T2-1 5P20 CL PX
R
S
T
PhaseCurrent Measured at Secondary A
T2-2
R
S
T
COMMENTS:
Accepted by Name Signature DateHHIDOOSANFICHTNERDEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
Current Inejcted In Primary A
Current Inejcted In Primary A
REPORT NO.:
PAGE: 5 OF 5
11kV SWGR MV TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER: HHI
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
DC mA Ammeter
Single Phase Variac
CT Injection kit
11kV CT CIRCUIT LOOP RESISTANCE MEASUREMENT
7. Bus Bar Protection CT Circuit Loop Resistance (RL)
Phase Calculated RL at 75°C
R
S
T
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
Measured RL at Room Temp.( 24°C)
REPORT NO.:
PAGE: 1 OF 3
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
DC mA Ammeter
Single Phase Variac
CT Injection kit
11kV SGWR POTENTIAL TRANSFORMER TEST
1. Data
Phase R S T
Serial No.
Ratio
Class
Burden (VA)
2. Insulation Resistance Test: 500V DC (Result in Giga Ohm) for: 1 min. room temp. °C
Winding ConnectionsIR Value (Giga Ohms)
RemarksR S T
Primay - Ground
Secondary - Ground
Primary - Secondary
3. Polarity Test
PhasePolarity
Core-1
R
S
T
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
REPORT NO.:
PAGE: 2 OF 3
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
DC mA Ammeter
Single Phase Variac
CT Injection kit
11kV SWGR POTENTIAL TRANSFORMER TEST
4. Winding Resistance Measurement
Phase Primary Winding (KΩ)Secondary Winding
Core-1 (Ohm)
R
S
T
5. Voltage Ratio Test: Primary Injected Voltage : VAC 1 -Phase
VT Ratio=11,000/1.73/110/1.73
a-n Standard Ratio Measured Ratio Remarks
R 100
S 100
T 100
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
Applied Volt 1 - phase
Sec. Measured Voltage
REPORT NO.:
PAGE: 3 OF 3
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: SERIAL NUMBER
Meg Ohm Meter
DC mA Ammeter
Single Phase Variac
CT Injection kit
11kV SWGR POTENTIAL TRANSFORMER TEST
6. Magnetization current Measurement
Phase Magnetizing current in Primary Secondary Voltage
R
S
T
7. Zero sequence voltage measurement
Phase Magnetizing current
RS
ST
TR
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
Voltage Applied in Primary
Voltage Applied in Primary
Secondary Zero sequence Voltage (open delta)
REPORT NO.:
PAGE: 1 OF 11
11kV SWGR MV TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
Relay Test Unit
11kV SWGR MULTIFUNCTION RELAY
REF543 PROTECTION RELAY
SERIAL No. :
1. Visual checks
Conditions of Relay
Installation and wiring checking
Relay connected to local earth bar
Status Input
Relay Auxiliary supply
2.Insulation Resistance measurement on Control & Aux. circuits
IR value (500 V DC for 1 min ):
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
REPORT NO.:
PAGE: 2 OF 11
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
Relay Test Unit
Three Phase relay test kit
11kV SWGR MULTIFUNCTION RELAY
3.PROTECTION FUNCTIONS
1. DATA
1.1 REF543-Inputs
Input - Analog Type Ratio
CT
2. OVERCURRENT IDMT CHARACTERISTICS (51)
2.1 Settings
Main Setting Second Setting Setting Range
Iset / In 0.05….40.00 In
K 0.05….1.50
Curve Type NI,VI,EI,LI
Used Sensors 1….6
2.2. Check on Overcurrent IDMT Characteristic: Curve VI
Sl.No.Operating Time
2*Is 5*Is
1
2
3
3. EARTH FAULT IDMT CHARACTERISTIC (51N)
2.1 Settings
Main Setting Second Setting Setting Range
Iset / In 0.05….40.00 In
K 0.05….1.50
Curve Type NI,VI,EI,LI
Used Sensors 1….6
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
Pick up Current A
Drop off Current A
TMS Setting
REPORT NO.:
PAGE: 3 OF 11
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
Relay Test Unit
Three Phase relay test kit
11kV SWGR MULTIFUNCTION RELAY
b. Check on Earthfault IDMT Characteristic: Curve NI
Sl.No.Operating Time
2*Is 5*Is
1
4. CB TRIP, SIGNALING
CB Trip OK: Signaling OK
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
Pick up Current A
Drop off Current A
TMS Setting
REPORT NO.:
PAGE: 4 OF 11
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
Relay Test Unit
Three Phase relay test kit
11kV SWGR MULTIFUNCTION RELAY
3.PROTECTION FUNCTIONS
SERIAL No.
1. DATA
1.1 SPAU 140C
Input - Analog Type Ratio
2. RESTRICTED EARTH-FAULT CURRENT (87B-R)
2.1 Settings
Main Setting Second Setting Setting Range
Iset / In 0.5 … 5 % In
Time 35 msec
2.2. Measurement
Pick up Current Drop Off Tripping Time
1
3. RESTRICTED EARTH-FAULT CURRENT (87B-S)
3.1 Settings
Main Setting Second Setting Setting Range
Iset / In 0.5….5% In
Time 35 msec
3.2 Measurement
Pick up Current Drop Off Tripping Time
1 0.042
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
REPORT NO.:
PAGE: 5 OF 11
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
Relay Test Unit
Three Phase relay test kit
11kV SWGR MULTIFUNCTION RELAY
4. RESTRICTED EARTH-FAULT CURRENT (87B-T)
4.1 Settings
Main Setting Second Setting Setting Range
Iset/ In 0.5…5% In
Time 35 msec
4.2 Measurement
Pick up Current Drop Off Tripping Time
5. UNDER VOLTAGE LOW SET PROTECTION U< (27)
5.1 Settings
Main Setting Second Setting Setting Range
Start Value 0.1 …. 1.2 Un
Time 40 …..300000 msec
5.2. Measurements
Pick up Voltage V Drop Off Voltage V
1
6. CB TRIP, SIGNALING
CB TRIP OK SIGNALING OK
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
Time at rated Voltage (msec)
REPORT NO.:
PAGE: 6 OF 11
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER CALIBRATION DATE
Meg Ohm Meter
Relay Test Unit
Three Phase relay test kit
11kV SWGR MULTIFUNCTION RELAY
4.Mechanical Functional Test
Earth Switch Circuit Breaker Lock Lever KeyResults Status
Closed Open Closed Open Open Close
1 1 1 1
1 1 1 1
1 1 1 1
1 1 1 1 CB Insertion Possible
1 1 1 1
1 1 1 1
1 1 1 1
1 intermediate 1
1 1 1 1
1 1 1 1
1 _ _ _ _ _ _
1 _ _ _ _ _ _
Note: Everytime CB is moved to rack in or rack out position, rack in / out key turn and hold to Anticlockwise (30 deg)
COMMENTS:
Accepted by Name Signature Date
DOOSAN
EMPLOYER/ENGINEER
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
Service Position
Test Position
CB Insertion not Possible
CB Insertion not Possible
CB Insertion not Possible
CB Disconnection not Possible
CB Disconnection not Possible
CB Disconnection Possible
CB Closing Not Possible
CB Door Not Posible Open
CB Door Not Posible Open
Cable comp Door not posible to close
Cable comp Door not posible to open
REPORT NO.:
PAGE: 7 OF 11
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
Relay Test Unit
Three Phase relay test kit
11kV SWGR MULTIFUNCTION RELAY
5.Electrical Functional Test
(i) SS1 Local/ Remote Control Key in Remote
Circuit BreakerAction Results Status
Closed Open
1 1 Local Closing CB Not Closed
1 1 Local Closing CB Opened
1 1 Remote Closing CB Closed
1 1 Remote Opening CB Opened
1 1 Local Closing CB Not Closed
1 1 Local Opening CB Opened
1 1 CB Opened
1 1 Remote Closing CB Closed
1 1 Remote Opening CB Opened
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
Service Position
Test Position
Emergency Opening
REPORT NO.:
PAGE: 8 OF 11
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
Relay Test Unit
Three Phase relay test kit
11kV SWGR MULTIFUNCTION RELAY
(ii) SS1 Local/ Remote Control Key in Local (A Type)
Circuit BreakerAction Result Status
Test Service Closed Opened
1 1 Local Closing CB Closed
1 1 Local Opening CB Opened
1 1 Remote Closing CB Not Closed
1 1 Remote Opening CB Opened
1 1 Local Closing CB Closed
1 1 Local Opening CB Opened
1 1 CB Opened
1 1 Remote Closing CB Not Closed
1 1 Remote Opening CB Opened
Note: REF Key in No Control mode bay control no action
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
Emergency Opening
REPORT NO.:
PAGE: 9 OF 11
11kV MV SWGR TEST REPORTDATE: ______________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL
Meg Ohm Meter
Relay Test Unit
Three Phase relay test kit
11kV SWGR MULTIFUNCTION RELAY
6. LED Checking
FUNCTION OF SIGNALLING LEDs
NR DESCRIPTION OFF GREEN YELLOW RED STATUS
READY Internal self test FAULT NORM _ _
ALARM LOCK ( 86 ) NORM _ _ TRIP
INTERLOCKS ERROR
1 ARC FAULT CABLE ZONE _ NORM _ TRIP
2 ARC FAULT C.B ZONE _ NORM _ TRIP
3 ARC FAULT BUS ZONE _ NORM _ TRIP
4 C.B SPRING CHARGED _ CHARGED DISCHAR _
5 C.B TRIP COIL _ NORM FAULT _
6 REF 543 PROT _ OK OFF
7 87B/ ARC NORM TRIP
8 Alarm page 1 of 3/see > page2 _
page 3
1 51 NORM _ _ TRIP
2 51N NORM _ _ TRIP
3 27 NORM _ _ TRIP
4 VT fuse
5 MCB
6 VENT
7 87B A /ARC
8 Alarm page 2 of 3/see > page1
page 3
1 PROT. GTG TR
3 Alarm page 3 of 3 /see page 1
page 2
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
SERIAL NUMBER
CALIBRATION DATE
DEWA
REPORT NO.:
PAGE: 10 OF 11
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
Relay Test Unit
Three Phase relay test kit
11kV SWGR MULTIFUNCTION RELAY
7. Binary Input
Binary Input Initiating Device Result
BI01 CB On
BI02 CB Off
BI03 CB test Position
BI04 CB service Position
BI05 Earting Switch off
BI06 Earting Switch On
BI07 Trip Coil Supervision Alarm
BI08 Watchdog
BI09 Arc Fault
BI10 Protection Trip
BI11 Selector switch remote
BI12 CB tripped Arc F50/51,F87B & CB Open
BI13 Spare
BI14 Protection Activated (F50/51,F87B& Arc)
BI15 ARC fault Control Compartment
BI16 ARC fault Main Bus Compartment
BI17 ARC fault C.B. Compartment
BI18 ARC fault Cable Compartment
BI19 F27/59 Protection Trip
BI20 F87B Protection Trip
BI21 Protection Activated
BI22 MCB Trip & No Control Voltage
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
REPORT NO.:
PAGE: 11 OF 11
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE / MODEL SERIAL NUMBER
Meg Ohm Meter
Relay Test Unit
Three Phase relay test kit
11kV SWGR MULTIFUNCTION RELAY
8. Binary Output (A Type)
Binary Output Initiating Device Result
BO01 Closing QC
BO02 Opening QO
BO03 Prot trip (86)
BO04 Cubicle remote position
BO05 Spare
BO06 CB Tripped
BO07 Group alarm control MCB trip
BO08 Aux. Supply On
BO09 ARC Fault
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
CALIBRATION DATE
REPORT NO.:
PAGE : 1 OF 1
11kV MV SWGR TEST REPORT
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE/MODEL
Relay Test Unit
11kV SWGR SYNCHRO CHECK RELAY
SYNCHRO CHECK RELAY SPAU140 C
SERIAL No. :
1. Visual checks
Conditions of Relay
Installation and wiring checking
Status Input
Relay Auxiliary supply
2.Relay Test
Voltage applied in terminal Voltage applied in terminal Close Permissive
Voltage Degree Hz Voltage Degree Hz Ok Not Ok
High
Low
COMMENTS:
Accepted by Name Signature Date
HHI
DOOSAN
FICHTNER
DEWA
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
SERIAL NUMBER
CALIBRATION DATE
Relay Test connected to local earth bar
Relay check at extreme limit of voltage
REPORT NO.:
PAGE : 1 OF 4
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE/MODEL
Digital Multimeter
Primary Current Injection Test
11kV SWGR - CALIBRATION OF METERS & TRANSDUCERS
CT Ratio: Input:
Aux. Supply: Range:
1. Calibration of Ammeter
Data of Ammeter:
Sl.No. Phase % Error
1 R
2 R
3 R
4 R
5 S
6 S
7 S
8 S
9 T
10 T
11 T
12 T
COMMENTS:
Accepted by Name Signature Date
DOOSAN
EMPLOYER/ENGINEER
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
11kV MV SWGR TEST REPORT
SERIAL NUMBER
CALIBRATION DATE
Current injected A
Ammeter reading
Calculated AMP
REPORT NO.:
PAGE : 2 OF 4
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE/MODEL
Digital Multimeter
Primary Current Injection Test
11kV SWGR - CALIBRATION OF METERS & TRANSDUCERS
2.Calibration of Voltmeter
VT Ratio: Input:
Aux.Supply: Output range:
Data:
Sl.No. Phase Voltage applied V % Error
1 R
2 R
3 R
4 R
5 S
6 S
7 S
8 S
9 T
10 T
11 T
12 T
3. Calibration of Energymeter Input: Aux. Supply:
CT Ratio: VT Ratio: Output:
Sl.No. PF Calculated KWH % Error
1
2
3
COMMENTS:
Accepted by Name Signature Date
DOOSAN
EMPLOYER/ENGINEER
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
11kV MV SWGR TEST REPORT
SERIAL NUMBER
CALIBRATION DATE
Voltmeter reading
Calculated voltage
Voltage applied
V
Current injected
A
Test Duration
Registered KWH
REPORT NO.:
PAGE : 3 OF 4
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE/MODEL
Digital Multimeter
Primary Current Injection Test
11kV SWGR - CALIBRATION OF METERS & TRANSDUCERS
1. Calibration of Ammeter Transducer
DATA:
CT Ratio: Input:
Aux. Supply: Output:
Sl.No. Phase % Error
1 R
2 R
3 R
4 R
5 S
6 S
7 S
8 S
9 T
10 T
11 T
12 T
COMMENTS:
Accepted by Name Signature Date
DOOSAN
EMPLOYER/ENGINEER
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
11kV MV SWGR TEST REPORT
SERIAL NUMBER
CALIBRATION DATE
Current injected A
Transducer output mA
Calculated output mA
REPORT NO.:
PAGE : 4 OF 4
DATE: ___________________
Ref No.: __________________
LOCATION / AREA : DRAWING NO :
KKS NO : MAKER:
TEST INSTRUMENT: MAKE/MODEL
Digital Multimeter
Primary Current Injection Test
11kV SWGR - CALIBRATION OF METERS & TRANSDUCERS
2.Calibration of Voltmeter Transducer
DATA:
VT RatioInput: Aux. Power supply:Output:
Sl.No. Phase % Error
1 R
2 R
3 R
4 R
5 S
6 S
7 S
8 S
9 T
10 T
11 T
12 T
3. Calibration of Watt Transducer
DATA: INPUT: Volts (V): OUTPUT: VT Ratio
Ampere (I): CT Ratio: Aux. Supply
Sl.No. PF % Error
1
2
3
COMMENTS:
Accepted by Name Signature Date
DOOSAN
EMPLOYER/ENGINEER
DUBAI ELECTRICITY & WATER AUTHORITYJEBEL ALI POWER AND DESALINATION STATION 'M'
Contract No. : CNE/001/2006
11kV MV SWGR TEST REPORT
SERIAL NUMBER
CALIBRATION DATE
Voltage applied V
Transducer output mA
Calculated output mA
Voltage applied V
Current injected
A
Transducer output mA
Calculated output mA