12 environmental impact statement 12.1 … resources management kangra coal (pty) ltd. 12-1 12...
TRANSCRIPT
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-1
12 ENVIRONMENTAL IMPACT STATEMENT
12.1 INTRODUCTION
Kangra Coal intends to extend the current operations under the 2014
Consolidated EMPr. This Chapter describes the key findings of the EIA and
summarises the positive and negative impacts and risks associated with the
following activities:
The development of the Central Discard Dump at Maquasa East
operations;
The mining of the MWE underground works (portion of the Maquasa
West Extension omitted activities from the current 2014 Consolidated
EMPr);
The development of Adit 5 to access the MWE underground workings;
and
The development of an overland conveyor and service road connecting
Adit 5 with the existing Maquasa West operational area.
12.2 SUMMARY OF IMPACTS IDENTIFIED AND ASSESSED
The following sections present a brief summary of the impacts identified and
assessed in Chapter 7. In accordance with Appendix 3, condition 3 (l) of the
EIA Regulations, December 2014, the final site map has been included below
(Figure 12.1). This map superimposes the proposed activities on the
environmental sensitivities of the site.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-2
Figure 12.1 Final Site Map
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-3
12.2.1 Central Discard Dump
A summary of the potential impacts associated with the construction,
operation and decommissioning of the central Discard Dump is presented in
Table 12.1.
Most of the environmental disturbances are expected to occur during the
construction phase when vegetation clearance, topsoil removal, excavations
and construction will take place. The most significant impacts (medium to
high) are associated with the vegetation removal; exposure of soils to the risk
of erosion and uncontrolled impact from the site. These impacts include the
siltation and contamination of the Egude River and associated wetland, as
well as the erosion within the footprint area.
Geology: No impact is expected on the geology of the site.
Topography: In the context of the surrounding mine area, the impact on
the topography of the site is not considered to be of great significance and
rehabilitation is expected to occur in accordance with the approvals
received in order to ensure the site is in line with the planned end land use
of the MRA.
Soils, Land Use and Land Capability: The potential impacts to the soil,
land use and land capability are not considered to be a fatal flaw to the
proposed project, largely because the intention for this proposed project is
that the facility be adequately lined. The proposed Discard Dump is
located adjacent to a rehabilitated opencast pit, within the MRA, which
precludes the use of this land for any other purposes during the LoM.
Therefore, while soil compaction and a change in land use have been
identified as permanent changes to the soils on this site, these are not
considered to be fatal flaws to the development.
Terrestrial Ecology: During the impact assessment, the following
conclusions were reached:
o Impacts during the construction phase were considered to be
medium to low after mitigation.
o During the operational phase, impacts were considered to be
medium to low after mitigation.
o Post closure activities were considered to have a positive impact on
the vegetation, after mitigation.
o During the decommissioning phase, impacts were considered to be
low after mitigation.
o Impacts at a regional scale were considered to be low after
mitigation.
Based on the results obtained during the survey, there is no reason why
the development of the proposed Discard Dump, cannot commence.
Avifauna: The main identified impacts for the site on the avifaunal
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-4
community are during the construction and operational phases. The
closure and post closure phases through appropriate rehabilitation are
generally associated with lower impacts. During the construction phase
the impacts are expected to be moderate. These impacts are generally
reduced through the mitigation measures. However due to the nature of
construction most still remain as moderate impacts.
If all mitigation and action plans are followed the overall impact will be
limited to moderate or low. Appropriate measures for rehabilitation post –
closure need to be followed to ensure low levels of impacts associated with
the area.
Wetland and Aquatic Environment: The wetland unit delineated has
already been modified; however, further contamination during the life of
the facility will further degrade the wetland ecosystem. The aquatic
habitat is still in a generally good state, but face potential degradation due
to the development. However, based on the results presented in the
Wetland and Aquatic Assessment the proposed development will not
have a detrimental effect on these systems if all the mitigation measures
recommended are adhered to. Furthermore, the implementation of a
Wetland Rehabilitation Plan compiled by a qualified wetland specialist
may improve the wetland conditions in the long term.
Surface Water: Although the proposed Discard Dump is located within
100m of the Egude River, this is not considered to be a fatal flaw. The
development may safely proceed, provided that the liner system (after
approval of the design by the DWS) and detailed stormwater management
plan are implemented. Furthermore, all mitigation measures
recommended in this document, the EA and IWUL (once issued) should
be adhered to.
Groundwater: No fatal flaws were identified during the groundwater
assessment. The potential groundwater quality and quantity impacts
associated with the proposed Discard Dump and PCD is countered by the
fact that the facilities will be designed to mitigate all adverse
environmental impacts on groundwater resources (i.e. liner system,
concurrent rehabilitation methodology). The environmental impact
significance rating is expected to reduce to a low significance.
Heritage and Archaeology: No sites of heritage or archaeological
significance were encountered, therefore no impacts are anticipated.
Noise: The location of the proposed development within the existing MRA
means that the noise to be created is not expected to be above the current
ambient noise levels. The noise impacts are therefore considered to be of
low significance and do not represent a major environmental issue for the
proposed development.
Visual: The proposed Discard Dump is not located within the viewshed of
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-5
any residential or rural areas, or major roads. The location of the site close
to the existing mining and mining related activities also means that there
will be a limited impact on the character of the overall area.
Air Quality: The air quality impacts are limited to dust creation, which
can be managed through the implementation of the mitigation measures
recommended in this report. These impacts do not represent a major
environmental issue for the proposed development.
Socio-economic: The proposed Discard Dump is expected to have a
limited negative impact on the nearby Driefontein community in terms of
the nuisance impacts created, such as noise and dust. Furthermore, the
development will accommodate for the expansion and continuation of
Kangra’s mining operations in the area, which will allow for the
preservation of jobs in the long term and the implementation of Kangra’s
SLP. The net impact on the socio-economic environment is therefore
positive.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-6
Table 12.1 Summary of Potential Impacts: Central Discard Dump
Impact Description Construction Phase Operational Phase Decommissioning Phase
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Topography
Change to natural topography M L H H
Improvement to topography M (+) M (+)
Soils, Land Use and Land Capability
Soil Erosion M L M L
Soil Compaction L M M L M L
Soil Contamination M L M L L L
Loss of Land Capability H M
Change in Land Use H H
Acidification of soils overlying
carbonaceous horizon
M L
Improvement of soil conditions over
time
M (+) M (+)
Terrestrial Biodiversity
Loss of flora species of conservation
importance
L L
Displacement of fauna species,
human-animal conflicts & interactions
M L M L
Loss of ecological connectivity and
ecosystem functioning
M L
Loss of fauna species of conservation
importance
L L
Indirect impacts on surrounding
habitats
M L
Indirect impacts to surrounding plant
and animal communities
(fragmentation)
M L
Increase in alien vegetation M L
Improvement in vegetation M (+) M (+)
Avifauna
Avifauna species identified as
common residents
L L
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-7
Impact Description Construction Phase Operational Phase Decommissioning Phase
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Avifauna species identified as fairly
common residents
M L
Avifauna species identified as
uncommon residents
M M
Avifauna species identified as
migratory
M M M L
IUCN listed avifaunal species H M
Loss of habitat suitable for IUCN or
uncommon species
H M
Loss of unique or protected habitat
types (including loss and
degradation)
M M
Loss of nesting site for breeding
species
M M
Loss of ecological connectivity and
ecosystem functioning
M L M L
Indirect impacts on surrounding
habitats
M L M L
Impacts on water and riparian habitat M L H (+) H (+)
Degradation of the rehabilitated area H L
Rehabilitation of the wetland and
associated riparian zones
H (+) H (+)
Wetland and Aquatic Environment
Increased sediment transport into
down slope water resources
M M M M
Altered runoff characteristics of the
landscape
M M M M
Erosion within watercourses M L M L M M
Water quality deterioration M M H M
Increase in alien vegetation M M
Improvement to riparian zones L (+) L (+)
Surface Water
Siltation of surface water resources
and associated soil erosion
H L M L H L
Reduced runoff to surface water
resources
H L M L
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-8
Impact Description Construction Phase Operational Phase Decommissioning Phase
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Increased runoff to surface water
resources due to surface compaction
H L
Surface water contamination M M M M M L
Deterioration of surface water quality
– Discard Dump Footprint H M
Deterioration of surface water quality
– PCD H L
Improvement to surface water quality M (+) M (+)
Groundwater
Groundwater quantity: reduction of
recharge from site preparation
L L M L
Groundwater quantity: reduction
from use of liners
L L L L
Groundwater quantity: reduction of
recharge from compaction of soils
L L
Groundwater quality: deterioration –
PCD
M M M M
Groundwater quality: deterioration –
Discard Dump
M M M L M L
Air Quality
Dust creation M L M L M L
Release of fugitive dust from exposed
discard material
M L
Noise
Noise creation M L M L L L
Visual
Change to aesthetics of the landscape L L
Poor visibility due to dust creation L L M L
Visual impact of discard dump M M
Light pollution M M
Improvement of landscape
appearance
M (+) M (+)
Socio-Economic
Creation of temporary employment L (+) L (+)
Nuisance caused by dust & noise
creation
L L L L
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-9
Impact Description Construction Phase Operational Phase Decommissioning Phase
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Maintenance of long term
employment
M (+) M (+)
Reduction of nuisances such as noise
and dust
L (+) L (+)
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-10
12.2.2 Maquasa West Extension Underground Works
The MWE underground works are an extension of existing mining operations,
and as such there will be no construction phase and therefore only impacts
associated with the operational and decommissioning phases are presented in
Table 12.2.
Surface Water: Impacts on surface water quality due to contaminated
decant from baseflow outlets (wetlands) and springs during the
decommissioning phase will be Medium prior to mitigation.
Groundwater: Impacts to groundwater include:
o Reduction in groundwater baseflow to the Kransbank Wetland due
to mine dewatering. Bord and pillar mining will have a Low
impact on fountains and therefore streams in the long term with
mitigation.
o Impact on groundwater quality due to contaminated mine water:
the mine water will decrease in quality as the materials in and
adjacent to the mining horizon has high pyrite content. Poor
quality mine water will have a Medium impact on the
groundwater quality in the long term if mine water is introduced
into the environment through decant.
Socio-economic: The development will accommodate for the expansion
and continuation of Kangra Coal’s mining operations in the area, which
will allow for the preservation of jobs in the long term and the
implementation of Kangra’s SLP. The net impact on the socio-economic
environment is therefore positive.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-11
Table 12.2 Summary of Potential Impacts: MWE Underground Works
Impact Description Operational Phase Decommissioning Phase
Significance before
Mitigation
Significance after
Mitigation
Significance before
Mitigation
Significance after
Mitigation
Geology
Impacts on geology associated with underground
mining activities
L L
Surface Water
Impacts on surface water quality due to
contaminated decant from baseflow outlets
(wetlands) and springs
M L
Groundwater
Reduction in groundwater baseflow to the
Kransbank Wetland due to mine dewatering
L L
Impact on groundwater quality due to
contaminated mine water
M L
Socio-Economic
Job retention and employment opportunities H (+) H (+)
Loss of jobs due to cessation of underground
mining activities
H M
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-12
12.2.3 Adit 5 and Overland Conveyor
A summary of the potential impacts associated with the construction,
operation and decommissioning of Adit 5 and the overland conveyor is
presented in Table 12.3.
Most of the environmental disturbances are expected to occur during the
construction phase when vegetation clearance, topsoil removal, excavations
and construction will take place. The most significant impacts (medium to
high) are associated with the vegetation removal; exposure of soils to the risk
of erosion and uncontrolled impact from the site.
Geology: No impact is expected on the geology of the site.
Topography: No impact is expected on the topography of the site
Soils, Land Use and Land Capability: The potential impacts to the soil,
land use and land capability are not considered to be a fatal flaw to the
proposed project, largely because the following embedded controls will be
included in project design:
o Project footprint to be minimized to limit surface disturbance;
o Existing roads to access the site to be used where possible;
o Drainage control measures and culverts to control natural runoff
and overland flow to be used;
o Topsoil stripping, stockpiling and management will be planned
prior to ground disturbance works commencing to establish the
volume of soil to be stripped and areas where it will be stockpiled;
and
o Construction of conveyor line will be done in a way to minimise
surface disturbance.
Terrestrial Biodiversity: Impacts on terrestrial ecosystems are only
associated with the construction phase and include the loss of
conservation important floral species and the sensory disturbance and
displacement of fauna. These impacts were considered to be Low after
mitigation.
Wetland and Aquatic Environment: Three distinct wetland types were
identified as being associated with the proposed main adit and overland
conveyor, namely: Channelled Valley Bottom Wetlands; Unchannelled
Valley Bottom Wetlands; and Hillslope Seepage Wetlands. It is unlikely
that surface water flows will be affected to any degree by the proposed
Main Adit. Although the adit will overlie one spring, and be directly
adjacent to another, these systems do not contribute a large amount of
surface flow to the Kransbank wetland. Reduced surface run-off resulting
from the capturing of surface water runoff from surface infrastructure can
be mitigated by the construction of clean- and dirty-water separators to
allow clean water to reach streams, and by minimising unnecessary
retarding of surface water recharge.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-13
Groundwater: No fatal flaws were identified during the groundwater
assessment. Groundwater levels are unlikely to be affected by surface
infrastructure developed as part of Adit 5.
Heritage and Archaeology: The burial ground containing at least 12
graves, reportedly associated with an Ngwenya family, lies within the
proposed footprint of Adit 5. As these burial grounds fall within the
footprint of Adit 5, the impact will be a High significance prior to
mitigation and will require relocation in accordance with Section 36 of the
National Heritage Resources Act (Act 25 of 1999), Regulations 33 -35.
Noise: The location of the proposed Adit 5 and overland conveyor within
the existing MRA means that the noise to be created is not expected to be
above the current ambient noise levels. The noise impacts are therefore
considered to be of low significance and do not represent a major
environmental issue for the proposed development.
Visual: The location of Adit 5 and the overland conveyor close to the
existing mining and related activities means that there will be a Low
impact on the character of the overall area.
Air Quality: The air quality impacts are limited to dust creation, which
can be managed through the implementation of the mitigation measures
recommended in this report. These impacts do not represent a major
environmental issue for the proposed development and would vary
substantially from day to day depending on the level of activity, the
specific operations, and the prevailing meteorological conditions.
Socio-economic: The development will accommodate for the expansion
and continuation of Kangra Coal’s mining operations in the area, which
will allow for the preservation of jobs in the long term and the
implementation of Kangra’s SLP. The net impact on the socio-economic
environment is therefore positive.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-14
Table 12.3 Summary of Potential Impacts: Adit 5 and Overland Conveyor
Impact Description Construction Phase Operational Phase Decommissioning Phase
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Soils, Land Use and Land Capability
Soil erosion M L M L M L
Soil compaction M M M M M M
Loss and sterilisation of fertile topsoil
layer
L L
Chemical soil pollution M L M L M L
Loss of current land capability L L L L L L
Change of land use M L M L
Terrestrial Biodiversity
Loss of Conservation Important Floral
Species
H L
Sensory disturbance and
displacement of fauna
L L
Wetland and Aquatic Environment
Increased sediment movement M L
Confinement of longitudinal flow H M
Loss and disturbance of wetland
habitat
H M
Habitat fragmentation M L
Reduced water quality from point
source discharges
M L
Reduced water quality from erosion
from point source
M L
Reduced water quality due to surface
exposure of acid generating materials
at Adit 5
M L
Surface Water
Surface water quality M L M L M L
Air Quality
Dust generation M L M L M L
Noise
Generation of noise M L M L L L
Visual
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-15
Impact Description Construction Phase Operational Phase Decommissioning Phase
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Significance
before Mitigation
Significance after
Mitigation
Impacts to the landscape and visual
environment
L L L L L L
Heritage
Burial grounds and graves H L
Exposed natural geological features L L
Socio-Economic
Creation of employment
opportunities
M M
Procurement and spending in local
economy
M M
Physical displacement H M
Economic displacement M L
Community health and safety M L
Increased pressure on social
infrastructure
M L
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-16
12.2.4 Cumulative Impacts
The preceding impact assessments assessed the impacts associated with the
Project largely in isolation. A cumulative impact is one that arises from an
impact associated with a proposed Project, that when viewed in isolation may
be acceptable, but when combined with multiple developments in the greater
area affected by the proposal may not be acceptable. A summary of the
cumulative impacts is presented in Table 12.4.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-17
Table 12.4 Summary of Potential Cumulative Impacts
Impact Description Significance before Mitigation Significance after Mitigation
Topography
Change in topographical characteristics of the site M L
Change to topography of MRA H L
Groundwater
Potential groundwater contamination risk (ore stockpiles at plant) M L
Potential groundwater contamination risk (contaminant soil) M L
Continued groundwater contamination M M
Contaminated groundwater reaching surface water, impact nearby
groundwater and surface water
M M
Potential groundwater contamination risk (overburden dump) L L
High sulphate containing water may form and water quality may continue to
deteriorate
H M
Water decanting from operations will be high in SO4 and TDS – forming AMD H M
Reduction in groundwater quantity M M
Degradation of groundwater quality (discard dump and PCD) M M
Soils, Land Use and Land Capability
Loss of arable land capability H M
Soil erosion M L
Soil compaction H M
Loss of land capability H M
Change in land use H H
Terrestrial Biodiversity
Increase in local & regional fragmentation / isolation of habitat M L
Increase in environmental degradation, pollution of air, soils and water M L
Loss of fauna and flora of conservation importance M L
Further fragmentation of vegetation communities and habitats M L
Harm to animals and plants and introduction of invasive plant species M L
Loss of resident avifaunal species L L
Loss of migratory avifaunal species M L
Loss of Conservation Important species H M
Fragmentation of vegetation communities and habitats M L
Introduction of invasive plant species and loss of nesting sites M L
Loss of wetland and riparian habitat and decrease in water quality M L
Wetland and Aquatic Environment
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-18
Impact Description Significance before Mitigation Significance after Mitigation
Decline in habitats and biota M L
Increased sedimentation M L
Surface Water
Erosion, siltation and hydrocarbon contamination of surface water resources M M
Overall reduction in clean water runoff M L
Degradation of water quality within the downstream surface water resource
(Egude River and Heyshope Dam)
M M
Air Quality
Increase in ambient PM10 levels M M
Degradation of air quality within the mining area and immediate surrounds M L
Noise
Increase in environmental degradation and pollution M M
Additional noise impacts M M
Traffic
Increase in traffic volumes M L
Traffic safety issues M L
Visual
Change to aesthetics of the landscape M M
Socio-Economic
Disruption and nuisance factors associated with decommissioning (noise,
visual and traffic impacts)
M M
Job losses due to mine closure H M
Population changes and “out flux” of people from the area M M
Safety and security risks M M
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-19
12.3 RECOMMENDATIONS
Based on the detailed impact assessment undertaken and the proposed
mitigation and management measures, the EAP is of the opinion that the
proposed amendment of the Kangra Coal Consolidated EMPr (MP
30/5/1/2/2/133MR) for the proposed expansion into the MWE area, the
construction of the Adit 5, overland conveyor and servitude road and the new
discard dump should be granted Environmental Authorisation (EA). The EA
should be granted provided Kangra Coal adheres to the management and
mitigation measures proposed. The EAP recommends that the following
should be made conditions of the EA:
Central Discard Dump
Surface water: It is recommended that the monitoring points identified in
Section 9.1 (GCS, 2016) are included in the monitoring programme to
establish the baseline conditions of the affected reach of the Egude River
prior to the establishment of the proposed Discard Dump.
Groundwater: It is recommended that a numerical model is constructed,
during the operational phase of the proposed Discard Dump. This model
should be updated using the groundwater monitoring data collected to
assist in closure planning objectives and management plans.
Aquatic environment: There is currently no biomonitoring programme in
place within the vicinity of the proposed Discard Dump. It is
recommended that a programme is established prior to construction in
order to establish the baseline conditions of the affected watercourse.
Aquatic biomonitoring surveys of the aquatic invertebrate community
(SASS5) should be undertaken on a biannual basis.
MWE Underground Works
Groundwater:
o The potential interaction of the flooded underground workings on
the local groundwater systems, many decades after mine closure,
should be investigated further in terms of:
Mine water quality.
Preferential flow along coal seam outcrops.
Potential for contaminant movement in the local aquifers.
o Soon after the commencement of mining, high risk areas should be
identified where the flooded underground will have the highest
potential to impact the local surface water regime (e.g. mining close
to the mountain side and/or at shallow depths). A cost-benefit
analysis should be performed to determine if such areas can be
excluded from the mine plan.
o After the cessation of mining, the proposed Adit 5, should be sealed,
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-20
based on engineering and hydrogeological considerations.
Adit 5 and Overland Conveyor
Air Quality: Fine particulates (specifically PM10) and ambient dustfall
monitoring should commence during the construction phase and continue
throughout the life of the project.
Surface and Groundwater: monitoring every quarter to determine
compliance with site specific Water Quality Objectives (WQO).
Noise: Noise complaints received during construction and operation are to
be addressed through the formal grievance mechanism. If a complaint is
received, it will be tested and verified by an independent noise specialist.
Should the complaint be valid according to acceptable limits as per best
practice guidelines, then Kangra Coal will design and implement a
localised mitigation measure to abate the noise impact and will follow up
the implementation of the mitigation measure with monitoring to confirm
its efficacy.
Terrestrial Biodiversity: Floral species search and rescue - all footprint
areas approved for development will be resurveyed in detail by a qualified
botanist with appropriate field experience and locations of all conservation
important species identified for transplanting recorded and visually
marked. The designated Environmental Officer should be included in the
search. Protected Species will require permits for removal. e.g. Eucomis
autumnalis can be successfully relocated to surrounding areas.
Heritage and Archaeology: Relocation of burial grounds and graves must
be in accordance with the National Heritage Resources Act (Act 25 of
1999).
Socio-Economic:
o Development of a project specific Recruitment Policy in accordance
with the Employment Equity Act (Act 55 of 1998), Basic Conditions of
Employment Act, 1997 and The Broad-based Socio-economic
empowerment Charter for the South Africa Mining and Minerals
Industry, 2010.
o Development and implementation of a Resettlement Action Plan and
Livelihood Restoration Plan for those households requiring
resettlement.
Kangra Coal will establish a “Grassland and Wetland Rehabilitation
Fund” (GWRF) for the exclusive purpose of “Additional Conservation
Actions” (ACA’s), in particular to rehabilitate the wetlands within the
impact zone of the Eastern Highveld Grasslands habitat. The GWRF will
be established under the following conditions:
o The GWRF will be to a value of ZAR 6,000,000 (Six million South
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-21
African Rand);
o The GWRF will be established at the same time as the start of
construction of the main adit and the overland conveyor;
o Funds from GWRF will be used exclusively for planning and
implementation of biodiversity rehabilitation with a focus on
rehabilitation of grassland and wetland habitats;
o The GWRF will be used exclusively for the area as delineated in
Annex 12A: “Kangra Coal GWRF Rehabilitation Area”;
o Activities that will be funded by the GWRF will include:
Removal of alien vegetation, particularly within water courses;
and
Rehabilitation of wetlands within the Eastern Highveld
Grassland Ecosystem.
o Due consideration will be given to the loss of a source of fuelwood
used by the affected local people (due to alien vegetation removal)
and provision of a suitable substitute or replacement;
o The GWRF will not be used for standard mitigation and
rehabilitation actions associated with the direct impacts of the
construction of the main adit and overland conveyor or other
rehabilitation and mitigation measures already committed to by
Kangra Coal in existing permits or pending permit applications; and
o Implementation of rehabilitation actions funded by the GWRF will
commence one year after the completion of the construction of the
main adit and overland conveyor.
Given that this is a response to a cumulative impact, the proposed GWRF
may be referred to in other applications proposed by Kangra Coal. It
should be noted that Kangra Coal proposes a single fund to the value of
ZAR 6,000,000.
12.4 CONCLUSION
The aim of the inclusion of the proposed expansion of the current operations
under the 2014 Consolidated EMPr is to provide information to inform
decision-making that will contribute to environmentally sound and
sustainable development. This report is to be submitted to the MDMR to
provide information and an independent assessment, thus enabling the
MDMR to make an accountable and properly informed decision regarding
whether or not to grant approval of the amended EMPr in terms of Section 102
of the MPRDA.
This report will also assist the MDMR to define under what conditions the
development should go ahead if authorisation is granted. In considering the
expansion of the current operations, it is inevitable that there will be certain
negative environmental impacts. However, these have largely been mitigated
and should be viewed along with the fact that new resources are required to
maintain the current levels of production and employment. Should the mining
operations close, jobs will be lost, both directly at the mine and indirectly in
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
12-22
terms of local contractors and businesses providing goods and services to the
operation, as well as the people dependent on those working for Kangra Coal
(both directly and indirectly).