12030-20/site c brian murphy, executive project director ... · section 4 - project description...
TRANSCRIPT
Ministry of Forests, Lands and Natural Resource Operations
Regional Operations North Area
Mailing Address: PO BOX 9352 Stn Prov Govt Victoria, BC V8W 9M1
Tel: 250-952-0596 Fax: 250-356-2150 Website: www.gov.bc.ca/for
12030-20/SITE C April 4, 2013
Brian Murphy, Executive Project Director Environmental Assessment Office Linda Jones, Panel Manager Canadian Environmental Assessment Agency By email: [email protected] [email protected] Dear Mr. Murphy and Ms. Jones: RE: Proposed Site C Clean Energy Project Environmental Impact Statement (EIS) Review
Thank you for the opportunity to comment on the EIS for the proposed Site C Clean Energy Project. The following package represents the collated comments of the BC Provincial Government Natural Resource Sector (NRS) Agencies, which are comprised of the Ministry of Environment, the Ministry of Aboriginal Relations and Reconciliation, the Ministry of Energy, Mines and Natural Gas, the Ministry of Agriculture, and the Ministry of Forests, Lands and Natural Resource Operations and all of the associated divisions within these agencies that participated in this review. The BC Ministry of Transportation and Infrastructure has also provided comments to be submitted with the NRS agencies as part of this review. It should also be noted that our review has been focused on the sections and Valued Component’s (VC’s) relevant to the mandates of our various ministries. BC Hydro has completed a variety of studies, conducted extensive analyses and collected significant amounts of data on many values to support this project. This has resulted in a comprehensive package that contains significant information that, regardless of the outcome of this Environmental Assessment process, provides great value to the Province of BC. Many of the NRS agencies have been working with BC Hydro staff on various aspects of this project and we are aware that more detailed permitting level information related to this project is still under development and has not been included in the EIS as it is not required by the EIS Guidelines. Our review has focused on the content of the EIS as provided, and where information appears to be incomplete or missing; comments have been included to that effect. It should also be noted, that, while not the focus of this exercise, in some cases spelling or grammatical errors have been identified by staff, these have been included for completeness.
2
Throughout our review it was noted that many comments are directed at clarifying if and where in the report, additional information on a subject may be available. It is suggested that BC Hydro include more complete references as to where additional information can be found, as it is not always clear when reading a section that additional information is available elsewhere in the document. It was also noted that the EIS did not always effectively use the available data referenced in appendices to support the conclusions made within the sections of the EIS. Commenting on the EIS is an important step in ensuring all projects are subject to careful and rigorous environmental review by the NRS agencies. Our review has identified the following areas of concern, in addition to our attached detailed comments. Level of detail contained within the Mitigation and Management Plans
We have noted that the EIS contains varying levels of detail regarding the mitigation plans, management plans, and follow-up programs. We understand that many of these plans are provided at a more detailed level at the permitting stage. Therefore, the NRS agencies take the view that as long as the proposed mitigation is feasible, reasonable or the proposed technology or approach has been used successfully elsewhere, then we are fine with the level of information provided at the EIS stage knowing that detailed plans would be required prior to permitting decisions. However, in some instances, these plans were heavily relied on as rational for assumptions and findings. To address this, the NRS agencies request BC Hydro include any developed plans, and specifically those plans that have been used as rationale for findings, into the amended EIS. Additionally, the NRS agencies request BC Hydro to provide a schedule of when the remaining mitigation and management plans will be available for review as part of the permitting process. Governance Structure for Mitigation and Compensation funds and Programs
Various forms of compensation programs have been identified in the EIS for many different VC’s. The NRS agencies note that use of common governance structures for these mitigation and compensation funds and programs would be helpful to increase efficiency and reduce confusion due to differences in programs wherever possible. For example we are aware that BC Hydro currently funds programs such as the Peace Williston Fish and Wildlife Compensation Program, and we encourage BC Hydro to explore synergies with existing programs or develop new ones as required. Consistency with standard data collection analysis procedures and guidelines
While BC Hydro has collected significant baseline data on several indicators and values, and conducted extensive analyses on these values, it appears in many cases that BC Hydro has used different standards than usually used by the province to collect and analyze these data. Examples include; hydrologic assessments, base mapping for ecosystems, and fish and fish habitat assessments. While it is possible that the standards used for data collection and analysis of these values are equivalent to or better than those commonly used in BC, limited rationale or background has been provided to support this. It is recommended that BC Hydro include
3
rationales for the methods used so that it is clear that the appropriate standards are met or that the proposed equivalents are documented as being equal or better in quality and reliability. This information would also further support the assessment of findings. Implementation of Effects Assessment Methodology with regards to Fish, Wildlife and Ecosystem Resources
A large portion of the NRS agency comments contained in the attached table relate to how the Effects Assessment Methodology outlined in the EIS Guidelines was implemented with regard to fish, wildlife and ecosystem values. We look forward to receiving BC Hydro’s responses to our comments; however, the NRS agencies may request further discussion on this issue in May or June so that we may gain a better understanding of the processes used and the information that went into the findings. Project Access Road
It is not entirely clear at this time that BC Hydro has provided sufficient rationale to support the construction of a new access road to the project site in addition to the existing infrastructure. Additional rationale will be required to justify the expectation that access and use of this road be restricted to the public and other industry. While analysis of alternatives was conducted and included in the EIS, it is not clear that BC Hydro has fully considered the potential impacts of constructing this road, and how reliance on this road could be reduced through further use of rail, as well as upgrading existing infrastructure. Further work on this issue may be required to determine if construction of this road as proposed is the best option, not just from a financial perspective, but also from an environmental and social perspective. We believe that many of our concerns and issues with the EIS can be addressed by BC Hydro in the coming months prior to the establishment of a Joint Review Panel. Should EAO or CEAA require follow up on any of the comments or questions contained in this response, please feel free to contact me so that you may be directed to the appropriate agency contact. Sincerely,
Gary Reay Executive Director, Strategic Projects Natural Resource Sector Lead, Site C Project ec: Natural Resource Board Members NRS Assistant Deputy Ministers
This page intentionally left blank.
April 4, 2013
Site C Clean Energy Project
Environmental Impact Statement Review Comments
Comments provided by the following BC Provincial Government Natural Resource Sector Agencies:
Ministry of Environment Ministry of Aboriginal Relations and Reconciliation Ministry of Energy, Mines and Natural Gas Ministry of Agriculture Ministry of Transportation and Infrastructure Ministry of Forests, Lands and Natural Resource Operations
This page intentionally left blank.
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
n/a n/a 1
Various forms of compensation programs have been identified in the EIS for many different VC’s.
The NRS agencies note that use of common governance structures for these mitigation and
compensation funds and programs would be helpful to increase efficiency and reduce confusion
due to differences in programs wherever possible.
Exec
summary Pt
2
63 2
Table – Key Mitigation Measures Bullet 2 - Bullet notes stockpiled surplus available to other
aggregate users. It should be noted that in MoTI pits and quarries, these will only be available to
BCH and MOTI
2.3 9, 10 11, 17 3
For ease of reference please further define which document readers are being redirected to as
there are multiple individual documents within Appendix C and F. i.e. - "see Appendix C for
discussion on definition of merchantable forest"
2.6.2 14 28 4
Please Clarify - Would Land Filling as a method of non-merchantable debris disposal be considered
for areas that are to be inundated? If so, have potential adverse effects of this to water quality
been assessed?
4 23 1 5
The re-alignment of Highway 29 proposes an 11 meter span pipe arch at Dry Creek. Indications are
that Dry Creek has significant bed load deposits. Has aggredation at the crossing and the potential
for it to reduce the ability of the structure to pass the required water flows and any floating debris
in the upstream pond been considered? Note: This scenario caused the plugging and the
subsequent failure of the Holdich Creek Pipes, resulting in the loss of several hundred meters of
Highway 23 in 1999.
Section 1 - Introduction - No Comments
Section 2 - Proponent Description
Section 3 - Project Overview - No Comments
Section 4 - Project Description
Volume 1
Final April 4, 2013 1
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
4.1.4 6 6
"Peace River-Boudreau Lake Protected Area" - please note this spelling should be used consistently
throughout the EIS. p. 35 S. 8.5.3.2
4.1.4 6 7
The EIS guidelines identify that the proponent is proposing to search for projects and activities that
will be carried out within the RAA to be taken into account in the Future Case without the Project
and in the Project Case.
The proposed Peace River-Boudreau Lake Protected Area is mentioned in several locations of the
EIS, but with the exception of the information in the Outdoor Recreation section, no direct analysis
of the Project’s impacts to the proposed protected area’s values has been provided. Should the
Project be approved, a reduced area (and associated values) would be available for provincial
protection. Request: Please clarify
the effect of the project on the proposed Peace-River Boudreau Lake Protected Area both in the
text, and spatially (where appropriate). A listing of specific values can be found in the Fort St. John
and Dawson Creek Land and Resource Management Plans. Outdoor Recreation section analysis
located in Vol. 3, S. 25 (page 25-25) lines 1-9 and Table 25.14.
p. 35 S. 8.5.3.2 s
4.3.5.2.3 3026 to
298
In the report there is a statement for the West Pine Quarry “The source of this permanent riprap
and bedding material is the West Pine Quarry, located on provincial Crown land approximately 75
km southwest of Chetwynd along Highway 97 (approximately 160 km from the Project site).” There
is nothing indicated in the report that States BC Hydro will prove out a suitable quantity and quality
of rock from the BC Hydro portion of the quarry to replace the material they will remove from the
MO TI portion of the quarry. This has been brought this to BC Hydro’s attention prior to this
review. Please address in the EIS.
4.3.7.1 37 10-19 9
Request - Figure 4.34 Map – it appears that this map omits 271 Road to Wuthrich quarry and "Howe
Pit entrance". Please add all appropriate access roads.
Final April 4, 2013 2
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
4.3.7.2.1 37, 3839-41,
1 - 510
"Access to the dam site area via the Project access road would be controlled 24 hours a day, seven
days a week throughout the construction period, so that only authorized traffic would use the
road." - Please provide a rationale for requesting restricted access to the Project Access Road.
4.3.7.2.1 37, 3840-41,2-
411
"After Construction..." Decisions on the level of access post project construction and
decommissioning of alternate access routes should be made prior to final design and application for
tenure of the Project Access road, as these considerations may factor into road design, cost, and
details and conditions of a potential tenure, and will have effects on the public and other tenure
holders.
4.3.7.2.1 38 6-8 12
It is not clear that the existing rail access and construction of the rail siding was considered in the
analysis of Alternate Access Routes in section 4.3.7.2.2. Please clarify if the level of rail use was
included in the analysis. If more concentrated effort is put onto moving construction materials and
equipment by rail transport to the site, are lower impact access road options being considered?
4.3.7.2.1 38 4-5 13
Please Consider adding additional description of deactivation and reclamation options for existing
road network after the Project Access Road is constructed and in service.
4.3.7.2.2 38 21-41 14
Alternative Access Routes Considered: Please consider adding additional information on
consideration of the alternatives to the Project Access Road. Efforts should be made to minimize
project footprint wherever possible, please discuss if consideration was given in the analysis to
building the Project Access Road to a standard that allowed for all anticipated industrial and public
traffic to the vicinity of the Project construction site.
4.3.7.2.2 38 21-41 15
Alternative Access Routes Considered: Section 4.3.7.2.1 - Page 4-38, Lines 9-11 discuss upgrading
the existing road network to a suitable standard until the Project Access Road is constructed.
Please clarify if the cost and impact of upgrading the existing road network was included in analysis
of this section.
Final April 4, 2013 3
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
4.3.7.4 39 35-36 16
“Some additional access roads may be required to individual structures and work sites.” EIS
Guidelines states that: “The EIS will describe all the facilities ... including access roads required for
clearing, construction and maintenance of the transmission line.” Please add the additional detail
required for consistency with the EIS Guidelines.
3.3.4
4.3.7.5 40 1-11 17
This section describes the construction of access to the proposed Hudsons Hope berm, but does not
reference a map. Please consider adding a map for clarity.
4.4.3 44 2-3 18
Schedule of activities in Figure 4.40 shows “Construct temporary facilities (including camps)“ and
“Clear and grub north and south banks” (presumably provincial jurisdiction) before “Federal
authorizations”. Please clarify what Federal Authorizations are referred to in this graphic. Is it
anticipated that any of these Federal authorizations would be required for the construction of
temporary facilities or for the clearing and grubbing of the north and south banks?
5 1923 to
2519
Please elaborate on the three bullets that discuss the issues with capacity from the market.
5 15 1 to 4 20
Re. Table 5.9 - What percentages of capacity savings forecast by 2021 (1400 MW) are attributed to
energy-focused vs. capacity-focused measures?
5 15 1 to 4 21Re. Table 5.9 - What prospective capacity measures have been considered for the commercial and
residential sectors in the analysis?
5.2.2.3 22 1 to 6 22
To what extent have any delays in timing (i.e. to potential delays in the EA process, permitting,
construction, etc.) to the in-service date of the Project been factored into this analysis?
Section 5 - Need for, Purpose of, and Alternatives to the Project
Final April 4, 2013 4
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
5.3 22 1 to 4 23
For clarity, consider adding explanations to tables 5.13 and 5.14 as to why the 5,100 Gwh/year of
energy and the 1,100 MW of dependable capacity from the Project do not appear to factor “in full”
starting with the in-service date in 2022.
5.3.1 24 6 to 7 24
Please restate the first Clean Energy Act Objective in Table 5.15 as it appears in the table in full as
amended by July 24, 2012 Order In Council No 572 “ British Columbia’s Energy Objectives
Regulation”
5.4.2.4 3711 to
2325
Has BC Hydro considered the experiences of other jurisdictions in terms of addressing DSM
uncertainties and Is BC Hydro's treatment of DSM uncertainty in line with the practice of other
utilities?
5.5.4.2 68 19 26
For clarity, please consider adding an explicit explanation to the EIS that in Fig 5.12 Effective Load
Carrying Capability of wind resources does not count as dependable capacity and that this is
consistent with standard utility practice
6 n/a n/a 27
General comment on section - Based on the information provided in the EIS Section 6 and
appendix E, it is not clear how the environmental benefit of leaving the Moberly River free-flowing
(i.e.- moving the dam upstream of the mouth of the Moberly) was evaluated. Please clarify what
values were considered and how were these incorporated. The assessment is potentially clouded
by evaluating each option against a myriad of parameters that may not be relevant to the key
question re: the feasibility and cost-benefit of moving the dam upstream of the Moberly.
Section 6 - Alternative Means of Carrying out the Project
Final April 4, 2013 5
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
6 n/a n/a 28
General comment on section - The information provided in the EIS Section 6 and appendix E
suggests that the magnitude of the impacts on the Moberly River was not represented correctly as
it is not consistent with the fisheries evaluation that reasonably predicts that the Moberly River
stock of Arctic grayling have a high likelihood of going extinct. Further, back-flooding the mouth of
this river will have a cascade of effects that will substantially change the Moberly at the ecosystem
level and the loss of these ecosystem values has not been considered. While it is appreciated that
there was a sensitivity analysis that includes weighting the Moberly very heavily, the inputs need to
be credible to ensure that the weighting is meaningful
6 n/a n/a 29
General comment on section - The information provided in the EIS Section 6 and appendix E
indicate that the evaluation of benefits and effects was undertaken using expert solicitation
approaches. It does not appear that NRS agency staff who are very familiar with this watershed
were included in the expert approach. Please clarify who was involved in the environmental
evaluation for the alternative assessment. Please re-evaluate be using the full range of impacts
that would be avoided by relocating the dam.
7.1.2.1 3 12 30
“Within the 97% Clean Energy Act clean or renewable Target” – this statement is incorrect, Part 1
Section 2 (c) states B.C.’s energy objective as: “(c) to generate at least 93% of the electricity in
British Columbia from clean or renewable resources and to build the infrastructure necessary to
transmit that electricity” – Please change 97% to 93% or rationalize why 97% has been used here.
7.1.3 5 4 to 14 31
In explaining the expected annual cost to rate payers when comparing the portfolios, please clarify
the material differences between the assumptions for expected recovery of the Project’s annual
cost and the assumptions for the expected recovery of the costs of the alternative portfolios.
Section 7 - Project Benefits
Section 8 - Assessment Process
Final April 4, 2013 6
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
8 19 32
EIS Guidelines “This subsection will include a list of supporting references used in this section of the
EIS.” It appears that this information is not included in the EIS, Please add.
6.5
8.4 12 24-28 33
“Under Section 32 of the Hydro and Power Authority Act, R.S.B.C., 1996, c. 212, except as otherwise
provided under that Act, BC Hydro is not bound by any statute or statutory provision of British
Columbia." A list of potential key federal and provincial permits that would be required by BC
Hydro for construction or operation is shown in Table 8.1. There are several acts and authorizations
listed in Table 8.1 that are not listed under Section 32 of the Hydro and Power Authority Act.
Consider providing a rationale for that legislation that BC Hydro has noted that does not apply to it
under section 32 of the BC Hydro & Power Authority Act.
8.4 12 24-28 32
Please clarify if there are any instances or circumstances in which BC Hydro may not apply for the
standard authorizations as noted in Table 8.1, and if so, please consider discussing what standards
would BC Hydro follow in these instances.
App A2 of
1086 33
Does the calculation of wood utilization/disposal include sites required for temporary
accommodations. Additionally, as the majority of wood utilization/disposal is anticipated to occur
early in the project, within the reservoir activity zone, how will natural re-vegetation be dealt and
would such re-vegetation be a wildlife year-round/seasonal attractant prior to reservoir infilling?
App A Exec
Summaryii of xv 20 - 21 34
For clarity, please reword "as defined by British Columbia's Ministry of Forests, Lands and Natural
Resource Operations" to reference the Interior Appraisal Manual, Table 1-1 Interior Merchantability
Specifications.
App A
Introduction
1 of
10810 - 12 35
Correction Required: "based on Historic utilization by the forest industry within the Peace Region”
–Merchantable timber is not based historic utilization, please remove this statement
Section 9 - Information Distribution and Consultation - Not Reviewed
Appendices for Volume 1
Final April 4, 2013 7
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App A
Introduction
1 of
10810 - 12 36
Correction required: Merchantable timber is defined by the Cruising Manual as authorized under
the Forest Act not by the Ministry of Forests Lands and Natural Resource Operations.
App C1 4.5 10 37
“...the future use of the site should be considered in relation to the official community plans of both
the regional and local government.” Please consider discussing final use and reclamation in more
detail at this stage so that measures to reclaim the land can be built into the plans. (Eg: plans to
save and store topsoil so it can be used in reclamation later need to be made before the topsoil is
stripped. Also final safe contours should be planned before excavation.)
App C2 3.0 410th
bullet38
“Setback boundaries range from 5 to 44 metres from the property line.” Figures 4.2 shows well
sites immediately adjacent to the southern boundary, which in the figure appears to be one of the
narrow (5m) setbacks. Please clarify if consideration has been given to blasting in this quarry in
regards to the 5m setback from existing development.
App C3 4.1 7 39
Information Requested - Area proposed (yellow line) is very much larger (~10x) than area for
proposed use (purple line, Green polygon and Roads). This area also overlaps a drainage, a
separate ridge and an existing road. Please provide a rationale for the large size identified or
reduce the area identified to more closely reflect what is actually needed. Also, Please clarify
whether analysis and assessment of potential effects reflected the larger identified area, or the
smaller area actually identified for use.
App C3 5.1 81st
paragra
ph
40
Appendix C2 P4, App C3 P8, For the percentages of yield vs. wastage discussed in the various quarry
development plans, please identify the standards and parameters that BC Hydro is using and
discuss - i.e. Portage Mountain Quarry (appendix C3) - 35% yield / 65% wastage, Wuthrich Quarry
(appendix C2) - 20% yield / 80% wastage
Final April 4, 2013 8
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App C3 5.1
and 5.68 & 11
2nd
paragra
ph
41
5.1:“The site would remain an active quarry under the control of BC Hydro for its use.” And 5.6:
“BC Hydro would continue to operate the Portage Mountain Quarry. ...” For clarification, future use
of these sites would likely be the subject of future applications and statutory decision. Please
propose reclamation appropriate for possible/eventual closure of the quarry.
App C3 5.2 81st
paragra
ph
42
“as shown in Table 6.1” There does not appear to be a Table 6.1. in this appendix, it seems that
this reference should be to Table 5.1, please correct or clarify.
App C3 5.3 95th
bullet 43
If the locations of structures and facilities have been contemplated or are know at this time, such as
offices, maintenance and storage areas for fuel and explosives etc. please consider including on the
associated map (figure 4.1) in this and other similar sections of the EIS. This statement also
indicates that explosives may be stored on site, which contradicts other statements in this section
to the contrary. Please clarify or correct.
App C4 7 9 44
Request: report notes that “The Ministry of Transportation and Infrastructure and BC Hydro have
agreed that BC Hydro can develop the lower ridge along the Canadian National Rail line as well as
stockpile and load in areas contained within their map reserve tenure.” There is nothing indicated
in the report that States BC Hydro will prove out a suitable quantity and quality of rock from the BC
Hydro portion of the quarry to replace the material they will remove from the MO TI portion of the
quarry. MOTI has brought this to BC Hydro’s attention prior to this review.
App C4 All 45
There is no mention of truck/equipment wash station or washroom facilities in this section, as has
been described in other appendices. Please clarify if this was overlooked, or if these facilities will
not be established at these sites. If these facilities are not going to be established, please consider
providing a rationale why not.
App C4 1, 2,
4.2
6, 7,
11
Para2,
P2, P146
throughout this section, the map is referred to as both “Figure 1.1.1” and “Figure 1.1" please
correct for consistency.
Final April 4, 2013 9
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
Appendix C1
- C547
Quarry Development Plans - Reclamation and Future Use & References: It is not clear, based on
section 8.4 or Table 8.1 that BC Hydro will apply for a Notice of Work under the Mines Act, or
whether or not this legislation applies to these sites. In either case, it is suggested that BC Hydro
include reference to the "Health and Safety Reclamation Code for Mines in BC". This should also be
the standard used for devlelopement, reclamation, safety and other associated activities unless
stated otherwise for the quarries in question.
Appendix C1
- C548
Quarry Development Plans - Reclamation and Future Use: It is not clear in the EIS whether the
Quarries are considered to be "temporary construction facilities" or not, however if this is the case,
section 3.3.11 of the EIS Guidelines states that the EIS will describe "Decommissioning of temporary
construction facilities and any associated reclamation" . The appropriate sections of the Plans do
not go into detail regarding proposed reclamation. Please consider including additional
information.
Appendix C1
- C549
Quarry Development Plans - Temporary and final slopes: Please clarify the standards or criteria
that have been used to identify the final temporary (1.5H:1V etc.) and final slopes (2H:1V etc.) and
face heights. A rationale discussing adequacy of these slopes including discussion of angle of
natural repose would be helpful.
10 50
Pedogenic soils are not identified as a valued ecosystem component nor are they addressed in
relationship to ecosystems or forestry. Productive soils were not selected as a VC. Instead, soil is
addressed under VCs Agriculture. Enduring features and geodiversity have not been identified as VC
or addressed.
8.3
Volume 2Section 10 - Effects Assessment Methodology
Final April 4, 2013 10
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10 51
Description of VCs - Overall Methods
Issue: The Definitions section of Volume 2 defines "baseline" as follows: "Air quality conditions, in
terms of emissions or ambient concentrations, associated with existing sources in the study area,
including all human-caused and natural sources."
Concern: This definition is incorrect; baseline is described for more values than Air Quality.
Request that the Proponent:
Expand the definition of "baseline" under Definitions to include more than air quality.
10 52
Overall Methods
Issue: It is not clear how uncertainty has been considered and incorporated into the assessment.
Concern: Given that information used to assess values will be imperfect, considering that
environmental and ecological processes are stochastic and constantly changing, and considering
that activity impacts have a certain likelihood of occurring, there are a number of uncertainties that
play into the assessment of each VC.
Request that the Proponent:
Clarify how uncertainty has been evaluated throughout the various stages of VC selection and
assessment.
Final April 4, 2013 11
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.1 10 30-31 53
Overall Methods
Issue: Section 10.1 refers to the preparation of "A framework for environmental management to
be implemented during construction and operation of the Project." (pg 10-1 line 30 - 31)
Concern: The framework for environmental management is introduced in section 10.1 without
information on what it is and how it was developed.
Request that the Proponent:
Provide more information about the “…framework for environmental management…” (section
10.1). What is this framework based on? What does this look like?
10.2 54
Selection of VCs - Overall Methods
Issue: Section 10.2 sets out a list of questions used to identify candidate VCs (page 10-2 line 14) but
does not provide more information on how candidate VCs were selected.
Concern: The process of identifying VCs reported needs to be described in more detail for
transparency.
As a general comment, it is counterintuitive that things like “contaminated sites”, “greenhouse
gases”, “noise and vibrations” are considered as Valued Components. These are not components
that are valued, they are disturbances to mitigate against.
Request that the Proponent:
(a) Clarify if there is a standardized process for the identification of candidate VC’s based on the
questions listed in Section 10.2. Was the identification of VC’s based simply on “considering” the
questions listed?
(b) Consider aligning approaches for VC selection with Provincial Values initiatives like
Environmental Mitigation, Cumulative Effects Assessment, and Values work.
Final April 4, 2013 12
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.2.2 55
Selection of VCs - Overall Methods
Issue: The assessment of interactions is described only in very general terms in section 10.2.2.
Concern: It is not clear how interactions were assigned to each candidate VC. The Proponent will
be working with imperfect information so it is important to describe how uncertainty is managed.
Request that the Proponent:
Clarify the following:
(a) What is the definition of an interaction for the purposes of these assessments?
(b) What spatial and temporal boundaries were used when considering interactions between
project components and VC’s (e.g., LAA only or LAA and RAA?) Did this process consider
interactions where there may be a significant lag time between the activity and the effect e.g., as
with watershed processes.
(c) How was uncertainty incorporated into this analysis of interactions?
Final April 4, 2013 13
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.2.3 56
Selection of VCs - Overall Methods
Issue: From the EIS: "Step 3 in VC selection involved the question of whether the effect of an
interaction on each candidate VC carried through could be effectively assessed under a separate
and related, but “more appropriate”, candidate VC." (Section 10.2.3). Thus, individual candidate
VCs, such as “migratory birds”, “ungulates”, or “bats” are merged into “Wildlife Resources”.
Concern: Aggregating VCs leads to a significant challenge in interpreting the ecological
consequence to individual VCs. Aggregation of VCs results in a mixing and lack of clarity as to which
Project activities result on which adverse effect on which individual VCs; how effectively the
resulting Residual Effects are mitigated; and how “significance” can be determined for residual
adverse effects related back to specific VCs.
Request that the Proponent:
(a) Individual species groups should be considered as separate VCs so that mitigation measures,
residual adverse effects, and significance can be determined and demonstrated – and effectiveness
tracked – by species group (or species) instead of being generalized across the aggregated VC of
Wildlife Resources.
(b) What were the principles and process used to determine which VC’s can be appropriately
represented within another assessed VC?
(c) What other considerations were used to assess for alternate VC representation aside from the
similar effects pathway?
Final April 4, 2013 14
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.3.1 4 20 57
Assessment of Impacts - Overall Methods
Issue: The spatial boundary of the Project Activity Zone (PAZ) does not include existing
infrastructure “that will be used without modification” (Page 10-4, line 20, Table 10.1).
Concern: It is likely that portions of existing infrastructure, while not requiring
modification/upgrades, will experience increased duration/frequency of vehicle traffic.
Request that the Proponent:
Clarify whether there has been an assessment of the potential impacts to wildlife resources of
increased duration and frequency of vehicle traffic on existing roads outside of the PAZ. Is this issue
addressed in the assessments for the LAA and/or RAA?
Final April 4, 2013 15
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.3.1 58
Assessment of Impacts - Overall Methods
Issue: From the description in section 10.3.1 Spatial Boundaries (pg 10-4 lines 6 - 19) it appears
that a spatial assessment unit is attached to the VC (i.e. wildlife resource, vegetation and ecological
community) but multiple “groups” are assessed within a VC (eg. For the wildlife resource VC, groups
like butterflies & dragonflies, migratory birds, ungulates, carnivores, etc. are assessed as indicators).
Concern: The spatial assessment unit for localised dragonflies would be considerably different than
that for wide-ranging ungulates. This will ultimately misrepresent the actual condition of the
assessed group depending on spatial ecological factors for each group assessed. Also, it is not clear
how “characteristics” for VC’s were compiled to define the LAA; again, groups within a VC are
ecologically very different from one another so its difficult to know if the LAA is appropriate for all
groups assessed.
Request that the Proponent:
(a) Clarify how the EIS reconciles the differences in spatial scales appropriate to organisms that
vary considerably in size and home range.
(b) Describe how aboriginal traditional knowledge was used to inform spatial scales and extent of
potential changes.
(c) Describe the inputs to the definition of the LAA boundary.
Final April 4, 2013 16
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.3.1.1 6 59
Assessment of Impacts - Overall Methods
Issue: The assessment area for Harvest of Fish and Wildlife Resources in the PAZ defined in as
“within reservoir impact lines and the Peace River downstream to the Alberta border” (Page 10-6
line 10 Table 10.2).
Concern: Displacing harvesting (fishing and hunting) effort in the Project Area Zone may increase
harvesting pressure in adjacent areas. The assessment of impacts to hunting and fishing and,
therefore, to wildlife, need to look at areas outside of the PAZ.
Request that the Proponent: Clarify if the assessment includes an analysis of the implications of
displaced harvesting of fish and wildlife from the PAZ; will this increase and/or initiate harvesting
pressure in other areas? If so, what are the anticipated impacts?
10.3.2 6 10 60
Mitigation and Monitoring - Overall Methods
Issue: Section 10.3.2 Temporal Boundaries, states that "construction will occur over an eight-year
period, and the Project is intended to be operated and maintained over the long term with no
future decommissioning contemplated.
Concern: Long term monitoring is essential, especially if future decommissioning has not been
considered.
Request that the Proponent: Clarify intentions regarding long-term monitoring of VC’s given the
timelines described for Project construction and operations e.g., relating to potential lag time of
effects, species with multi-year cycles, effectiveness of mitigation?
Final April 4, 2013 17
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.4.1 61
Description of VCs - Overall Methods
Issue: Section 10.4.1 does not provide a definition of what is meant by "baseline condition".
Concern: Section 10.4.1 describes the information that accompanies the baseline descriptions (the
relevant legal framework, methods used to collect baseline data and the sources of baseline
information) and states that "an overall baseline description is provided" (from the EIS Guidelines
section 8.5). However section 10.4.1 does not provide details as to what the baseline includes.
Section 10.1.5.2 identifes a demarcation date (September 5, 2012) for the Baseline Case for
Cumulative Effects Assessment (CEA). It is not clear whether the baseline conditions outside of the
CEA are similarly demarcated. It is also not clear what spatial area the baseline describes for a
given VC - the PAZ? the LAA? Is the RAA applied for assessments outside of the CEA?
In general, the current conditon of all VCs should be described or presented in a manner that allows
a reasonable assessment of Residual Effects. Baseline conditions should be described in the context
of a spatial scale relevant and appropriate to each VC being assessed. To the extent possible, this
information should allow a quantitative assessment of Residual Effects in comparison to current
condition.
Request that the Proponent:
Provide a more detailed definition in Section 10.4.1 of a "baseline description". This should include
a description of the spatial and temporal boundaries applied to each VC.
Final April 4, 2013 18
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.4.2 62
Selection of VCs - Overall Methods
Issue: From the EIS: "All project/VC interactions noted as “2” were carried through to the effects
assessment (where “2” = Interactions may result in adverse effect and the nature of the effect
and/or effectiveness of mitigation measures is uncertain)" (Section 10.4.2, pg 10-8 lines 5 - 11;
Appendix A Matrix Table 2).
Concern: There could be potential to miss some adverse effects and thus cumulative effects
where project/VC interactions noted as “1” are not carried forward to the assessment phase
because they are assumed a priori to not exist or be negligible. (“1” means that adverse effect may
result from an interaction, but the effect is well understood and standard measures to avoid and
minimize are available and effective, therefore are no, or negligible, residual adverse effects)
(Section 10.4.2 pg 10-8 lines 1 - 4).
Request that the Proponent:
(a) Describe the implications of being mistaken when making an a priori assumption that potential
project interactions can be fully mitigated (i.e., assigning a rank of "1" when it should be a "2")
(Section 10.4.2).
(b) Provide rationales for the assignment of ranks to individual species or species groups to assess
potential project interactions since Appendix A reports ranks for Wildlife Resources as a whole and
rationales for all VCs together.
Final April 4, 2013 19
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.4.2.1 8 34-40 63
Mitigation and Monitoring - Overall Methods
Issue: Generally speaking, mitigation measures are not given as measurable and verifiable.
Mitigation measures include things that are vague and undefined, or not, in themselves, actions to
“mitigate” adverse effects. Batching mitigation measures for aggregated VCs compounds the lack
of clarity as to what will be done for mitigation, and how effective the measures may be.
Concern:
From the EIS: “Mitigation” and “mitigation measures” are defined as per s. 2(1) of CEAA 2012:
“measures for the elimination, reduction or control of the adverse environmental effects of a
designated project, and includes restitution for any damage to the environment caused by those
effects through replacement, restoration, compensation or any other means”(Section 10.4.2.1 pg
10-8 lines 34 - 40). Section 10.4.2.1 lacks a clear set of procedures for the development and
reporting of mitigation measures (e.g., requiring that mitigation measures link back to adverse
effects on specific VCs).
Request that the Proponent:
Provide clear procedures, a structured approach, and clear demonstration of how steps in the
mitigation hierarchy were considered (avoid - minimize -restore on-site - offset), and corresponding
mitigation measures selected, with respect to adverse effects on specific (i.e., individual, not
aggregated) VCs.
Final April 4, 2013 20
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.4.2.1 64
Mitigation and Monitoring - Overall Methods
Issue: Mitigation measures (see “proposed mitigation” in several tables) include things that are
not, in themselves, actions to “mitigate” adverse effects.
Concern: Where mitigation plans are used as rationale for findings, enough conceptual detail
about proposed mitigation is needed to be able to evaluate the effectiveness of mitigation
proposals and use that to estimate Residual Effects. The EIS Guidelines, s. 8.5.2.2 requires an
evaluation of effectiveness and, where there are uncertainties, and description of the potential
risks related to these measures; this is not possible without some level of conceptual detail.
Creating a plan is not a mitigation measure.
Examples of mitigation measures in the draft EIS include:
o Provide inputs to the final design phase (e.g., known wetlands, bat hibernacula) so that further
reductions and avoidances can be considered. (This is about planning and actions that may be
considered but may not happen.)
o Incorporate locations of rare species along rights-of-way into GIS-based mapping.
o Implement Environmental Management Plans. (What specific actions would the Plans include?
Itemize those actions / mitigation measures.)
o Consider the use of supplemental ungulate feeding programs during severe winters (this is
contrary to provincial government policy).
o Maintain a spatial database of wildlife features. (Then what? What specific action or mitigation
measure does this relate to, for what VC?)
Request that the Proponent:
Where mitigation plans are used as rationale for findings, please provide sufficient detail about
proposed mitigation to enable an evaluation of mitigation effectiveness and estimation of Residual
Effects.
8.5.2.2
Final April 4, 2013 21
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.4.2.2 9 4-5 65
Mitigation and Monitoring - Overall Methods
Issue: Section 10.4.2.2 states that "Residual adverse effects are the effects of the Project that may
remain after taking into account the implementation of mitigation measures, including
compensation" (page 10-9 lines 4 - 5).
Concern: If compensation counts towards reducing Residual Effects to zero (i.e. if there’s enough
compensation than Residual Effects are nullified), there are still likely to be “functional” impacts
that contribute to cumulative effects.
Request that the Proponent: Clarify the process for determining where, when, and how much
compensation (offsetting?) should be applied, and how compensation will address adverse effects
on VCs.
10.4.2.2 66
Estimate of Residual Effects - Overall Methods
Issue: Basing the assessment of the Residual Effect to conditions of the value on September 5,
2012 may not adequately take into account the ecological context of that condition and overall risk
to maintaining the value..
Concern: The ecological context of the current condition/baseline is missing from the estimate of
Residual Effects i.e., what the current condition of VCs represents in terms of risk to maintaining the
VCs.
Request that the Proponent: Clarify the baselines that residual adverse effects are characterized
against (after all mitigation including compensation/offsetting). What are Residual Effects
measured against, in relation to what changes in the environment for each VC. See also the request
for clarification of the definition of "baseline condition".
Final April 4, 2013 22
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.4.2.3 67
Determination of Significance - Overall Methods
Issue: The definition of “Significance” and the methodology to determine significance (or non-
significance) of residual adverse effects, including thresholds, is unclear. This lack of clarity is
compounded because residual adverse effects themselves are generalized, and characterization is
descriptive and may encompass aggregated VCs.
Concern: More detailed explanations should be provided for each determination of significance (or
non-significance) of residual adverse effects.
Request that the Proponent:
Include a description of the steps used to derive significance based on quantitative descriptors used
to characterize Residual Effects in future iterations of the EIS.
Final April 4, 2013 23
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.4.2.3 68
Determination of Significance - Overall Methods
Issue: Although species-specific Residual Effects and significance determinations are mentioned,
the ultimate determination of significance is for “Wildlife Resources” as a Valued Component.
Concern: Aggregating VCs in the determination of significance could result in a loss of detail and
individual effects being swamped when wildlife are considered as one group. “Significance” (or
non-significance) of residual adverse effects for any one species cannot be understood when
multiple species are aggregated (for example, into “Wildlife Resources”) and “Significance” applies
generally to the broad category.
Request that the Proponent:
(a) Provide a rationale for why the final determinations of significance were made for Wildlife
Resources as a Valued Component, rather than for individual Species Groups and, (preferably)
species or species guilds.
(b) Describe the limitations and uncertainties associated with reporting significance for 'Wildlife
Resources" as a whole.
(c) How is the measurement of the indicators (e.g. species groups for the “Wildlife Resource” VC)
rolled-up to actually define the VC? How are such disparate indicators and information brought
together to report out on Wildlife Resources as a single VC?
Final April 4, 2013 24
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.4.2.4 11 1-5 69
Mitigation and Monitoring - Overall Methods
Issue: Follow-up Programs are proposed (in accordance with section 23.5 of the EIS Guidelines) to
verify the accuracy of the assessment or the effectiveness of mitigation measures. Follow-up
Programs have been developed where the likelihood, nature, or extent of a predicted adverse
Residual Effect on a VC, or the effectiveness of a recommended mitigation measure, is uncertain
(section 10.4.2.4 page 10-11 lines 1 - 5). Technically feasible, cost-effective, and environmentally
sound measures (e.g., alternative mitigation method, adaptive management) are proposed.
Concern: It is appropriate to scale the level of monitoring with uncertainty; however, to only
commit to Follow up Programs where uncertainty is identified is too limiting (e.g., re. opportunities
to improve mitigation methods through adaptive management).
Request that the Proponent:
Consider a broader range of criteria for monitoring the accuracy of the assessment or the
effectiveness of mitigation measures than are currently described in Follow-up Programs in the EIS
(section 10.4.2.4 page 10 - 11 lines 1 - 5).
Final April 4, 2013 25
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.5 22 7-13 70
Cumulative Effects Assessment - Overall Methods
Issue: The EIS states that, in accordance with EIS Guidelines in s. 8.5.3: "assessment of potential CE
of the Project on a VC has been conducted if a potential residual adverse effect of the Project on
that VC has a spatial and temporal overlap with a Residual Effect of another project or activity"
(section 10.5 pg 10-22 lines 7 - 13). The EIS defines “cumulative effects” by potential Residual
Effects of other projects and activities from the baseline date (September 5 2012).
Concern:
The comparison of the Future Case without the Project and the Project Case does not adequately
evaluate the significance of the incremental effect of the Project. Reasons include the following:
o It is not clear how the Residual Effects of other projects (that may be in early stages of
application) are determined.
o It is not clear if any potential interactive effects among the Project and these other
projects/activities would be considered, or possibly missed.
o Adverse effects may be missed since this approach only considers effects that meet the definition
of residual adverse effects. Smaller effects resulting from “minimizing’ or not fully offsetting still
result in residuals that accumulate incrementally into cumulative effects over areas and time.
o There is no direct mention of desired future conditions or objectives for VC’s. Cumulative effects
assessment is meaningless without objectives for VC’s.
Comment Continued in next box
Final April 4, 2013 26
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.5 22 7-13 70
Comment Continued
Request that the Proponent:
(a) Clarify the following:
(i) How is the baseline case is compared to the residual cumulative effects to describe the
significance of the effect on the VC?
(ii) How are the Residual Effects of other projects and activities (that may be in early stages of
application) determined?
(iii) Are potential interactive effects among the Project and these other projects/activities
considered?
(iv) How does the CE assessment identify and address smaller effects that result in residuals that
accumulate incrementally into cumulative effects over areas and time.
(v) What are the desired future conditions for VCs in the context of the CE assessment?
(b) Consider running a number of CE “scenarios” with varying degrees of parameters (e.g. tenures,
time periods, severities) included to get a sense of best and worst case.
(c) Provide justification for the determination that some projects are not expected to have
cumulative effects.
(d) State more clearly that only Project habitat alteration and fragmentation are carried forward
into the Cumulative Effects assessment.
(e) Crown Range tenures (authorized by FLNRO) and associated activity are not considered in the
cumulative effects assessment, but may contribute to cumulative adverse effects on some wildlife
taxa (page 14-91). Consider other projects such as ZED Septimus wind park in the CE assessment.
Final April 4, 2013 27
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
10.5.5 22 11-15 71
Mitigation Measures - Overall Methods
Issue: From the EIS: "BC Hydro has recommended a number of possible regional approaches to
mitigation of CE ... which may involve government departments and/or third parties in independent
and/or collaborative initiatives"(sec 10.5.5 g 10-22 lines 11 - 15).
Concern: Question about the expectation of government department involvement in mitigation of
cumulative effects.
Request that the Proponent:
Clarify:
a) What is the expected role of the provincial government in mitigating adverse effects or
cumulative adverse effects of the Project?
(b) Would BC Hydro fund all such mitigation (through compensation or offsetting)?
11 72
The EIS Guidelines state that he narrative will include... "the description of any existing studies of
changes to the environment resulting from those projects that are similar to potential changes
resulting from the project, including any mitigation measures that were implemented, and any long
term monitoring or follow up program that were conducted. The effectiveness of those mitigation
measures and key results of monitoring or follow-up programs would be described . This
narrative discussion should include historical data, where available and applicable, to assist
interested parties to understand the potential effects of the Project and how they may be
addressed." - The effectiveness of mitigation measures and key results of monitoring or follow-up
programs is not clearly addressed in Section 11. Please add the appropriate information.
9.1 Previous
Developments
Section 11 - Environmental Background
11.1 - Previous Developments
Final April 4, 2013 28
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11 73
The EIS Guidelines state: "should include historical data, where available and applicable, to assist
interested parties to understand the potential effects of the Project and how they may be
addressed." This topic is not adequately addresses in terms of soils, agriculture, and terrain
inventory. There are existing studies and data that were not referenced or used. For example,
studies summarizing loss of ecosystems, previous terrain and soils mapping. Please include in the
EIS.
Historical data was addressed in terms of previous geotechnical studies.
9.1 Previous
Developments
11.1.1 74
The EIS Guidelines state : "An understanding of those facilities, of the environmental changes
understood to have resulted from those facilities, and of the mitigation measures employed may
provide information that could be used to better assess the potential effects of the Project..."
Please provide additional historic data on the regional state of values prior to installation of the
WAC Bennett Dam and the Peace Canyon Dam in addition to the baseline information used.
Productive agricultural land in the Peace Valley has already been lost due to these 2 other dams as
well as other projects and this should be made clear in the Executive Summary so that it will not be
lost to stakeholders and decision-makers.
Baseline information collected by the proponent for the previous dam projects is not summarized
or provided, or could not be found.
9.1 Previous
Developments
Final April 4, 2013 29
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.1.2 75
The EIS Guidelines state : "An understanding of those facilities, of the environmental changes
understood to have resulted from those facilities, and of the mitigation measures employed may
provide information that could be used to better assess the potential effects of the Project..."
Please provide additional information summarizing the historic regional state of VC's and the total
regional loss to VC's from this and other projects past and present for reference. e.g., How much
agricultural land of the various classes has been lost in the region (using data that predates
reservoirs in the region)? What proportion of the productive agricultural lands has been lost from
previous projects? What proportion of the productive land does this represent for the region? for
the province? These same questions could be asked for ecosystem, soils, etc.
Regional historic baseline descriptions should predate the 2 existing dams. regional loss of values
should address loss of values from the 2 existing dams and the additive losses from the proposed
dam. and the additive loss from the proposed Project should be summarized.
9.1 Previous
Developments
11.1.3 76
This is a very brief section that references some monitoring programs on the existing reservoirs. It
does not cross reference monitoring recommended or described in appendix B part 2. 9.1 Previous
Developments
11.2.3.8 77
EIS Guidelines state: "Characterization and classification of the proposed reservoir shoreline will be
carried out," - Shore line classification is outlined in section 11.2.3.11 cross references Volume 2
Appendix B Part 2. Data for the classification of the shoreline was not delivered to the province
however an overview of the data was presented to the province. Shore line is classified into broad
material type groups in order to make material specific assumptions for the erosion models. The
Model description and results are found in Appendix B part 2 sections 7.
9.2.1 Geology, Terrain
and Soils
11.2 - Geology Terrain and Soils
Final April 4, 2013 30
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.2 78
This section provides an overview of the terrain and geology. The terrain description emphasizes
surficial materials. It touches on landforms but does not cover all relevant landforms (e.g., fans). For
geomorphic processes landslides (bedrock mechanisms) are covered extensively but other
processes such as seepage, earthflow, gullying, etc. are not expanded upon and their relevance to
the project not described. V2 Appendix B parts 1 and 2 are cross referenced. Some key findings
described in Appendix B Part 2 are not adequately covered in this section. For example, the
number, percentage and volume of landslide features with active slow mass movement processes
(e.g., earth flow) below the reservoir level should be summarized in section 11.2.
9.2.1 Geology, Terrain
and Soils
11.2.2 79
EIS Guidelines state: "The EIS will contain a description of bedrock and surficial geology..." - An
overview of bedrock and surficial geology is covered in section 11.2.2. There is a good cross
reference to section 11.2.2.4 where more detailed description of potentially unstable bedrock
features near the dam site are described.
9.2.1 Geology, Terrain
and Soils
11.2.2.3 80
EIS Guidelines state: "This will include....Regional bedrock and surficial geology" This section
emphasizes terrain stability as it relates to road construction and logging practices. There is a lack of
follow-through to mitigation sections. There is an overemphasis on initiation zones of landslides
and not on other geomorphic hazards and constraints or erosion potential. It is stated (11-17
line13) that this study is superseded by geotechnical analysis. However, the results of the
geotechnical analyses would be more useful if it was used to update the terrain mapping.
9.2.1 Geology, Terrain
and Soils
11.2.2.4
11-17
to 11-
20
81
This section describes a huge variety of potential failure planes in the bedrock and surficial
materials at the dam site: bedding planes with low frictional resistance, shear zones, fractures,
seepage zones, steeply dipping relaxation joints with water flow near valley walls, and other
weaknesses, and a buried channel connecting Moberly creek and the Pine river (a potentially
permeable zone? – ground water implications on stability?). This section lacks a clear statement of
impact on the reservoir and the dam. There needs to be a cross reference to mitigation measures
including how these findings are taken into consideration in the dam design and monitoring
programs.
9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 31
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.2.3.2 82
EIS Guidelines state: "Characterization and classification of the proposed reservoir shoreline will be
carried out, including: Descriptions of geological materials and/or thickness of colluvium and a
description of the underlying geological materials located at the normal maximum reservoir level;" -
There is a cross reference to Volume 2 Appendix B Part 2. The lumping of 'sand and gravel' units
makes the interpretations in section 11.2.3.2 very broad. This is appropriate for geotechnical
calculations.
The implications to shoreline erosion and slope stability are addressed but not the implication of
upstream/slope geomorphic processes. Recent geologic materials are a key to these processes and
are not covered. See other comments relating to cumulic landforms.
9.2.1 Geology, Terrain
and Soils
11.2.3.3 83
EIS Guidelines state: "Characterization and classification of the proposed reservoir shoreline will be
carried out, including: Inventory of landslides, including their estimated mechanism, volume and
current degree of activity; " - Landslides within the project activity zone are summarized. Slow
mass movement processes are not adequately described in this section. Details are present in
Appendix B Part 2.
9.2.1 Geology, Terrain
and Soils
11.2.3.3 84
EIS Guidelines state: "Characterization and classification of the proposed reservoir shoreline will be
carried out, including: Site-specific characterization of significant historic and pre-historic landslides
based on the results of surface mapping, geotechnical drilling, instrumentation monitoring, and
slope stability analyses, where available;" This topic is summarized in section 11.2.3.3 with details
in Volume 2 Appendix B part 2. Tributary streams were not investigated for landslides relevant to
debris dam and flood potential. Investigation was limited to the project impact area. Potential
impacts to the project were not fully explored.
9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 32
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.2.3.3 85
There are significant landslides and stability issues in the valley. These are described in detail. The
mitigation of these issues is not cross referenced and is covered very poorly in section 35 with some
significant gaps in requirements (see comments related to WCB regulations below). The presence
and implication of slow mass movement processes is not adequately covered in this section.
Including what factors contribute to transformation from slow deformation to rapid movement.
Details present in Appendix B Part 2 section 4.1.2 regarding the active movement along failure
plains and in the landslide deposits are not mentioned in section 11.2.3.3. These facts and their
implication to the project need to be summarized and addressed in section 11.
9.2.1 Geology, Terrain
and Soils
11.2.3.8 86
EIS Guidelines state: "Characterization and classification of the proposed reservoir shoreline will be
carried out, including: Description of the geology at select representative cross-sections and
extrapolation along the shoreline using borehole and surface mapping observations to produce
geological fence diagrams;" - Section 11.2.3.8 summarizes boreholes and detailed cross sections.
The data has not been delivered to the province. Some example cross sections are provided.
9.2.1 Geology, Terrain
and Soils
11 87
It would be very helpful if sections were cross referenced. For example ecosystem mapping is
referred to in section 11 but not properly referenced so that it is easy to find. Text refereeing to
Terrestrial Ecosystem Mapping is found on line 26 page 11-94 and line 15 page 11-151 but no tie to
ecosystem baseline in the Environmental Background section. Surficial materials and soils are
critical to ecosystem distribution and health. Similarly, it does not appear that the ecosystem
section adequately references the geology and terrain information or the limited soils information
in the agriculture section. Volume 5 Section 37.1.5 was particularly useful to put the geomorphic
findings into perspective but is not referenced from section 11 or related sections that were
reviewed.
9.2.1 Geology, Terrain
and Soils
11 88Pedogenic soils are not addressed. 9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 33
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11 89
EIS Guidelines state: "The EIS will contain a description of ... geotechnical and geochemical
processes (such as erosion, slope stability and acid rock drainage) that may affect land or resource
use" - Erosion and terrain stability were reviewed as much as possible without the full data set
(vector and LiDAR). Slope stability issues where investigated in detail by the proponent and are
described in Volume 2, Appendix B parts 1 and in more detail in part 2. These issues need to be
summarized in a clear and concise fashion in section 11 and related sections so that the information
critical to decision makers in clear and tradeoffs are outlined. This section should also cross
reference other sections that take the geotechnical findings into consideration.
The focus of the geotechnical studies was on the impact of the reservoir on stability and
displacement wave modelling. The scope needs to be expanded to cover the potential impacts of
the inherent instability on the project and activities. Stability issues outside the project activity zone
that could detrimentally impact the project should be fully explored. This includes but is not limited
to:
• potential impacts of landslides outside the stability impact line
• investigating potential debris damming and outburst floods in tributary streams
• investigating evidence of past catastrophic flood and debris events in sediment records present in
wetlands and fans; and
• investigating/monitoring large slow mass movement features in the activity zone.
Detailed landslide inventory data was not available to the province. An overview was presented
9.2.1 Geology, Terrain
and Soils
11.2.5 90
EIS Guidelines state: "The EIS will contain a description of ... existing and predicted changes to
seismic conditions" - Seismic hazards are covered in section 11.2.5. Reference to increased Seismic
activity caused by hydrocarbon extraction (BC Oil and Gas Commission 2012) is stated in Volume 2
Appendix B part 2 section 3.2.1 paragraph 5 but not mentioned in section 11.2.5.
9.2.1 Geology, Terrain
and Soils
11.2.3.10 91Please Clarify the extent and scope of the geotechnical investigation that are still to be completed. 9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 34
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.2.4 92
The EIS and Acid Rock Drainage and Metal Leachate Management Plan discuss monitoring and
reporting during construction activities, however there is no mention of monitoring or reporting to
be implemented during operation. Please Clarify if BC Hydro intends to implement any monitoring
for Acid Rock Drainage or Metal Leachate beyond the construction period of the dam and into
operations for any of the Project components.
9.2.1 Geology, Terrain
and Soils
11.2.5 93Questions and follow-up: Suggest that an expected situation of "harmless seismic events" be
confirmed; yes or no and if no, qualified in simple illustrative terms?9.2.1 Geology, Terrain
and Soils
11.2.3.9 30 17 – 26 94Please provide details of the “hybrid modelling approach” and model results. 9.2.1 Geology, Terrain
and Soils
App B, Part
295
Field investigation was focussed on refinement of the stability impact line. The Cache Cr slide was
not selected for detailed drilling and slope movement monitoring as the failure plane of this large
slide is well above the reservoir level. However, further investigation and monitoring of this slide is
recommended as it poses sedimentation and landslide risk in an area where the reservoir is
relatively narrow and confined.
Historically toe erosion of the feature has likely removed material downstream. Could this feature
potentially ‘pinch off’ or fill in this section of the reservoir? See bathometric map. Also consider
untrained loading of the saturated landslide deposit from upslope movement.
029_v1_s4_fig_04-23_site-c-rsvr-bthymtry-tls-5of6.pdf
9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 35
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.2,
mostly
11.2.2.2
96
EIS Guidelines state: "The EIS will contain a description of ... key landforms (such as mountains,
uplands, slopes, terraces and streams)" There is a very general overview scattered between the
sub-sections in 11.2, mostly 11.2.2.2. The location and relevance of major glacial and post glacial
landforms is not clearly summarized with statements of relevance to the project. Where is the 'so
what?' in section 11.2.2.2.This section lacks cross reference to other relevant sections and
appendices. There is no section on post glacial terrain (landforms include: fans, modern floodplain,
wetlands, colluvial slopes, earth flow features, etc.). Many of these cumulic landforms hold the key
to Holocene sedimentation rates and major events. Coring of wetlands and fans may provide
valuable information to the project.
9.2.1 Geology, Terrain
and Soils
11 97
In general it is difficult to find specific mitigation measures related to the issues summarized in
section 11. e.g., unstable slopes and large landslide features are identified in the studies but the
summary does not cross reference how these are addressed in section 35 or other sections.
Similarly other section (e.g., groundwater 9.3) does not adequately reference the stability summary
or appendices.
9.2.1 Geology, Terrain
and Soils
11 98
Pedogenic soils are not addressed in section 11. Engineering soils are covered with regard to terrain
stability, groundwater etc., in section 11. Instead, soils are only addressed in the section on
agriculture as they relate to agricultural capability. Soils should be described in section 11 including
their distribution, classification, age, chemistry. Discussion on soils should include their relationship
to other valued components such as the base of terrestrial ecosystems, forest productivity, water
quality and storage, carbon storage and sequestration capacity, base line representation and loss
due to reservoirs over time. Cross reference should be made to soil background information from
sections that address erosion, forestry, ecosystem, agriculture, mitigation and reclamation section.
Basic soils survey and inventory information can be used to inform planning and mitigation
processes.
9.2.1 Geology, Terrain
and Soils
11.2 99
"Geology, Terrain and Soils" - This section is mis-named as it does not deal with soils. Soils are
discussed under Agriculture. - Please correct to avoid confusion. 9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 36
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.2.1 100
This section provides a good overview of the physiography and topography in the area. The
relevance of these to the proposal is not clearly stated in each section. Please add this information.
Previous terrain and soils mapping were not referenced.
9.2.1 Geology, Terrain
and Soils
11 101
EIS Guidelines state: "This will include....and soil conditions" - Soils survey and descriptions of soil
development, classification and properties are not covered or cross referenced in section 11 nor are
they covered in the terrestrial ecosystems section. Soils are only addressed with relationship to
agriculture capability.
9.2.1 Geology, Terrain
and Soils
11.2.3.8 &
11.2.2.3102
EIS Guidelines state: "The EIS will describe... the stability of the terrain within the project activity
zone" - This topic is covered in 11.2.3.8 and 11.2.2.3. The latter lacks relevance to the project as a
whole as there is an emphasis on road construction and logging.
Detailed terrain stability inventory data has not been provided to the province delivered although
an overview has been presented to staff.
9.2.1 Geology, Terrain
and Soils
11 103
Investigation focuses on the life of the reservoir up to 100yr. What will happen to stability after that
time period? Stability issues should be considered for the full life span of the reservoir. The scope of
the geotechnical investigation should also include the decommissioning or ongoing maintenance of
the project.
9.2.1 Geology, Terrain
and Soils
11.3.1.1 53 33-34 104
"Wherever possible, farmland, and ranchland acquired by BC Hydro is being maintained in a
productive state, either by leasing back the property to the original owner or to another tenant" -
Please clarify the portion of BC Hydro owned farmland that is in production vs. not in production.
This statement does not appear to be quantified or discussed further in this section. Please provide
a rational and information supporting this statement.
9.2.2
11.3 - Land Status, Tenure and Project Requirements
Final April 4, 2013 37
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.3.1.1 54 15 105
3rd bullet in the Notes section of the table: "Additional Crown or private lands may be purchased in
fee simple for sources of construction materials or mitigation. The construction material lands may
be available for redevelopment post-Project." Please provide additional information on how much
additional land is being contemplated (by Crown and Private). If exact numbers amounts are not
known at this time, please provide a range. Also, please consider providing additional information
concerning the mitigation types that may required additional fee simple land.
9.2.2
11.3.1.1 54 15 106
For completeness and clarity, please consider summarizing tables 11.3.1, 11.3.2 and 11.3.3 into one
table showing total area required for the Project by project component broken down into fee
simple categories and long term, and short term Crown tenure. Having total footprint identified by
category summarized would be useful. Grand totals should also be provided for each individual
table.
9.2.2
11.3.1.1 54 15 107
Please Clarify - Title (Estimated Fee Simple Tenure Required) is unclear. It appears, from context
that BCH intends to acquire all the land area in the table as fee simple, including area of Crown land
to be inundated (4523ha). In this table and elsewhere through the document the word “Tenure”
used with “Fee Simple” is potentially confusing. Please consider clarifying.
9.2.2
11.3.1.3 55 6 & 7 108
“Rights to the underlying Crown land for the reservoir would be acquired through the issuance of a
Water Act permit from the Province.” This appears to contradict first line of Table 11.3.1 (Land
acquired in fee simple for inundation, including Crown land) - Please Clarify 9.2.2
11.3.2 55 23 109
A BC Hydro Statutory Right of Way may be appropriate for application on land that is currently fee
simple (agreement between proponent and current landowner), but a Statutory Right of Way may
not fulfill BCH’s needs as it relates to a tenure issued by the Province on Crown land. Further
discussion on appropriate tenure types for the desired purposes is required for this and other
tenures.
9.2.2
11.3.2 56 1 110Information Requested - Transmission tie in at Site C is listed as 51 ha, while at Peace Canyon, it is
32ha. Please clarify the reason for the difference at the 2 sites. 9.2.2
Final April 4, 2013 38
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.3.2 56 1 111
Project Access Road - a Statutory Right of Way may not be the correct type of tenure for this
project component. Further discussion on appropriate tenure types for the desired purposes is
required for this and other tenures.9.2.2
11.3.2 56 1 112
Table 11.3.2 Impact Lines are mentioned in Line #1, and then Stability Impact Lines are discussed
separately in line 2. Please clarify if there the difference between the two, or correct the overlap if
one exists.9.2.2
11.3.2.3 57 37-38 113
“road would be classified as a private road to restrict public access to ensure safe operation. ... BC
Hydro would obtain a permanent statutory right-of-way from the Province and...” It should be
noted that a Statutory Right of Way does not restrict public access unless conditions are added to
that effect. Having the road classified as a private road is not necessary to restrict public access
during construction. Other tenure instruments may better suit BC Hydro’s needs.
9.2.2
11.3.2.3 57 37-38 114
In other sections of the EIS it is suggested that the existence of the access road may be a reason to
decommission other roads in the area. Please provide a rationale for the need to keep the road as
private and to restrict public access after construction. 9.2.2
11.3.3.3 59 37 115
“Where exclusive use of the land is required, e.g., for worker accommodation, BC Hydro
would enter into a lease agreement for specific areas.” Note - Most industrial work camps on
Crown land are tenured under a Licence of Occupation. Further discussion on appropriate tenure
types for the desired purposes is required for this and other tenures.9.2.2
Final April 4, 2013 39
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.3.460 &
61
22 – 26,
1 – 2 116
Table 11.3.4 and Reference to Volume 2 Appendix C MAPS, Figures 6 and 7:
The current presentation of information related to Petroleum and Natural Gas subsurface title
versus surface activity approvals makes it difficult to perceive distribution of each and therefore
potential impacts and mitigation solutions. This can be corrected as described below:
a) Figure 6 “Ministry of Energy, Mines and Natural Gas tenures” contains a layer titled “Petroleum
Title Tract”. This layer appears largely incomplete when compared to the subsurface tenures seen
in the “Petroleum Active Titles” layer available from DataBC (GeoBC) and the BC Geographic
Warehouse (BCGW), and also differs from the “Tenures” layer seen in Figure 7.
b) Figure 7 “Oil and Gas Tenures” appears to indicate, in the main, surface activity permits, such as
well drilling permits, issued by the Oil and Gas Commission (“OGC”) and only a few of potentially
affected subsurface Petroleum and Natural Gas title issued by the Ministry of energy, Mines and
Natural Gas (“MEMNG”).
This information, and that listed in Table 11.3.4, could be much better illustrated by separating
surface tenures and permits issued by the OGC from subsurface titles issued by MEMNG, through
the creation of two different map layers. One layer would contain OGC approvals and permits
issued under the Oil and Gas Activities Act and its authority to issue permits under five Specified
Enactments (see OGAA section 1, “specified enactments”). OGC issues approvals for surface
activities. Another layer could show subsurface Petroleum and Natural Gas title issued by MEMNG.
This data is available in the “Petroleum Active Titles” layer from DataBC (GeoBC) and BCGW, or
from this FTP site:
ftp://ftp.mem.gov.bc.ca/CSGISS/PNG_Tenure/
Table 11.3.4 could then list the content of each layer’s data set.
9.2.2
11.3.460 &
61
22 – 26,
1 – 2 117
Table 11.3.4 identifies potential conflicts with a total of 74 tenures issued by the Ministry of Energy
Mines and Natural Gas, however does not differentiate between types of tenures or the Acts
associated with those tenures. Please ensure that all coal and mineral tenures are identified and
conflicts are resolved. For further information, please contact MEMNG.
9.2.2
Final April 4, 2013 40
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.4.2.3 66 11 118
The data provided in Tables 11.4.3 and 11.4.4 and associated figures appears to be inconsistent
with the suggestion that there is considerable attenuation. The identified change of -40 to + 179%
appears to be substantial. Please clarify.
9.3.1 Surface water
regime
11.4.6 83 119
Climate change – modeled changes should be presented given the life of project. This section reads
as if this analysis has occurred, if so, please include this information in the EIS. 9.3.1 Surface water
regime
11.4.2.4.2 68 3 120
Normal operations will have an influence on hydrologic regime but spills may have the greatest
influence. Consider providing more investigation/discussion on spills, particularly larger spills that
have been experienced at the facility and the influence of these spills on downstream conditions.9.3.1 Surface water
regime
11.4.2.4.3 68 7 - 21 121
Please clarify why the timeframe of 2008-2010 was chosen? These years do not include the
greatest range of releases from the facility. Consider looking at both normal operations and spills
to determine potential downstream effects on both the channel and its surrounding infrastructure. 9.3.1 Surface water
regime
11.4 69 12 122
Please clarify why the water years used here for modeling are different than others used through
the report. Consider using complete and similar record length to avoid confusion and for ease of
comparison. 9.3.1 Surface water
regime
11.4 69 2 - 40 123
Please consider modeling the Approach and Methods identified in Section 11.4.3.1 for spill
response as well.9.3.1 Surface water
regime
11.4 76 124Please consider presenting a summary of historical inflow information and modelled findings as it
would aid review. 9.3.1 Surface water
regime
11.4 76 125
Please provide additional detail on the how spills from dams upstream could influence site C. Also,
recommend that historical frequency information be blended into subsequent analyses rather than
Generalized Optimization Model (GOM) only.
9.3.1 Surface water
regime
11.4- Surface Water Regime
Final April 4, 2013 41
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.10
p.11-
171
throug
h 11-
186
126
Please clarify if any stations will be maintained for longer term meteorological and climate
monitoring and if the same standards would be used as other stations operated by BC Hydro. Also,
please consider providing information real time through BC Hydro's weather station network. 9.3.1 Surface water
regime
11.4 127
No mitigation is relevant here or proposed other than upping the minimum flow release in
accordance with the added mean annual discharge through increased catchment area by 100 cms. 9.3.1 Surface water
regime
11.4 128
Reporting of averages over the period of record should refer to the long-term mean annual flow (LT
mad) to make a distinction to the mean annual discharge for a single calendar year. More
importantly, the data treatment describes large differences in natural versus regulated flows that
are already imposed by existing dams. The values could have been better qualified using Tennant-
type coefficients to provide common or equivalent metrics to other know flow determination and
contrasts. What does the minum flow of 283 cms mean in %TL mad at Hudson's Hope and is lower
than that prescribed by rivers with significant braids and side-channels (>50%TL mad). An
equivalent flow of 24%TL mad on a POD or Site C TL mad of 1276 cms is 306 cms which is lower
than the proposed minimum of 390 cms.
9.3.1 Surface water
regime
11.584 to
91129
Please provide a more complete summary of the Technical Appendix E (Water Quality Baseline).
Condensing this subject area to 7 pages from the 233 pages in Appendix E has left out much
information. Please consider revising similar to other Appendices (such as App H) in the
Environment Background Report.
9.3.1 Surface water
regime
11.4.2.1 63
6-12 &
figure
11.4.1
130
Consider adding additional detail to describe the flow interactions with the lakes (Claire lk, Baril
Lake, Mamawi lk., etc. ). 9.3.1 Surface water
regime
11.4.2.1 63 26-33 131
It appears that all that is described for baseline conditions for Site C is that "seasonal runoff
patterns are similar for Site C as... those described for Williston Reservoir" This is not a sufficient
description for this report since the focus is on Site C. Please Clarify if there is additional
information available elsewhere in the EIS. If this information has been collected and not included
in the EIS, please consider including.
9.3.1 Surface water
regime
Final April 4, 2013 42
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.4.2.1 63 26-33 132
It is unclear how the numbers presented are calculated. Please clarify if all the tributaries gauged
and the source of this data was not presented in the report, or was this description of flow
components based on an estimation? If based on an estimation, please discuss uncertainties and
yearly variability.
9.3.1 Surface water
regime
11.4.2.1 63 26-33 133Please clarify what the tributary inflow is in comparison to the mainstem flow. 9.3.1 Surface water
regime
11.4.2.1 62 37-39 134
Please Clarify, it does not appear that an overview of the Peace River was included in Volume 2
figure 11.4.1 as stated, as this is a map depicting watershed boundaries. Please include a map
depicting an overview of the Peace River.9.3.1 Surface water
regime
11.4.2.1 63
6-12 &
figure
11.4.1
135
Please consider revising Figure 11.4.1, as it appears to contain inaccuracies. i.e., some lakes are
amalgamated. The watershed boundary also appears to be in error and lake Athabasca is depicted
as one large lake instead of a number of smaller lakes (Claire lk, Baril Lake, Mamawi lk., etc. ). The
Watershed boundary goes through the middle of the amalgamated lake. This leads the reader to
wonder, does the Peace flow into Athabasca lk and then does the Slave river leaves the Athabasca
lk ... or perhaps as it is on Google Earth does it just changes names at the junction of the outflow
from Athabasca?
9.3.1 Surface water
regime
11.4.2.1 63 4-5 136
Please provide additional detail and description of flow of the Peace River between the Peace
Canyon Dam and the BC/Alberta border.9.3.1 Surface water
regime
11.4.2.1 63 26-33 137
Please provide additional details for this section. It appears that this paragraph is all that describes
tributaries and the mainstem flow regime below Peace Canyon dam to proposed Site C. Please
provide additional detail for this section as more content and depth are needed. As presented in
the EIS, this section is currently insufficient. It is also not clear that any streamflow data was
collected, please clarify if this is the case.
9.3.1 Surface water
regime
Final April 4, 2013 43
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.4.2.1 63 26-33 138
Request the proponent provide the range of inflows and the range of annual variability in addition
to the average range of inflows of 110m3/s that has been identified. 9.3.1 Surface water
regime
11.4.2.1 63 13 139
Although it does not appear to be required by the EIS Guidelines, please consider providing a range
of values, such as min-max, median and 95% C.I. In addition to the mean. This information can be
more valuable, particularly for inflows as they can influence the frequency and magnitude of spills.9.3.1 Surface water
regime
11.4.2.265
Table 1-2 140
For Table 11.4.2, Please provide a rationale for only using data from 1992-2010. 9.3.1 Surface water
regime
11.4.2.3 65 12-13 141
Please clarify how far down the Peace the zone of influence is. Also, please clarify what the zone of
influence is on daily flows? 9.3.1 Surface water
regime
11.4.2.3 65 11-13 142
Please provide additional detail - What is the number of observations in the respective time
periods (pre and post). Is this based on instantaneous or max/min daily mean value? 9.3.1 Surface water
regime
11.4.2.4 66 5-13 143
Please clarify if higher discharges = higher release from the dam. Why would night be less discharge
than the day? Explanation as to cause would be helpful to understand releases and seasonal
patterns.
9.3.1 Surface water
regime
11.4.1 62 12 144
Please provide the data to confirm the assertion that flow is not affected by project rather than
stating it is “expected” to be negligible. 9.3.1 Surface water
regime
11.4.1 64Table
11.4.1145
Table 11.4.1 – indicates Peace R. above Hudson’s hope is approximately 25% of watershed area, yet
contributes close to 58% of mean annual discharge according to table. This appears to conflict with
the argument made in this section that influence of discharge from above Hudson’s hope is not
noticeable at Peace Point, please clarify.
9.3.1 Surface water
regime
Final April 4, 2013 44
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.4.2.1 63 24 - 25 146
"Only 9m3s-1 of inflow is associated with local tributary inflow into Dinosaur Reservoir
Downstream of the W.A.C. Bennet Dam." Please provide the times scale and clarify what the
annual contribution and variability. This statement also appears out of place as the paragraph
discusses the Williston reservoir inflows.
9.3.1 Surface water
regime
11.4.2.1 63 39 147
The data presented is a limited period of record that appears to be missing 20 years of data after
dam construction. Can the limiting station (i.e. 1992) be excluded or two series of records
assessed? The reduced record may influence subsequent analysis.9.3.1 Surface water
regime
11.4.2.2 63
35-45
and
table
11.4.1
148
Although it does not appear to be required by the EIS Guidelines, please consider providing
additional data in table 11.4.1. such as Median flows, monthly Maxs, Mins , Lows, Monthly statistics
(medians and Means) and / or exceedances as well as supporting discussion.
9.3.1 Surface water
regime
11.4.2.2 63
35-45
and
table
11.4.1
149
Please provide a rationale for basing the characterization on only WSC data. In other sections of
this EIS, data was collected and it appears that no streamflow data was collected beyond the use of
WSC sites.
9.3.1 Surface water
regime
11.4.2.2 64 2-10 150Please provide a more in-depth discussion of the data presented in table 11.4.1. 9.3.1 Surface water
regime
11.4.2.2 64 2-10 151Please provide a rational for choosing a partial data set. If the system’s Mean is altered by including
more data, this change should be discussed and explained in the report. 9.3.1 Surface water
regime
11.4.2.2 63
35-45
and
table
11.4.1
152
There are a number of tributaries that are not described or accounted for in this report. Please
clarify if streamflow data was collected to characterize background below the Peace Canyon dam.
If so please include the data in the EIS.
9.3.1 Surface water
regime
11.4.2.3 66 1-6 153Consider including a discussion of the range of flows pre and post. 9.3.1 Surface water
regime
11.4.2.3 66 1-6 154
Please clarify how and why the average Max’s are calculated. Are these daily or monthly or
instantaneous values? Please consider providing rationale for this in the EIS as well as discussing
how other drivers (co-variants) are parsed out of this approach. Please clarify why this approach
was used over more conventional approaches.
9.3.1 Surface water
regime
Final April 4, 2013 45
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.4.2.3 65 11-13 155
Please clarify why the EIS is averaging the maximums and the minimums in this example and how
many observations are in the sample. With no discussion on potential climatic changes and other
flow drivers this procedure is very unconventional. Consider revising this section so that changes
expressed via changes in the exceedance statistics for return period flows of certain magnitudes
(pre and post). Also, consider providing monthly exceedance statistics based on daily avg data
compared to return period (1 in X yr flood) or exceedance values between pre and post (i.e., the 80
(20)% exceedance values pre and post). Please provide additional data so that conditions can be
fully described.
9.3.1 Surface water
regime
11.4.2.3 66 1-6 156
Please consider comparing pre and post flows using probability and exceedance based calculations
based on developing those relationships with pre and post data respectively. Also, please consider
providing a comparison via the return period of flows of certain magnitudes. 9.3.1 Surface water
regime
11.4.2.3 66 1-6 157Please include a discussion and analysis of climatic variables (annual ppt) and the effects that
climatic variability on the pre/post periods selected. 9.3.1 Surface water
regime
11.4.2.3 66 1-6 158
Please provide additional data so that conditions can be fully described. Please clarify why absolute
max and mins are compared in this manner. Please provide a rationale / justification for use of this
approach.
9.3.1 Surface water
regime
11.4.2.3 65 6-8 159
Please provide additional detail as the parameters of the means are not characterized. Is this
referring to daily means, monthly means or Instantaneous mean maximums and minimums?
Also, please clarify what the spring summer means are? Is this April to Sept? Please be explicit with
respect to what mean represents and data used to calculate (i.e., Daily or monthly and measured,
estimated or modelled). The difference between daily means and monthly means can be important
to consider, particularly in the seasons where flow is increasing or decreasing.
9.3.1 Surface water
regime
11.4.2.4 65 16-25 160
This section doesn't fully describe baseline flows, rather it describes BC Hydro operations and effect
on flows. Additional data and discussion of variability in water levels here would be helpful. 9.3.1 Surface water
regime
Final April 4, 2013 46
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.4.2.4.1 67 29-31 161
"the relative contribution of regulated flows to the total flow at downstream locations is the
highest in the winter" - this statement does not appear to be supported or explained in the figure
as identified. Please provide further explanation and consider revising the graphics to clarify this
point.
9.3.1 Surface water
regime
11.4.2.4.1 67 22 162
Increase in discharge during low flow periods of winter may alter ice dynamics along mainstem and
perhaps tributaries as well. Please clarify if there is a discussion about ice dynamics and influence
on downstream damming/flooding elsewhere in the EIS.9.3.1 Surface water
regime
11.4.2.4.1 67 15-31 163
This paragraph presents a figure 11.4.6 that is meant to convey knowledge of seasonal flows and
regulation effects to the reader. Please provide additional description, also, alternate graphics and
data presentations, and additional data would be helpful in providing more clarity 9.3.1 Surface water
regime
11.4.2.4.1 67 30 164Please clarify, it appears that what is actually meant here is Figure 11.4.6 here as 4.7 is a spill trace.
9.3.1 Surface water
regime
11.4.2.4.3 68Table
11.4.5165
Please Clarify: Are the values provided in the table ("daily water level changes" for the three years
2008, 2009, and 2010) annual averages, maxima, or some other statistical measures
11.4.4.2.3 75 166
This section it describes the method of analysis however does not appear to address the issue of
"Spill Frequency, Magnitude, Duration and Seasonality. Please provide additional information on
how the project will address spills of frequency X and what the potential effect on downstream
hydrology is. It is also noted that modeled spills are considerably less frequent than historical
records indicate. Please ensure that modeling is consistent with historical records, or provide
rationale as to why not.
9.3.1 Surface water
regime
11.5.1 84 9 – 17 167
BC-approved water quality guidelines take precedence in BC. Where guidelines for certain
substances are not available working water quality guidelines should be used.
11.5 - Water Quality
Final April 4, 2013 47
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.5.2.1 87 10-39 168
This summary of the report does not report location and dates when TSS exceeds guidelines – this
is a key piece of information that should be presented in this summary (as is done for metals). The
information in the appendix should be brought forward here. 9.3.2
11.5.2.2 84 NA 169
During reservoir infilling, what is the anticipated duration and impact (i.e. dissolved oxygen,
nutrients) to aquatic life of organic material (i.e. leaf litter, branches, bark) that will become
suspended in the water column and/or float on the surface?
11.5.2.2 86 26-227 170
Water quality summary states Williston and Dinosaur reservoirs “show evidence of weak
stratification occurring in the summer period”. However the thermal gradient in the summer near
the dams is significant with surface temperatures up to 17C and the thermal stratification in this
period (as is predicted for Site C Reservoir) has implications for biological and chemical processes
(like DO Depletion) and the significance of the thermal stratification should not be minimized. It
should be noted that the Site C Reservoir is likely to be quite different than either of the upstream
reservoirs for a number of reasons, and further discussion of anticipated differences should be
discussed.
9.3.2
11.5.2.3 87 6 – 8 171
30-day DO concentrations are based on 5 approximately evenly spaced samples over a 30 day
period. Please clarify if this requirement has been met. (see Volume 2, Appendix E).
11.5.2.4 22 – 24 172
BC guidelines state “Change from background of 10 mg/L at any time when background is 25 to 100
mg/L during high flows or in turbid waters; Change from background of 10% when background >
100 mg/L at any time during high flows or in turbid waters”.
11.5.2.4 25 – 35 173
Mean TSS concentrations should be calculated based on 5 samples in 30 days. Please clarify if this
was done. Calculations of mean TSS concentrations over all seasons do not provide insight to when
TSS may be of concern.
Final April 4, 2013 48
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.5.2.4 87 14 – 15 174
Please refer to BC approved water quality guideline for turbidity, suspended and benthic sediments -
http://www.env.gov.bc.ca/wat/wq/BCguidelines/turbidity/turbiditytech.pdf.
11.5.2.5 88 8 – 9 175
Please refer to BC working water quality guidelines for alkalinity.
http://www.env.gov.bc.ca/wat/wq/BCguidelines/working.html#table1
11.5.2.6 88 29 – 30 176
BC’s water quality guidelines for nitrogen include total ammonia nitrogen. Guidance on the
application of the guideline is provided in Table 16 of this document. This should be followed for
water quality assessments in BC.
http://www.env.gov.bc.ca/wat/wq/BCguidelines/nitrogen/nitrogentech.pdf
11.5.2.6 88 – 8941 – 44,
1 – 10177
Please refer to the BC water quality guidelines for nutrients and algae for this assessment. The
guideline of 0.01 mg/L specified in Appendix E of Volume 2 (p. 8) is not a 30-day mean value to
protect aquatic life; it is a maximum value to protect drinking water sources in lakes. The guideline
to protect aquatic life in lakes is within a range of 0.005 – 0.015 mg/L. B.C. does not have a total P
guideline for streams, but do have a maximum value for chlorophyll a of 100 mg/m2 (this
information is summarized in the Water Quality Criteria (i.e., Guidelines) for Nutrients and Algae
Overview Report.
11.5.2.7 89 38 – 40 178
5 samples in 30 days are needed to determine if chronic guidelines are met. Please Clarify if this
was done.
11.5.2.7 89 21 – 24 179
Please clarify which guidelines are being used. Many parameters have both chronic and acute
values (e.g. Al, Co, Cu, Pb, Ag, Zn). A minimum of 5 samples, evenly spaced over 30 days, are
required to determine if average guidelines are met.
Final April 4, 2013 49
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.5.2.7 89 24 - 28 180
The authors refer to CCME (1999) on the development of water quality guidelines. Please be
advised that BC has its own protocol for developing water quality guidelines that should be
followed. BC’s guidelines for aquatic life are developed to protect the most sensitive species, at the
most sensitive life stage, for an indefinite period. BC also allows for the development of site-specific
water quality objectives in situations where the approved guidelines are not appropriate. Guidance
is provided in MacDonald (1997), but it should be noted that we are currently updating our
procedures.
11.5.2.7 89 21 181
The BC water quality guideline for aluminum is for dissolved Al, not total Al.
http://www.env.gov.bc.ca/wat/wq/BCguidelines/aluminum/aluminum.html#tab1
11.5.2.7 90 1 – 29 182
There does not appear to be enough information to do a proper assessment of baseline water
quality conditions. Monitoring should included at least 2 5-in-30 periods (high/turbid flow and
low/clear flow) in order to determine if chronic guidelines are being met. This approach may have
resulted in lower frequencies of guidelines being exceeded (see Table 11.5.2). Clear and turbid flow
periods should be assessed separately.
Appendix E 183
Reference should be made to the approved BC standards for designing water quality studies or
interpreting water quality data (http://www.ilmb.gov.bc.ca/risc/pubs/aquatic/design/index.htm)
(http://www.ilmb.gov.bc.ca/risc/pubs/aquatic/interp/index.htm) 9.3.2
Appendix E 3 184
Section 2 - Data Souces: Report indicates that older data were treated separately using the
rationale that laboratory analytical methods have changed, and earlier data may not be directly
comparable to more recent data. These older data are valuable and in many cases are comparable
to present data and are essential in assessing trends over longer time periods – which may not be
possible with recent data. The older data seems in this case to be discounted – Was this data's
value and relevance assessed prior to being discounted. If so please provide further information on
the rationale for discounting it.
9.3.2
Final April 4, 2013 50
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
Appendix E
3.6.112 185
TKN is defined as being the bioavailable N fraction using McNeely et al 1979 as a reference. Below
(section 3.6.2) SRP is defined as being the bioavailable P fraction but no reference is given. There is
considerable controversy in how bioavailable are defined – perhaps more recent references should
be referred to here? In App P (Part 1 p 38), the sum of nitrate and ammonium (DIN) is used to
define bioavailable N – not TKN.
9.3.2
App E
3.6.113 186
In the discussion of unionized ammonia, a threshold value of 0.019 mg/L is noted. No reference for
this concentration is given, please provide a reference and rationale for use – guideline values are
dependent on ambient temperature and pH rather than a fixed concentration.9.3.2
Appendix E
Section
3 -
Genera
l
187
The emphasis in this section seems to be on metals and nutrients. TOC and DOC should have been
included at least in a preliminary survey or historical data discussed. They have relevance to aquatic
productivity, mercury methylation and drinking water potential as well as many other applications.
Data are included in Appendix J Part 1 p 42 and Appendix P Part 1 p39 and should be referred to
and commented on.
9.3.2
App B,
Geology Soil
and Terrain
Reports -
Part 4
188
Acid Rock Dranage and Metal Leachate Plan This appendix has minimal information related to
water quality other than reference to the geological survey work reported in the Geochemistry
subsection of Volume 2 Section 11.2 Geology, Terrain and Soils. Evaluation of risk is taken from
previous reports and no specifics as to monitoring or assessment during construction other than
shallow well monitoring and a plan to be put in place if a problem arises. There is a mention of
elevated selenium in some area but little comment as to the risk. Some basic specifics for dealing
with ARD and selenium in the event that it becomes a problem would seem appropriate. Consider
worse case situations so as to prepare for mitigation measures. Mitigation of ARD or Selenium
contamination is a concern and needs to be evaluated in more detail than was done.
9.3.2
Final April 4, 2013 51
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
Appendix B
Part 417 189
The discussion of metals shows consistent pattern of association between high metals and TSS. Also
reservoirs tend to have lower TSS concentrations than streams which have higher energy flows.
One of the conclusions that might be drawn from this is that the creation of Site C might reduce the
potential toxicity of metals to aquatic life since the metals would be partially lost from the water
column. Discussion of TSS should be expanded to consider the consequences of TSS on water clarity
in the proposed Site C Reservoir. Water clarity will be an extremely important factor in many
aspects of Site C Reservoir (fisheries as well as chemistry and other aspects of biology).
9.3.2
Appendix B
Part 4
A 4.0
QA /
QC
P 12
189
The QA/QC data seem quite minimal in comparison to what is recommended in standard
references on the subject. The RIC protocols suggest that 10% of samples should be a part of
QA/QC. The evaluation of QA/QC samples does not follow the standard Ministry of Environment
methods. Please clarify what reference was followed in evaluating the QA/QC samples and provide
rationale for use.
9.3.2
Appendix H 190
Reservoir Water Temperature and Ice Regime - The work reported on in this topic area appeared
to be well done. The approach and methods were well explained and used models that seemed
realistic and the results seemed plausible. The only missing aspect would have been to run a similar
modelling scenario for dissolved oxygen. Other measurement and evaluations seem to indicate that
DO is not likely to be an issue but it would have been useful to run a modelling simulation to verify
that DO depletion in the deeper water at the base of the dam would not be a problem. DO has a
major effect on mercury methylation and many other chemical and biological processes, so it is an
important parameter in many ways. DO modelling should be done.
9.3.2
Appendix J 191
Aspects of water quality that affect potential mercury methylation are covered (Part 1 p 42) – but
are not included in the Water Quality Appendix E (sulfate and DOC/TOC) Please provide additional
information. Also, please include consideration of a worst case eventuality as well as the
thoroughly discussed likely case. 9.3.2
Final April 4, 2013 52
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
Appendix P general 192
Part 3 of this Appendix is the most important and the most technically difficult of the sections
related to water quality and aquatic ecology. Predicting changes at different trophic levels and the
interactions between them and the influences of physical and chemical changes that take place in
the creation of a reservoir is difficult. The accuracy of the predictions depends on many factors but
one of the most important discussed here is the many assumptions that are made as a prerequisite
to running models and evaluating the results. Please review the assumptions made with regard to
the models in this section as some appear to be questionable and ensure that the correct
assumptions have been made. More detail on specific assumptions that are cause for concern are
outlined in other comments.
9.3.2
Appendix
Part 3 -
Exec
Summary
p iii 193
The use of the outputs from CE-QUAL-W2 for the predictions of phytoplankton and periphyton
biomasses used as input to EcoPath predictions of potential changes to higher trophic taxa (i.e.,
zooplankton, benthos, and fish) carries with it some risk as the accuracy of the CE-QUAL-W2 model
for biological production seems to carry some weakness. Part of this uncertainty is because CE-
QUAL-W2 was calibrated to data on existing conditions in Dinosaur Reservoir, which as noted above
is not an ideal model for the future Site C Reservoir and part because the strength of the model
appears to be in physical and chemical simulation (rather than biological). The dependency of the
model on the Dinosaur Reservoir data inputs and the assumption that the Site C Reservoir biology,
chemistry and physics will resemble Dinosaur Reservoir is a very poor. The results from W2 are
difficult to accept at the conceptual level. The results of the model indicate that phytoplankton
biomass densities were predicted to increase about 30 times relative to current biomass, in both
the early stage and long term. Average periphyton densities in the simulated reservoir were
expected to decrease to 5% of their current value. The former result (phytoplankton) seems
reasonable the latter (periphyton) does not.
Comment Continued in Next Cell
9.3.2
Final April 4, 2013 53
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
Appendix
Part 3 - Exec
Summary
p iii 193
Comment Continued
The decrease is explained as being a result of the assertion that the littoral of the new Site C
reservoir would be only 10% - presumably of the whole reservoir surface area – however the
reservoir is much larger. On page iv, the loss of complete riverine habitat is given a 29.6 km2 and
the new littoral area is given as 9.42 km2 so a reduction to one third not 5%. (These
inconsistencies need to be corrected and consistent throughout the BC Hydro submission.)
Conceptually the amount of littoral in the Site C Reservoir (from the shoreline out to the 6 meter
depth) should represent a large area if the reservoir averages 1 km wide. The littoral might not
support the same biomass because of lower flow and water movement but that would be partly
compensated by the clearer water conditions in the reservoir providing potential biomass of
periphyton that should be comparable to the riverine levels of periphyon. It is unclear why the
model predicts such huge decrease in periphyton biomass. The BC Hydro Report requires clarity on
the model results. The input of this assumption of substantial periphyton biomass reduction into
EcoPath would change the outputs significantly. It is suggested that the modelling be redone with
different assumptions for data inputs.
Appendix P
Part 1
Fig 3.11
& 3.16194
The relative proportions of phytoplankton versus zooplankton standing crop in Dinosaur Reservoir
is interesting. Figure 3.11 shows wet weight biomass averaging about 1000 mg/m2 in 2010 (about
half that in 2011) but zooplankton biomass shown as averaging about 500 mg/m2 DRY weight in
2010. If the conversion for WW to DW cited is used, then the biomass of the zooplankton would be
about 3X that of the phytoplankton on average. It would be unusual to have an inverted biomass
structure in the plankton community. Although zooplankton productivity is calculated, no estimate
of phytoplankton productivity is provided - only WW biomass (Fig 3.11 ) and chlorophyll (Table
3.10). Please consider including or provide rationale why not.
9.3.2
Final April 4, 2013 54
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
Appendix P
Part 1Fig 3.14 195
The presence of Didymo is significant as it has been identified as a problem species in several other
countries – especially Chile and New Zealand where it has caused considerable ecological
disruption. No reference to this potentially problem species is made. Please clarify if efforts have
been made to verify if Didymo is present and describe.
9.3.2
Appendix P
Part 1
10 (and
other
places)
196
Algal PB is a term used in the beginning of the report but later Periphyton PB is used – which is a bit
confusing (Periphyton Biomass?)
9.3.2
Appendix P
Part 169 197
In Table 3.24, zooplankton for Dinosaur Reservoir is calculated for an area of 9.58 km2 although the
footnote indicates that zooplankton in the littoral (2.56 km2) is negligible. The production should be
assessed over only the pelagic area? (9.58 minus 2.56), which should change the annual production.
The production should be assessed for the littoral (2.56) and pelagic (7.02) zones separately to
assess a more realistic annual production.
9.3.2
Appendix P
Part 1 -
Section 4
92 198
In Hypothesis 4 it is noted that “The reservoir was classified as oligotrophic or ultra-oligotrophic
based on comparison of trophic indicators to other systems of known trophic state and to
classifications in respected text (Section 3.4). On the basis of nutrients and biological production the
conclusion is supported but the Secchi data do not support a classification of oligotrphic . The
reasons for not using the Secchi data and why this metric was rejected should be noted. 9.3.2
Final April 4, 2013 55
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
Appendix P
Part 1 -
Section 4
92 199
In Hypothesis 5 the discussion revolves around spatial patterns of periphyton down the river and
whether it is related to phosphorus concentration – specifically whether the increased loading of
bioavailable P when proceeding downstream causes increased periphyton growth. The conclusion
reached is that there is no increase in algal biomass that corresponds to the increased SRP load.
However, there are other factors that explain the lack of correspondence. The first possibility is that
algal production (and biomass) is limited by light and not by P. Light penetration / transmissivity in
the river apparently was not measured so could not be evaluated as a possible factor in biological
production. Please measure and evaluate this factor as the creation of a dam at Site C and the
presence of a larger body of water in the valley and longer water residence time is likely to result in
higher TSS settling rates and clearer water with more light penetration.
9.3.2
Appendix P
Part 1 -
Section 4
92 200
The rationale regarding defining the littoral zone for Dinosaur Reservoir in Hypothesis 1 has some
problems. There is no problem with the depth chosen (6m) but some of the logic is hard to
understand. One of the arguments for the 6 m boundary was that this was the depth to which light
penetrated allowing photosynthetic growth (“vertical extent of living algal biomass growing on
epilithic surfaces”). However the data presented in Figure 3.1 shows significant periphyton growth
to 12 or 13 meters and it is hard to see how 6 meters can be derived from this particular graph. A
second piece of evidence is the Secchi disc data which shows that these measurements (Table 3.11)
are 4.9 in 2010 and 2.3 in 2011 (a very high flow year). The general relationship between Secchi and
1% light is a factor of between 2 and 3 so in 2010 (the more typical year) the 1% light penetration
depth would be 9.8 to 14.7 m not the 6 meters chosen. While the 6 meters is reasonable, the
reasons used to rationalize the value is not. Please revise the rationale and clarify the points above.
9.3.2
Final April 4, 2013 56
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
Appendix P
Part 2
Part 2,
1 of 4 201
The accuracy of predictive models depends on a number of things. One of the assumptions that the
application of CE-QUAL-W2 to the Peace and Site C Reservoir system seems to make is that the
width of the river is treated as a homogeneous cross section. This is in contrast to Part 1 where
much effort was made to define littoral and pelagic zones since the dominant ecological processes
in each are quite different. In the reservoir after filling, the shore zone out to a depth of 6 meters
would be a system dominated by periphyton as primary producers and benthic invertebrates as
primary consumers. In the dominant pelagic zone (most of the 980 m average width), the dominant
producer is phytoplankton with zooplankton as the next level of the food chain. Without
consideration of these two distinct ecological zones, it is unclear how the model can accurately
model the new reservoir and predict periphyton and phytoplankton quantities. It is recommended
that a more detail/clarification on this modelling procedure and it's accuracy be added to the
report.
9.3.2
Appendix P
Part 2
Modelling
figures
20 202
It is not clear what Figure 4.20 is attempting to portray - Please consider presenting this information
in a different way.
9.3.2
Appendix P
Part 2
Modelling
figures
27 203
In Figure 4.27 the low observed D0 values at Peace 1 (a value of <2 mg/L in 2008) and at Peace 2
that lie considerably outside the predicted concentration line need some explanation. Since they
also occur at the same time at Peace 4 and 5, there appears to be a sampling problem - If the data
are real, please provide an explanation for these low D0 values. If there is any doubt as to their
accuracy, they should be disregarded and not used. Please provide further explanation for the low
D0 value.
9.3.2
Appendix P
Part 2
Modelling
figures
31 204
In Figure 4.31, it appears that the direction limits for ammonium changed in mid 2010 and it seems
strange that the modeled concentration produced by W2 also track this analytical detection limit
change. This also seems obvious in looking at the modeled concentration of nitrate in Figure 4.33.
Please explain.9.3.2
Final April 4, 2013 57
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
Appendix P
Part 2
Modelling
figures
46 205
In Figure 4.46 the simulated DO profiles especially for Peace 3 for mid August or mid September
would be far more useful than July 8 or October 30 which are the profiles shown since the August
and September periods would be the most sensitive and more likely to show if there were any
significant DO depletion in the deeper waters of the reservoir. Please consider revising. 9.3.2
Appendix P
Part 2
Modelling
figures
58 206
The predicted phytoplankton biomass appears to underestimate the observed values fairly
consistently and by a significant amount. This seems counterintuitive for phytoplankton and is also
likely for periphyton. The observed phytoplankton biomass (presumably before reservoir flooding)
should be much higher than after the reservoir has filled and the conditions for phytoplankton are
much more favorable. If this is different there should be more clarification of the data. Please
explain. As a general observation, parameters such as temperature seem to be predicted much
more accurately than biological parameters – which is understood to be the primary purpose of this
modelling.
9.3.2
Appendix P
Part 2
Modelling
figures
118 of
121 5.0
Summa
ry
207
Some of the conclusions reached using CE-QUAL-W2 seem reasonable but others seem less
plausible. One of the reasons for less confidence in the biological predictions may be the reliance of
using Dinosaur reservoir data as a predictor of how Site C Reservoir may function. Dino Reservoir is
very narrow and steep sides and not at all what the topography of Site C is like. Many of the other
fundamental properties (water exchange time, nutrient supply, substrate) differ fundamentally and
will affect how accurately data from one reservoir can be transferred to another. A number of
relevant parameters were modeled including TSS but some prediction of water clarity (which
should have a reasonable relationship to TSS) is not and this would be a critical factor in modelling
both phytoplankton and periphyton biomass and production in the proposed Site C Reservoir. It is
recommended that the modelling be done on the basis of a different comparative that may be
more consistent with the proposed Site C reservoirs.
9.3.2
Final April 4, 2013 58
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
Appendix P
Part 3
Figures
6B.1-4208
Figures 6B.1 - 4: These figures show in visual form what was being attempted to describe in the
above comments. The circles are presumably proportional to the biomass of each individual
component and show the relative small size of the primary producers in comparison to the
secondary trophic level - and the relative importance of the detritus component in the food chain.
Whether or not it is realistic is likely a topic of some discussion. It is recommended that the figures
are clarified.
9.3.2
Appendix P
Part 3
Table
6A209
This table contains much of the basic information that was used in the EcoPath simulation and it is
interesting to look at the larger view of the applicability and if some of the quantitative estimates of
the trophic components – especially how primary and secondary levels of production quantities
look in what might be seen in a more conceptual view of the Site C Reservoir biota. With
phytoplankton biomass estimates at 2.25 t/km2 and the levels of secondary biomass of cladocera
(2.1) and copepods (3.8) indicate similar quantities of biomass in the water column for all three
groups (on an average basis) which unusual but not unrealistic. Whether or not this biomass of
phytoplankton would provide a sufficient food base for zooplankton would primarily depend on the
P/B ratios that are applied to each group. The choice of P/B ratios is important and the values used
differ in this report from some used in the literature. Similarly the comparison of the biomass of
benthic algae in the reservoir at a low 0.6 t/km2 and the benthic invertebrate biomass at 3.8, the
chosen P/B ratios are critical in assessing whether the modeled biomass values are reasonable. The
wild card value that was used was for detritus at a very high 50t/km2 – presumably will compensate
for the low periphyton biomass as a food source for benthic invertebrates. However the detritus
value is given as a “guesstimate” with no indication of what it was based on. It is recommended
that additional clarification is required regarding the biomass modelling and the P/B ratios.
9.3.2
Final April 4, 2013 59
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
Appendix P
Part 3
Section 3
12 210
In this section some of the background for the W2 output values for phytoplankton and periphyton
to production quantities poses a possible source of error. The table indicated P/B ratios of 43 for
periphyton and 28 for phytoplankton. Typical "average" P/B ratios cited in textbook sources like
Wetzel (2001) are much higher (113 is the value cited for phytoplankton). The result would again be
an underestimation of primary production. Please address9.3.2
Appendix P
Part 3
Table
3.2
P. 15
211
The extrapolation of the W2 output values for phytoplankton and periphyton to production
quantities is another possible source of error. The table indicates P/B ratios of 43 for periphyton
and 28 for phytoplankton. Typical “average” P/B ratios cited in textbook sources like Wetzel (2001)
are much higher (113 is the value cited for phytoplankton). The result would be again be an
underestimation of primary production. Please address9.3.2
Appendix P
Part 3
Table
4.1,
P 18
212
The table shows are of littoral using a 10 m depth of light penetration - which may be a more
realistic estimate. However it is noted that all calculations use the 6m assumption. These
inconsistencies need to be addressed in the BC Hydro Data. 9.3.2
11.6.1 92 20 - 22 213
" An evaluation of project construction on groundwater (GW) quality indicated that there is a low
likelihood that GW chemistry would undergo change and affect GW use". No rationale has been
given for this statement given. Please make reference to the relevant sections that support this
statement.
9.3.3
11.6.10 101 3 - 5 214
Please ensure that, when developed, the "Contaminated Site and Groundwater Quality
Management Plans" include ongoing GW quality monitoring as needed and appropriate to identify,
characterize, monitor, and remediate any impacts associated with GW elevation rise. 9.3.3
11.6 - Groundwater Regime
Final April 4, 2013 60
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.6.4.2
Genera
l
comme
nt
215
The condition of a well may affect the water quality, such as pathogens, especially shallower wells
in proximity to the reservoir shoreline where there is greater change in groundwater levels. The
conditions of the drinking water wells should have been assessed as part of the field program to
assess whether there were any sanitary issues with them.9.3.3
11.6.4.2 95, 961 - 36;
1 - 5216
When a reservoir fills and groundwater (GW) gradients are changed, the redox can have a
significant influence on the water quality (e.g., Fe, Mn). Experience in Revelstoke in the mid-1980’s
suggests when reservoir levels are high there, the well water quality deteriorates; when the
reservoir level drops, water quality improves. Establishing redox conditions initially will help
address likely causes of changes in well water quality during construction and operation of Site C. It
appears redox was not measured. BCH should measure redox conditions and assess potential
implication for well water quality during dam construction and operation.
9.3.3
11.6.4.3 11-96 6 - 21 217
Modelling work should be consistent with best practices documented in: Guidelines for
Groundwater Modelling to Assess Impacts of Proposed Natural Resource Development Activities9.3.3
11.6.4.4 96 31 - 34 218
It appears that contaminated sites have been identified in or near the flood zone. What is the
remediation strategy for the contaminated sites before the construction of the reservoir to make
sure that the risk of groundwater contamination is minimized? It should be noted that
groundwater contamination may affect the entire regional aquifer if it gets polluted at some part of
an aquifer.
9.3.3
11.6.5.1 97 9 219 Information on the springs can help identify potential aquifers to allow assessment of impacts on
them? Please clarify if the flow and chemistry of these springs was measured. 9.3.3
Final April 4, 2013 61
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.6.5.2 97
General
comme
nt
220
The effect of groundwater level changes on slope pore pressures and risk of slope instability has not
been addressed in Section 11.6. Slope stability was briefly referred to in the EIS Guidelines for the
Groundwater Regime in Section 9.3.3 (2nd bullet). The affect of groundwater level changes on risk
of slope instability should be assessed, and if so should be briefly described here as well. 9.3.3
11.6.5.2 98 8 - 12 221What are the specific implications for those wells, springs, infrastructure and land use that could be
affected? 9.3.3
11.6.6 98 30 - 32 222
Please clarify what, if any, remedial measures will be implemented to minimize contamination of
water sources before filling of the reservoir. Mitigation measures should include initial and ongoing
GW quality monitoring (as needed) in inundated agricultural areas to assess and monitor impacts
associated with GW elevation rise. In particular, monitoring should address soluble pollutants
related to agricultural activities (e.g., nitrates).
9.3.3
Section
11.6.6223
Please clarify if project has the potential to impact the groundwater regime in surrounding
tributaries (eg. Halfway, Moberly)? Groundwater upwelling is an important environmental factor in
bull trout red site selection.
11.6.7 99 2 - 4 224
Groundwater quality could become influenced in situations where either a flooded septic field or a
contaminated site with impacted groundwater is located in close proximity to an operating water
well. For impacted domestic water wells, please consider including initial and periodic GW quality
monitoring (as needed) to assess and monitor (if needed) any associated effects between GW
elevation rise and GW quality as mitigation measures.
9.3.3
11.6.7 99 2 - 4 225
Six know/identified water wells are expected to undergo direct submersion. Please clarify if
alternative potable water sources have been identified for the current water users in the area after
decommissioning these wells. 9.3.3
Final April 4, 2013 62
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.6.8 99 32 - 33 226
In addition to the loss of the agricultural land, formation of wetlands may also occur along the sides
of the reservoir where groundwater level rises to the surface, which leads to a significant eco
system change in the area. Please clarify if this scenario has been considered in the EIS.9.3.3
11.6.8 99 15 227
Please expand the study to identify known and potential aquifers and assess what percentage of
aquifer areas may be lost. 9.3.3
11.6.9 99 35 - 40 228
It has to be emphasised that, decommissioning of structures and remediation of contaminated sites
before the inundation is a very critical step to minimize the risk of contamination of regional
potential aquifers in the area. Polluting a regional aquifer will aggravate the already stressed water
resource condition in the region.
9.3.3
11.8.4.1 130 23-27 229
Please clarify why the minimum duration of wetted work was used in the calculation of sediment
loading. The precautionary principle would seem to push one towards using the maximum
duration.
11.8.5.1 138 28-36 230
Please clarify the following issues within this section.
1. Talks about grain size bias in the sampling and having to estimate the grain size curves. If that
was the case, why was it not re-sampled?
2. Why was there limited site access to the shoreline resulting in Lidar being uses instead.
3. Thickness of colluvial deposits were estimated based on LIDAR imagery – please clarify if any test
pits were done, and if not, why?
11.8.5.1 139 40-45 231
This paragraph describes the ‘acceleration’ of the sediment deposition model by applying a
multiplier of 10 to a 5 year run to simulate that of a 50 year run. While not knowing the nuances of
the model they were using, this sort of ‘jiggling’ does raises concerns if more detail is not provided.
11.8.6 145 10 232 Please define ‘Further downstream’. How far downstream?
11.8- Fluvial Geomorphology
Final April 4, 2013 63
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
11.9 30 233
Baseline is here is defined as conditions prior to anthropogenic disturbances. The report does not
discuss whether baseline metal data is available prior to the development of the WAC Bennett and
Peace Canyon dams.
11.9 19 234
Baseline conditions are defined as after the installation of the WAC Bennett and Peace Canyon
dams. A baseline selected in the pre-regulation period would be more suitable when considering
aquatic organisms.
11.9 29 235
Mean peak concentration was used to on the assumption that this better approximates typical
human exposure (eg. eating fish). This does not indicate the range in Hg levels and does not
quantify the distribution of samples around this mean (eg the percent of the population with Hg
concentrations that may result in behavioural or reproductive impacts).
236There is no discussion of what effects the predicted Hg values could have on fish health and
behaviour for the species in the Peace
11.9- Methyl Mercury
Section 12 - Fish and Fish Habitat
Final April 4, 2013 64
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.1 237
Focus is on a limited subset of fish species - The fish fauna in the Peace River system is diverse (39
spp.) and provincially distinctive and this is adequately not reflected in the EIS.
Concern: The depth of information on species assemblages and individual species varies in the EIS,
with detailed treatment available on a relatively small subset of species, primarily the more
charismatic ones.
Request that the Proponent:
(a) Clarify what empirical data exists on fish species and populations not emphasized in the EIS (see
Detailed Examples).
(b) Where empirical data exists on other fish species, summarize the status and future outcomes of
these species and populations in the LAA and RAA.
Final April 4, 2013 65
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.1 238
Arbitrary division of fish fauna into large-fish and small-fish components - The EIS splits the fish
fauna into large and small fish for some assessments, however, such a division appears arbitrary, is
not well supported and may make assessments inaccurate.
Concern: The division of the fish fauna into “small” and “large” appears arbitrary and not provided
with references from biological study (pg12-25, line 29). Assumptions on seasonal and annual
movement/migrations life history functions of small species are questionable without supporting
references. For example, the statement that the ability of a “fish” to move extended distances
(upstream) is related to its maximum size may be true for large fish in the short-term (1 year);
however, many small fish move upstream as an essential life-history function (e.g., sculpins), it may
take several generations to complete the same distance a large fish does in one season, but it is no
less important to biodiversity and survival of the “small” fish species.
Request that the Proponent:
(a) Redo the assessment without the seemingly arbitrary division into large and small fish (unless
solid support for this approach can be provided from the literature).
(b) Provide literature sources to support assumptions on the ranges and temporal movements of
small fish species over periods of time (e.g., annual vs. longer periods).
(c) Clarify whether sufficient empirical data exists on small-fish species and populations for the
Project area. If this data exists, summarize and discuss the status and future outcomes of these
species and populations in the LAA and RAA.
Final April 4, 2013 66
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.1 239
Arbitrary division of fish fauna into large-fish and small-fish components: More detailed
evaluation of focal species is a reasonable approach, but non-focal species receive too little
attention. Monitoring is needed to verify important assumptions in the analyses, particularly where
the information base is limited.
Concern : Since the decision not to focus on some species was due to the limited information base,
attention should be given in follow-up programs to improve information on those species and
monitor to evaluate whether assumptions used in the assessment of impacts are reasonable (and if
not then impacts must be addressed after the fact). For example, there appears to be a general
assumption that small fish don’t migrate and therefore won’t be affected by entrainment or
blocked passage.
Request that the Proponent:
(a) Provide a rationale (with references) for the general assumption that small fish don’t migrate
and therefore won’t be affected by entrainment or blocked passage.
(b) Monitoring should include fish species other than focal fish species in order to test assumptions
applied in the EIS to assess impacts.
12.1 240
Habitat suitability, preferences, and effects of altered flow regimes - The suite of habitat values
appears to be comprehensive but habitat suitability and preference information is incomplete.
Concern: A large body of information has been brought to bear on understanding fish populations
and potential impacts. Inclusion of this information would help clarify current fish species and
population distributions (see Question 2).
Request that the Proponent:
(a) Describe the present use of the Peace River and its tributaries by Arctic grayling and other
species by life stage
Final April 4, 2013 67
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.1 241
Habitat suitability, preferences, and effects of altered flow regimes - The impacts of daily flow
fluctuations in the Peace River downstream of the proposed project are poorly addressed in the EIS.
This is a substantial omission from the assessment.
Concern: Daily flow variations associated with the dam would increase in magnitude as a result of
the project, and high flow periods would shift from night to day. These changes will likely result in
impacts over a large spatial scale (downstream to the provincial border) but the impacts and
residual effects on fish are not addressed in the assessment.
Request that the Proponent:
(a) Describe potential uncertainties related to predictions of the future quality of habitats
downstream of the Site C dam. Including the effects of flow variations and the consequences of
shifts away from typical daily flow variations for fish populations.
(b) Provide a synthesis of available information on depth-velocity/physical habitat to explain
existing fish distributions and likely future outcomes in response to the Project.
Final April 4, 2013 68
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.1 242
Ranking of fish habitat and fishing values - Habitat-related and recreational fishery-related Valued
Components are poorly defined.
Concern:
The replacement of river habitat for high-throughput reservoir habitat is a key consideration for
valuation. Values for river versus reservoir habitat and fisheries are different. Overall harvest is the
value examined; however, angler preferences and other factors influence the valuation of existing
and future habitats and fishing opportunities.
Species changes between the existing river environment and the future reservoir may limit the
attractiveness of the future reservoir fauna to recreational anglers. Anglers may place higher value
in catching a bull trout than a kokanee. LGL (2009) (and roughly, table 24-7) indicates that the vast
majority of fishing effort is currently upstream of the Site C dam location. A survey of current users
may indicate a lower perceived value of reservoir habitat. If this is the case, the two types of fishery
are not weighted equally, which could imply a significant reduction in recreational fishing values
overall.
Request that the Proponent:
More thoroughly assess impacts to fish values in the future reservoir in regard to potential
recreational fishery. Talking to the resource users about their perceived valuation of these
components would add useful (and relevant) context to the EIS. To answer this properly, an angler
preference survey (or some similar method) would be useful.
Final April 4, 2013 69
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.2 243
First Nations fishery values - It is not evident whether the EIS includes First Nations harvest levels
for food and ceremonial purposes as an indicator..
Concern: Fish Values for First Nations received little attention, and should be expanded upon.
Request that the Proponent:
(a) Provide information on the current status of FN use of fish in the LAA and RAA, as available;
and
(b) Assess how First Nations harvest of fish for food and ceremonial purposes might change as a
consequence of the Project.
12.3 244
Limitations to understanding current status of species and populations: Assessment data appear
to be predominantly qualitative or “index level” - There are shortcomings in quantitative
information on some components and attributes of the fish and fish habitat values. Also the level
of detail for habitat descriptions varies between main-channel Peace River and its tributaries, and
among the tributaries.
Concern: Basic biological information (baseline or background) was not presented for most species
in the LAA, tributaries to the LAA, and the RAA. Most assessments are made on the higher profile
“focal” or “charismatic” species.
Habitat is described as suitable for fish sporadically and with varying degrees of detail: For
example. There is no comment on suitability of habitat for fish in areas with known information
(e.g., Chowade or Murray), but fish habitat values are described in areas with less information (e.g.,
Cypress described as high and side channels in Moberly identified as important spawning and
rearing habitat for northern pike)
Continued in next box
Final April 4, 2013 70
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
244
Previous Comment Continued Request that
the Proponent:
(a) Describe the limitations of the fish population assessment procedures used and the
consequences for the level of uncertainty about current population status, in order to provide a
more credible context for comparing the current fish fauna with the projected outcomes for the
Site reservoir, its tributaries, and the portion of the Peace River downstream of the dam.
(b) Explain how “general patterns of distribution and abundance” (incidental, scarce, restricted,
abundant) were quantified to develop numerical stock status. Include a definition of these terms as
used in the EIS. Is this based on data from Table 5.2.2 (p. 72)?
(c) Include a discussion of abundance versus distribution when observations appear somewhat
contradictory. For example, Arctic grayling were listed as scarce in the Peace River mainstem in BC
(limited to a few areas and not abundant), but are recorded as widely distributed along with bull
trout (found in 6 of 9 survey zones in mainstem Peace) section 5.2.2 (p. 76). See p. 72, 80, 104.
Continued in next box
Final April 4, 2013 71
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
244
Previous Comment Continued Detailed
Example:
According to the Fish and Fish Habitat Technical Data Report and supporting consultant reports, the
fish inventory/stock assessment methods essentially involved localized sampling at spatial intervals
in both the Peace River LAA/RAA and tributaries to the Peace River in the LAA, most frequently in
marginal shallows. Gear used varied based on site conditions and could include various
combinations of large and small-boat electrofishers, backpack electrofishers, beach seines, and gill
nets. Sample sites included main-channel margins, side channels, and tributary junctions. Fishing
effort and habitat types were recorded, but data generated were limited by several factors
including emigration/immigration from the non-enclosed areas surveyed and the differential ability
to catch different species and life stages.
These surveys were accompanied by fish fence operations to document spring and fall use of
tributaries, rotary screw traps to obtain indices of downstream fish movements in the Peace River
and tributaries, bull trout spawner and red surveys in one drainage, movement studies of sport fish
by radio telemetry, and fish habitat descriptions throughout the LAA/Peace River RAA.
Final April 4, 2013 72
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.3 245
Lack of description of methods for fish assessment - It was difficult to find details on
methodologies employed for fish population assessments. The inventory methods employed are
generally not well described in the main body of the report. Field assessment techniques are not
even mentioned broadly by name.
Concern: The type of data collection approaches and sampling methodologies used will generate
estimates for current fish species and populations that carry a level of uncertainty that is not fully
discussed in the current EIS. This uncertainty carries through to the Impact, Mitigation, and
Residual Effects components of the EIS.
A lack of information on methodologies makes it difficult to determine the level of rigor around the
status of fish resources and determine whether fish and fish habitat inventories and the
information they generated are credible. Based on what is known about the methods, there is the
potential that total abundances, biomass, and productivity of species in the Peace River and its
major tributaries within the LAA are currently underestimated. This will affect the evaluation of the
success of project’s mitigation actions including the reservoir “replacement” fish community, and
residual impacts. Uncertainties also need to be clearly defined.
Final April 4, 2013 73
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
245
Previous Comment Continued
Request that the Proponent:
(a) Provide more details in the text of the EIS regarding methods of fish population assessment or
provide clear cross-references and links to relevant supporting documentation.
(b) Provide a more fulsome presentation and discussion of uncertainty to present a more credible
context supporting existing fish population and habitat assessments and projected future outcomes
after the Site C completion.
Detailed Example:
See specifics in detailed examples above. The studies are variously and vaguely termed as
“standardized fish investigations” or “structured and repeated fish collection methods”, but the
reader needs to look into the appended Fish and Fish Habitat Technical Data Report, supporting
documents, and sometimes deeper into the referenced literature by accessing web-based search
engines (usually consultants reports) to find out enough about methodologies to determine
whether fish and fish habitat inventories and the information they generated are credible.
Final April 4, 2013 74
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.3 246
Issue: Incomplete sampling or analysis of fish habitat and population data - Fish
population/community sampling (and habitat sampling in some locations) was distributed unevenly
across the project area. For example, no fish community sampling was conducted over the dam
site. The species composition of the fish fauna in the LAA and RAA portions of the Peace River and
major tributaries to the LAA, and the relative abundance are described primarily in a qualitative
sense. Population status is not described quantitatively. Descriptions are based from sampling
programs and studies which generated qualitative data or semi-quantitative index data at best.
Request that the Proponent:
(a) Provide a rationale to explain variation in level of sampling in different areas within the LAA
and RAA, and for the analysis and presentation of a subset of the collected data. For example: (i)
Only 2011 data for fish abundance was presented. The EIS states that similar patterns were
recorded in 2010 and 2012. What was the justification for only presenting the data from one year
when 3 years of data are available? (ii) Tributary data on fish were collected in both 2008 and
2009. Why was only 2009 data presented? (iii) It appears that
no mesohabitat data were collected for the lower, middle mainstem, and upper East regions of the
Kiskatinaw River. Also, no macrohabitat information was presented for upper east and upper west
regions. Clarify whether data was collected for these areas and, if it exists, why it was not used in
the assessment.
(b) Clarify if habitat data were collected for lower and middle main-stem Beatton. Is there a
forecast of how will the lower reaches of the Beatton and other tributary streams may be affected
by flow changes?
(c) Re-analyze fish population and community information using all available data (including gaps
noted above).
Final April 4, 2013 75
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.3 247
Incomplete sampling or analysis of fish habitat and population data - There is uncertainty
regarding the contribution of mainstem Peace River spawning to population recruitment and the
diversity of fish using side channel habitats.
Request that the Proponent: Provide additional information to substantiate the EIS claim of a
relative (or lack of) importance of Peace River spawning habitat (mainstem spawning to
recruitment of nearly zero; pg 12-27, line 21), and the relatively low level of diversity associated
with side-channel fish community composition (pg 12-28 line 29; see Details)
Additional Details: 12-28, 29: The statement that mainstem side-channels support only 5 fish
species is questionable. Side channel (and tributary) productivity and diversity often greatly
exceeds that of river mainstems. These areas also supported abundance and diverse benthic
macroinvertebrates communities, and therefore were essential for juvenile and larval fish such as
the Arctic Grayling. Perhaps the Peace River is different, but no references are provided.
Final April 4, 2013 76
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.3 248
Use of relative abundance and total biomass to characterize current and future fish faunas - The
EIS would be improved with reliable quantitative estimates of population abundance, productivity
(e.g., biomass), and distribution by habitat and life stage. Limited or little quantitative fisheries
information was presented for most species. Stock assessment data are qualitative at best. True
abundance and biomass data are needed. These characteristics are therefore incompletely known
for the Peace River and its tributaries in the LAA. Habitat suitability information by life stage and
species would be helpful.
Concern: The quality of the data describing baseline conditions will affect the interpretation of
potential impacts to fish and fish habitat values, and the relative success achieved by the post-
project replacement fauna in the reservoir.
Additional Details: Use of the metric “long-term average standing stock biomass” seems a
simplistic and inadequately defined measure of the fish community. Also there is no biodiversity
measure, and as written implies the replacement of several fish species with another fish species is
not a significant residual effect if the comparisons are made only in terms of biomass.
Request the Proponent: Describe species and life stage abundance and distribution at mesohabitat,
reach and larger scale to the extent that sufficient stock assessment data are available. Such
information would clarify the use of the main channel of the Peace River by several species
including Arctic grayling. This would be preferable to the existing EIS approach of using broad
measures of faunal and focal species biomass for characterizing current status.
Final April 4, 2013 77
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.3 249
Uncertainty about the spatial boundaries of discrete fish populations and the importance of
migrations - The relationships between populations in the LAA and its tributaries, and the RAA
portion of the Peace River and the LAA are uncertain; for example, the role and importance played
by seasonal migrations for spawning and other life history phases. These relations are also
described primarily from qualitative information (indices of seasonal migrations, spawners). The
separation of resident versus migratory components for different species such as bull trout in the
LAA remain problematic.
Uncertainty exists on (1) the relative abundances of migratory vs. resident populations of species
using the same drainages for spawning and rearing; e.g., Halfway River bull trout; and (2) the
contribution to spawning populations in the LAA and its tributaries made by migrants from the
Peace River originating downstream of the proposed Site C dam. These uncertainties affect the
nature and level of project impacts as well as mitigation strategies and effectiveness.
It is unlikely that detailed migration studies have been completed for the majority of species in the
area (information used from other biogeographic zones is probably not transferable).
Concern: There was limited description of the species, life-stage, timing, and quantity of fish
migrating by the proposed Site C dam site, especially for small fish, or at other possible dam sites.
Most of the techniques and information presented in Section 12 and the supporting technical data
report related to determination of presence/absence of fish species.
Comment Continued in Next Cell
Final April 4, 2013 78
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
249
Continued
Radio telemetry work to define fish migrations seems sufficient to get a general impression of
migration timings and distances, but inadequate to quantify the characteristics of the population
proportion migrating, range of migrations, migration frequency, etc., as the number of species and
sample sizes of tagged fish were small and limited to a size of fish that could carry tags. Tag
(battery) life was relatively short compared to the lifespan of the species. Results could also be
limited by river conditions and the very large geographic area. Also, capture locations were few,
relative to the number of populations and life-history types potentially present. Therefore, it
appears conclusions are qualitative with no measures of confidence (uncertainty) possible. Mark/
recapture work had similar limitations, and was limited to fewer species.
Request that the Proponent:
(a) Acknowledge gaps in the current understanding of life histories and spatial extent of
populations throughout the LAA/RAA.
(b) Describe the implications of these gaps in regard to the uncertainty about the status of current
populations and comparisons to future post-Site C fish fauna outcomes.
(c) Describe the approach to estimating resident and migrant components of different fish
populations, e.g., Pine River bull trout, including the level of confidence in these estimates.
(d) Review assumptions/ conclusions on longnose sucker movements being “local”.
Final April 4, 2013 79
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.3 250
The definition of fish population and method used to define their geographic areas may be out-of-
date and incomplete. The “same point of time” portion can be broadly interpreted.
Contemporarily definitions of populations contain a component such as “a distinct group which has
little demographic or genetic exchange”. Use of a “geographic area” to define a fish population
may not be correct for highly migratory species such as those found in the Peace River. With Bull
Trout, for example, it may be more appropriate to use genetic clustering methods to define
populations. Assuming a geographic population structure may over estimate structure (see
Warnock et al. 2010). [Warnock, W.G., J.B. Rasmussen, and E.B. Taylor. 2010. Genetic clustering
methods reveal Bull Trout (Salvelinus confluentus) fine-scale population structure as a spatially
nested hierarchy. Conservation Genetics 11:1421–1433.]
12-29, 44: The Peace River is likely a migration area from more than “several”, or 8 of the 32-39
fish species in the watershed. The provided list of 8 excludes all the “small fish” such as redside
shiner and longnose dace, which probably depend on the mainstem as a migration corridor. Small
fish do migrate, both at the individual and population levels. The summaries of the fish studies in
the appendices indicate many of these small fish species were caught in trap nets, which suggests
they were moving over some distance. Daily migrations may be short for most individuals, but
seasonal and occasional (every few years) migrations may occur and be important for population
persistence.
Comment Continued in next cell
250
Comment Continued
Longnose sucker movement strategy is describes as “local”. This conclusion should be reviewed.
This species is long lived (20+ years), can grow to a large size (30-50 cm), are numerous in the
project area, and there is some evidence of local, complex, and possibly long migrations (see
McLeod et al. 1978, in McPhail 2007). They do spawn in streams, and they do migrate in other
areas (Bailey 1969; Montgomery et al. 1983), which suggests spawning migrations could be long,
involving main-stem Peace River and downstream end of tributaries. This is suggested in the EIS in
12-26, line 33.
Final April 4, 2013 80
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.3 251
Uncertainties about life histories - The use of “general life history parameters” is probably not
appropriate for many of the fish populations in the Peace River (Page 12-9 line 14).
Concern: Location-specific information should be provided to supplement the more general
understanding of life history and habitat, particularly for focal species. There is little information
specific to the Project area for many of the fish species assessed but life history characteristics can
vary with location, for example, due to hydrology. Where local information is not available,
descriptions from other freshwater biogeographic zones may apply (e.g., on migration timing,
distances). Key publications describing these species in BC (e.g. McPhail 2007) often rely on studies
conducted in other parts of North America, or the world.
For example, little is known about the habitat used by different life stages of mountain whitefish in
central and northern BC and life-history characteristic of the longnose sucker are based on accounts
from elsewhere in N.A. However, these species are the most abundant in the project area (McPhail
2007) and are likely keystone species, similar to salmon in coastal rivers e.g., as drivers of
productivity and nutrient dynamics. Both mountain whitefish and longnose suckers are highly
migratory with at least 5 known migrations and associated habitat shifts:
• post spawn fall migrations to overwintering sites
• spring feeding migrations
• summer feeding migrations
• fall pre-spawning migrations
• spawning migration
Comment Continued in next Cell
Final April 4, 2013 81
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
251
Above Comment Continued
Request that the Proponent:
Clarify sources of location-specific information on fish species used in the assessment. (See also
previous Comment re “Uncertainty about the spatial boundaries of discrete fish populations and
the importance of migrations”)
Additional Details
Page 12-16, line 1: Table 12.7: Pygmy Whitefish have fluvial populations in the interior of BC,
although little is known about their life history and ecology (see McPhail 2007, p. 381) ().
Reference: McPhail, J.D. 2007. The Freshwater Fishes of British Columbia. The University of Alberta
Press. Edmonton, Alberta.
Final April 4, 2013 82
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.3 252
Issue: Definition of baseline conditions - Baseline conditions are defined as present conditions, but
the true baseline is the pre-impoundment pre-flow control era for the Peace River
Concerns:
12-9, 10: There may be trends in fish populations that are relevant to the overall assessment of
impacts and residual effects. It is likely that the Peace River is still adjusting to the original
perturbations caused by regulation (e.g. geomorphologically) and the fish community may be
undergoing a long-term adjustment. While it may be unreasonable to consider pre-impact as the
baseline, it is still a useful reference point.
12-46, 15: The use of current conditions as a baseline for temperature may be problematic.
Particular attention should be given to the historical condition, since that is the important context
for the native fish fauna and their preferences and tolerances. The EIS predicts that the proposed
Project will have limited effects on water temperature. However, when superimposed on prior
changes, the incremental impacts could be greater than projected. Therefore, current condition is
not the only baseline that needs to be considered.
Request that the Proponent:
(a) Include a description of pre-impoundment conditions to use as a reference point.
(b) Review trends in fish populations since the existing dams were created and report on trends
relevant to the assessment.
(c) Provide a review of the extent to which water temperature changes due specifically to this
Project are diminished due to the already regulated state of the river. What are the cumulative
effects of all impoundments (existing and proposed) on water temperatures and fish?
Final April 4, 2013 83
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.3 253
Lack of aquatic nutrient data from the Peace River and tributaries - Orthophosphorus data was
only collected in 2007/08 and in 2010. No total phosphorus data was collected.
Concern: Orthophosphorus and total phosphorus would further inform a description of future
forebay epilimnion and aquatic productivity. This is likely a limitation to the productivity model
accuracy, as is the apparent homogenization of the limnetic area with an overly optimistic level of
productivity – which would result in an overestimation of predicted secondary productivity levels
and fish populations abundance/assemblage.
Request that the Proponent:
(a) Clarify if empirical data on orthophosphorus are available to refine forecasts of future
conditions; and
(b) If these data are not available, provide a more complete discussion of uncertainty associated
with these forecasts of forebay epilmnion and aquatic productivity.
Final April 4, 2013 84
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 254
General categorization of effects and identification of interactions - Conceptually, the
categorization and identification of ecosystem components and processes affecting fish and fish
habitat both within the Local Assessment Area (LAA) and Regional Assessment Area (RAA) are
generally complete and well laid out as are the potential interactions and impact sources over all
phases of the project. However, there is concern that all identified impacts have not been fully
described.
The broad scale outcomes where the interactions were judged significant, are well described in
general. However, there is uncertainty in the full extent of outcomes for the LAA, its tributaries,
and the RAA for fish and supporting trophic levels (see below).
Concern: Significant effects were identified for several stocks of fish including Moberly River Arctic
grayling, Halfway River bull trout, and Peace River mountain whitefish. The possibility of losing
these stocks was acknowledged.
However, the description of the likelihood of these outcomes could have been improved. The
projected effects on other fish species varied in level of detail, and modelled effects on other
trophic levels raised concerns linked to models used, assumptions, and input data (see below).
Final April 4, 2013 85
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 255
Describing any and all impacts associated with the Site C development as “potential” - The
damming of the Peace River, the consequent disruption of fish migrations, the elimination of river
habitat, the creation of reservoir habitats, the changes to the flow regimes associated with the
operation of the dam, and alterations to fundamental ecosystem processes are all clear and certain
impacts to aquatic habitats. This is not reflected in the text of the EIS.
Concern: The project will certainly alter and impact habitat. The use of the term “potentially” sets a
tone that does not particularly establish an atmosphere of openness. The text should indicate that
habitat will be affected, as this is the subject of the EIS content around mitigation. The term is
inconsistent with the report’s findings and could be interpreted as misleading (pg 12-1 line 4).
Request that the Proponent: be more forthcoming in the EIS about the obvious changes that will
occur to Peace River and its aquatic communities. This would establish a stance that strengthens
confidence and credibility support of confidence and credibility in the EIS. It is also the reality that
drives the project components concerned with mitigation, residual effects, and cumulative effects.
Final April 4, 2013 86
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 256
Evaluating the significance of fish community changes - Comparisons of Peace River fish faunas
with Site C reservoir faunas were made primarily from the perspective of community biomass.
Concern: The method of evaluating significance is based on evaluation at the community biomass
level, rather than at the species level. The grouping of fish species can be misleading and it can
mask species specific effects. Increases in fish biomass are not equivalent to increases in
harvestable fish biomass. The species and proportions that are harvested depend on a number of
other factors such as, availability, catchability, regulatory regimes, angler preferences, etc.
Significant changes in relative and actual species composition should be considered as well, this is
not captured by using total biomass as an indicator.
It is unclear how a biomass-based significance criterion will capture the goals in the provincial
Conservation Framework that pertain to species diversity and conservation.
Using biomass as a criterion does not necessarily meet the goal of long-term recreational
opportunities. If a large portion of the biomass is non-game species, this will have adverse effects
on recreational opportunities.
Discussion of outcomes could have been presented more clearly. As presently written, some
reviewers were confused with the presentation of species group responses within which most of
the group response could have been accounted for by a subset of species.
Comment continued in next Cell
Final April 4, 2013 87
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
256
Comment Continued from previous Cell
Request that the Proponent:
(a) Present the predicted biomass outcomes of species groups more clearly, including an
explanation of whether the biomass measure represents a relatively small number of large sized
individuals or the equivalent weight of larger numbers of small sized fish.
(b) Evaluate the projected changes in regional faunas at a more detailed level of resolution i.e., for
individual species, to the extent that sufficient reliable data are available. At the very least focal
species should be evaluated individually.
Example: There is a projected 45-80% decrease in burbot, lake trout, rainbow trout, walleye, and
northern pike, which assumed would be counteracted by a 1.8-1.9 fold increase in arctic grayling,
mountain whitefish, and bull trout (page 12-47, lines 9 – 17). This appears to be contradicted by the
sentence further down that bull trout and Arctic grayling are expected to decline.
Increases in the grayling/ mountain whitefish/bull trout group (Group 2) would reflect a decline in
Arctic grayling and bull trout, and an increase in mountain whitefish. However, this is represented
as an overall increase in Group 2 fish (i.e. an implied positive effect).
Note also, mountain whitefish aren’t nearly as desirable as a sport fish so the impact of this change
on fishing values may be negative.
Final April 4, 2013 88
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 257
Reservoir littoral and limnetic habitat development - Overall, habitat conditions that would be
created in the reservoir, including limnetic productivity, remain quite uncertain as noted in the
following issues:
(i) The projected success of lakeshore littoral habitat development, the habitat value of large rip
rap, and the establishment of a productive reservoir fish fauna may be more uncertain than stated
by the proponent due to the assumptions used.
(ii) The text suggests that reservoir spawning and rearing habitats are created merely by the
flooding of land. This requires major assumptions. Just as there aren’t spawning and rearing
habitats everywhere there’s water, those habitats won’t be created everywhere in the flooded
zone. Many other characteristics, such as substrate, water velocities, cover, etc. will determine
where these habitats will be.
(iii) The extent of littoral habitats in the reservoir may be exaggerated, since the low productivity in
the upper 20 km of the reservoir does not seem to have been accounted for. This may mean that a
large proportion of the littoral habitat (i.e. < 6 m deep) occurs in a reach that is relatively
unproductive due to the continued effects of cold and variable outflows from the Peace Canyon.
(iv) It is not correct to state that aquatic vegetation has established itself in Dinosaur Reservoir, in
fact, a great deal of time and money has been spent to try and create habitats that support
submerged vegetation. Two of the main reasons why it has not worked are water level fluctuations
and heavy sedimentation rates. In this statement sedimentation is being characterized as
promoting vegetation growth, and its subsequent role as fish habitat.
Comment Continued in Next Cell
Final April 4, 2013 89
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
257
Comment Continued from Previous Cell
(v) Appendix P. GIS analysis of changes in habitat area addresses habitat loss due to inundation, but
does not talk about variation in different habitat types due to daily and seasonal variation in water
flow. Also, the EIS states that loss of fluvial habitat types (low area) is balanced against gain of
lacustrine habitat types (extremely high area) but does not provide a justification for this
conclusion.
Concern: Assessment of comparative impacts to specific fish habitats should be valued based on
something [example?] other than gain and loss of area.
Request that the Proponent:
(a) Provide a functional description of reservoir littoral fish habitat along with the attributes as
they relate to specific species and life-stages, in order to help evaluate future habitats,
(b) Expand the explanations/rationale on the balance of river habitat amounts/quality lost due to
inundation with the amounts and expected quality of littoral and limnetic habitats of the future
reservoir. Are fluvial habitat types (low area) of equal habitat value to lacustrine habitat types
(extremely high area)? Should they be valued based on something other than on a square-km basis?
Comment Continued in Next cell
Final April 4, 2013 90
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
257
Comment Continued from Previous Cell
(c) Provide an analysis of the following:
(i) how much area is dried during low flow downstream of the Site C reservoir; and
(ii) how much area is dried up during low flow upstream of the dam?
(d) Provide more discussion on the degree of uncertainty of future littoral habitat quality and
quantity.
Additional Details:
12-34, lines 28 and 43: It is mentioned that several stages of construction will provide “additional
fish habitat” when water levels increase; however, a description of the habitat relative to the
species and life stages that would be present to use it is not offered.
12-35, 4-8: The limnetic area is defined as areas where water is < 6 m deep; however not all
shallow, limnetic habitat is created equal. Also the loss of terrestrial habitats was not considered.
The text also implies a net gain in habitat resulting from the creation of the reservoir; however, it is
really only a net gain in wetted area, not necessarily fish habitat, or more importantly productive
epilimnetic habitat. The loss side of the habitat conversion equation seems to omit the loss of
mainstem river habitat, but the gain side appears to include the limnetic area (from which the old
river habitat was a part). The extent, nutrient and thermal characteristics of the epilimnion is also
not provided. This area is fundamental to aquatic productivity including fisheries productivity.
Final April 4, 2013 91
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 258
Habitat fragmentation and its potential consequences - The creation of site C dam and reservoir
may lead to the resultant habitats being split into 4 or more ‘zones’ (upper reservoir, main
reservoir, Site C to Pine River confluence, Pine River confluence to the provincial border).
Concern: Although post-project habitats are arguably contiguous (except for passage issues at the
dam), their different characteristics may lead to population fragmentation.
Request that the Proponent:
Include an assessment of potential for population fragmentation as a result of dam construction
and the creation of the reservoir.
Examples:
(i) Populations residing downstream of the Pine River confluence (i.e., cool water lotic fauna) will
be isolated and distinct from those in the reservoir (warmer lentic habitat). The area downstream
of the Peace Canyon dam may continue to show low productivity.
(ii) The reach immediately downstream of the proposed Site C dam will likely show decreased
productivity similar to the current state downstream of the Peace Canyon Dam (which include
bedrock conditions for 7 km, cold water in summer, low fish productivity, dominated by larger fish,
recruitment largely based on entrainment).
Final April 4, 2013 92
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 259
Aquatic primary and secondary production and review of modeling - Levels of uncertainty
associated with assessments of impact on fish and fish habitat have been inadequately reported in
the EIS. The following are examples of uncertainties in the assessment:
• Projected “increases in aquatic productivity” are uncertain. In spite of the modelling summary
that suggests the reservoir will be more productive than the river, these projections appear to be
doubtful considering the literature compiled in Volume 2, Appendix P, Part 3. Fish species which
can respond to the changes in productivity will dominate in the future.
• Interactions between temperature and productivity generate uncertainty about future reservoir
productivity. While the loss of river habitat is clearly identified, this is suggested to be offset by
greater productivity in the newly created reservoir. Fairly high flushing rate of the reservoir may
limit such productivity. The upper 20 km of the reservoir will continue to be cold and unproductive
due to the continued influence of Peace Canyon outflows. As a result. This may also affect
expectations about the resultant littoral areas. Expected habitat quality of littoral areas may be
overly optimistic.
• Periphyton was poorly estimated by stepwise multiple regression (bad analysis to perform). Flow
variation was a stated variable in both regressions of periphyton and phytoplankton, but the
temporal scale of this variation not mentioned. Periphyton not well explained by using particle size
and flow. Models of benthos biomass and richness were used to predict conditions after Site C:
periphyton wasn’t predicted, due to poor predictive ability.
• Question arises whether data from 2 years are sufficient to model future conditions. Were there
large perturbations in the data to provide power for such predictions? Was the time-scale of flow
variation relevant for the daily vs. seasonal flow variation to be expected?
Comment Continued in next box
Final April 4, 2013 93
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
259
Comment Continued
•Models for both benthos and periphyton and predictions do not account for the influence of
underlying productivity, which will not vary much over the two years of data. Since productivity
(particularly N and P) will change following construction, it is nearly impossible to say what benthic
and periphyton production rates will be, so it seems future predictions are speculative at best.
• Benthos richness and bio-volume were reasonably well explained – mostly by distance from the
dam (stream order arguments), flow variation and depth. Little discussion presented on how this
creates complex spatial patterns; i.e., immediately downstream of the Site C dam, there will be
extremely low benthos abundance, causing complex patterns in higher trophic levels (impacts on
capacity to support fish). This will have implications for the ecosystem, but also for the fisheries
that are supported by them (which are based in Fort St John, very close to the dam).
Uncertainty is acknowledged in the EIS; however, for habitat impacts of this magnitude require
greater attention to levels of certainty.
Request that the Proponent:
(a) Revisit modeling efforts for predicting future changes in primary and secondary production in
the reservoir and downstream of the Site C dam to respond to questions about analytical approach,
data characteristics, and related questions posed here which all have implications for the validity
and/or level of certainty around predicted outcomes.
Comment Continued on next Box
Final April 4, 2013 94
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
259
Comment Continued
(b) Provide a response to the following questions about methods:
(i) How normal were the data following transformation? Normality tests are prone to errors when
sample sizes are low. Could a plot be shown to indicate that data are normalized?
(ii) Variables used in the regression include variation in flow, etc. On what time-scale is this
variation measured… weekly, monthly, seasonal or hourly? All time-scales are relevant and may
influence predictions.
Additional Details:
• 12-35, 22-25: As mentioned here, the initial increase in productivity will diminish over time until
an equilibrium is met. This equilibrium will likely have a lower level of productivity as is typical with
a reservoir. None of the literature reviewed in Appendix P, Part 3 had reservoir data sets that
showed an increase in primary productivity, following formation. Sedimentation and high flushing
rate appear to be dominant factors in suppressing production, and Site C’s reservoir will have the
additional factors of cold water and two upstream reservoirs to trap nutrients. IMHO, this cold, run
of the river reservoir will not produce significant phytoplankton nor periphyton, with low numbers
of cladoceran zooplankton. Information suggesting there will be sufficient stratification in the
reservoir to support epilimnetic productivity was not apparent.
• Calibration of phytoplankton and periphyton abundance showed a poor match to seasonal
variations observed in Dinosaur reservoir. This suggests that the predictive ability for production in
the newly formed reservoir is low.
Comment Continued in next cell
Final April 4, 2013 95
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
259
Comment Continued
• The reservoir is predicted to show thermal structure in the summer, however, calibrations based
on Dinosaur reservoir showed limitations in the ability to predict water temperatures during the
period that thermal stratification was forming (June and early July). This could have impacts when
coupled with a fairly short productive summer season. Additionally, the two models used to predict
water temperatures predicted temperatures that repeatedly differed by about 5°C. Since the
reservoir thermal structure would also affect factors such as nutrient retention, this contributes to
broader uncertainty regarding the resultant productivity in reservoir habitats.
• App P3, 5.1.1.1: Model development. Trends in benthic and periphyton biomass
analyzed by multiple regression (backwards stepping) where data were log10(x+1) transformed.
The more appropriate analysis would have been a GLM using a zero-inflated Poisson distribution.
There are many problems with using step-wise analyses like the one proposed which may influence
results. Similarly, the zeros in the data may have some mechanistic trends which may also influence
results (but were not accounted for).
• Overall, estimates for all trophic levels don’t account for daily variation in water flow, other than
experiments to see how species richness and biomass was affected by dewatering in Appendix P).
Not accounting for daily variation in water flow may lead to under-estimates or over-estimates of
biomass and mortality.
Final April 4, 2013 96
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 260
Aquatic primary and secondary production and review of modeling - CE-QUAL Estimates of
Periphyton and Phytoplankton are that periphyton biomass will increase ~4% downstream of dam,
but this area has high flows during the day.
Concern: An examination of how dewatering affects biomass and richness is provided in Appendix
P, but this information does not appear to be incorporated into the main analysis. The EIS states
that the data used for the models apply only to areas that will be continuously wetted. This does
not take into account possible loss due to dewatering.
Request that the Proponent:
(a) Clarify if a 4% reduction in means that during the night, significant areas may be dewatered,
resulting in drying/death of periphyton.
(b) Clarify if the potential for dewatering and drying/death of periphyton is accounted for in the
assessment
(c) Include an examination of how dewatering affects biomass and richness as part of the main
analysis.
Final April 4, 2013 97
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 261
Fish species and population responses – Reservoir - More details are sought regarding inputs and
uncertainties related to analyses of fish species and population responses in the reservoir:
• 12-30, 11: One key aspect potentially changed by the project is loss of life history types (or
biodiversity) from some fish species, but this outcome is not mentioned specifically. Perhaps it is
part of genetic diversity (12-31, 4).
• Within the reservoir, while fish will continue to be present the resultant fish community is
uncertain. For example, the establishment of a planktivorous species is probable (possibly only
maintained by entrainment); however, whether this species is lake whitefish or Kokanee does not
appear to be certain.
• In general, there is substantial uncertainty regarding the resultant community that will establish in
the reservoir, as well as the extent (magnitude and spatial extent) of downstream impacts. While
this is reflected at some points in the document, at other locations increased certainty is implied
which may present an overly positive outlook. Will Kokanee or lake whitefish be the dominant
planktivore in the reservoir? Will northern pikeminnow be the dominant predator? These
questions cannot be answered with certainty, but have important influences on how
desirable/acceptable fish community changes are.
• Reservoir productivity biases: While fish biomass may increase in the reservoir, this increase may
be primarily the result of entrained Kokanee. If so, this may mask actual negative effects on
reservoir productivity and its impact on intrinsic fish production.
• Reservoir operations: Although the reservoir is expected to maintain a fairly stable water
elevation, the water license will allow for some variation in water elevation. For example, in
summer this could have a strong effect on reservoir thermal structure and reservoir productivity. It
could also affect entrainment.
Final April 4, 2013 98
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
261
Comment Continued
• Utility of Ecopath mass balance models to estimate changes in Peace River fish biomass and food
webs: Rationale not provided.
Harvest rates were assumed to be the same before and after Site C dam construction. Given that
there is a whole EIS section on harvest, reasonable estimates could have been made regarding
harvest rates for each species in each river section (upstream and downstream of the dam).
• They find biomass and harvest of planktivorous fish (whitefish and kokanee) will increase in the
reservoir following construction, and continue to increase, but this is entirely based on their
assumption of increasing biomass of these fish in Williston. There is substantial uncertainty around
that assumption and should be acknowledged. All other harvests go down, but this is partially
masked by increase in planktivorous fish
• Balancing the model:
• A good job done in rationalizing all changes to best guesses for biomass, etc. for each group which
were needed to balance the model.
• Ecopath models of future food webs were based on predicted phytoplankton and periphyton
biomasses from the CE-QUAL model, which was quite bad at estimating upstream production and
not based on changing nutrient conditions.
• Changes in whitefish and kokanee data were based on trends over the last several decades (4
points in total) and observations from other systems. This seems weak, but they did specifically
model different scenarios.
• It is unclear why walleye and northern pike are expected to increase. Spawning and nursery areas
for both of these species will likely decrease in a reservoir environment.
Final April 4, 2013 99
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
261
Comment Continued
• It is unclear why it is concluded that Arctic grayling and bull trout would extend their distribution
downstream in the project area. Bull trout at least, are there now.
• Northern pikeminnow is not a sport fish species. If northern pikeminnow becomes the dominant
predator in the reservoir there will be significant impacts to the fish fauna and recreational
use/harvest.
Uncertainty is acknowledged in the EIS; however, changes to habitat and fish community of this
magnitude require greater attention to levels of certainty.
Request that the Proponent:
(a) Evaluate the effects of reservoir water level variations on thermal profile, reservoir productivity,
and entrainment.
(b) Discuss the potential contribution of entrained fish versus intrinsic Site C reservoir productivity.
(c) List the multiple assumptions embedded within the EIS and identify appropriate actions if
assumptions are invalid (e.g. based on monitoring or other information).
(d) Explicitly discuss the use and purpose of Ecopath model, and all key assumptions embedded
within it which control model outcomes, and which contribute to uncertainty.
(e) Provide more clarity on outcomes in the reservoir and its tributaries for species such as walleye,
northern pike, Arctic grayling, and bull trout.
(f) Here, and elsewhere, “show the work” behind analyses forecasting future outcomes, at least
briefly in summary form. A more open discussion of how outcomes were derived would increase
the level of confidence around modeled outcomes, or at least provide proper context and levels of
uncertainty around them.
Final April 4, 2013 100
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
261
Comment Continued
Additional Details:
• Bull trout, as one example, have numerous life-history types and several have been lost from
populations in Alberta due to riverine developments. Many of the fish species in the project area
have several life-history types documented (see McPhail 2007).
• Kokanee entrainment may have strong effects on the fish community in the resultant reservoir.
However, continued entrainment from Williston Reservoir was simply assumed, and this
assumption was not evaluated; i.e., will entrainment rates be high enough to support a kokanee
population to be the dominant pelagic species?
• Estimates of kokanee growth and size would be helpful to understand the future population. If
established, this population might have individual too small to interest anglers.
• Overall harvest in the reservoir is assumed to increase, but excluding whitefish and kokanee,
harvests actually decrease. Kokanee populations are assumed to increase based on very little data
from Williston Lake showing possible population increases.
Comment Continued in Next Cell
261
Comment Continued
6. The need for an Ecopath model of the system following construction is not explained except that
the guidelines require an estimate of the ecosystem. There may be minor changes to parameters
and state variables in order to ensure the model balances, but the utility of this is questionable. It
basically shows what you put in to the model, rather than providing any insights (apart from being
able to visually see the relationships; i.e., building a food web diagram). Some rationale is provided
in Table 6.2, but not explicitly stated in the text. Even the table lists benefits over passage models,
but don’t rationalize using Ecopath rather than just displaying the inputs used (which is largely all
that Ecopath was used for).
Final April 4, 2013 101
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 262
Fish species and population responses – Tributaries - More details are sought related to the inputs
and uncertainties related to analyses of fish species and population responses in tributaries:
1. The future outcomes for some of the single species models can be questioned based on certain
input values and model assumptions.
2. There seems to be very little consideration on the impacts to fish and fish habitat in the flooded
areas of the LAA tributaries above the dam site. There is the potential to have significant impacts in
these areas depending on the current use of these areas for tributary species (e.g., Could the
flooded area in the Halfway impact Arctic grayling overwintering habitat?).
3. Consideration should be given to potential impacts on post-project tributary populations on the
potential for the reservoir to be a “population sink” due to predation of species originating in the
tributaries (e.g., Arctic grayling).
4. Uncertainty about the future of ecologically important areas such as tributary junctions in the
LAA.
Concern: More detailed explanation and discussion of issues related to inputs and the derivation of
outcomes would increase the level of confidence around modeled outcomes, or at least provide
proper context and levels of uncertainty around them. Information on predation risks to tributary
populations would provide beneficial additional context to the uncertainties for species such as
Arctic grayling.
Final April 4, 2013 102
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
262
Comment Continued
Request that the Proponent:
(a) “Show the work” behind analyses forecasting future species outcomes, at least in summary
form. This includes:
(i) an explanation of model input data pertaining to life histories that appear to be well outside of
natural ranges; and
(ii) a more open discussion of how outcomes were derived.
(b) Provide information on possible life-history-related impacts on post-Project tributary
populations, such as Arctic grayling, due to predation by reservoir species.
Additional Details:
• Predicted population productivity for bull trout is driven partly from presumed 83% bull trout egg-
to-fry survival rates (based on a single study with eggs contained within perforated steel cylinders),
and density independent growth and survival of juveniles.
• 2 12-95, 7: The statement that tributary, or fluvial, Grayling populations can provide recruits to
the reservoir (Peace mainstem) to maintain populations misses the likely outcome that the Peace
mainstem will become a sink for tributary populations as these recruits will likely never return from
the mainstem (predation northern pike minnow, and possibly by burbot, northern pike, walleye,
etc).
• 3It is an assumption that the current and important staging areas for bull trout in the LAA such as
at the mouth of the Halfway River (recognized by the establishment of a no-fishing zone for a radius
of 5 km.), will persist in the reservoir environment.
Final April 4, 2013 103
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 262
Fish species and population responses – Downstream of Site C - Biological outcomes are still quite
uncertain. The key issue with regard to assessment of downstream habitats in the EIS is that flow
fluctuations on fish were not addressed. Habitat inundation effects were only considered upstream
of the Pine at one location. Attention to both impact categories is therefore deficient.
The spatial variability in benthic production is mentioned only in the summary and how between
the Site C dam and the Pine River there are virtually no opportunities for invertebrate production.
The implication is that this area will be largely devoid of invertebrates, and therefore, consumer fish
species.
No fish community sampling was performed at the Site C dam location.
Transition between the coldwater and coolwater species assemblages creates a unique fish
community. It is thought that reservoir development will move this transition zone downstream,
however impediment to fish passage could significantly alter the makeup of the cold water species
assemblage which will impact the community in the downstream transition zone.
The relative importance of the Pine River in the post-dam scenario will greatly increase in its role of
flow attenuation and access to fish habitat away from the Peace River mainstem. This should be
highlighted because the degree to which fish species will be able to utilize the Pine assumes no
significant changes in the Pine River in the post-dam period.
Continued in next cell
Final April 4, 2013 104
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
262
Comment Continued
Concern: Downstream habitat impacts have not been sufficiently addressed. Impacts both
upstream and downstream of the Pine River confluence have received limited attention. Also the
possibility of habitats downstream of the dam becoming less productive (similar to current habitat
downstream of Peace Canyon Dam) has not been sufficiently addressed. The limited attention to
downstream impacts is a substantial omission.
Uncertainty is acknowledged in the EIS; however, habitat impacts of this magnitude require greater
attention to levels of certainty.
Request that the Proponent:
Use available information on fish communities at the location of the proposed dam and
downstream to provide an expanded discussion of post-Project changes to the environment and
fish community at these locations.
12.4 263
Issue: Fish mortality at the Site C dam - Potential for bias resulting in underestimation of fish
mortality.
Concern: A potential bias may exist that affects observations of GBD in fish exposed to total
dissolved gas (TDG) in rivers and reservoirs: dead fish don’t float (pg 12-58, line 20): Mortality is
often underestimated in fish kills as the majority of dead fish may not be found because they sink to
deep waters out of sight and are washed downstream, and struggling fish can be quickly caught by
predators.
Request that the Proponent:
Provide information on sources of error associated with estimates of mortality related to the dam
and its operations as part of discussions related to potential future losses of fish at the Site C dam.
Comment Conitnued in Next Cell
Final April 4, 2013 105
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
263
Comment Continued
Additional Details:
See McCubbing et al. (2005), which documents that only 1% of fish killed in a chemical spill were
collected and enumerated despite widespread efforts.]
Also: McCubbing, D.J.F., C.C. Melville, G. Wilson and M. Foy. 2006. Assessment of the CN sodium
hydroxide spill August 5th, 2005, on the fish populations of the Cheakamus River. Report prepared
for the BC Ministry of Environment, Surrey Regional Office. Final Draft. 123 p.
Note: During at fish kill at Ruskin Dam (Stave River) caused by a TDG event in 2007, anglers
reported seeing dead sculpins, char, and steelhead two days before the event was reported to
officials and biologists responded. The same anglers reported taking home one struggling steelhead
(hatchery fish) they could reach from the shore. This may not have been in the BC hydro report on
the incident, because it was considered anecdotal information. The post-event investigation
discovered the TDG event probably occurred for 2-3 days before it was discovered.
Final April 4, 2013 106
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 264
Issue: Impacts to sustainability of fish populations due to entrainment - The report estimates the
rate of entrainment to be low (< 10%) of for all species except for bull trout, kokanee, lake
whitefish, and lake trout (pg 12-60, line 17).
Concern: This statement, reframed, is stating that the rate of entrainment is predicted to exceed
10% for bull trout, kokanee, lake whitefish, and lake trout. A 10% entrainment rate may be
unsustainable for many species. Entrainment is equivalent to mortality if the fish can’t return. For
species which are long lived such levels of entrainment may severely constrain upstream
populations
Request that the Proponent:
Describe the long-term implications of predicted entrainment rates on fish species. In particular,
discuss the implications of predicted rates on long-lived species. Include references from the
literature.
Final April 4, 2013 107
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.4 265
Water quality impacts on fish habitat - There are gaps in the assessment of water quality (Vol 2
Section 11) with respect to impact on fish and fish habitat.
Concerns:
(i) Groundwater upwelling is an important environmental factor in bull trout red site selection and
should be considered in the assessment of impacts on bull trout (Sec 11.6.6 pg 11-100).
(ii) Mean peak concentration of Hg was used as an indicator on the assumption that this better
approximates typical human exposure (e.g., eating fish) (Sec 11.9.7 pg 11-167 line 29). This metric
does not indicate the range in Hg levels and does not quantify the distribution of samples around
this mean. There is no discussion of what effects the predicted Hg values could have on the health,
reproduction and behavior of fish species in the Peace River.
Request that the Proponent:
Respond to the following questions and concerns related to the impacts of changes in water quality
on fish and fish habitat:
(i) Evaluate the potential impacts and effects to bull trout related to changes in the groundwater
regime. Will the project potentially impact the groundwater regime in surrounding tributaries (eg.
Halfway, Moberly)? What are the implications for bull trout?
(ii) Report on the range and distribution of predicted Hg concentrations associated with the mean
peak concentrations reported in Section 11.9.7.
Describe the effects that predicted Hg values could have on fish health and behavior in the Peace
River. What is the % population (by species) with concentrations that may result in behavioral or
reproductive impacts?
Final April 4, 2013 108
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.5 266
Issue: A substantial proportion of the discussion around mitigation measures for fish and fish
habitat refers to mitigation in the future as dictated by project outcomes and “when feasible,
where practical, when economically feasible or as possible”. This approach makes it difficult to
evaluate mitigation due to the lack of clarity around these conditions.
Concern:
The suggested level of mitigation for the completed project appears inadequate. (see below
comments for further details)
12.5 267
Issue: Monitoring programs are proposed to evaluate assumed outcomes post-Project but not pre-
Project.
Concern: While post-project effectiveness monitoring is welcomed, the challenge with such an
approach is it defers risk of non-compliance until after the Project is built (i.e., after a non-reversible
decision has been made) and also puts unclear limitations on addressing any residual effects (i.e.,
linked to economical and technical feasibility).
Request that the Proponent:
(a) Undertake detailed planning and implementation of mitigation and monitoring prior to Project
construction.
Final April 4, 2013 109
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.5 268
Issue: There appears to be an overall approach in the EIS which assumes that the negative effects
(e.g., loss of river fish habitats) are offset by proposed gains (e.g., reservoir productivity).
Concern: The suitability of such an approach is low because it does not represent a like-for-like
replacement. Uncertainty in the achievement of proposed positive effects also limits the suitability
of such an approach.
Request that the Proponent:
(b) Provide a detailed rationale, supported by literature sources, to support the EIS assumption
that the negative effects (e.g., loss of river fish habitats) will be offset by proposed gains (e.g.,
reservoir productivity).
12.5 269
Issue: Concern that fish habitat and/ or environmental compensation as a result of the project
might detrimentally affect essential operation and maintenance requirements along the highway
corridor.
Request that the Proponent:
(a) Clarify that essential operation and maintenance requirements along the highway corridor will
not be detrimentally affected by the addition of fish habitat and/or environmental compensation as
a result of the project.
(b) Consider off-site compensation and aggregating, where possible, where required so that the
resulting compensation is more biologically productive and can be further removed from the
transportation corridor.
Final April 4, 2013 110
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.5 270
Issue: Concern about future responsibilities associated with post-construction compensation
monitoring on MoT lands and RoWs as well as any repairs and modifications to that compensation
to ensure functionality over the long-term.
Request that the Proponent:
(c) Clarify that any long-term post-construction compensation monitoring requirements resulting
from the project that impact, or are located on MoT lands or RoWs, will be the responsibility of BC
Hydro, as will any future repairs/modifications to that compensation which may be required by
environmental agencies to ensure functionality.
(d) Clarify that fish-bearing stream crossings affected by the realignment of Highway 29 that are
found to be barriers to fish passage, shall have fish passage restored. This includes new stream
crossing installations and all installations shall ensure fish passage is maintained under flow
conditions when fish would be migrating for all fish species and life stages present.
Final April 4, 2013 111
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.5 271
Operations phase – Reservoir - Broadly, the development of a reservoir fish fauna is the
mitigation measure proposed for the loss of river conditions in the LAA. The predicted success of
this is partly founded on the proponent’s previous experiences. A level of uncertainty exists in the
Site C LAA given the potential effects of high through-flows (22-day residence time) on primary and
secondary production supporting fish populations in the future reservoir.
The uncertainty of future habitat structure and fish community composition in the reservoir affects
habitat mitigation options and prevents the evaluation of suitable levels/types of mitigation
measures.
No specific mitigation is proposed in the event of the loss of the migratory Arctic grayling
population in the Moberly River, or migratory bull trout in the Halfway River. The proponent
proposes that mitigation/compensation options await the outcomes of post-project effectiveness
monitoring.
Concern:
The uncertainty in the composition and productivity of the fish fauna limits the identification of
mitigation options at this time. For example, if reservoir kokanee cannot successfully access
suitable spawning sites in the LAA tributaries, kokanee recruitment and populations may have to
depend entirely on entrainment from upstream.
Although the proponent expects the development of littoral habitats in the reservoir to be
successful, post-project effectiveness monitoring will be needed to confirm the level of success.
Continued in Next Cell
Final April 4, 2013 112
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
271
Comment Continued
While this approach may be acceptable under the circumstances, the transfer of risk to regulatory
agencies must be matched by the ability to compensate/mitigate if assumptions are untrue and
outcomes are not achieved. This makes it critical to define terms such as ‘economically and
technically feasible’ as potential constraints on mitigation and compensation measures.
Request that the Proponent:
(a) Consider monitoring the success of proposed habitat enhancement structures in littoral areas
and the status of fish populations in the reservoir and tributary to it, including the Halfway River
bull trout and Moberly River Arctic grayling populations
(b) Prepare a mitigation/compensation strategy in the event of negative results.
(c) Consider developing borrow pit recreational opportunities to offset recreational and harvest
impact losses.
(d) Expand on options to further improve reservoir habitats
Additional Details:
12-66, 35: While river habitat cannot be replaced, there may be options to improve either the
reservoir habitats or downstream river habitats. Such options appear to have been given relatively
limited attention.
P67L4 and 5 Without further details about the extent of contouring and fish enhancement works it
is difficult to evaluate the net effect of these measures.
Mitigation for lost recreational opportunities is possible for borrow pits that are not located within
the littoral zone. As part of the mitigation for recreational and harvest impacts, funding could be
provided to stock or aerate these borrow pits.
Final April 4, 2013 113
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.5 272
Operations phase – Fish passage at Dam -
Opportunities were missed in the design of mitigational fish passages.
(i) It is understood that a substantial effort was undertaken to select the optimal type of dam for
the Site C development in terms of cost, efficiency, and so forth; however, the largest mitigation
opportunity for fish populations in the LAA and RAA was missed in the Site C Dam proposal. Fish
passage options proposed are retrofitted to the dam design. A more fish friendly approach would
have been to design optimal fish passage facilities, then design a dam around it. Different dam
orientations may have improved fish capture efficiency by creating optimal collection points. Fish
approaching a dam from the downstream area often collect at the most upstream point of the dam,
and fish approaching from upstream often collect at the most downstream point of the dam. The
proposed dam crossing the river perpendicular to the streambank, and the powerhouse passing
flows perpendicular to the river flow is probably the most difficult orientation for the retrofit of fish
passage facilities.
(ii) The other largest mitigation opportunity missed was the chosen location of the Site C dam. By
locating the dam only 2 km upstream of the Moberly River, the loss of habitat in the river,
migration obstructions, and introduction of new reservoir fish species (e.g., northern pike) into the
Moberly would have been largely avoided, for a small change in head and storage volume.
Final April 4, 2013 114
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
272
Comment Continued
Concern: The potential for success for the proposed mitigation for migration blockage at the Site C
dam with the trap-and-haul proposal for bull trout and other migrants is uncertain, and may be low.
Fish passage mitigation assumes a successful trap-and-haul program as well as persistence of
favourable environmental cues that will stimulate bull trout to maintain pre-dam migration
patterns.
The proposal to implement a periodic capture and translocation program for the small-fish fauna
“contingent of the results of research on the genetic exchange requirements of upstream and
downstream populations” appears dubious. Who is committed to doing this research, and when?
Request that the Proponent:
(a) Prepare a mitigation strategy in the event of negative results.
(b) Commit to support studies of “genetic exchange requirements” for members of the small-fish
fauna.
(c) Evaluate the assumption that movements are unimportant to small-sized fish species.
(d) Provide a review of the potential effectiveness of trap-and-haul methods in the context of the
proposed Project. Suggest that the review assume the method is ineffective until proven
otherwise.
(e) Provide the Fish Passage Management Plan for review.
Final April 4, 2013 115
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
272
Comment Continued
Additional Details:
• 12-71, 5: An additional consideration for mitigating fish entrainment is positioning the intakes
deeper in the water column. This should entrain fewer fish which are often surface oriented.
• 12-65,L9: Several reviewers disagree that movement is not an issue for small fish. This is an
assumption that should be evaluated further. Small fish in general require greater attention.
• 12-72, 12: Studies of the genetic exchange requirements for small-fish species would have been
useful to have within the EIS. However, failing that they are important to include within the
ongoing monitoring work.
• The incomplete knowledge on the current role and importance of migrants in sustaining fish
species distributed on both sides of the Site C dam location may confound the trap-and-haul
strategy. Because an individual of a species (e.g., bull trout) shows up at the base of the dam does
not necessarily imply that the individual was a migrant intent on reaching the mainstem of the
Peace in the LAA and its tributaries. Moving this individual upstream may be a effort and cost
wasted.
12-71,30: We have little experience with trap-and-haul in BC. It is employed on the Columbia River
with salmon. Further review of its potential effectiveness in this case may be required. One
approach within the review may be to assume that it is ineffective, until proven otherwise.
Final April 4, 2013 116
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.5 273
Operations phase – Peace River downstream of Site C dam - Near-shore habitat/side channel
enhancements downstream of the Site C dam have the potential for success, but post-project
effectiveness monitoring will be required for confirmation.
Concern: The success of near-shore habitat/side channel enhancements may be counteracted by
the low levels of benthic productivity anticipated downstream of the dam and trophic level impacts
on the fish community.
Request that the Proponent:
(a) Prepare a mitigation strategy in the event of negative results. Considerations should include:
(i) How will shear zones and point bars be constructed to be effective under variable flow
levels/conditions. What will make them good fish habitat? (pg 12-66, line 18; pg 27-28).
(ii) Stated bounds for compensation options which are currently undefined but conditional on what
is “technically and economically feasible” (pg 12-67, line 17).
Additional Details:
Further mitigation should be included (i.e., for impacts downstream of the Pine River confluence).
Final April 4, 2013 117
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.6 274
Residual Effects on individual fish populations - The following populations were recognized in the
EIS as being vulnerable to significant impacts and populations that would be potentially lost.
However, reviewers question the estimates regarding the likelihood of loss.
• Moberly River Arctic grayling
• Halfway River bull trout
• Mountain Whitefish in the LAA
Concern: There is a concern that the EIS underestimates the likelihood of loss of some fish
populations. For example, reviewers disagree that the probability of losing the migratory Halfway
River bull trout is Low (page 95 line 23). This seems like an overly positive assessment. This species
may face >10% mortality due to entrainment, which could have substantial effects over the longer
term. Also all entrainment represents a loss to the upstream population (without upstream
passage for which effectiveness has been proven). The effectiveness of trap-and-haul is unproven,
so their migration to areas upstream of the dam could be lost or reduced substantially.
Request that the Proponent:
Consider preparing a contingency mitigation plan early in the process post-approval to proactively
address the potential loss of these fish stocks.
Final April 4, 2013 118
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.6 275
Effects on fish populations downstream of the Pine River - Residual but unaddressed habitat
impacts from the Pine River to the BC border and beyond. Reviewers are unconvinced that habitat
impacts would be limited to areas upstream of the Pine River. These effects may also depend on
season and the relative flow in the Pine and Peace rivers.
Concern: Reviewers agree with the statement (12-48, 33-36) that the extent of the change on all
fish populations downstream of the Pine River would be based primarily on the degree to which
Pine River and other tributary inputs (i.e., Beatton River, Kiskatinaw River, Clear River, and Pouce
Coupe River) would attenuate the flow and thermal and ice regime as a result of the operations of
the Project. However, the uncertainty regarding the resultant downstream aquatic fauna appears
to have received a low level of attention in the EIS.
In a number of cases, the mitigation of impacts appears to be largely focused on areas upstream of
the Pine River confluence. Such a geographically restricted area may not be justified. Impacts will
likely extend further downstream than the Pine confluence and there is a need for greater
assessment /mitigation attention for those areas.
An elevated level of attention to habitat downstream of the Site C dam is recommended
Comment Continued in next box
Final April 4, 2013 119
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
275
Comment Continued
Request that the Proponent:
(a) Revisit estimates of the likelihood of loss of
(i) Moberly River Arctic grayling,
(ii) Halfway River bull trout and (iii) Mountain Whitefish throughout the LAA. Consider trends in
these populations in their regional context (including the effect of existing dams) and uncertainties
related to data and analyses and proposed fish mitigation measures (as described in previous
comments).
(b) Consider preparing a contingency mitigation plan early in the process post-approval to
proactively address the potential loss of these fish stocks.
Additional Details:
12-58, 31: Stranding in some localized areas downstream of Site C could be frequent and therefore
of concern. 2D habitat modeling shows that impacts would occur downstream to near the border
(and possibly beyond). However, impacts are only addressed downstream to the Pine River
confluence. Mitigation is possible to avoid mortality. What isn’t addressed however, is the lost
productivity due to the flow fluctuations.
12-42, 40: This project represents an increase in the daily flow variation for habitats downstream
of Site C. This is a negative impact. The report appears to take the position that impacts
downstream of the Pine are so limited that they do not need to be addressed or compensated for.
Further review of supporting documentation indicates this is not accurate.
Final April 4, 2013 120
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12.6 276
Estimate of species effects of multiple developments - The assessment lacks contextual
information on existing developments in the RAA. As an example, the development of the entire
Peace River drainage upstream of the Peace Canyon Dam has had a major impact on populations of
Arctic grayling in the region but this not included as a consideration.
Also, the description of Previous Developments (s 11.1.2.2 Aquatic Resources) provides a broad
overview of impacts on fish communities without discussing individual species.
Concern: The addition of the Site C development has the potential to lose migrant Arctic graying in
the Moberly River. This represents a regional cumulative effect of multiple developments. This
concern might be applied to other fish species as well.
Request that the Proponent:
(a) Clarify how aquatic ecosystem alterations linked to historic hydro-electric developments and
associated impacts on fish species were included in the baseline and how / if this was this factored
into assessing residual effects on fish species in the context of regional-level impacts to fish species
and populations such as Peace River Arctic grayling. A number of impact categories should be
examined such as long-term water temperature alterations, a shift from predominantly benthic to
pelagic-based food webs, and barriers to upstream movement of fish.
(b) Provide a more detailed description of impacts to individual fish species as a result of previous
developments in Section 11.1.2.2.
12 1 4277
P1L4 should indicate that habitat will be affected, use of potentially contradicts the report’s findings
and is misleading.
12 4 1
278
P4L1 It would be useful to verify whether items excluded from this table based on a score <2 are
reasonable to exclude. The brief explanation of items scored <2 suggests most are likely reasonable
to exclude, but verification would be useful.
12 16 Table
12.7279
P16Table 12.7 It isn’t clear how to interpret blanks (e.g. w.r.t. recruitment source)
Final April 4, 2013 121
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12 18 Table
12.8
280
P18 Table 12.8 Table is a useful summary, however, there is a lot of detail left out, particularly with
regard to movements. For example:
Bull trout – Movements from the Halfway to Pine and the mainstem have been detected, but
aren’t reflected here. Given entrainment and lack of upstream passage, fish engaging in this
movement pattern will likely be lost from areas u/s of the dam. Resident and migratory groups in
the Halfway are stated as distinct, but should clarify what this is based on.
Lake whitefish – this pattern is very interesting and suggests the localized spatial structure suggest
possible genetic. This should be verified/refuted. If there is any amount of distinction between
tributaries associated groups this may be lost when the reservoir is formed (but maintained d/s).
Mountain whitefish – similar to lake whitefish, but less potential for distinction.
Yellow perch – will likely not be present upstream of the dam. While we may not consider this a
focal species, potential impacts such as this should still be mentioned. The identification of focal
species doesn’t mean that all others should be ignored when impacts can be reasonably predicted.
Suckers – they appear widespread. Future work might be considered to evaluation assumptions of
a) population heterogeneity b) impacts in the reservoir area in particular.
Northern Pike – not a focal species, but one that we need more information on. Further
information needs for this species could be considered in a monitoring plan
12 30Table
12.10281
P30 Table 12.10 I think further attention should be given to all these reports, and each should be
thoroughly reviewed by at least one person.
12 39 9 282P39L9 This sentence is confusing. Does it mean that there will be a general increase, but walleye
are expected to decline?
Final April 4, 2013 122
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
12 46 6 283P46L6 The basis for this statement is unclear to me. Not likely critical, but could be clarified.
12 62 1 284P62L1 further review of Gulliver (2012) would be useful, but has not been done due to time
constraints.
12 67 19 - 20 285
P67L19-20. This sentence is misleading. With regard to seasonal pattern it is correct, but it is
misleading with regard to daily pattern since changes will occur. Also impacts will extend beyond
the Pine, and as such the limitation of the report focus to areas upstream of the Pine confluence is
not justified. Both the spatial extent and the severity of this impact are misrepresented.
12 71 4 286P71L4 The term "practical" should be defined in some manner.
12 82 16 287Is RAA missing from the Geographical Extent criteria?
12 all 288Pages are indicated from 1 to 105 and lines for the start of text relevant to the comment (e.g.
format is P1L1 for line 1 on page 1)
12 all 289
General – the reports format is generally good, but not great. In particular the limited use of sub-
headings and left justifying nearly all text makes it hard to discriminate breaks between sections,
lists etc.
12.8 96 14 290Wrong table reference, should read 12.26.
12.4.2.1 39 12-Oct 291Confusing and contradicting statement. Are walleye expected to increase or decrease?
12.6.2 12-86 17 292
Using biomass as a criterion does not necessarily meet the goal of long-term recreational
opportunities. If a large portion of the biomass is non-game species, this will have adverse effects
on recreational opportunities. This should be reflected in the EIS
Final April 4, 2013 123
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App P s2.2 293
Williston and Dinosaur Reservoirs
The section discussing the relative abundance of different species in the two reservoirs is difficult to
follow. The text bounces between talking about absolute abundance and relative changes. Please
discuss how absolute abundances changed over time.
App P s2.2 294
Williston and Dinosaur Reservoirs
The EIS seems to say bull trout and kokanee are most important in Williston, and lake trout and
kokanee are most important in Dinosaur, but then states that findings are similar and they base Site
C results on this – confusing
App P3 295
a) This report should be cited as follows:
ESSA, Limnotek, and Golder 2012. Future Aquatic Conditions in the Peace River. Site C Clean Energy
Project, BC Hydro. Environmental Impact Assessment. Volume 2 Appendix P Aquatic Productivity
Reports, Part 3 Future Aquatic Conditions in the Peace River. Prepared for BC Hydro. October 10,
2012. 131 p. + 6 app.
7, 8 1; 44 296
It is stated in the Guideline document (pg23) that “Data collection methods, models and studies
shall be documented so that the analyses are transparent and reproducible.” However, regarding
“Data Collection Methods,” there appear to be no specifics in the main document that would allow
“reproducible” data collection for Fish and Fish Habitat.
Ix, 63,
2011 - 2 297
“Abbreviations and Acronyms”
The acronyms here do appear to be from Provincial Guidelines for Fish Inventory species codes,
however, two of the acronyms are incorrect with consistency to the provincial guidelines. EIS
Document has: “WP - Yellow perch; YP – Walleye”. These should be: YP - Yellow perch; WP –
Walleye. Mistake is on pages ix, 63, 201
Section 13 - Vegetation and Ecological Communities
Ecological Communities
Final April 4, 2013 124
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 298
Selection and Description of VCs - Ecological Communities
Issue: VCs include at-risk ecological communities, sensitive ecosystems and rare ecological
features, including CF Goal 2 Priority 1 and 2 ecosystems. This represents a fairly comprehensive list
of those ecosystems that may be impacted.
The exception to this is the definition of ‘old growth’ as a sensitive ecosystem. This landscape is
characterized by frequent natural disturbance which limits old growth. As a result, it would be more
reasonable to assess the distribution of structural stages across ecosystems in comparison to the
Range of Natural Variation rather than simply look at ‘old growth’.
Concern: If "old growth" distribution is assessed by itself, the potential impacts to VC's maybe
underestimated due to the frequency of natural disturbance.
Details: Table 3 of Tech Rep. #59 (Delong 2011; see Reference) indicates range of distribution of
age classes which, when linked to ‘successional’ stages, provides a basis of natural (historical)
distribution of all seral stages related to First Nations interests. A comparison of these categories
to the distribution of structural stages over the Project area would provide a more robust measure
of effects and direction for mitigation.
Reference: DeLong, 2011 Tech Report #59.
http://www.for.gov.bc.ca/hfd/pubs/Docs/Tr/Tr059.htm
Request that the Proponent: Provide an
assessment of the existing distribution of structural stages across ecosystems in comparison to the
Range of Natural Variation rather than simply looking at ‘old growth’. Recommend using the
natural distribution of seral stages described in Delong 2011.
Final April 4, 2013 125
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 299
Selection of VCs - Ecological Communities
Issue: Not all of the Candidate Valued Components have been selected for the Valued
Components Assessment and a rationale for the selection of VCs is not provided. Some unique
ecosystems (noted in EIS Guidelines item) have not been defined or described with respect to range
extensions of rare ecological communities. For example, an alkaline community type (Puccinellia
nuttalliana – Hordeum jubatum) identified at Watson Slough is not reported on in the list of
Ecological Communities at Risk. This ecosystem is red-listed in BC and if new inventory locates the
ecosystem in a different area, it is still an ecological community at risk that should be reported and
assessed. Concern: Omitting to include
rare or sensitive ecological communities in the assessment may result in an underestimate of
impacts.
Request to the Proponent:
(a) Identify and describe all rare and sensitive ecological communities in the LAA and RAA based on
surveys and a review of the literature. (b)
Provide a rationale for the VCs selected and not selected to be included the assessment.
(c) Include the alkaline community type Puccinellia nuttalliana – Hordeum jubatum as a VC in the
assessment.
Final April 4, 2013 126
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 300
Description of VCs - Ecological Communities
Issue: The distribution of sampling effort for surveys of sensitive ecological communities and rare
plants number is not described in detail. Also Appendix R: Preface: p. I of XII: Scope: baseline data:
focus of additional work was restricted to additional rare plant survey only. What was rationale for
exclusion of other species and of rare ecosystems?
Concern: It appears that fewer surveys were conducted on the south side of the Peace River. If
that is the case, sensitive ecological communities and rare plants in that area may not be
adequately described.
Request that the Proponent:
(a) Provide a map showing the distribution of sample locations and discuss the design and rigour of
their sampling program. Include clarification of how the types of plant communities sampled along
the transmission line constitute a random sample (S13.3 lines 1-2).
(b) Provide a rationale for some locations receiving less survey effort and discuss the implications
of gaps in coverage (e.g., on the south side of the Peace River), including the identification of rare
plant communities and potential effects of the access roads and transmission line.
(c) Provide a rationale for restricting additional surveys to rare plants and not including rare
ecosystems.
Final April 4, 2013 127
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 301
Description of VCs - Ecological Communities
Issue: it is noted in Appendix R Section 1.1.1.1 that some of the ecosystems found by ecosystem
mappers in the Peace Valley did not correspond well to the descriptions found in the regional
guide. As described, some of the more common ecosystems, as suggested by the field guide, were
actually uncommon on the steep side slopes of the valley and that some of rare units, as noted by
the field guide, but were very common in the valley bottom. Likewise, Appendix R: Table 1.1.1
reports new and non-correlated map units that were not considered as potentially being
ecosystems.
Concern: These ecosystems are similar to discoveries of new plant or animal species during the
course of a baseline inventory. They should be considered as “unique ecosystems” from the study
area, until additional inventory proves otherwise. These findings suggest that the ecological
communities of the Peace River Valley are somewhat unique within the BWBSmw and the
surrounding landscape. More information and data regarding residual effects on rare ecosystems is
warranted in the landscape context. Continued in next box
Final April 4, 2013 128
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
301
Continued
Request that the Proponent:
(a) Clarify the following points:
(i) Were the issues and solutions adopted discussed with provincial experts to ensure consistency
both within the region and across the Province? (ii)
Are the descriptions provided for ecological communities at risk generic for British Columbia, or
specific to the Peace Valley? Did any of the ecological communities at risk, other than those only
known to occur in the Peace River valley, possess characteristics unique to the area?
(iii) What does the term ‘unique ecosystems’ mean in terms of an indicator for the
Vegetation/Ecological Community VC? Is this related to these new and non-correlated map units?
(iv) Were considerations of regionally uniqueness incorporated into the assessment of impacts and
residual effects? If not, what are the implications of not including these as unique ecosystems in
the assessment?
(b) Describe the extent of these communities in their regional and provincial context to determining
impacts and effects prior to development.
(c) Consider treating new and non-correlated map units as ecosystems unique and potentially new
to science for the purposes of planning, management, avoidance, mitigation and compensation
until inventory proves otherwise.
Final April 4, 2013 129
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 302
Description of VCs - Ecological Communities
Issue: The discussion of the relationship of site series and ecological communities is somewhat
simplified. Where site series are formally correlated to plant associations that are equivalent to the
ecological community, early successional status is generally the only reason to not identify the site
series as equivalent to the ecological community unless field sampling proves that the map unit is
incorrect.
Concern: Site series are only identifiable when linked to a Biogeoclimatic Unit (zone/subzone or
zone/subzone/variant). Site series numbers alone are meaningless in terms of relaying information
about a specific site series or the ecological community type it represents. Grouping site series
numbers without the Biogeoclimatic unit cannot be a way of determining area of occupancy of
ecosystem types. If this was done it is a big methodological error that will need to be corrected.
Additional Details: Biogeoclimatic (BGC) zones represent the combined area of related regional
climates (e.g. subzones). BGC units do not themselves represent species habitat. Regional climates
(subzones) are sometimes distinguished by further climatic variation as variants of the subzone and
each subzone or subzone/variant combination includes a zonal ecosystem that represents the
regional climate where the vegetation community is not influenced by local topo-edaphic
conditions, terrain, or soil types. All ecosystems identified as site series within each subzone or
subzone/variant must be identified with both the BGC unit and the site series number.
Request that the Proponent: Clarify whether site series numbers without Biogeoclimatic Units in
identifying representation of ecosystem types. If necessary, re-run the analyses correctly linking
site series numbers to the relevant Biogeoclimatic Units.
Final April 4, 2013 130
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 303
Description of VCs - Wetlands
Issue: All wetlands have been grouped for assessment into a category of “sedge wetlands”. This
grouping is so broad as to not provide adequate description of whether these wetlands occur on
peat land or mineral soils which would alter the appropriate management or mitigation response.
Concern: There are very distinct wetland types in the LAA. Inappropriate lumping of wetlands
could result in impacts on the different wetland communities being missed. Without
characterization and quantification it is also not possible to know whether mitigation measures are
appropriate. For example, each wetland type performs a different ecological function (as habitat
but also water filtration, flood control, CO2 sinks, etc) and without separation into wetland types,
particular ecological functions might be put at risk.
Comment Continued in next cell
Final April 4, 2013 131
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
303
Comment Continued
Additional Details: The following is a description by Provincial Research Ecologist Will MacKenzie of
wetlands in the Project area based on a visit in the spring of 2012:
"The interesting thing about [the Project area] is the suite of types is more reminiscent of the
Chilcotin rather than the rest of the boreal (warmer). Watson slough is a Wm03 (Awned sedge) but
also Woolly Sedge (Wm12) and Bulrush (Wm06). These types then occur higher up in the valley.
Also something like the Baltic rush (Wm07) and Field sedge (Ga03) in some areas (mostly above the
impact area on the slopes. Marsh types
would be relatively easier than other wetlands to recreate in other locations. Some Tamarack -
Water sedge ecosystems (Wb06) occur in the valley bottoms. Probably lots of these in the general
region certainly very common in the boreal in general, these would be difficult to reconstruct. Some
of these ecosystems have been impacted by beaver flooding, which is not an uncommon natural
occurrence. The resulting ecosystems are a hodgepodge of willow swamp and marsh types."
Request that the Proponent:
(a) Identify wetlands in the Project area according to the provincial wetland classification scheme
and map the quantity, extent and distribution for each.
(b) Assess impacts, develop mitigation measures , estimate effects for each wetland class (by plant
association) individually.
13 304
Description of VCs - Ecological Communities
Issue: The report seems to be using ecosystems and habitat interchangeably.
Concern: Using the terms ecosystem and habitat interchangeably has potential to miss or
misrepresent habitat for the purpose of assessment
Request that the Proponent: Clarify the definition of these terms and ensure that each is used in
the appropriate context.
Final April 4, 2013 132
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 305
Description of VCs - Ecological Communities
Issue: The BC Conservation Framework (BCCF) is not current with the CDC list of species and
ecological communities at this time and the list of BCCF rankings and the BCCF recommended
Actions may not address all species of conservation concern.
Concern: The BCCF provides Actions for recovering species and ecosystems at risk. A number of
ecosystems identified in the Peace River valley are "new" so don't have actions for recovery.
Request that the Proponent: Consider BCCF rankings and recommended Actions in the context of
current CDC listings and "new" (as-yet unlisted) ecosystems identified in the Project area. Also
applies to mitigation measures (see below).
Final April 4, 2013 133
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 306
Description of VCs - Ecological Communities
Issue: The methodology for baseline mapping (Broad Habitat Mapping) of ecosystems in the RAA
(and part of LAA) contains a number of technical inconsistencies with provincial mapping standards
and accuracy assessment guidelines. Data from one scale was re-interpreted at a finer scale (1:50K
biophysical data was used to populate 1:20K VRI polygons) and a spatial shift applied resulting in
polygons with potentially incorrect attributes. A statistically valid accuracy assessment was not
completed and very few habitat types were actually sampled. A comparison of quality and
reliability of the baseline mapping to standard map products is not provided with the EIS.
The current status and distribution of terrestrial ecosystems were described adequately in the area
in which Terrestrial Ecosystem Mapping (TEM) was completed.
Concern: Baseline mapping is one of the fundamental data layers for the assessment. The quality
of this map layer influences subsequent interpretations such as the accuracy of habitat maps for
wildlife and the area calculations of all of the ecological communities and area by structural stage.
There may be inadequate information on the distribution and condition of terrestrial ecosystems in
the RAA to reasonably identify significance of loss associated with development. Specific concerns
include: (i) Since the
methods are non-standard and untested it is particularly important that the documentation
includes a reasonable comparison to more standard methods vis-à-vis quality and reliability.
Final April 4, 2013 134
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
306
Comment Continued
(ii) The “pre-processing of the biophysical habitat information”, as described on page 18 (App R S
1.1.2) 8, is essentially altering the original intent of the biophysical data. The attributes of each
biophysical polygon were photo interpreted by an ecologist, so to “slightly shift the lines to better
match the VRI polygons” potentially results in polygons with incorrect attributes; and
(iii) There may be issues with the methods used for Accuracy Assessment (see comment below).
Request that the Proponent:
(a) Clarify in detail the methodology used to create the baseline ecosystem mapping. Methods
need to be presented as transparent and repeatable. Include a description of:(i) mapping
methods; (ii) accuracy assessment methods and values; (iii) an explanation of the spatial shift (How
significant was this? How did it affect the product?); and (iv) a summary of the differences between
the use of the biophysical air-photo-interpreted and VRI lines, with an explanation of how the
differences in linework were mitigated.
(b) Describe how the thematic and spatial accuracy of the Broad Habitat Mapping (BHM) is the
same or different than TEM re thematic and spatial accuracy.
(c) Clarify the vintage of air photos on which Broad Habitat Mapping was based (mid 80s to early
90s) as well as the dates of current airphotos. Were they current to 2012?
(d) Clarify whether “pre-processing of the biophysical habitat information” was completed prior to
converting the biophysical data to a raster format; and
(e) Consider submitting the full complement of mapping data to provincial government staff for
review. Access to this data, would provide clarity with respect to the methods used and allow for a
much more comprehensive review.
Final April 4, 2013 135
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 307
Description of VCs - Ecological Communities
Questions re Broad Habitat Mapping:
1. Please clarify the following statement from Vol. 2, Appendix R, Part 1, pp20 “The 07-SH and $07-
SH:ac units had the poorest accuracy at 35% and the 05-SO unit had relatively poor accuracy at
43%. There was a common error related to differentiating the 04-BL and the 08-BT; these units are
located adjacent to each other on the edatopic grid and this error may have contributed to the high
number of acceptable classifications for non-seral forested units in Table 1.1.6” Does this mean
that of only the 07 and $07 plots the proportion correct or acceptable only tallied 35% and 43%
respectively?
2. A rational for why the 04 and 08 were more difficult to differentiate is presented here but there
is no rational for the low accuracy of the 07 and $07 units. Is there any rational for this and if so,
what is it? Tree species composition from VRI is sited next as a confounding factor for seral unit
accuracy. The use of structural stage from VRI can be challenging for certain applications.
Continued in next cell
Final April 4, 2013 136
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
307
Continued
3. In the same paragraph from Vol. 2, Appendix R, Part 1, pp20 accuracy is referred to as both
70.4% and 69%. Table 1.1.6 shows from where 70.4% is derived (" “The overall broad habitat map
accuracy calculated from the 2010 field plots was 70.4%") but there is no reference to 69% in the
text. Most mapping accuracy projects focus on forested site series as the non-forested units are
generally easier to differentiate. The accuracy of broad habitat mapping forested
units—69%—exceeds the minimum requirement of 65% for mapping projects and wildlife habitat
modeling (Meidinger 2000). Which value is it?
4. It is noted that 2673 polygons were visited in the TEM LAA (equal to 37% visitation) but only 283
polygons were checked for bioterrain? Why were so few polygons assessed from a bioterrain
perspective? Was a terrain specialist involved in most of the ecosystem plot data collection? If not,
both the bioterrain and ecosystem mapping should be critically reviewed, as should the plot data.
Final April 4, 2013 137
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 308
Description of VCs - Ecological Communities
Issue: There are a number of questions and concerns related to the Accuracy Assessment (AA) of
the Broad Habitat Mapping: (i)
The AA appears to be sampled in a targeted, non-random fashion resulting in biased results. It is
noted in Vol 2 App R Section 1.1.2 that certain ecosystem units were not sampled and others were
targeted. (ii) The map
accuracy values noted in this report are statistically invalid. It also assumed that the AA outlined in
the report was completed by the mapper? This is non-standard. A statistically valid accuracy
assessment (as outlined in the Accuracy Assessment Protocol, Meidinger 2000) is supposed to be
conducted by an independent third-party and use randomly selected polygons from the entire map
area. The data generated from the AA is supposed to be kept independent from the map data.
(iii) The accuracy assessment only reported out on the first leading decile instead of all deciles.
Structural stage information should be summarized across all three deciles rather than only the first
decile. Certain structural stages associated with sensitive ecosystems may not be the most
prevalent on the landscape and thus maybe under represented if assessed using a first decile
approach.
Continued in next cell
308
Comment Continued
Request that the Proponent:
(a) Provide a rationale for why the accuracy assessment for the biophysical mapping only reports on
the first leading decile instead of the entire value. How might reporting to the first leading decile
affect the overall analysis?
(b) There is mention of quality assurance completed by third party ecology and bioterrain
specialists (Vol 2 App R S 1.1.1.1 Pg 15). Who did this QA? How much of the mapping was reviewed
and at what stage? What were the findings? Is there a QA report?
(c) Was the sampling method for the AA consistent with standard protocols? Was the sampling non-
random? If so, please describe how sampling sites were selected and the implications of a non-
random sampling method on the assessment of accuracy.
Final April 4, 2013 138
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 309
Description of VCs - Ecological Communities
Issue: The current status, distribution and significance of terrestrial ecosystems were not described
adequately in areas covered by the Broad Habitat Mapping (BHM). These mapping products do not
provide sufficiently reliable mapping to locate occurrences of ecological communities, specific
wetlands, etc. and can only be used as a broad roll-up of areal extent, e.g. timber harvesting
allocation. The BHM would also not be particularly suited for identifying areas of compensation
without additional field inventory.
The current status and distribution of terrestrial ecosystems were described adequately in the area
in which Terrestrial Ecosystem Mapping (TEM) was completed.
Concern: CDC does not map occurrences from Predictive Ecosystem Mapping (PEM) products as
the reliability and sampling have proven to be insufficient for specific location information. CDC
also has not used PEM products to determine area of occupancy of small patch rare ecological
communities for status ranking factor of rarity. However, TEM products are used but are always
reviewed for confidence level and sometimes resampled. For areas outside of the LAA (and some
of the recently added LAA which is BHM, not TEM, accuracy of quantifying area lost is subject to
considerable error of omission and commission within an EIA project
Continued in next cell
Final April 4, 2013 139
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
309
Continued
Request that the Proponent:
(a) Clarify the limitations and uncertainties associated with the Broad Habitat Mapping when
reporting on estimates of areas of terrestrial ecosystems impacted by Project development.
(b) Explain how differences in the quality and accuracy of the two ecosystem map layers (BHM and
TEM) were reconciled in reporting areas of ecological communities.
(c) How might differences between BHM and TEM affect the subsequent interpretations re habitat
value as well as area of representation of ecological communities?
(c) Consider field verifying sites such small patch rare ecological communities for size and location.
Final April 4, 2013 140
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 310
Assessment of Impacts - Ecological communities
Issue: The EIS characterizes the post-dam hydrology but does not provide an assessment of effects
to ecological communities resulting from changes to the hydrologic regime and water table post-
inundation.
Concern: There may be significant impacts to plant communities that are currently located on a
mesic site but that become located on a sub-hydric site post-inundation. The EIS notes the real
impact to zonal plant communities are result of flooding but the overall impact may be even higher
once changes to hydrology adjacent to the inundated area are taken into account (see Details). For
example, there are likely to be far-reaching effects on plant communities sited on old fluvial fans.
Also, wetlands may be particularly impacted by a change in hydrologic regime post-inundation. For
example, new wetlands may form along the sides of the reservoir where groundwater level rises to
the surface, which would result in a significant ecosystem change in the area.
Additional Details: The following is a description by Provincial Research Ecologist Will MacKenzie of
cottonwood stands in the Project area based on a visit in the spring of 2012:
"The cottonwood stands along the mainstem [of the Peace River] are largely in a state of decline
due to the changing flood regime (they never have surface flooding anymore). The understory is
converting from the normal mid bench understory to an upland suite of species. Some flood release
management might be able to create new cottonwood stands or refurbish older stands (maybe, this
would take a huge release - last year's "highest in 20 years" flood levels did not lead to surface
flooding of the existing stands)."
Continued in next cell
Final April 4, 2013 141
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
310
Continued
Request that the Proponent:
a) Clarify the potential impact of changed hydrology post-inundation on plant communities within
a 5% slope (gently to non-sloping sites) that are now coincident with the new water table. Include a
comparison of the spatial extent of existing plant communities and future projected communities
when one includes both inundation and changed hydrology.
(b) Assess impacts to wetlands that may are likely to result from changes in the hydrology of areas
on the fringe of the reservoir post-inundation and in areas affected by the post-dam water table.
(c) Clarify whether there is a strategy to deal with the newly emerging wetlands along the banks of
the reservoir.
Final April 4, 2013 142
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 311
Assessment of Impacts - Old forests
Issue: The EIS describes plans to remove 'merchantable' trees in the riparian, leaving
unmerchantable trees as a mitigation measure (Table 13.15 on pg 13-13). The impacts of the
removal of large, old trees from the riparian buffer was not assessed.
Concern: Blue-listed old and mature riparian and floodplain forests will be reduced in provincial
representation as a result of this Project and the EIS estimates an overall loss/degradation of nearly
> 40% of the riparian habitat. The planned removal of large old trees in riparian areas will
contribute to further reductions in representation of riparian and floodplain forests. There are also
other impacts likely from the removal of riparian vegetation. For example, the removal of any
vegetation in the riparian buffer zone will increase the risk of erosion in these sensitive areas. Also,
removing the merchantable trees reduces potential for recruitment of future old growth riparian
ecosystems.
Request that the Proponent: (a)
Clarify to what area the proposed removal of merchantable trees applies. Is the intent to clear
vegetation immediately before filling the reservoir or will it be retained throughout operations?
(b) Provide an assessment of the implications to rare and sensitive ecological communities of the
removal of merchantable timber from riparian areas.
(c) If riparian vegetation is to be retained throughout operations, consider retaining merchantable
trees, especially large poplar and aspen, in the 15 m riparian buffer to aid in the regeneration of the
riparian forest that has high value to wildlife.
Final April 4, 2013 143
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 312
Assessment of Impacts - Ecological communities
Issue: The EIS does not provide a full landscape context in which to assess impacts to ecological
communities. The Project Active Zone occurs in a unique valley-bottom environment. Impacts
should not just be assessed in direct impact zone; Impacts need to be reported in the context of
what is available in the larger area.
Concern: The overall significance of effects may be underestimated if impacts to ecological
communities are assessed without consideration of ecosystem abundance and condition in the
RAA. For example, the percentages noted for rare communities lost in the BWBSmw are
meaningless if only stating relative to what is present in the LAA. What if these areas represent the
only occurrence of these communities in the BWBSmw? Or, what if these communities exist
elsewhere in a protected area or in an area slated for development as well? Likewise, it is not
possible to identify whether the seven tufa seeps that are to be destroyed, or negatively impacted,
are the only seven tufa seeps in the entire RAA, or if they commonly occur throughout the region.
Comment Continued in next cell
Final April 4, 2013 144
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
312
Comment Continued from Previous cell
Request that the Proponent:
(a) Provide an analysis of representation of ecosystem units in a regional context. Of the 60
different ecosystem units found in the LAA, how well represented are each of these units within a
given Biogeoclimatic (BGC) unit or region? In particular, how common are the valley bottom forest
and riparian wetland types (those with “the largest proportional loss”) within the given BGC unit?
Within the Region? Within the province?
(b) Include an assessment of rare ecological communities lost in the BWBSmw relative to the
region and province. How much riparian forest exists in the BWBSmw? What structural stages are
present and what is the areal extent of each? How does this compare to the range of natural
variation within these riparian forests? How many occurrences of rare plants are present? What is
the area of these occurrences? How common are the types of wetlands found in the BWBSmw? In
the region? To what extent are all of these values captured in the protected area versus the area to
be developed?
Final April 4, 2013 145
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 313
Assessment of Impacts - Ecological communities
Issue: The EIS states that there will be sizeable losses of old and mature riparian and floodplain
ecosystems in the LAA, however these ecosystems will persist downstream of the reservoir" (Pg 13-
39 lines 9 - 13). It would be reasonable to expect that the riparian and floodplain ecosystems
downstream of the planned reservoir will be significantly negatively impacted by altered flow
regime.
Concern: These ecosystems are maintained by their natural flood regime, it is likely that they will
be lost, or significantly degraded, rather than act as remnants of high quality intact forest.
Request that the Proponent:
Assess the probable loss of rare and sensitive ecosystems due to impacts downstream of the
proposed dam. Please include (i) a quantification of the type or amount of riparian ecological
communities (e.g. Fm02) that may be lost or significantly degraded by the downstream flow
regulations; and (ii) include the existing impacts of the Peace Canyon Dam and the W.A.C Bennett
dam on equivalent ecosystems as part of the regional context.
Final April 4, 2013 146
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 314
Assessment of Impacts - Ecological communities
Issue: The EIS lacks a comprehensive assessment of impacts due to loss of ecological function.
There is a section assigned to discussing impacts on Ecological Function, however this section
appears to only focus on the species at risk that may be associated with these ecosystems, rather
than the more comprehensive topic of ecosystem function as a whole.
Concern: Analysis of the impacts of the predicted levels of ecosystem loss on the function of
ecosystems is critical to determining impacts of this Project.
Request that the Proponent: Provide an assessment of impacts due to loss of ecological function
that include a thorough summary of the impacts of ecosystem loss on ecosystem functioning
beyond the impacts on individual specie and assesses impacts on hydrology; impacts on wetland
function and longevity; and impacts on stand structure and resilience.
Final April 4, 2013 147
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 315
Assessment of Impacts - Ecological Communities
Issue: The EIS states (Vol 2 Pg 13-27 Table 13.15): “If there is limited or no existing data to help
facilitate avoidance measures, then supplemental pre-construction surveys will be conducted.”
There should not be any gaps in the data if the inventories have been completed as suggested by
this report.
Concern: Assessment of impacts and effects may be underestimated if there are gaps in the
inventory of ecological communities.
Request that the Proponent:
(a) Clarify the level of confidence provided by existing mapping of ecological communities and
whether additional surveys are likely to be needed prior to construction.
(b) Explain how gaps in data might affect the estimates in the EIS of area of ecosystems and
number of plant occurrences directly impacted.
13 316
Assessment of Impacts - Ecological Communities
Issue: The EIS states (Vol 2 Pg 13-32 Table 13.15): “Prior to work commencing, surveys will be
conducted to identify invasive species populations”
Concern: An inventory of the extent of invasive species should be a factor in the assessment of
ecological communities and rare plant species status.
Request that the Proponent:
(a) Clarify whether an inventory of invasive species has been completed to date and this data
included in the baseline assessment of the status of ecological communities and rare plant species.
(b) If this was not included, please explain the implications of not factoring in the existing extent of
invasive species in the assessment of the status of ecological communities and rare plant species.
Final April 4, 2013 148
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 317
Assessment of Impacts - Ecological communities
Issue: In Section Vol. 2, S13.3 Effects Assessment, it is stated:" Vegetation and ecological
communities and rare plant populations in the LAA adjacent to any Project components may still be
changed through edge effects associated with fragmentation, spread of invasive species, or changes
in hydrology, but the exact spatial extent of any change is difficult to quantify. A qualitative
assessment of changes in the condition of a community and rare plants due to these stresses –
including long-term maintenance of the transmission line right-of-way – is considered". In looking at
Vol. 2 Appendix R, part 2, 2.11, Terrestrial Ecosystems (pp 84-85), fragmentation and edge effect
are discussed but only in context of increased edge due to added roading (Table 2.11.8).
Concern: Information on edge effects should be presented in the EIS to provide a more
comprehensive sense of true impact.
Request that the Proponent: Clarify if there are GIS data for total edge effect within the PAZ that
includes all project components as stated in S13.3. If this data exist, please present it in the EIS.
Final April 4, 2013 149
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 318
Mitigation Measures - Ecological Communities
Issue: The proposed mitigation does not specifically address the issue of climate change and
associated impacts on vegetation or ecological communities. The impacts could be both positive
and negative and will vary by individual species and ecosystem.
Concern: In several instances, the EIS describes mitigation effectiveness as “Effective – these are
standard measures that have been applied successfully in the past”. However, there is a high
degree of uncertainty about whether past engineering practices will be effective with respect to
climate change impacts. Likewise, the effectiveness of management / restoration practices for
vegetation and ecological communities may be reduced in the future under climate change.
Climate change impacts are likely to alter hydro-geomorphological processes over the proposed
100 yr life span of the dam.
Request that the Proponent: Consider incorporating climate change adaptation techniques in early
project stages to increase resilience over the long-term. For example: The mitigation measure to
“Retain vegetation on steep unstable slopes that would be highly susceptible to landslides if the
vegetation as removed” (Vol 5 Pg 38-6). Given the climate scenarios and projects for changes in
precipitation and slope instability, it might be prudent to incorporate additional conservative
measures on slope angle as an adaptation technique when determining which areas need to be
revegetated.
Final April 4, 2013 150
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 319
Mitigation Measures - Ecological Communities
Issue: Details concerning mitigation and monitoring are not sufficient to determine accuracy of
assessment of residual effects and determinations of significance. The EIS refers to environmental
management plans for details of mitigation, but the plans do not contain details or make clear links
between impacts and mitigation requirements. There are essentially no specific actions in the table
of mitigation measures to address the condition or loss of Ecological Communities at risk or
Sensitive ecosystems. What is proposed for mitigation is unlikely to be entirely effective, as
acknowledged in the assessment.
Concern: Specific consideration needs to be given to address the loss or reduced condition of at-risk
or sensitive ecological communities. A net loss of terrestrial ecosystems is a net loss of habitat to a
variety of wildlife species and a potential increase in the level of conservation concern of both
plants and animal species within the area of impact. Mitigation measures that are unlikely to be
effective should not be used to reduce estimates of residual effect. Considerations:
(i) Very few mitigation measures are proposed for terrestrial ecosystems as most are directly lost
due to flooding of the reservoir or construction of the dam. The one exception to this is the Wilder
Creek mitigation plan which could provide some mitigation. However, Wilder Creek will only
provide mitigation of a very small proportion of the habitat that is being lost. For example,
approximately 12 hectares of wetland habitat will be created to replace the approximately 675 ha
of wetland that will be lost to this project.
Final April 4, 2013 151
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
319
Comment Continued
(ii) Translocation is not possible for ecological communities (plant species, yes, plant communities
no) and is not feasible to include as a mitigation measure.
(iii) BC Conservation Framework (CF) Actions are indicated for plant species but there is no
equivalent compensation recommendation for ecological communities e.g., several of the listed
ecological communities recommend monitoring action.
Request that the Proponent:
(a) Clarify intentions to compensate for direct loss of terrestrial ecosystems due to inundation or
other aspects of development. Will there be an attempt to compensate so that there is no net loss
of ecosystems where possible e.g., by restoration activities or conservation of other occurrences of
same/similar ecological communities or sensitive ecosystems.
(b) Provide scientific evidence of the effectiveness of translocation of ecological communities in
other locations. If this does not exist, please remove translocation as a mitigation measure.
(c) Include Conservation Framework (CF) Actions for ecological communities in mitigation and
monitoring plans and list in the details of technical reporting in Appendix R.
(d) Table 13.15 states that “Disturbed sites will be planted quickly with ground cover, shrubs or
trees that are regionally appropriate...”. Please clarify what is meant by “quickly”. Also
recommend clarifying in the text that "all vegetation will be replaced with native vegetation and
localized seed stock".
(e) Engage provincial government staff when developing detailed mitigation plans.
Final April 4, 2013 152
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 320
Mitigation Measures - Ecological Communities
Considerations re mitigation and monitoring:
(i) Timing and avoidance measures need to be developed as a condition of permitting.
(ii) Relevant management plans (e.g., Soil Management, Site Restoration and Re-Vegetation Plan;
Vegetation and Invasive Plant Management Plan, Operational Vegetation Management Plan) should
be completed in consultation with interested agencies, First Nations, and the public.
(iii) Consider identifying environmental protection zones for ecological communities at risk or non-
wetland sensitive ecosystems. (iv)
Retain tree roots (including merchantable timber) within riparian buffers to forestall erosion.
(v) Mitigation measures forImpacts on sensitive sites should take into account how
common/uncommon these communities are both inside and outside the LAA/RAA.
Comment Continued in next cell
Final April 4, 2013 153
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
320
Comment Continued from previous cell
(vi) Consider using the baseline information as a tool for monitoring the status of
(1) rare plant occurrences and ecological communities left intact or partially intact
(2) habitat changes over time
(3) ecological community species composition, e.g. spread of invasives or spp shifts due to changes
in site conditions (wetter sites). Recommend setting up permanent sample plots with climate
stations to monitor change from pre-development to post-completion.
(vii) Recommend that further consideration be given to avoiding Project activities, or using
intensive mitigation measures, in the following areas:
• Portage Mountain – This proposed quarry area provides habitat for Siberian polypody and
hibernating bats. The rare plant is not known to occur elsewhere in the LAA, while bat hibernacula
are important habitat features and their preservation a priority.
• Watson’s Slough – This wetland supports numerous rare plants, and a range of wildlife, including
the listed western toad and Yellow Rail. BC Recommend the consideration of alternative avoidance
and mitigation measures
13 321
Mitigation Measures - Ecological Communities
Issue: There is little to no detail on follow-up plans around commitments on monitoring (methods,
field testable objectives, timing, frequency, duration) or contingency/adaptive management per
requirements of 23.5 in the EIS Guidelines.
Concern: A robust monitoring plan is needed to monitor the effectiveness of mitigation measures
over time. Government staff require access to data to effectively design and evaluate monitoring
outcomes.
Request that the Proponent: Engage in a data-sharing protocol with the Province that would allow
the provincial government to manage the data and have it accessible for use in monitoring the
effectiveness of mitigation measures.
Final April 4, 2013 154
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 322
Mitigation Measures - Wetlands
Issue: The creation of new wetlands is mentioned throughout the EIS to address compensation for
a number of taxa, but there is no detail on what types of wetlands are going to be created (e.g,.
marshes, bogs, fens) and what species these will be created for. The EIS only refers to fish-free or
fish present wetlands.
Concern: Some characteristics of wetlands can take decades to centuries to replicate and there is
no detail in how this will be expidited or how it will be attempted.
Request that the Proponent: If the Project is approved, work with provincial government staff to
develop a detailed mitigation plan for wetlands that considers the types of wetlands and habitats
impacted and opportunities to create new wetlands of different types. Include consideration of
different wetland functions (species habitat, water filtration, flood control, CO2 sinks, etc.).
Final April 4, 2013 155
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 323
Mitigation Measures - Ecological Communities
Issue: Tufa seeps have been identified as a rare and senstive ecosystem unique to the Project area.
Tufa seeps provide highly specific habitat that support a number of rare and possibly endemic
species. The are an ecosystem of high conservation concern with respect to this Project. Most of
these communities will be lost in the Project footprint.The two remaining are in vulnerable
locations (e.g., along the proposed transmission line). Also a rare marl fen at Watson Slough will be
lost.
Concern: Conservation of tufa seep and other rare ecosystems requires a detailed inventory to
locate other occurrences of these ecosystems at least in all of the Ecosections that overlap the RAA.
They are too small to be picked up by TEM or PEM mapping.
Request that the Proponent: (a)
Develop a management plan prior to construction to avoid and, where avoidance is not possible,
mitigate impacts to tufa seeps.
(b) Clarify whether an attempt has been made to find other tufa seeps in the RAA and environs or
will the Project impact all of the known tufa seep habitat.
(c) Clarify all Project-related activities that have potential to impact the tufa seep on the proposed
transmission line and describe measures to avoid impacts to this ecosystem. Request that the tufa
seep on the transmission line be avoided entirely and its hydrology maintained.
Final April 4, 2013 156
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 324
Mitigation Measures - Ecological Communities
Issue: The EIS states that “Reclamation and restoration activities for post-construction would alter
community structure” (page and line).
Concern: There is no information in the EIS document or other documents regarding actual
restoration for particular rare plant communities. This sounds like only reclamation.
Request that the Proponent: Clarify whether it intends to restore or reclaim rare plant
communities.
Final April 4, 2013 157
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 325
Mitigation Measures - Ecological Communities
Issue: In Vol 2 Appendix C, Section 1.2, At-risk and Sensitive Ecological Communities, it is stated
that OGMA’s are designated as Sensitive Ecological Communities. It is also noted that 4 Landscape
Units (LU’s) within the LAA encompass 1275 ha of legal OGMA’s. Under the Forest and Range
Practices Act these OGMA’s are stipulated in the Forest Stewardship Plans of forest licensees with
Major Licences to Cut and form the basis for their meeting old growth biodiversity targets set out
under the Provincial Old Growth Biodiversity Order. However, the values for the proportion of
OGMA area in the PAZ that would expect to be lost due to operations and construction do not
appear to be present and nor does any discussion on how the land status relationship between BC
Hydro, Ministry of Forests Lands and Natural Resource Operations and forest licensees is being
dealt with.
Concern: There appears to be no mention in the EIS of actual impact to OGMA’s nor how loss of
OGMA’s will be compensated for.
Request that the Proponent:
(a) Clarify whether the impact to designated OGMAs has been assessed as part of the EIS and
whether there are plans to compensate for loss of OGMAs.
(b) If there are mitigation strategies to address loss of OGMA area from the crown landbase, please
make this information available for reviewers and the public.
Final April 4, 2013 158
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 326
Mitigation Measures - Ecological Communities
Issue: As the majority of wood utilization/disposal is anticipated to occur early in the project,
within the reservoir activity zone, how will natural re-vegetation be dealt with?
Concern: Re-vegetation could be a year-round/seasonal attractant to wildlife prior to reservoir
infilling.
Request that the Proponent:
(a) Clarify intent with respect to natural re-vegetation prior to reservoir infilling?
(b) Consider revegetating to minimize attractants to wildlife.
Final April 4, 2013 159
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 327
Estimate of Residual Effects - Ecological Communities
Issue: Not all of the residual effects to ecological communities are summarized 18-24. Further,
there has been no association between what the loss of these terrestrial ecosystems means in the
greater context of healthy environmental conditions.
For example, loss of 44% of the 09/Fm02 ecosystem will result in loss of one of the most
structurally complex ecosystems on this landscape. We can anticipate significant impacts on
wildlife species as a result of this (e.g. fisher, marten, bats, and other cavity nesting species).
Furthermore the loss of 675 ha of wetland has not been associated with impacts on ecological
function (i.e. maintenance of water quality).
Concern: The ‘high level’ nature in which the residual impacts to terrestrial ecosystem are
presented makes it impractical to evaluate the accuracy of the statements provided. Also, some of
the assumptions are questionable. For example, it is unlikely that many of the terrestrial ecosystem
impacts will be reversible over time, when a large proportion of the impacts are under the Project
Activity Zone. Likewise, given the nature of these impacts, it is difficult to image many of these
terrestrial ecosystems having high resilience.
Request that the Proponent:
(a) Report on residual effects by individual ecological communities, including separate reporting of
effects on Tufa seeps, different wetlands and other at-risk ecological communities. Question the
assumption of reversibility. Tufa seeps should be identified and summarized separately not
combined with wetlands and rare plants.
(b) Re-evaluate the assumptions used in assessing residual effects such as the reversibility of
impacts on ecological communities, based on existing literature and monitoring outcomes from
other similar developments.
Final April 4, 2013 160
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 328
Estimate of Residual Effects - Ecological Communities
Issue: The effects assessment, as outlined in this section, appears to be focussed solely on the loss,
fragmentation and disturbance within the LAA. It does not make any reference to these effects
relative to the current and/or historical representation of these ecological communities within the
valley, BGC unit, Ecosection, region, etc. The assessment would be improved with a quantification
of similar habitat/terrestrial ecosystems that were lost below the Dinosaur and Williston reservoirs.
Most of these projects would have also collected baseline data, so it should be known whether or
not they impacted spp and ecosystems similar to those impacted by the Project.
Concern: If an ecosystem is likely to be destroyed or severely impacted there is a need to identify
the impacts on the ecosystem in the context of the area that has already been destroyed through
previous development. The cumulative loss of these ecosystems can be substantial. For example,
44% of the 09/Fm02 ecosystem type from the LAA is expected to be lost during Site C, whereas we
might already have lost up to 50% of that original habitat under the previous two reservoirs, and
can expect further losses downstream of Site C reservoir. The data to do this analysis is available
through the ecosystem modelling project that was completed for the Williston reservoir (modelling
pre-inundation habitats) in 2006.
Comment continued in next cell
Final April 4, 2013 161
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
328
Comment Continued from Previous Cell
Request that the Proponent:
(a) Report on residual effects to individual rare or unique ecosystems(re.g., tufa seeps, old forest
and alluvial floodplains), in the context of historic distribution.
(b) Provide additional baseline information regarding pre-dam distribution and extent of
ecosystems.
(c) Provide a more detailed description of impacts to ecological communities as a result of previous
developments in Section 11.1.2.2
Rare Plants
Final April 4, 2013 162
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 329
Selection of VCs - Rare plants
Issue: The Proponent has mostly assessed the appropriate suite of values. Results are provided for
vascular, moss and lichen plant species and some species new to science not yet described.
However, a number of rare plant species were identified during surveys of the proposed Project
area in 2008 that are not included in the EIS. A number of these species are proposed for listing
with CDC but are not yet listed.
(i) Packera plattensis and Scolochloa festucacea were found in the LAA (CDC received in Jan 2012);.
(ii) Previously-undescribed species of vascular plants listed in 2008: Carex sp. nov (cf atherodes
and tenera), Cystopteris sp. nov., Epilobium sp. nov., Muhlenbergia sp. nov., and Viola renifolia var.
nov.
(iii) Sphagnum contortum is a Blue-listed species;
(iv) Two macrolichens, Fulgensia subbracteata and Xanthoparmelia camtchadalis that are found
nowhere else in BC and would thus be ranked as Red-listed by the CDC (in progress);
(v) 9 microlichens, e.g., Acarospora terricola, which are not listed by BCMOE (CDC only tracks
macrolichens at this time) but worthy of noting because they are likely candidates for BC lists and
even national COSEWIC lists (i.e., Buellia elegans). It is only a lack of capacity at the CDC prevents
them from listing them provincially; and
(vi) Two undescribed species of mosses.
Epilobium leptocarpum was found in 2008 but is in the process of being yellow-listed so need not
be added.
Request that the Proponent:
(a) Include all of the species mentioned above as rare plants in the assessment (with the exception
of Epilobium leptocarpum).
(b) Clarify the steps taken to date to identify and process these species. For example, have
specimens been deposited in a recognized herbarium (e.g., at UBC) and if so, how many specimens
of each were deposited?
Final April 4, 2013 163
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 330
Selection of VCs - Rare plants
Issue: Little bluestem is probably not the most at risk example to focus on for the assessment (it is
also known from southeastern BC). The specimens for Chyrsosplenium iowense have recently been
reviewed and there are only 3 good collections (Tupper Ck, Beatton R, and the LAA). Along with
Artemisa herriotii (Western Mugwort) these are probably the most impacted by this project with a
loss of 1/3 of known sites.
Concern: The determination of significance does not mention effects to two of the potentially most
impacted rare plant species.
Request that the Proponent:
Incorporate Chyrsosplenium iowense and Artemisa herriotii into the species account and
determination of significance (contact [email protected]).
Details: Western mugwort will probably be the most impacted BC-listed entity (likely be uplisted if
the Project proceeds). The EIS states that “it should be noted that the taxonomy of western
mugwort is uncertain” (Appendix R pg 346). Curtis Bjork pointed out the misnaming of our material
as A. longifolia and the correct name as A. herriotii in 2011. The challenge is that some of the
standard global references do not always cover the regional nuances (for example, an author may
not have reviewed all the material well enough). The Natureserve Global names don’t always match
the CDC names but there is flexibility within the Natureserve system to allow for this until the
standard can be updated. Scoggan is the reference that best fits.
Final April 4, 2013 164
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 331
Selection of VCs - Rare plants
Issue: Table 13.12: Geum triflorum var. triflorum is not CDC-listed but in 2008, Curtis Bjork
suggested a specimen review which has since been done at UBC and the Royal BC Museum in
Victoria. Since this variety is only known to occur in the Peace River Valley, the loss of occurrences
to construction will likely significantly affect its conservation status rank (CDC rank). CDC will list
this entity in April this year as only few collections are known in BC.
Concern: Limiting the assessment to species that are currently listed by CDC may result in loss of
vulnerable species that have yet to be listed.
Request that the Proponent:
Proactively evaluate the potential impact on Geum triflorum var. triflorum given that it is endemic
and its loss will likely significantly affect its conservation (CDC) status rank.
13 332
Description of VCs - Rare plants
Issue: The rare plants that were assessed have been described fairly well (current status,
distribution and significance). There is no definition provided of an occurrence.
Concern: How a plant occurrence is defined has a bearing on its status. CDC defines an occurrence
by a standard 1 km separation distance.
Request that the Proponent: Clarify the definition of a rare plant occurrence used in the
assessment.
Final April 4, 2013 165
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 333
Description of VCs - Rare plants
Issue: The Conservation Framework Action Priorities and Groups (bins) are being actively
updated/reviewed and as a result, some of the bins in the EIS are not current. The total number of
CDC vascular plants is not 39 (because some were not listed that were in 2008 list and some should
now be removed because of upcoming CDC downlisting.)
Concern:
The CDC listings of rare plants in the EIS may not be current.
Request that the Proponent:
Update description of rare plants based on current listings and taxonomic bins. If ranks are
adjusted to the April 2013 list, ensure that other rank changes are also incorporated. (There should
only be a few that are relevant, plus a few name changes.)
13 334
Description of VCs - Rare plants
Issue: The taxonomic bin for Utricularia ochroleuca is not appropriate. There is at least one good
specimen for this species in BC (Liard River hotsprings), but most others are likely misidentified (A.
Ceska, pers. comm. 2013). This species does not need any taxonomic work, but it does need
specimen review and inventory. The species account for Meadow Arnica (Appendix R Section G.2)
notes that "the authoritative Flora of North America did not accept subspecies incana as a
legitimate taxon ... and other botanists working on the Site C project have questioned its validity..."
Concern:
The specimens for the present study may be misidentified and should be sent to an expert for
confirmation.
Request that the Proponent:
Send samples of Utricularia ochroleuca and Arnica chamissonis ssp. Incana to an outside expert to
confirm their identity.
Final April 4, 2013 166
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 335
Assessment of impacts - Rare plants.
Issue: Rare plants are lumped together for the purpose of assessment.
Concern: Rare plants require species by species management. Lumping rare plants potentially
masks impacts and results in missed opportunities for species-specific mitigation measures.
Request to the Proponent: Provide separate species by species assessments and mitigation
measures for rare plants.
Final April 4, 2013 167
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 336
Assessment of impacts - Rare plants.
Issue: Impacts on rare plants are understated in the summaries of effects. Volume 2 Sec 13.3.1.2
(pages 13-19) states, “The large majority - 122 – of 142 BCMOE-listed vascular plant occurrences
[that will be impacted] are expected to be lost during construction,” but the Executive Summary
(Page 46) notes that “...occurrences of rare plants would be lost including two red-listed rare plant
species, Drummond’s thistle and little bluestem.” This would be more accurately summarized by
noting that 6 (7?) are red-listed including Drummond’s thistle and little bluestem - rather than
mentioning just two. The summary of loss provided in the residual effects section of Vol 2
Appendix R Part 1 (page 108), at least 35% of occurrences will be lost (85 occurrences in the dam,
reservoir, and quarry sites).
Concern: The way the information is presented, it is difficult to know what the actual effects are
and how they have been interpreted. The magnitude of impacts are underplayed in the Executive
Summary.
Request that the Proponent:
(a) Provide a clear link from the assessment of effects to rare plants in Appendix R to the results
reported in the main document.
(b) Clarify whether all Red- and Blue-listed species were considered individually in the assessment
of effects.
(c) Provide an explanation of how the loss of plant occurrences in the dam, reservoir and quarry
sites might impact individual rare plant species at a local and provincial scale.
Final April 4, 2013 168
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 337
Mitigation measures - Rare plants
Issue: The EIS provides few details about mitigation measures for rare plants.
Concern: 122 occurrences of BCMOE-listed plant species are predicted to be impacted during the
construction phase of the Project and another 20 during operations (S13.3.1.2). Efforts should be
made prior to construction to avoid or mitigate anticipated impacts. A robust restoration plan is
needed for vegetation communities and rare plant occurrences.
Request that the Proponent: Develop and implement a Rare Plant Management and Mitigation
Strategy (see Details). It is recommended that planning for restoration of plant communities begin
as soon as possible in anticipation of possible Project approval. This would have the added benefit
of demonstrating a commitment to restoration and monitoring prior to construction.
Continued in next cell
Final April 4, 2013 169
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
337
Continued
Details:
(i) Provide a strategy for how each occurrence of rare plant will be dealt with throughout the
Project. Planning should be on a species-by-species basis.
(ii) Consider setting up a nursery in the area, funded by the Project, to support reclamation and
restoration, with a special emphasis on propagation of rare plants.
(iii) Agronomic species are not acceptable for re-seeding.
(iv) Bank seeds and specimens of rare species in recognized institutions and provide sufficient
funds for their curation. Provide support to grow back-up specimens and preserve genetic material
(e.g. long-term cryo-storage of seeds such as through the Millennium Seed Program at Kew Gardens
in Richmond, UK).
(v) Maintain a spatial database of known rare plant occurrences and/ or provide data to the BC
Conservation Data Centre.
(vi) Monitoring post-construction for survival and health of rare plant occurrences should continue
past the 10 years recommended in the EIS.
(vii) Consider funding basic research into the distribution or taxonomy of rare plant species that are
affected by the Project and providing financial support for publication of data on rare plant species
in the Project area.
Final April 4, 2013 170
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 338
Mitigation measures - Rare plants
Issue: Translocation is proposed as a mitigation measure and described in the EIS as "the removal
of live rare plant individuals or propagules ...from the Project activity zone, and their subsequent re-
establishment at another location" (Sec 13.3.2 og 13-23 line 20).
Concern: The “other locations” for plants or their propogules will need to be compatible habitat to
the plants' location of origin, both in community structure and function or the translocation will fail.
Request that the Proponent:
Consider the following during restoration planning and in preparation for translocation of rare
plants.
(i) Provide a detailed outline of the restoration plan for all vegetation communities and rare plant
occurrences including a list of plant species and the habitat attributes for each.
(ii) Ensure that any translocation of plant species follows appropriate guidelines, which includes
ensuring that the new location has the same habitat attributes, community structure and function
as the original location. Follow the document “Guidelines for Translocation of Plant Species at Risk
in BC” (see Reference).
(iii) For each rare plant and each rare plant occurrence, describe the type of habitat it uses and the
location of potential alternative habitats to support a translocation.
(iv) Provide specifics on the steps that will be followed including: the timing, the habitat and the
type of follow-up monitoring that will be done.
Continued - next cell
Final April 4, 2013 171
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 338
Continued
(v) Rare plants should be propagated and also have their genetic material preserved prior to such
translocations (see comment above).
(vi) Locally sourced seeds and propagules will need to be collected ahead of destruction so that
rare and regionally-appropriate species can be grown in a nursery to provide materials for
restoration or used for re-seeding.
(viii) The following definition of a restored ecosystem can provide guidance: “An ecosystem has
recovered - and is restored - when it contains sufficient biotic and abiotic resources to continue its
development without further assistance or subsidy. It will sustain itself structurally and functionally.
It will demonstrate resilience to normal ranges of environmental stress and disturbance. It will
interact with contiguous ecosystems in terms of biotic and abiotic flows and cultural interactions.”
(Society for Ecological Restoration Primer definitions: http://www.ser.org/docs/default-document-
library/english.pdf)
Reference: Maslovat, C. 2009. Guidelines for Translocation of Species at Risk in British Columbia.
B.C. Minist. of Environ. Victoria, BC.
http://a100.gov.bc.ca/pub/eirs/finishDownloadDocument.do?subdocumentId=8321.
Final April 4, 2013 172
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 339
Mitigation measures - Rare plants
Issue: There is an emphasis in the EIS on pesticide and herbicide use for the treatment of invasive
species. There are other methods for control of invasive species that are not chemical-based (e.g.
integrated pest management; mechanical treatment, biocontrol) that are not investigated.
Concerns: (i) Chemical treatments can cause long-term envronmental impacts, including toxicity
and bioaccumulation. (ii) The use of herbicides to limit tree growth (e.g, along transmission lines)
may destroy or damage rare plants.
Request that the Proponent:
(a) Develop an Invasive Species Management Plan that considers a range of treatments options,
including early detection, preventation and mechanical or other non-chemical methods, for long-
term application. It is recommended that herbicides only be used as a last resort to control invasive
plant species.
(b) Describe how impacts to rare plants will be avoided during management of weeds and tree
growth.
(c) Include plans to protect ecosystems, plant habitats, plant communities and vegetation post-
construction and during operational activities into the future. Monitoring should continue beyond
the 10 years recommended in the EIS but after 10 years could be at 2 to 5 year intervals. Such
empirical data is important for determining trends in populations and for determining success of
objectives in restoration and reclamation projects.
(d) Consider partnering with and funding the Northeast Invasive Plant Committee to become
involved with monitoring for invasive species within the Project footprint and adjacent areas (i.e.
transportation routes).
Final April 4, 2013 173
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 340
Mitigation measures - Rare plants
Issue: Five species were identified during surveys that are potentially new to B.C.
Concern: There is little discussion in the EIS of specific methods to preserve these five species or
their habitats and no recognition of the need to collect propagules or otherwise safeguard their
continued existence. There is also no mention of plans to look for them elsewhere to see if their
destruction due to this development would be causing an extinction.
Request that the Proponent:
(a) Clarify any steps that are in place or planned to steward these five previously unidentified plant
species as part of any Rare Plant Management and Mitigation Strategy (see Details) . The EIS notes
that “Research to determine the taxonomic authenticity of these 5 potential species is
ongoing...”(App R Part 1 Sec 1.3.2.2 Pg 68). Since taxonomic research could take several years,
what is the commitment by the Proponent to protect the sites in the meantime and/or take
propagules for safe-keeping?
(b) Describe measures that have been taken to steward these plants since they were first
identified in 2008.
Details:
The following actions are recommended for previously unidentified plant species:
(i) Send seeds to a long-term repository; (ii) Propogate the plant material; and (iii) Ensure that
information is provided to the appropriate repositories of information on rare plants such as the BC
Conservation Data Centre.
Final April 4, 2013 174
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 341
Mitigation measures - Rare plants
Issue: Table 38.1: Under Proposed Mitigation column at the end of Section 13: “Undertake a study
that attempts to clarify the taxonomy of Ochroleucus bladderwort” but there are no other specific
mitigation measures identified for this species.
Concern: It would be proactive to ensure that the location of Ochroleucus bladderwort along the
existing transmission line is not affected. Since this species occurs in aquatic habitats, this includes
not affecting the surrounding hydrology.
Request that the Proponent:
Avoid impacting the wetland that contains Ochroleucus bladderwort as part of mitigation planning.
This should be an outcome of planning the transmission line to avoid or minimize impacts to
wetlands and hydrology.
13 342
Mitigation measures - Rare plants
Issue: The cliffs at Portage Mountain support a rare vascular plant (Siberian polypody), which was
not found elsewhere in the LAA. Portage Mountain also supports a bat hibernaculum.
Concern: The distinct and important habitat values at Portage Mountain suggest that this location
is of high conservation value.
Request that the Proponent:
(a) Describe measures to avoid or mitigate impacts to the rare plant occurrences at Portage
Mountain.
(b) Clarify whether the high ecological values at the site were considered in an evaluation of
alternative quarry locations.
Final April 4, 2013 175
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 343
Mitigation measures - Rare plants
Issue: It is stated that BC Hydro will undertake further surveys in the RAA to identify additional
occurrences of 18 rare plants directly affected by the Project.
Request that the Proponent: Describe plans for follow-up in the event that additional or novel
occurrences of rare plant species are identified. This includes mitigation and monitoring measures
and other steps to provide steward these occurrences.
Details:
(i) Surveys to identify target plants in the study area must be done at the appropriate time of year
by a qualified botanist. The rare plant occurrences need to also have important information like
habitat included, not just UTM’s (i.e., spatial data).
(ii) A qualified botanist should on site when wetlands are to be transversed by the Project to
ensure that the spatial data is interpreted correctly and rare plant/community occurrences are
successfully avoided.
13 344
Residual Effects - Rare plants
Issue: The autecology of individual species needs to be taken into account in the assessment of
residual effects.
Concern: Individual plant species have different tolerances to impacts that are not individually
summarized in the assessment.
Request that the Proponent: Assess Residual Effects on rare plants on a species by species basis in
consideration of their varying tolerances to impacts.
Final April 4, 2013 176
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 345
Residual Effects - Rare plants
Issue: The reporting of estimates of Residual Effects on rare plants is difficult to follow. The
rationales provided for the estimates do not always appear to be consistent with the impacts.
Examples:
(i) The Magnitude of effects is characterized as High for construction but Low for operations,
reported as "the additional loss during operations would not exceed the 10% threshold." This
suggests that the post-construction impacts can somehow be quantified when it is not well
understood how plants will be affected by operations.
(ii) It is not clear why Confidence is Low for rare plants (for construction and operations). Is this
confidence in the assessment of impacts or confidence in the effectiveness of mitigation measures?
Specific disturbance responses to excessive flooding are well-known. Plant species generally
tolerate flooding or they do not.
(iii) The reporting of Resilience as High for operations is questionable. The response of plants to
typical periodic flood events cannot be compared with the magnitude of the dam effects.
Request that the Proponent:
(a) Explain how the magnitude of additional impacts to rare plants during operations was
calculated?
(b) Consider bumping Confidence from Low to Moderate. There is a high level of confidence in loss
of rare plant occurrences associated with the dam, reservoir and quarry locations although some
other impacts are less certain.
(c) Consider characterizing the Resilience as something other than High since the response of
plants to natural flooding events cannot be compared to changes from the dam.
Final April 4, 2013 177
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13 346
Residual Effects - Rare plants
Issue: The concluding statement regarding residual effects of the Project on Vegetation and
Ecological Communities (Vol 5 s 40.11 pg 40-5 lines 31 - 36) seems to suggest that the effects of
the Project are inconsequential since pre-existing projects and activities have a significant effect
themselves.
Concern: It would be more informative to describe the incremental effect of the Project given
these pre-existing impacts rather than stating that "..., the effects on those VCs resulting from other
projects and activities that have been or will be carried out are considered significant, even without
the Project." (lines 34 and 35).
Request that the Proponent: Describe the scope, area covered and percentage of vegetation and
rare plant species affected by these “other projects and activities...” and discuss in relation to the
incremental effects of the proposed Project.
App R Table
1.3.3
14a
347
Provide a title for the table to explain what the numbers in the columns mean – occurrences?
Observations? Individual plants? CDC occurrences are specifically defined and should not be
confused with observations.
App R 22348
Typo BC ranks the taxon S2 – it is S2S4
App R 23
349
It might be worth mentioning the issue with entity reported in 2008 here: Carex sp nov cf tenera
(intermediate to Carex crawfordii ).
35.2 33350
These sections only include wildlife as defined in the old terms, i.e. does not include plants.
App R Part
1, S 1.1.2
2351
This section appears to be incorrectly headed; should it be 1.1.1.2?
App R Part
1, S 1.3.2.1
6352
Reference source not found in the third paragraph on pg 66.
Final April 4, 2013 178
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App R Part
1, S 3.1
11353
There are three general categories of mitigation, rather than four as stated in the first sentence of
this section.
13 18-19 2a
354
“Reclamation and restoration activities for post-construction would alter community structure”.
This sounds like only reclamation. The EIS uses the terms reclamation/restoration interchangeably.
The word "reclamation" is typically used in mining activities. "Restoration" is the process of
assisting the recovery of an ecosystem that has been degraded, damaged, or destroyed.
13 4 8 355
Section 13: INCONSISTENCY WITH REFERENCE :
DeLong reports on the Fire cycle in the BWBWmw1 in the Boreal Plains as ~ 100 yr cycle, and in the
Boreal Foothills, areas of BWBSmw, ESSFmw2 and SBSwk1 have varying fire cycles by mountain and
valley areas, e.g. 120 years and 150 years respectively (see Tech Report p. 9 and discussion).
DeLong 2011 is also referenced in Appendix R: Veg/EcolComm 1.1 Ecosystem Mapping p. 4 which
notes only the ~100 year cycle for the Project, and not the 120 or 150 yr cycle in some areas.
TECHNICAL MERIT: Quantitative method? In either case, it is not clear how exactly the EIA will
quantify the “loss of Old Growth” with respect to natural range of variability, or if the cumulative
effects of past harvesting is incorporated into the assessment, or only the effects of the Project
Activities.
13.1.4 4 9 356
The term habitat is being used interchangeably with ecosystem all through the EIS documents (e.g. -
Important habitats found within the project area including shoreline habitats, banks, wetlands and
floodplain); The term habitat should only be used when inferring its relationship to specific species.
13 6 15 357
Appendix R: 1.1.2 describes the Habitat Mapping Approach, 1.1.2, where there is a lack of
differentiation between vegetation ecology and species habitat: “Sensitive communities’ are not
equivalent to ‘Habitat’. Habitat can be a feature of the ecosystem, not the entire ecosystem.
Section 13 - General Comments
Final April 4, 2013 179
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13.1.4 7 6 358
In the March 2012 document “Environmental Assessment of the Site Clean Energy Project
Comment Table for Draft EIS Guidelines” it is suggested by the BC Conservation Data Centre (CDC)
the all occurrences of the term “plant communities” be changed to “ecological communities”. This
does not appear to have been done in Vol 2 Section 13
13.1.5.2 8 23-26 359
In the March 12 document “Environmental Assessment of the Site Clean Energy Project Comment
Table for Draft EIS Guidelines” more detail was requested around temporal boundaries. That
provided in Vol 2, Section 13.1.5.2 is still vague and there is no reference to any further information
in Appendices.
13.1.5.2 12 1 360
Regarding section 11.2.3.1 Rare and Sensitive Plant Communities:
The EIS will describe ecological communities at risk, which are identified as those ecological
communities currently designated on the provincial Red and Blue lists, communities that are ranked
1 or 2 for Goal 2 of the Conservation Framework , and sensitive communities that are communities
that are less resilient to disturbance such as wetlands ; it was noted in the first review of these
guidelines that this statement is not accurate. While all wetlands are sensitive to hydrological
regime changes, some wetland types (e.g. occurring on primarily mineral soils) are more resilient
than others so the statement above is in accurate. Suggested change to text on pp55: Remove the
words “such as wetlands”
13.2.1.2 15 12+ 361
In the effects assessments section values for impacts to ecosystems and plants are presented by
area in tables 13.8-13.12. The process to derive these values is “area of vegetation/ecological
community loss, assessed by overlaying the project 5 activity zone on the ecosystem maps and
conducting a GIS-based analysis of the area 6 lost due to project activities”. Although the
appropriate information is present in the tables, because information presented here is the
fundamental indicator of magnitude of impact, this information should be presented as proportions
(%) of the i) the ecosystem area and ii) the total PAZ. Preferably also in graph form where it is easy
for the public to visualize the relative impacts/losses.
Final April 4, 2013 180
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
13.3.1 16 15 362
In Volume 2 Appendix C Part 1- Land Status, Tenure and Project Requirements Maps. The following
is stated “The figures in this appendix are maps described in Chapter 11.3 Land Status, Tenure and
Project Requirements. These maps provide the following information:” Ten Figures are referenced
(as maps) at the beginning including “Figure 3 Forestry Tenures: Third party forestry tenures within
the Project activity zone. (1:300,000)” However, there are only 4 maps there and none of them are
related to Forestry Tenures – Where can they be found?
13.4.1 22 39 363
Incorrect reference to the agricultural land base, rather than vegetation and ecological
communities.
13.5 22 1+ 364
Cumulative Effects – for this section it would be useful to see data from the spatial maps of current
and projected CE’s summarized by baseline rare plant and ecosystem mapping for the RAA, LAA
and PAZ
13 1 - 19 17 365
CLARIFY TITLE OF TABLES: Does this list include the site series for all Biogeoclimatic units occurring
in the LAA (BWBSmw, SBSvk2, ESSFmv2) or only the site series for BWBSmw ? This situation occurs
frequently throughout the report where the reader has to go back to the text to interpret what the
table data is about and in some cases even the text is obscure as in the example given here. If
required as in some publications, these Table Titles would not be able to stand alone for data
presentation and comprehension.
13 21-24 13 366
STATEMENT “Rare communities include red- and blue-listed communities ranked 1 or 2 for Goal 2
(to prevent species and ecosystems from becoming at risk) of the Conservation Framework.” This
sentence seems to be implying that to be considered for the effects assessment, the selected rare
communities must be both red- or blue-listed, AND must be ranked 1 or 2 for Goal 2. Suggest
rewording to clarify intent here (e.g. see 13-11, line 12-14)
13 47 12 367
The size of the size of the proposed Peace River Boudreau Lake Protected Area is identified
incorrectly and inconsistently here and in other locations (section 14.6.2.3) please ensure that the
correct area for the proposed protected area is used consistently throughout the document - See
Vol. 3, Table 25.14
Final April 4, 2013 181
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App R Part
1, S 2.1.18 368
The references in the first part of this section are incorrect; reference is to “0”, but should be
Appendix D.
13 Appendix
R - 1.1.2369
Appendix R: p.12 Discussion of seral stages. This section is somewhat simplified in that the criteria
used are only two indicators of successional processes; other factors include severity, frequency
and time since disturbance, etc. 35:35
Section 14 - Wildlife Resources
Butterflies & Dragonflies
Final April 4, 2013 182
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 370
Selection and Description of VCs - Invertebrates
Issue: The Invertebrate section only looks in detail at butterflies and dragonflies. Other
invertebrate groups are not discussed or assessed.
Concern: There are many other invertebrate groups that have potential to be impacted by the
Project. The two invertebrate groups with baseline studies (butterflies and dragonflies) are not
suitable surrogates for all invertebrate groups. Not considering other taxa means that impacts to
species in these groups will not be recognized, opportunities for mitigation missed and overall
effects on invertebrates will be underestimated.
Request that the Proponent:
(a) Discuss and assess invertebrate groups other than butterflies and dragonflies. The major groups
of invertebrates could include Orthoptera, Ground beetles, lady beetles, longhorn beetles, tiger
beetles, click beetles, and other beetle groups (there are at least 100 beetle families in BC), true
bugs, pollinators (e.g. bumble bees, wasps, and flies), spiders and other arachnids, gastropods,
moths and other larger invertebrates. There is not one invertebrate group that is more important
than another invertebrate group, so listing these groups does not mean they should be the only
ones included.
(b) Consider implementing the following approach to provide a robust assessment of impacts and
residual effects on invertebrates and invertebrate assemblages:
i) Complete inventories of all invertebrate groups within the flood zone and transmission corridor,
as well as outside these zones (see Details). Analyze data from the impacted and non-impacted
zones for correlations.
Final April 4, 2013 183
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 370
Continued
ii) Complete habitat mapping, using vegetation mapping or TEM polygons, for all areas sampled,
and identifying representative assemblages of invertebrates in each polygon type. Rare habitat
types, or habitats that are unique, are likely to have a distinct assemblage of invertebrate fauna
compared to more common vegetation types.
iii) Assess the overall impact to invertebrates by quantifying the area of habitats impacted by the
Project and comparing this to the total area of those habitats in study area and region. This
approach will also allow an identification of polygons of highest priority for avoidance or mitigation
measures.
iv) Monitoring regimes and mitigation will need to be proposed for these additional groups and
potentially individual species.
v) Specimens should be prepared, curated and deposited at the Royal British Columbia Museum
(Victoria). All bycatch should be kept (e.g., non target species groups) and placed in a collection
container and deposited at the Royal British Columbia Museum for future research opportunities.
Additional Details:
Inventory methodology, at the very least, should include light trapping, pitfall traps, pan traps,
cover boards, hand collection, beating and aspiration of specimens, as well as net collecting and
aquatic surveys. Inventory should span the entire growing season. This should be repeated for a
minimum of two years. At the minimum, GPS track, search effort and survey time (using GPS),
vegetation information and trap type need to be consistently documented.
Reference Martin, J.E.H. 1978. The insects and Arachnids of Canada Part 1: Collecting, preparing
and preserving insects, mites and spiders. Biosystematics Research Institute, Ottawa, Ontario.
Research Branch Canada Department of Agriculture. Publication 1643.
Final April 4, 2013 184
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 371
Selection of VCs - Invertebrates
Issue: Baseline studies have not been undertaken for invasive invertebrates.
Concern: Invasive species can be more effectively managed if it is known what invasive species are
present at baseline. What are the expected introduced invertebrates present (e.g., earthworms,
gastropods, ants, wasps, etc)?
Request that the Proponent: Establish a baseline of invasive invertebrates to inform future invasive
species management.
Final April 4, 2013 185
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 372
Description of VCs - Invertebrates
Issue: The assessment would benefit from additional baseline information about butterflies,
dragonflies and other invertebrate groups in the Project area. For example, the Peace region has
numerous invertebrate species that are westernmost range extentions, as well undescribed (to
science) species. There are museum records, inventory studies, and past projects from which
information can be drawn although these are not numerous. There are a few records in BC
museums. There have been a few biodiversity surveys in the Alberta Peace region, but without
inventory within the BC area, correlations cannot be drawn.
Concern: The baseline information on invertebrates is incompleted without a comprehensive
review of available information and data on invertebrate groups in the region.
Request that the Proponent:
(a) Host plant surveys would be beneficial for butterflies.
(b) Clarify whether there are species of butterflies or dragonflies in the region that have yet to be
described.
(c) Include additional descriptions on invertebrate groups, including dragonflies and butterflies,
including information from the literature, from survey data lodged with the Royal BC museum and
through discussions with taxonomists and other invertebrate experts with knowledge of the region.
Continued in next cell
Final April 4, 2013 186
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
372
Continued:
Additional Details:
Consider contacting Canadian taxonomists to ask their professional opinion on whether there are
unique species in the Peace Region, what possible species could be present and whether there may
be undescribed species/subspecies within the region. Agriculture Canada has a number of Canadian
taxonomists available to help with this information. Initially contacting the Royal BC Museum for a
list of taxonomists and although this reference is old, there are some contacts for experts
http://www.for.gov.bc.ca/hfd/pubs/docs/wp/wp09.pdf.
Reference: Crispin Guppy pers. comm., regarding new subspecies of butterflies.
14 373
Description of VCs - Invertebrates
Issue: There are descriptions for only 11 of the 14 red or blue listed butterfly species. Uncertain if
3 species (Alberta arctic, coral and striped hairstreak) were not included intentionally or if this was
just missed. Maps are included for these additional 3 species. (App R S2.1 pg 15 - 17)
Request that the Proponent: Clarify
whether Alberta Arctic, Coral and Striped Hairstreak were intentionally not included or were they
just missed? If they were intentionally not included, please provide a rationale for their omission.
If they were just missed, please add a description about these species to the text.
Final April 4, 2013 187
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 374
Description of VCs - Invertebrates
Issue: The EIS is missing details about survey methods for butterflies and dragonflies.
Concern: It is not possible to assess the character and quality of data used without information on
survey methods.
Request that the Proponent:
(a) Provide documentation of GPS track, search effort and survey time (using GPS), vegetation
information and trap type.
(b) Provide more details regarding sampling design and effort. Clarify that RISC standards were
followed and whether there were deviations from those standards.
(c) Provide criteria used to select the 50 sites sampled. Was there any stratification done to ensure
all wetland/aquatic types were included in sampling (e.g,. sphagnum bogs and small creeks)?
(d) Clarify whether the sampling effort was sufficient to inform relative habitat suitability for each
TEM unit.
Final April 4, 2013 188
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 375
Description of VCs - Invertebrates
Issue: More information is needed about how habitat suitability maps for butterflies and
dragonflies were developed and the inferences that were made based upon those maps.
Concern: It is not possible to fully understand or evaluate habitat suitability maps and their
application if the inputs and assumptions are not provided.
Request that the Proponent:
(a) Clarify whether survey time was included in the calculation of density. Survey time can have a
big influence on density measures.
(b) Provide definitions for high, moderate and low-rated habitat for butterflies and dragonflies.
(c) Describe the assumptions and criteria behind habitat ratings. For example, some TEM polygons
that were sampled and had no species detected and were ranked low while others with no species
detected were ranked N. What is the rationale for this ranking? Are some habitat types ranked as
being more important to specific species than others?
(d) Describe how the habitat suitability maps were developed. For example, is the mapping based
on (i) recorded use vs. lack of use; (ii) mapping of known habitat associations followed by ground-
truthing and refining; (iii) mapping based on existing ecosystem type maps without not ground-
truthing; or (iv) some other method?
(e) Clarify if the suitable habitat as shown on the suitability maps for butterflies is a combination of
high and moderate habitat ratings.
Final April 4, 2013 189
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 376
Description of VCs - Invertebrates
Issue: It appears that relative habitat suitability for each taxon was determined using the recorded
use or lack of use.
Concern: Lack of use over the 2 years of surveys does not mean the species is not found there.
Request that the Proponent: Factor in
expert opinion about potential habitats to adjust the ranking of habitat suitability so that habitats
are not overlooked due to lack of use over two years of survey (e.g., C. Guppy)
14 377
Description of VCs - Invertebrates
Issue: Habitat suitability maps have not been provided for the individual species of dragonflies,
including the other listed dragonflies that are found in the northeast of the province. Different
species have different habitat requirements. There has been little surveying done and other species
could found in the area as well, if looked for.
Concern: Not including all species will result in gaps in habitat suitability mapping and will
potentially mask impacts on individual species and underestimate overall effects. (This applies to
dragonflies and butterflies).
Request that the Proponent: Complete
mapping for individual dragonflies species, using what information and data is available.
Final April 4, 2013 190
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 378
Description of VCs - Invertebrates
Issue: The EIS states that habitat suitability indices could not be completed for species captured in
low numbers despite information available on habitat/vegetation associations.
Concern: Habitat suitability indices were not completed for some species but the literature outlines
clear habitat/vegetation associations. For example, the Bronze Copper has known habitat
associations and field studies to support a preference for wetter herbaceous sites. Also, there
might be other methods of rating habitats that were not considered.
Request that the Proponent:
(a) Explain why habitat suitability indices could not be completed for species captured in low
numbers (e.g. Bronze Copper) when there are clear habitat/vegetation associations in the
literature.
(b) If habitat suitability ratings were not possible why were other methods not pursued (e.g.
habitat suitability index or 2 class HSR)?
(c) If habitat suitability mapping of the Bronze Copper butterfly is not to be completed, please
consider targeting this species for further inventory. Given that several other Red- or Blue-listed
butterflies appear to be geographically and morphologically distinct (new unnamed sub-species),
this may be useful and important to determine whether the Bronze Copper is the same as or
morphologically distinct from the rest of the Bronze Copper species in BC.
Final April 4, 2013 191
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 379
Assessment of impacts - Invertebrates
Issue: Butterflies and dragonflies are inappropriately grouped and assessed together (EIS Table
4.3.1). The assessment also groups all species within each of these two taxa.
Concern: Butterflies and dragonflies are completely different organisms with completely different
life histories and vulnerabilities to development. Within each taxa, individual species use different
habitats. For example, it is incorrect to use the the term “wetland” to describe suitable breeding
habitat for all of the dragonfly and damselflies (pg 14-13, line 27 - 28). The “wetlands” identified
are habitat to a number of species, but not all. Some habitat types are missing (e.g., creek,
riverine and bog (sphagnum)).
14 379
Continued
Request that the Proponent: Assess
and report on impacts to butterflies and dragonflies separately:
(a) The EIS quantifies the amount of aquatic habitat to be lost during flooding. Please list separately
the amount of habitat lost for each species of butterfly and dragonfly. Include a consideration of
host plants that will be lost due to inundation.
(b) Clarify whether the assessment assumes that the three target species of dragonfly all utilize
every aquatic habitat equally. What are the implications of being wrong in this assumption?
(c) Table 14-6 (pg 14-27 and 14-28) is missing creek, riverine and bog (sphagnum) habitats. The
addition of these habitats will change the “Available Habitat” and “% lost”. Please reassess impacts
with these habitat types included.
(d) Provide a rationale for using wetlands as a surrogate for potential suitable dragonfly and
damselfly breeding habitat. The use of TEM to complete Habitat Suitability Ratings for the three
dragonfly/damselfly species listed in the Peace Forest District would enable assessment of more
accurate effects and mitigation. There are an additional three species listed in the northeast of BC
but few surveys have been completed and it is not known if those species occur in the study area.
Final April 4, 2013 192
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 380
Assessment of impacts - Invertebrates
Issue: The EIS contains little information on the assessment of impacts of disturbance and
displacement on butterflies, dragonflies or to other invertebrate groups.
Concern: Without more information on the assessment of impacts due to disturbance and
displacement it is not possible to evaluate whether the impacts to VCs have been adequately
captured.
Request that the Proponent:
(a) Provide more detail about methods and findings regarding the assessment of disturbance and
displacement on butterflies (and host plants) and dragonflies.
(b) Provide information from the literature on potential impacts to other invertebrate groups due
to disturbance and displacement.
Final April 4, 2013 193
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 381
Assessment of impacts - Invertebrates
Issue: Only a small number of activities that could cause disturbance or displacement to butterflies
and dragonflies are assessed. For example, in Section 4.3 disturbance and displacement is only
discussed with reference to temporary flooding due to natural causes or power generation. Also,
the effects of construction and operations are considered together when they are likely to have
different effects.
Concern: Impacts on butterflies and dragonflies may be underestimated if the range of sources of
disturbance and displacement are not considered.
Request that the Proponent:
(a) Provide a rationale for only considering temporary flooding as a cause of disturbance or
displacement. Discuss all potential sources of disturbance or displacement as a result of Project-
related activities and how each of these activities could be a source of disturbance or displacement
to butterflies and dragonflies. Report separately for each taxon and, to the extent possible, by
species.
(b) Clarify why natural causes of temporary flooding are included (there is way to control natural
flooding).
(c) Assess the effects of construction and operations on disturbance and displacement separately.
For example, the temporary flooding due to construction may be a displacement or disturbance
while the operational flooding will be a displacement. Other activities during construction, such as
clearing could be either, but more likely a disturbance.
(d) Discuss disturbance and displacement effects by species since there will be species that will be
irrevocably disturbed by construction versus others that are likely to return. For operations, there
is certainty where areas will be inundated, which will be positively correlated with displacement.
Final April 4, 2013 194
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 382
Mitigation Measures - Invertebrates
Issue: Little detail is provided about proposed mitigation measures and there is no mention of
monitoring plans. Restoration and mitigation measures are not adequately described. In many
cases, there won’t be the ability to mitigate for flooding impacts. An explicit link is not
demonstrated between mitigation and project effects.
Concern: There is not enough conceptual detail about mitigation measures to evaluate the
effectiveness of the proposed measures and the estimates of residual effects. As currently
described, the proposed mitigation measures for butterflies and dragonflies are not likely to be
effective, particularly for more habitat-specific species. Follow-up plans/monitoring should be
included for all species where mitigation measures have been proposed (e.g. dragonflies and
wetland creation) (see Details).
Request that the Proponent: Consider the following when developing detailed mitigation plans.
Proposed mitigation measures should be supported, where available, by references that
demonstrate the effectiveness of the measures in other locations.
(i) Mitigation for butterflies and dragonflies is very tied to habitat.
(ii) Much of the mitigation proposed in the EIS is related to wetland and aquatic habitats that are
more appropriate for dragonflies. Habitats for butterflies also need to be considered. Mitigation
measures specific to butterflies should consider all life stages, host plants and habitat.
Final April 4, 2013 195
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 382
Continued
(iii) “New wetland habitat areas will be created as partial compensation...” (Vol 2 S3.1 Pg 62). Plans
to create new wetlands should include a description of where the wetlands will be created and the
criteria to be used in decided how this should happen. It is important to create a variety of
wetlands to mimic the mosaic of different habitat types.
(iv) “Design a portion of the wetlands created to compensate for habitat loss to remain fish
free....”(Vol 5 S 39). New wetland habitat should consider a variety of wetland types rather than
simply fish free or fish present - not all dragonflies use the same type of wetland. Also, there are
many invertebrates other than dragonfly larvae that should be considered when developing
compensatory mitigation and monitoring.
(v) The proposal to “Avoid clearing during the breeding season; implement survey protocol if
avoidance is not feasible” is too general (Vol 2 S14.5.3 Pf 14-88 Table 14.22). There is not a single
breeding season for the dragonflies and butterflies (and other wildlife). This should be broken down
to at least the species groups or by the action to be avoided during the breeding season of that
group / group of groups.
(vi) Provide references to peer-reviewed literature regarding the effectiveness of proposed
mitigation measures.
Final April 4, 2013 196
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 383
Mitigation Measures – Invertebrates
Please consider the following when developing a monitoring plan:
(i) Monitoring of a broader range of invertebrate species than butterflies and dragonflies is
encouraged.
(ii) Habitat considered suitable should be monitored within and outside of impacted areas to
confirm that habitat remaining post-construction and inundation actually represents habitats that
will be lost or altered. This applies to butterflies, dragonflies and the other invertebrate groups. For
example, surveys should be completed, as a minimum, for each of the ecosystem types flooded.
(iii) Ongoing monitoring surveys of all invertebrate groups should be done for at least 20 years to
determine if mitigation measures are working and species are re-establishing. This will also help
with understanding the spread of alien invasive species.
(iv) Actions to be tested should be converted to field-testable monitoring objectives.
(v) The monitoring design should include a statistical evaluation of the adequacy of existing
baseline data. This will provide a benchmark against which to test for project effects and any
additional pre-construction or pre-operational monitoring needed to establish a firmer project
baseline.
(vi) The Follow-up Program should include a schedule indicating the frequency and duration of
effects monitoring.
(vii) The Follow-up Program should also include any contingency procedures/plans or other
adaptive management provisions as a means of addressing unforeseen effects or for correcting
exceedances as required to comply or to conform to benchmarks, regulatory standards or
guidelines.
Final April 4, 2013 197
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 384
Mitigation Measures - Invertebrates
Issue: Field survey results indicate that the Prairie Bluet (the one Blue-listed damselfly) was only
found at Watson’s Slough, which will be inundated per proposed plans.
Concern: Work is needed to characterize the habitat of Prairie Bluet prior to inundation.
Request that the Proponent:
(a) Clarify if there been any work done to determine why this species is found at this location e.g.,
is it due specific habitat associations, water chemistry, hydrology or all of the above (or other
reasons)?
(b) Watson’s Slough appears to have a distinct ecology in the area. What information is available
to inform replication of the wetland characteristics associated with this slough and Prairie Bluet
habitat?
Final April 4, 2013 198
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 385
Estimate of Residual Effects - Invertebrates
Issue: The reporting of Residual Effects does not separate butterflies and dragonflies. The residual
effects that are reported appear to be more specific to dragonflies. The EIS states that a
considerable amount of suitable habitat within the LAA will persist and support viable populations
but this statement cannot be made with certainty for all species.
Concern: Lepidoptera and Odonata differ in their vulnerability to Residual Effects. Lumping of
butterflies and dragonflies can mask effects on individual species. Species that more closely
associated with riparian, floodplain or aquatic habitats are particularly vulnerable.
Since Habitat Suitability Models were completed for 10 of 14 listed butterfly species, risks/threats
should be broken down by species or at least grouped into upland/lowland-riparian. This would
assist in informing mitigation and monitoring. Once habitat models are completed for the dragonfly
species these should be reported by species as well.
Request that the Proponent: (a)
Report estimates of residual effects separately for butterflies and dragonflies, by species where
possible.
(b) Demonstrate, through supporting references, that these estimates are based on a thorough
review of current literature and other available information, in general and specific to the region.
(c) Provide a separate assessment of mortality risks for butterflies, including a reference for the last
sentence – “mortality through vehicle collision...” (Vol 2 App R S 2.3 Pg 60). For example, butterflies
like to puddle in salty puddles, which may be on gravel roads thus increasing mortality. Has there
been research on this issue?
Final April 4, 2013 199
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 386
Estimate of Residual Effects - Invertebrates
Issues: The assessment of impacts and residual effects on butteflies and dragonflies is assumed to
reflect potential impacts to all invertebrates.
Concern: Two invertebrate species groups can not be used as indicators impacts to all invertebrate
groups. What are the impacts of hydrological changes due to a large reservoir on fly diversity and
abundance? Will flooding enable the increase of potential habitat for harmful/health risk flies? If
agriculture is to be intensified on remaining (non flooded) agricultural lands, are impacts expected
from pest invertebrate groups? Will increased evapotranspiration have an impact on pollinators?
How will aquatic invertebrates be impacted? What about sandy-gravelly banks for tiger beetles?
There is currently enough information in the literature and expertise to estimate the effects of the
proposed Project on other invertebrate groups.
Request that the Proponent: Provide a
thorough literature review to describe expected outcomes for other invertebrate groups, using
peer reviewed literature, professional opinion (taxonomic experts, ecologists and researchers with
experience in similar ecosystems) and results from studies on other dams. If no supporting
information is available, then this should be stated.
Final April 4, 2013 200
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 387
Estimate of Residual Effects - Invertebrates
Issue: The EIS says (referring to wetland habitat): “The total amount of potential breeding habitat
loss during construction and operations is 796 ha.” (pg 14-27). Pg 14-45 line 9 says ‘almost 500 of
potentially suitable aquatic habitat would be lost” when specifying inundation.
Concern: There is a discrepancy in the reporting of impacts on aquatic habitats.
Request that the Proponent:
(a) Clarify the difference in areas of potential breeding habitat to be lost;
(b) Clarify whether the increased water pressure and flooding will impact the remaining water
courses outside of the flood zone. What information is available on how this will impact aquatic
invertebrates, including dragonflies?
14 388
Estimate of Residual Effects - Invertebrates
Issue: There are references to removal “merchantable trees” in Vol 5 Section 39.
Concern: As these trees are likely large and healthy they provide habitat for numerous species,
including several species of invertebrate.
Request that the Proponent: Assess the effects of removing merchantable trees on invertebrate
species in general.
Final April 4, 2013 201
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 389
Estimate of Residual Effects - Invertebrates
Issue: Few details are provided about the determination of the significance of residual effects on
butterflies and dragonflies. The EIS makes observations about the possible outcomes qualitatively
but without substantiation in most cases.
Example 1: The habitats required for the dragonflies are given as “wetlands” without consideration
for the varying types required.
Example 2: Each butterfly species in Appendix R is listed and the amount of low, moderate and high
quality habitat that is in the flood zone but there is no discussion of what the loss of habitat types
means to these species in a regional and provincial (and national) context. Are some of these
butterflies westernmost extensions of their Canadian range?
Concern: Impacts to butterflies and dragonflies need to be considered on a species by species basis
in their regional and provincial context. An determination of significance of effects is not simply a
matter of loss of habitat area.
Request that the Proponent:
(a) Explain the criteria and rationale used in the determination of significance to butterflies and
dragonflies.
(b) Provide an assessment of the effects of loss of habitat types on individual species in their
regional, provincial and national context.
(c) The magnitude of effects will vary with each of the species and the habitats that they use. These
need to be characterized by order and by species.
14 all 3
390
It would be preferable if dragonflies and butterflies were broken out into two sub-sections. The
text flows back and forth from one to the other making it confusing to follow. It also results in
inaccuracies as the conclusions and recomendations are different for the two groups.
14 Table
14.15
6391
Dragonflies/damselflies are not listed under “project effect” as a key indicator.
Final April 4, 2013 202
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.2.1 17-18 1392
List the red and blue dragonflies and butterflies. This is done for the other taxonomic groups and is
a missing for these two groups.
14.3.11 2 - 5 5
393
These lines could refer to both dragonflies and butterflies; if the latter requires a herbaceous
wetland. The author uses generic “invertebrates” which is completely inappropriate for this report
or this statement. Other invertebrates (i.e. the majority) do not appear to be being considered in
this report. Stick to the two orders that are being assessed and make comments specific to each of
these two very different orders. If the author was choosing to make reference to all of the
invertebrates this section will require expansion.
14.3.11 2-14
and 1-2
on
page
4
394
These paragraphs belong with the discussion on dragonflies and damselflies; NOT under butterflies;
particularly the 2nd paragraph
14.3.2.1 23-24 7395
Obtuse sentence. Consider “Disturbance would be expected only for adult life stages, as immediate
effects on the majority of egg or larval stages will be mortality.”
14.4.1 Table
14.15
10
396
Project Effect is missing dragonflies in both rows. Dragonflies are wetland and wetland associated
key indicators, and are mentioned in the next column, so should be there.
14.5.1.3.1 5 16
397
This sentence is made of independent clauses: the characterization of low to moderate is not “thus”
based on the reasons provided. Why is there a percent change predicted? Please provide the
numbers and reasoning.
App R Part 2 2
398
Field survey results – indicates that Tables 1.1.2 and 1.1.3 include locations of dragonfly surveys by
year, but the tables do not include locations. Please clarify if the intent was that these tables
include location information.
App R Part 2 10399
1.2.3.4 references to maps for Assiniboine skipper are incorrect, should be 1.3.14 and 1.3.16
App R, Part
2 (2.1)
14
400
Are effects to Odonata and Lepidoptera habitats to be extrapolated to all invertebrates? First
sentence on this page should be limited to the two Orders included in the review.
Final April 4, 2013 203
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App R s3.2
401
Suggested wording: All butterflies (egg, larval and pupal stages) and dragonflies (larval life stages)
will experience mortality within the flood zone. Adults will have the ability to disperse, although the
habitat these species need to survive will be destroyed so the chance of population continuity is
diminished and adults will likely not be as successful at progeny.
14 App R 402
Baseline Data – reptiles
For reptiles, baseline studies were done on the two species of garter snake found in the area, the
only reptiles in the area and so that matches their commitment.
14 App R 403
Selection of VCs – amphibians
EIS Guideline: 14.2.2 Amphibians and Reptiles states:
"The amphibian and reptile baseline information will provide an understanding of the existing
habitat and species within the LAA as proposed by the Proponent. All species observations will be
summarized, but the focus will be placed upon the western toad (Bufo boreas) as it is a species of
concern under SARA." This
is appropriate. However, see comments below regarding species considered during the calculation
of residual effects and mitigation measures.
Amphibians & Reptiles
Final April 4, 2013 204
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 App R 404
Description of VCs - amphibians
Issue: The EIS does an adequate job of describing breeding habitat for amphibians but provides no
assessment of terrestrial connectivity or foraging/overwintering habitat. Columbia Frogs, Wood
Frogs and especially Western Toad spend extensive time in different seasonal habitats and an
assessment of seasonal habitat connectivity is necessary.
Concern: Sustainable amphibians populations require both terrestrial and aquatic habitat with safe
connectivity between the two seasonal habitat. A description of only breeding habitat may skew
the estimation of impacts, design of mitigation and the assessment of residual impacts (see
comment below).
Request that the Proponent: Describe (i) foraging/ over-wintering habitat for amphibians; and (ii)
connectivity between breeding and non-breeding habitats
Final April 4, 2013 205
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 App R 405
Assessment of Impacts - amphibians
Issue: There is a change mid-way in the EIS in how the VCs are evaluated – from being “all
(amphibian) species with a focus on Western Toads” to Western Toads being the only species
evaluated in the impact, mitigation and calculation of residual effects. Five amphibian species are
found in the project area (Boreal Chorus Frogs, Columbia Spotted Frogs, Western Toads, Wood
Frogs and Long-toed Salamanders). Two of these species Columbia Spotted Frog and Wood Frog
are ranked Priority 2 on the BC Conservation Framework.
Concern: Potential habitats for the full range of species will not be protected with mitigation
measures (such as sediment fencing etc.) if locations for mitigation are based only on surveys for
Western Toads. It is important that protection and mitigation measures be invoked for all
amphibian species and not just Western Toads.
Request that the Proponent:
(a) Use data collected on all amphibian species in an overall assessment of impacts; or be clear in
the document that only Western Toads were used as an indicator for assessing impacts on all
amphibian species and that all amphibian species in the project area are expected to suffer
similar impacts from the project, will benefit from similar mitigation measures, and that the
project will have similar residual effect on all species.
(b) Commit to undertaking measures to mitigate impacts to all amphibian species where found
(not just Western Toad).
Final April 4, 2013 206
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 App R 406
Assessment of impacts - Reptiles
Issue: For reptiles, the VCs included both reptile species in this area with a focus on hibernation
habitat. This is appropriate however one of the species, the Western Garter Snake, can be very
aquatic and forages extensively in shallow wetlands and riparian areas. The flooding of the reservoir
will result in significant loss of foraging area for this snake, which was not accounted for in the
estimation of impacts.
Concern: The full suite of impacts to snakes has not been assessed, potentially resulting in an
underestimation of overall impact.
Request that the Proponent: Assess the impact of loss of foraging area for the Western Garter
Snake and include in the estimation of impacts to this species.
14 App R 407
Assessment of impacts -amphibians and reptiles
Issue: The percentage impact is calculated based on the loss of only one seasonal habitat –
breeding habitat for amphibians and hibernation habitat for snakes - rather than considering all
seasonal habitats and connectivity between them. For example the EIS estimates a loss of 38% of
Western Toad habitat but did not consider the loss of upland riparian habitats and hibernation
habitats that are also important to toad survival.
Concern: Population level impacts are potentially underestimated because the animals need all
seasonal habitats and connectivity between these seasonal habitats.
Final April 4, 2013 207
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 App R 408
Assessment of impacts -amphibians and reptiles
From the EIS: 14.3.1.2 Amphibians and Reptiles : "For garter snakes, 15% of suitable hibernation
habitat will be lost due to the Project, the majority of which is a result of the filling of the reservoir
(Table 14.8)."
Issue: Impact is evaluated as percentage loss of habitat, but the impact on the population and how
it correlates with habitat loss is not addressed. This correlation will depend on the timing of the
project activities as this could affect the success of the mitigation measures (e.g., timing the
flooding of the reservoir at a time when snakes are not hibernating will reduce population level
impacts) (see comment below). Also, the Peace River valley is at the northern extent of the range of
garter snakes, and Project could have regional scale effects. Also, the filling of the reservoir may
change the microclimate in the hibernation habitat close to the margins of the "Site C" lake and
may cause the snakes to abandon these sites.
Concern: Basing the assessment of impact on habitat loss without considering how this translates
to a population level impact may underestimate overall effects on amphibians and reptiles.
Request that the Proponent: Estimate the effect of habitat loss and other changes on amphibians
and reptiles at a population level. This should include consideration of the Project being at the
northern extent of the range of garter snakes.
Final April 4, 2013 208
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 App R 409
Assessment of impacts -amphibians and reptiles
Issue: The flooding of the reservoir is proposed to happen in the winter. The assessment of
impacts does not consider the impact of timing of the flood on hibernating amphibians and reptiles.
For example, if snakes in the hibernacula are flooded when they are in deep hibernation, the impact
on the population will be large and may affect population recovery in the long-term. If the flooding
is during the active season and the snakes are able to find alternate hibernation habitat, then the
impact on the population may be less severe. A similar argument would apply to amphibians.
Concern: The assessment of impacts is incomplete without discussion of the effect of timing of
flooding on amphibians and reptiles.
Request that the Proponent: Include a discussion of the implications of timing of flooding of the
reservoir on impacts to amphibians and reptiles at a population level.
14 App R 410
Assessment of impacts - amphibians and reptiles
Issue: The Proponent claims that the effects of operations on habitat alteration and fragmentation
are considered reversible upon cessation of erosion (Vol 2 S 14.5.1.1 Pg 14-70). However,
o Erosion may be a continuous process over the entire life of the Project
o Even if erosion does cease at the impact line, habitat loss is permanent; it is gone in the same way
that habitat in the reservoir is gone, and therefore effects are irreversible.
o Will wildlife use the post-erosion habitat; i.e., will it return to baseline conditions, and did wildlife
use the habitat at baseline?
Request that the Proponent: consider the potential implications of habitat loss due to short-term
or ongoing erosion in their design of mitigation and monitoring plans
Final April 4, 2013 209
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 App R 411
Mitigation measures - amphibians and reptiles
Issue: The EIS is lacking in essential details to be able to decide if the proposed mitigation is either
reasonable or effective. For example, proposed mitigation measures for amphibians include the
erection of exclusion fencing, timing of activities, construction of wetlands, and tunnels for toad
passage under roads. All these sound fine but how effective they are going to be cannot be
assessed without the details. For example, the creation of wetlands has the potential to mitigate
effects on amphibians, but further detail on type of wetland (i.e., wetlands suitable for waterfowl
may not be not suitable for amphibians), location, number, and size is required before effectiveness
can be gauged.
Concerns:
It is difficult to evaluate the effectiveness of proposed mitigation measures without some details as
to what is planned.
Request that the Proponent:
(a) Provide references where available regarding the effectiveness of proposed mitigation
measures.
(b) Consider the recommendations for effective measures (see Details) when developing a detailed
mitigation plan.
Final April 4, 2013 210
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 App R 412
Mitigation measures - amphibians and reptiles
Consider the following during detailed mitigation planning:
(a) The timing of the mitigation measure is important. For example:
(i) if exclusion fencing is set up before the frogs migrate into a pond to breed, then mitigation is far
more effective than if exclusion fencing is erected after the amphibians have bred in a pond and a
salvage operation becomes necessary.
(ii) If compensation wetlands are built before the impacts start and amphibians start using these
wetlands and salvaged animals are translocated to these “new” wetlands before impact to “old”
wetlands, then the mitigation is more effective than if old wetlands are destroyed and then
compensation wetlands are built elsewhere and much later (after the population has crashed).
(b) For untested mitigation measures (and even established mitigation measures), there needs to
be a monitoring program and effectiveness assessment built in. If these measures are completely or
partially ineffective then the residual effects estimation needs to be adjusted and additional or
alternative mitigation measures put in place.
(c) Some of the mitigation measures need a commitment to ongoing maintenance. For example,
drift fences leading to “toad tunnels” or snake dens. There is no indication of who will be
responsible for this ongoing maintenance and implementation of mitigation measures
(d) The data indicate heavy western toad use of the areas around the Jackfish Road extension.
Recommend transects be conducted along the proposed access road to identify potential areas for
underpasses and fencing.
Final April 4, 2013 211
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 App R 413
Mitigation measures - amphibs and reptiles Issue: Some of
the proposed mitigation measures are experimental i.e., they have not been proven to mitigate
impacts elsewhere (at least no citations are provided). Examples:
(1) artificial snake dens are reported to have been installed in other BC Hydro facilities but no data
is provided as to their effectiveness. If that data is not available, there is a high degree of
uncertainty associated with their use and research and monitoring will be required to determine
their effectiveness.
(2) the use of underpasses to maintain dispersal movements across roads has been shown to have
mixed success and depends heavily on correct placement, structure and size.
Concern: If mitigation measures are not tested for effectiveness prior to construction and habitat
loss there will not be an opportunity to adapt mitigation to increase likelihood of survival.
Request that the Proponent:
(a) Initiate mitigation planning and implementation prior to construction to remove animals from
the area of impact and into alternative habitats and to test the effectiveness of mitigation
measures.
(b) Monitor and provide data on effectiveness of mitigation measures:
(i) for use by target species; and
(ii) in terms of potential population level conservation e.g., use of a snake den by one or two snakes
is not a sufficient demonstration of effectiveness.
Final April 4, 2013 212
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 App R 414
Estimates of residual effects - Amphibians
Issue: Almost 40% of the western toad breeding habitat in the LAA is expected to be lost with the
project. This is a large proportion of habitat to be lost for a listed-species. Additionally, Western
Toads have high site fidelity to their breeding habitat (Matsuda et al, 2006). This impact is
accurately described as a high magnitude of effect on habitat alteration. Given the federal and
provincial status of Western Toad, the large amount of habitat affected, and uncertainty around
success and extent of mitigation, it is unclear why effects on habitat alteration and fragmentation
were not found to be significant.
Concern: The conclusions of the assessment of residual effects do not appear to be consistent with
the Proponent's criteria for determination of significant adverse effects to Wildlife Resources.
Request that the Proponent: Provide a rationale for concluding that effects of habitat alteration
and fragmentation were determined to be not significant for Western Toad, which is a listed
species.
References: Matsuda, B.M., D.M. Green and P.T. Gregory. 2006. Amphibians and Reptiles of British
Columbia. Royal BC Museum Handbook.
14 App R 415
Estimates of residual effects - amphibians and reptiles
The EIS provides qualitative rankings of residual effects but no rationale that links back to the data
and literature sources. Construction, in particular, is expected to have permanent negative impacts
on amphibians and reptiles, although there may be continuing impact during the operations phase
due to road mortality depending on the effectiveness of proposed mitigation measures.
Request that the Proponent: Provide a rationale for concluding that residual effects on amphibians
and reptiles are not significant.
Final April 4, 2013 213
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.3.1 14-25 40 416
Some species tables in this section present habitat lost as a percentage of that available in the LAA,
while others do not. Please adjust so that percentage is included in all the tables, as this is useful for
determining magnitude.
14.3.1.6.1 14-36 417
Lines 14-16 refer to foraging opportunities being available over the water of the reservoir;
however, the reference cited in lines 23-25 appears to contradict this statement. Please clarify.
14.3.1.6.1 14-43 30-31 418
Please provide a reference for the statement “….including blasting within 300 m of bat hibernacula
during the winter, can cause premature arousal of hibernating bats”.
14.5.1.1 14-70 25 - 28 419
Effects of operations on habitat alteration and fragmentation are considered reversible upon
cessation of erosion. It is recommended that BC Hydro consider several points:
o Erosion may be a continuous process over the entire life of the Project
o Even if erosion does cease at the impact line, habitat loss is permanent; it is gone in the same way
that habitat in the reservoir is gone, and therefore effects are irreversible.
o Will wildlife use the post-erosion habitat; i.e., will it return to baseline conditions, and did wildlife
use the habitat at baseline?
Migratory Birds
Final April 4, 2013 214
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 420
Selection of VCs - Migratory Birds
Issue: The scope of the assessment of Migratory Birds has been limited to a handful of species at
risk, despite the guidance given in the EIS Guidelines (below). These analysis needs to be expanded
to include a large suite of species, rather than just those at risk.
The EIS Guidelines (12.2.3.3) state
“The migratory bird baseline information will provide an understanding of the existing habitat,
species, relative abundance*, distribution and temporal use within the LAA as proposed by the
Proponent for the following categories of migratory birds:
• Songbirds;
• Waterfowl and shorebirds;
• Marsh birds (Yellow Rail, American Bittern, Le Conte’s Sparrow, Nelson’s Sharp-tailed Sparrow);
• Woodpeckers;
• Common Nighthawk; and
• Others as appropriate. “
Concern: While the Province is especially interested in the species-at-risk within this group, the
number of VCs needs to be expanded to include a fuller suite of migratory birds. There are a
number of reasons for this:
(i) There is a high potential for large numbers of breeding bird to be impacted as a result of the
Project;
(ii) It’s possible that the loss of riparian lowland forests and associated wetlands may drive other
currently non-listed species dependent on these habitats in this area to becoming listed.
(iii) There is enough data from baseline surveys to support assessments of impacts on individual
species.
Final April 4, 2013 215
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 420
Continued
Request that the Proponent:
(a) Provide a rationale for how indicator species were selected. Were all habitat types in the LAA
represented by the listed birds selected?
(b) Include all species of Migratory Bird that are protected under the Migratory Birds Convention
Act.
(c) Add Sandhill Crane to the Marsh birds.
14 421
Selection of VCs - Migratory Birds
Issue: Table 1.1.1 Barn Swallow is Blue-listed (since 2009) and COSEWIC listed (since 2011) but is
not included in the list of species to be considered in the EIS. The EIS currently uses Bank Swallow as
an indicator species for all Swallows.
Concern: Barn Swallow needs to be added to the list of species and dealt with throughout the
document. It is incorrect to use Bank Swallow as an indicator for all Swallows (pg 14-71 line 7).
This species might be one of the Swallows most impacted by the Project, but their nest habits
(holes in banks) are quite different from Barn and Cliff Swallows (mud cups/gourds on structures)
and Tree/Violet-green Swallows (cavities in trees). The residual effects for each group will
therefore differ. The impacts may be minimal over the long term for bank nesters and the dam may
provide increased nesting opportunities for structure nesters, but for tree cavity nesters, much of
their breeding habitat will be lost forever.
Request that the Proponent:
(a) Add Barn Swallow to the list of species to be assessed.
(b) Expand the assessment of impacts to Swallows to report separately on bank nesters, tree cavity
nesters and structure nesters.
Final April 4, 2013 216
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 422
Description of VCs - Migratory Birds
Issue: Information presented on relative abundance of Migratory Birds is incomplete.
Concern: More robust estimates of densities and overall numbers by species should be possible
from the data collected by the Proponent. These estimates should be calculated and included in
the impact statement.
Request that the Proponent: Provide estimates of densities and overall numbers by species of
Migratory Bird and include these numbers in the EIS.
14 423
Description of VCs - Migratory Birds
Issue: The field work for birds in most of the study area appears to have been extensive. However,
the downstream portion of the study area is very poorly surveyed.
Concern: Survey effort for Migratory Birds in the downstream portion of the project appear to be
limited to a single transect and are inadequate to document the impacts and change in avifauna
expected when the hydrological and disturbance regime are changed by the dam.
Request that the Proponent: Consider further baseline surveys of Migratory Birds downstream of
the proposed dam site.
Final April 4, 2013 217
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 424
Description of VCs - Migratory Birds
Issue: Habitat suitability maps have been developed for just a few species of Migratory Bird. Two
of the habitat maps that do exist are poor predictors of actual bird locations.
Concerns:
(i) There is no habitat suitability mapping for the majority of species that will be impacted by the
project.
(ii) Two of the existing habitat maps ( for Cape May and Connecticut Warblers) do not accurately
predict the observed occurrences for the species in the eastern half of the study area. Either the
habitat models are incorrect OR the baseline mapping for parts of the study area is inaccurate or
not sufficiently detailed (concerns about Broad Habitat Mapping are detailed in comments for
Vegetation and Ecological Communities). Errors in habitat maps will misinform the assessment of
impacts on these species and their habitats.
Request that the Proponent:
(a) Determine the reason for the poor predictability of habitat maps and either (i) revisit habitat
model assumptions and inputs and correct habitat mapping for Cape May and Connecticut
Warblers so that it more accurately predicts observed occurrences for these species OR (ii) improve
the accuracy of baseline mapping and update habitat maps accordingly.
(b) Consider preparing habitat suitability maps for additional Migratory Bird species to allow an
expanded assessment of impact to this species group.
Final April 4, 2013 218
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 425
Description of VCs - Migratory Birds
Issue: The “Songbirds” are not adequately addressed in Appendix R Part 4 Section 1.1. The data
from the Breeding Bird Survey should have been adequate to allow estimates of numbers of
breeding individuals. The EIS states that 17,000-30,000 Songbirds are estimated to use the study
area, but there is no estimate of the proportion of these that will be lost to inundation or losses due
to the Project as a whole.
Concern: The assessment of effects and their significance may be underestimated without an
analysis of the impacts to numbers of breeding individuals is needed
Request that the Proponent:
(a) Provide an estimate of numbers of breeding individuals of Songbird.
(b) Estimate the percentage of Songbirds that will be lost to inundation and the overall loss of
Songbirds due to the Project as a whole.
Final April 4, 2013 219
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 426
Description of VCs - Migratory Birds
Issue: Request more information on the survey data for Migratory Birds.
Request that the Proponent:
(a) Consider submitting data from all Project-related bird surveys (not just Migratory Birds) to the
provincial Species Inventory Database (SPI).
(b) Provide the following clarifications re bird surveys:
(i) Were breeding bird point-counts completed in each of the years noted on line 17? If they
weren't, please provide an explanation for why this was not done.
(ii) Were migration encounter transects limited to fall of 2012? Were any undertaken in spring (pg
14-14)?
(iii) Provide a rationale for the use of motor vehicles to undertake encounter transects for Short-
eared Owls (pg 23, App R Part 6)?
(iv) Provide a rationale for why no encounter transects were undertaken within or adjacent to the
reservoir on the south side of the river (App R Map 1.6.16). Is this based on the habitat suitability
spatially depicted on Map 1.6.25?
14 427
Assessment of Impacts - Migratory Birds
Issue: There is no estimate of the expected number of Migratory Birds, by species, whose habitats
will be destroyed or altered as a result of development.
Concern: Table 2.1.1 summarizes projections of the areas of impacted habitats, however an
analysis of bird densities has not been presented that would allow these areas to be expressed as
the number of birds impacted as a result of lost of altered habitat. There is ample survey data to
support this analysis for most species (with the exception of impacted areas downstream of the
dam - see comment above).
Request that the Proponent: Provide an estimate of the numbers of individuals of each Migratory
Bird species that are expected to be impacted by habitat loss and alteration.
Final April 4, 2013 220
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 428
Assessment of Impacts - Migratory Birds
Issue: The potential loss of breeding habitat for beach-nesting birds is not included in this
assessment.
Concern: Nesting habitats along the sandy shore of the Peace River are likely to be lost to the
impoundment with associated impacts to breeding habitat for Nighthawks and other beach-nesting
shorebirds like Killdeer and Spotted Sandpipers.
Request that the Proponent:
(a) Describe the potential for (i) beach habitats to re-form post-development and (ii) continued
losses downstream of the dam due to changes in hydrology.
(b) Assess impacts to beach nesting shorebirds such as Nighthawk, Killdeer and Spotted Sandpipers.
Final April 4, 2013 221
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 429
Mitigation Measures - Migratory Birds
Issue: The mitigation measures for Migratory Birds described in Vol 5 Sections P 39.7 and 39.8 are
high level and not species specific. Detailed mitigation measures are not provided for individual
species of Migratory Bird, including the Red-listed species.
Concern: The lack of detail and species specificity makes it difficult to evaluate the effectiveness of
proposed mitigation measures or their ability to mitigate residual effects. A full and detailed
wildlife mitigation plan needs to be developed with areas and timelines defined and funding
identified.
Request that the Proponent:
(a) Describe conceptual mitigation measures for individual species of Migratory Birds that are linked
to projected impacts to birds or their habitats (see examples in Details). In particular, provide
mitigation measures for Red-listed species. If no mitigation measures exist, note this and factor it
into the estimate of residual effects.
(b) Explain how the following mitigation measure is expected to reduce impacts to nesting
migratory birds: "If clearing occurs during the critical bird breeding season (see Table 14.15), a nest
search protocol would be developed and implemented prior to clearing, to avoid disturbance and
possible mortality to nesting birds (S 14.5.1.3.3 14-84 line 41). The only way to avoid
disturbance/destruction of these nests would be to stop clearing in the area when nests are
located. Note that migratory birds are protected under the Migratory Birds Convention Act (MBCA)
and the BC Wildlife Act.
Final April 4, 2013 222
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 430
Mitigation Measures - Migratory Birds
Please consider the following when developing detailed mitigation and monitoring plans for rare
Migratory Birds:
(i) For Nelsons Sparrow: a key avoidance/ mitigation measure is to not disturb the wetland where
this species occurs along the proposed transmission line corridor. Recommend that the Proponent
try secure the other two known sites for the species as partial mitigation for the sites to be
inundated and disturbed.
(ii) Consider the habitat needs of Nelson's Sparrow during the development of compensatory
wetlands. Consider incorporating habitat features into created wetlands to attract this species?
(iii) Partial offsetting of impacts on Common Nighthawk could be achieved if appropriate features
are built into the design of some of the buildings and hard surfaces created in this project (.e.g flat
gravel roofs, gravelled surfaces). Other measures could be taken for species such as Barn and Cliff
Swallows.
(iv) The dam and other associated structures could create nesting opportunities for swallows if
designed for it and managed to encourage them. If this is done, an MOU should be established that
mandates avoidance of structure maintenance activities (cleaning, painting) during breeding
seasons (so that birds aren't disturbed and maintenance activities don't destroy mud nests).
(v) Manage water levels in managed wetlands in consideration of use by shorebirds (pg 39-27 line
52)
(vi) For some species, it may be possible to take nestlings into rehab centres for rising and later
release
Final April 4, 2013 223
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 431
Mitigation Measures - Migratory Birds
Issue: Few details are provided regarding proposed mitigation for loss of wetlands.
Concern: Wetlands provide a number of ecosystem functions, including providing habitat for a
number of rare plant and bird species. Avoidance is the preferred approach, but if that is not
possible, mitigation for should be carefully designed to capture a range of wetland types and
functions in consideration of the habitats to be compensated.
Request that the Proponent: The Comments for Vegetation and Ecological Communities (Ch 13)
discuss the need for a more comprehensive description of the variety of wetlands in the study area
and estimate of projected losses by wetland type.
(a) Clarify if it is only the wetlands presented in Appendix H that are being considered as
compensation for wetland loss (12.82 ha at Wilder Creek; Pg 14.52 Table 14.15) or is there an
intent to compensate for an equivalent area of lost wetland habitat?
(b) Is wetland management/creation contemplated for the downstream portion of the river?
Final April 4, 2013 224
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 432
Mitigation Measures - Migratory Birds
Please consider the following when developing detailed mitigation and monitoring plans for
wetlands:
(i) A variety of wetland types need to be created/ recreated/ secured in order to compensate for
the variety of wetlands that different species of birds use in the study area. What are the wetlands
and sensitive habitats that need to be avoided if possible (sizes? maps? water management,
planning, plantings etc?). (ii)
Wetlands will need to be large and/or varied enough to provide suitable nesting/foraging/migratory
habitat for the myriad of wetland species that will be displaced. They will also need to be spaced
appropriately.
(iii) Consider the benefits of one very large complex versus a number of various sized wetland
habitats suitable for water nesters, open-ground/shore nesters, wetland shrub and riparian nesters
(as well as other wildlife)
(iv) An inventory and monitoring program is needed to document the success of mitigation
measures with a commitment to further action if they are not successful.
(v) Consider opportunities for public viewing.
(vi) Involve an experienced agency like Ducks Unlimited Canada in wetland mitigation planning.
14 433
Estimate of Residual Effects - Migratory Birds
Issue: Question about the estimate of Confidence related to habitat alteration and fragmentation
(Pg 14-102 lines 1 - 3).
Concern: The assessment downplays the certainty of impacts on species in high value habitats that
will be irreversibly lost.
Request that the Proponent: Revisit the evaluation of effects of habitat alteration and
fragmentation (pg 14-102 lines 1- 3). The response will definitely vary by species, but one can
predict with confidence that species dependent on the lowland riparian forest habitats that will be
entirely inundated will lose their breeding populations from those habitats.
Final April 4, 2013 225
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 434
Estimate of Residual Effects - Migratory Birds
Issue: The proposed area to be inundated is the most productive Songbird nesting habitat in the
Peace River, but this loss is not adequately considered in the mitigation or estimates of Residual
Effects.
Concern: The EIS does not report a residual effect on Migratory Birds associated with the very
productive habitats along the valley bottom of the Peace River valley even though the habitat for
tens of thousands of birds will be permanently lost or altered.
Request that the Proponent:
(a) Clarify if the assessment considered the impacts and Residual Effects of productive Migratory
Bird habitats along the valley bottom of the Peace River valley.
(b) If not, please undertake an assessment, by species, of impacts to Migratory Birds due to loss or
alteration of productive valley bottom habitats, reported in terms of numbers of individuals
impacted by species. Include an assessment of impacts due to loss of continuity of riparian corridors
used by songbirds during migration.
Final April 4, 2013 226
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 435
Estimate of Residual Effects - Migratory Birds
Issue: There is no estimate of the number of individuals of each Migratory Bird species-at-risk that
will be lost due to the Project (S14.5.1.3.3). Effects are not reported in their regional and provincial
context.
Concern: Basing estimates of Residual Effect only on the loss of habitat in the local area has the
potential to seriously underestimate population impacts on individual bird species at a regional and
provincial scale. The Proponent has collected adequate data for the LAA to be able to estimate loss
in terms of number of individuals of the majority of species that in the area. For example, there are
only four known sites for Nelson's Sparrow in BC and 100% of these sites are within the Project
footprint. The Project could result in a loss of nearly 25-50% of the breeding sites for this species in
BC (one site is in the inundation zone and another along the transmission line right of way) yet the
EIS characterizes the Residual Effects for Nelsons Sparrow as a 20.4% loss in the LAA. Likewise s
14.5.1.3.3 of Volume 2 estimates the impact on migratory birds at less than "10% of the population
of ground- and shrub-nesting species", which is a broad generalization and does not specify
populations that are being referred to (local? Provincial? global?).
Request that the Proponent:
(a) For each species at risk, or nearly at risk (S1-S4), provide an estimate of
(i) the % of the provincial population that will be lost,
(ii) the % habitat lost locally, regionally and provincially, for the species, and
(iii) the potential implications for the CDC assessment of the species
(b) Report whether the Project has the potential to result in a up listing to a higher risk category for
any of the species assessed. Report on all assessments of Residual Effect in terms of impacts at the
local, regional and provincial scale.
Final April 4, 2013 227
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 436
Estimate of Residual Effects - Migratory Birds
Issue: The estimate of Residual Effects inappropriately groups species of Migratory Birds together.
Concern: Estimating Residual Effects based on a lumping together of species that use different
habitats could result in a masking of impacts and an overall underestimation of effects. For
example, The EIS states that “The percent loss of marsh bird habitat would be similar for Le Conte’s
Sparrow, Nelson’s Sparrow and Yellow Rail. The loss of Watson’s Slough would affect all three
species, although the species were reported present in other areas south of the Peace River." (Vol 5
S 39).
Grouping these marsh species for the purposes of the assessment is not a credible practice; they
use very different types of wetlands and are not present simultaneously in all mapped wetlands.
This assessment is made more difficult because wetland habitats are also inappropriately lumped
together.
Request that the Proponent:
(a) Report on all assessments of Residual Effect on a species-by-species basis.
(b) If groupings of species are made, these should be by habitat association and a rationale
provided for reporting by group rather than individual species.
(c) Apply the provincial wetland classification system to map out wetland habitat types and report
on impacts to wetland bird species by wetland type.
Final April 4, 2013 228
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 437
Estimate of Residual Effects - Migratory Birds
Issue: Only a few of the Project activities are reported in the section on Residual Effects to
Migratory Birds (S 14.5.1.3.3). For example, the EIS states that construction headpond flooding is
considered to be a residual effect but there is no statement about the residual effect of impacts
due to other Project-related developments (flooding and other permanent changes to habitats).
Concern: It is not clear from the reporting of Residual Effects whether all potentially impacting
activities associated with the Project have been factored into the estimate of Residual Effects.
Request that the Proponent: Report on
the estimate of Residual Effects on Migratory Birds related to all potentially impacting Project-
related activities, in particular those that will cause permanent loss or alteration of habitats.
Final April 4, 2013 229
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 438
Estimate of Residual Effects - Migratory Birds
Issue: Other than a brief sentence, in Section 2.2 of Appendix R, the Habitat Alteration and
Fragmentation Section is missing any consideration of the downstream impacts of the Project.
Concern: The proposed dam will reduce water flows and change the disturbance and hydrologic
regime away from what is required to create low bank riparian islands that provide important
habitats for migratory birds. The natural hydrologic regime reduces the speed of succession and
creates specific habitat types, some of which are heavily used, or solely used by migratory birds.
Request that the Proponent:
(a) Clarify whether downstream impacts of the dam (e.g., reduced flows, changed disturbance and
hydrologic regime) were considered in the estimate of Residual Effects on Migratory Birds.
(b) If an assessment of downstream impacts was not done, provide a rationale for this omission
and describe the limitations to the assessment of impacts and residual effects on Migratory Birds
and other waterfowl and shorebird species using downstream habitats. See also comment above
on lack of survey effort downstream of the dam.
14 439
Estimate of Residual Effects - Migratory Birds
Request that the Proponent: Clarify in the text that clearing of vegetation during breeding season
WILL (not may) cause destruction/disturbance of nests (Pg 14-42 line 27).
Issue: The language in the EIS downplays the potential impacts of the Project.
Concern: Using the word "may" instead of "will" when impacts are inevitable downplays the
potential impacts of clearing vegetation during the breeding season.
Final April 4, 2013 230
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.3 Table
14.5440
Please clarify the definition of Migratory Birds used in the assessment. If defined according to the
Migratory Birds Convention Act, then Rusty Blackbird doesn't belong in this group. Also, technically,
swallows are songbirds.
14.1.1.2 30 - 32
441
The list of birds covered under the MBCA is incomplete. Some missing groups are irrelevant as
they don’t occur in the area (e.g., tubenoses and cuckoos); however, others do occur and breed
there regularly including: Caprimulgidae (goatsuckers, e.g., Common Nighthawk which nests on the
banks of the river and other open ground); Apodidae (swifts); Trochilidae (hummingbirds). It could
be the proponents thought these were included in the category “insectivorous songbirds” but this
only includes Passeriformes. They could correct by changing this category to “migratory
insectivorous birds” a catch all phrase used in the MBCA that does include the aforementioned
groups, or by including the aforementioned groups.
14.1.1.2 30 - 32
442
On p 14-14 line 20-21 songbirds are defined to include passerines, swifts, hummingbirds, pigeons,
doves and kingfishers – this is simply wrong.
14.1.1.2 30 - 32443
Woodpeckers are missing from s14.1.1.2, pg14-1. They are listed in Table 14-4 as Key Species
groups and are included in the assessment S 14.3.1.3).
14.1.1.2 30 - 32
444
Use of the term “seabirds” as a group could be confusing as many people interpret this to include
cormorants/pelicans which are not MBCA birds (as well as other groups like loons, grebes, seaducks
etc). The MBCA uses the word Alcids to specifically restrict the meaning to auks, auklets,
guillemots, puffins and murres as intended – none of which are likely to occur in the impoundment
area.
14.1.1.2 10 - 11
445
Not sure why the discrepancy but I checked MBCA Regulation 6 on-line at the CWS website and its
last statement is: "except under authority of a permit therefore," not "except under authority of
a special permit or as provided in the Migratory Bird Sanctuary Regulations.” - Please Clarify
Final April 4, 2013 231
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.1.4 Table
14.4446
All these Migratory Birds are also protected under the BC Wildlife Act, so don’t understand why
only MBCA is mentioned in the rationale? This is especially relevant in the case of the Rusty
Blackbird, which is included in the Songbird section, as blackbirds are not covered by the MBCA.
14.2.3 34-35
447
Refers to “all seven rare species of warblers”? Presumably this is referring to the 7 species at risk,
two of which aren’t warblers.
14.2.3 15
448
60 species of waterfowl found?...there are not 59 species of waterfowl in the whole of British
Columbia..should this be waterbirds or is the number a typo?
14.2.3 19-20
449
Cormorants and herons are neither waterfowl nor shorebirds do they mean water birds?
14.2.3 22-28450
Likely means waterbirds?, not waterfowl.
14.3.1.3 18
451
Have to be careful about the use of the word “migratory”. Not all birds covered by the MBCA
migrate (e.g., most woodpeckers don’t), and some not covered by it do (e.g., some blackbirds,
some raptors etc). So “birds covered by the MBCA” is a legal not descriptive term. I have
presumed that the section title Migratory Birds referred to MBCA birds. However on line 18 it
states that “All other migratory species...” which is more of a colloquial usage that refers simply to
any species that migrates and wouldn’t be restricted to MBCA birds. It would be more accurate to
state “All other MBCA species...” This is an important distinction as it has legal ramification on
whether the fed’s or province has senior mgmt authority over the species.
App R 452
Wandering Tattler does not occur in the study area, nor would it be expected to. Recommend
removing section
App RTable
1.3.3453
Excessive amount of space is devoted to accidental /vagrant/migrant species and the real impact of
the loss of commoner species is not being addressed in this report.
Final April 4, 2013 232
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App RTable
1.3.3454
“waterfowl” - Please define - this number appears far too high for it to be the commonly accepted
list of species that are considered to be waterfowl.
App R P18 455List would be more suitable as a table.
14 456
Selection of VCs - Non-Migratory Birds
Issue: Concern about the lack of focus on Ruffed Grouse in the assessment although the species
account was thorough.
Concern: The species is relatively common provincially but the loss of lowland, old/mature,
riparian forests will have a major effect on individuals locally. This habitat type is unlikely to be
replaced post-inundation. Ruffed Grouse are also a valuable game species.
Request that the Proponent:
Provide a more comprehensive assessment of the impacts to Ruffed Grouse in terms of affect on
the number of breeding individuals and downstream impacts caused by changes in hydrology.
Non-Migratory Birds
Final April 4, 2013 233
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 457
Description of VCs - Non-Migratory Birds
Issue: There are important gaps in the coverage of field surveys of Non-Migratory Birds.
Concern: There are portions of the LAA with suitable habitat in which no surveys were conducted
and where data does not exist from previous inventories. The implications of this are that the
habitat models are not well-validated; if at all (there is no detail in the EIS on how the field data
were used to support the habitat models). Examples of gaps in field surveys include: (i) Some Sharp-
tailed Grouse leks may not have been identified due to gaps in survey coverage and therefore
effects on this species may have been underestimated. The EIS implies that areas not surveyed for
the Project are covered by previous inventories but there are known to be gaps in the knowledge of
lek locations in the LAA. (ii) Surveys of the use of low bank riparian islands by Ruffed Grouse
would provide an indication of the numbers of birds using these features.
Final April 4, 2013 234
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 457
Continued
Request that the Proponent:
(a) Provide a map of locations where previous surveys have taken place; this would provide the
reader with more background on actual survey coverage. The regional biologist can provide
information and guidance on data and information related to suitable habitat.
(b) Provide a rationale for gaps in survey locations for Sharp-tailed Grouse and discuss the
limitations of incomplete coverage in assessing impacts to this species.
(c) Further to the previous point, the model identifies a large contiguous patch of suitable Sharp-
tailed Grouse habitat between Windy Creek and Moberly River. Has this area been surveyed for
grouse, and if not, does BC Hydro plan to conduct surveys here?
(d) The living-growing season is stated to include June – September, while the living-winter season
includes October – March (App R Pt 5 S B1.6.2 Pg 53). Lekking activities, which were surveyed for
and discussed in the species account, occur in April and May. Were April and May excluded from
the habitat assessment ? If so, please discuss the implications of not including these months.
(e) Consider conducting surveys of the forested islands downstream of the dam site for Ruffed
Grouse and other bird species, including Migratory Birds (see comment above). Report in the EIS
how many Ruffed Grouse may occupy the islands at baseline.
Final April 4, 2013 235
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 458
Description of VCs - Non-Migratory Birds
Please response to the following detailed questions about Ruffed Grouse surveys and habitat map
(ref. Vol 2 AppR Part 5 Section 1.1, Pg 2-4):
1) Were Ruffed Grouse observations from 2006, 2008 and 2011 incorporated into the draft species
model prepared to determine point-count transect locations?
2) Listening time provided by the RISC standards is four minutes; please provide justification for the
longer listening period used for Ruffed Grouse.
3) Station listening time was extended if ambient noise interfered with ability to hear grouse. How
often was this the case? Please comment on how this ambient noise may have affected the survey
results.
4) Please comment on how many survey stations were completed in inclement weather conditions
(statement on page four suggests that only some point-count stations were not completed under
such conditions).
5) Although the number of point-count stations was reasonable (n=214), the distribution of
transects across the LAA is quite limited. Were these limitations due to logistical issues, such as
access, or lack of suitable habitat predicted by the draft model? Please comment on whether the
relatively poor coverage of the area might affect the final habitat model and predictions of project
effects.
Final April 4, 2013 236
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 459
Assessment of Impacts - Non-Migratory Birds
Issue: The EIS attributes the same recovery, disturbance tolerances and habitats to the two grouse
species (Sharp-tailed and Ruffed), when, in fact, the two species are quite different.
Concern: Sharp-tailed and Ruffed Grouse need to be addressed individually in the assessment for a
number of reasons: (i) the time required for the populations to recover will be different for the two
species; (ii) their habitat requirements and life strategies are different; and (iii) their resilience to
fragmentation and alteration of habitats is different. Sharp-tailed Grouse have fairly specific
requirements for all three life requirements and will not necessarily be resilient. There will be
differences in the magnitude of the effect of flooding on each species.
Additional Detailed information:
"The nesting requirement for the two species is different with little overlap (S 14.3.3.4, pg 14-47).
Sharp-tailed Grouse use more open areas and as stated in the Appendix : “Grouse in the Peace
River area used steep grassland slopes along the south and west-facing river breaks and shrub-
steppe communities in moist and gently-sloped areas along the river breaks (Goddard et al. 2009).
Forested habitat was rarely used.” For Ruffed
Grouse there are many references and statements regarding their use of Aspen stands and mixed
forest. (see B.1.5.1 in Appendix 092e1_v2_app_r_terr-veg-wldlf-rpt_p5-non-mig-birds.pdf)
14 459
Continued
Request that the Proponent:
(a) Treat Sharp-tailed and Ruffed Grouse as separate species for the purposes of assessment.
Assess and report impacts and residual effects on each species separately.
(b) Correct the statement in the text, and assumption in the assessment, that "the grouse may
move in the following spring" (Pg 14-47 lines 9 - 10). Reasons: i) The resulting vegetation will not
be suitable for both species; and ii) the habitat will possibly only be habitable by the next spring for
Sharp-tailed Grouse.
Final April 4, 2013 237
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 460
Assessment of Impacts - Non-Migratory Birds
Issue: The assessment of impacts to Sharp-tailed and Ruffed Grouse is incomplete.
Concerns:
(i) Incorrect assumptions about the establishment of the vegetation post disturbance. In the case
of the reservoir, dam and associated features, habitat loss can be expected to be permanent and
therefore irreversible.
(ii) Increases in general disturbance, predation, road kill and hunting as a result of increased access
were not quantified. These issues were identified as the major threats in the Appendix.
(iii) The analysis results showing a greater loss of habitat for Sharp-tailed Grouse compared to
Ruffed Grouse is more of an indication of gaps in the habitat mapping for Ruffed Grouse. Ruffed
Grouse are ubiquitous on forested islands in the LAA therefore one would expect a higher loss of
habitat due to the Project compared to Sharp-tailed Grouse which are more of a grassland species.
Request that the Proponent:
(a) Re-evaluate the assumptions concerning the establishment of vegetation post-disturbance in
the assessment of impacts.
(b) Provide quantitative estimates of mortality of Sharp-tailed and Ruffed Grouse due to increased
access.
(c) Explain why the results might show a higher area of impact for Sharp-tailed Grouse when so
much of Ruffed Grouse habitat is expected to be lost as part of the development. Is this result a
reasonable reflection of the distribution of habitats in the LAA or is it an artefact of habitat
mapping?
(d) Assess the characterization of effects and determination of significance in the context of the BC
Conservation Framework, given that both Ruffed Grouse and Sharp-tailed Grouse are ranked 2
within the Framework.
Final April 4, 2013 238
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 461
Mitigation Measures - Non-Migratory Birds
Issue: The EIS provides few details regarding mitigation measures for Non-Migratory Birds.
Concern: Options to mitigate habitat loss, particularly as a result of the reservoir and dam, are
very limited for upland gamebirds. There is no mitigation available for the inundation, either during
the construction phase or the actual inundation. The habitats are gone. Even if habitat loss is
temporary, there is the risk of mortality or disturbance that will be long-lasting (especially for
female Sharp-tailed Grouse). Whether they are aspen copses used by Ruffed Grouse or the grassy
slopes used by Sharp-tailed Grouse; these habitats both occur in the footprint of the reservoir.
The EIS states (S 14.4.2, Pg 14-58 Table 14-16) : "If clearing work during the critical bird breeding
season cannot be avoided, develop and implement a nest and lek search prior to clearing."
Searching does not mitigate loss; there needs to be a commitment to avoid disturbances once a
nest is found. Disturbances to known nests during critical bird breeding is in contravention of the
B.C. Wildlife Act.
Request that the Proponent:
(a) Consider guidance noted under Details when developing detailed mitigation measures for Non-
Migratory Birds.
(b) There is a known lek site at Area E located “immediately adjacent to the Project component
boundary”, and another adjacent to the Highway 29 realignment. Please clarify the distance that
the leks are located from the Project and whether additional buffers will be incorporated to avoid
disturbance of these wildlife habitat features (pg 14-35 line 15).
Final April 4, 2013 239
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 462
Mitigation Measures - Non-Migratory Birds
Please consider the following when developing detailed mitigation measures for Non-Migratory
Birds:
(i) Using pre-existing disturbance features (e.g. roads) will help reduce habitat fragmentation.
Mitigation would be more effective if the south bank access road followed existing resource roads;
(ii) Timing is the primary mitigation measure identified to reduce disturbance and displacement, as
well as mortality. Proposals to not clear vegetation during nesting season will be effective in
reducing disturbance to the Ruffed Grouse and to some extent to the Sharp-tailed Grouse. It is
recommended that the Proponent commit to clearing vegetation outside of the critical breeding
windows identified for birds. This will greatly reduce the risk for numerous avian species, not just
upland gamebirds.
(iii) Avoiding the clearing of trees during the nesting season will help to mitigate impacts to Ruffed
Grouse.
(iv) For Sharp-tailed Grouse mitigation should be focussed on minimizing impacts related to
burning of grasslands, flooding and disturbance.
(v) Access will increase as the result of the Project which will result in easier access for hunters.
Mitigation measures are needed to address increases in hunting pressure.
(vi) There is an expectation that agricultural land will increase and provide habitat, however
mitigation measures to intensify agricultural production runs counter to this (see comment below).
Final April 4, 2013 240
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 463
Mitigation Measures - Non-Migratory Birds
Issue: Mitigation measures proposed for agriculture conflict with mitigation measures proposed for
Sharp-tailed Grouse.
Concern: The EIS proposes to increase the productivity of non-inundated lands by increased
irrigation, addition of the good soil from the dam site, planting of vegetables in certain areas (Vol 3
S20.3). All of these measures, particularly the vegetables, are likely to render cultivated land much
suitable (likely not suitable at all) for Sharp-tailed Grouse. The "High" suitability rating would no
longer apply.
Request that the Proponent:
(a) Recognize and reconcile potentially conflicting mitigation measures for agriculture and Sharp-
tailed Grouse. This could include separating each type of mitigation and ensuring adequate areas of
high suitability habitat were retained for Sharp-tailed Grouse.
Final April 4, 2013 241
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 464
Estimate of Residual Effects - Non-Migratory Birds
Issue: Not knowing the extent to which the inundation may displace local populations of the two
grouse species is not a reason for characterizing the Magnitude of effects as “Low”. A
determination of Magnitude = Low must be supported by reasoning and numbers.
Concern: There are three concerns here.
(i) In general, whether an effect is Unknown might influence the Confidence in an estimation of
effect but not the Magnitude of that effect.
(ii) The magnitude of effects to grouse due to flooding should be able to be calculated. Although
the timing of inundation may be unknown – there can be a calculation made if it occurs during
nesting, which appears possible. There are maps of the proposed headponds that can be used
(111_v2_s11-4_fig_11-04-13_chnnlztn-hdpnd-inundtn.pdf and 112_v2_s11-4_fig_11-04-14_dvrsn-
hdpnd-inundtn.pdf).
(iii) There are two disturbances: the clearing and the flooding. These need to be discussed
separately as the approach to mitigating disturbance and displacement and its effectiveness will
differ between the two activities and the two species of grouse.
Request that the Proponent:
(a) Provide a more detailed rationale for estimating the magnitude of displacement as Low.
(b) Provide a more robust estimate of the Magnitude of effects on each species of grouse using
available maps of headpond locations.
(c) Discuss clearing and flooding separately for each grouse species and apply this information to
proposed mitigation measures for each.
Final April 4, 2013 242
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 465
Estimate of Residual Effects - Non-Migratory Birds
Issue: Impacts to Sharp-tailed Grouse due to disturbance during breeding season are
mischaracterized.
Concern: The estimate of Residual Effects downplays the timing and duration of Project-related
disturbance on Sharp-tailed Grouse and, therefore, may over-estimate the resilience of this species
to disturbance (S14.3.2.4, Pg 14-42, line 32). This is not a short-term one-time disturbance. As the
text notes, male Sharp-tailed Grouse wll return to their lekking site if the disturbance is removed.
However, if there is consistent disturbance over the breeding season they may not return and
females will not return (Baydack and Hein 1987).
Request that the Proponent: Clarify in the wording of Vol 2 Section 14.3.2.4 Pg 14-42 line 32 that
although male Sharp-tailed Grouse are somewhat tolerant of disturbance and males may move
back onto their leks, females will not, and the lek will become inactive (i.e., tolerance is not high).
Final April 4, 2013 243
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 466
Estimate of Residual Effects - Non-Migratory Birds
Issue: More information is requested concerning the methods and assumptions used to model
habitat for Ruffed and Sharp-tailed Grouse.
Concern: More details are needed of how “suitable habitat” was defined in order to review the
estimate of Residual Effects on grouse species (s14.3.1.4; pg 14-34). The original data is in the
appendix but it is too critical to the understanding of much of the analysis to not have some detail
in the main body of the report. Uncertainties related to assumptions in the models need to be
more explicit as they provide an understanding of the confidence with which the conclusions have
been made. For Sharp-tailed Grouse, the habitat models have rated
too highly the suitability of cultivated fields adjacent to the study area (see Detail #1) and along
transmission lines (see Detail #2) . As a result, the effectiveness of mitigation measures may be
over-estimated and the Residual Effects may be under-estimated.
Additional Detail
1. Within the text of the Appendix there are the following statements:
- “Cultivated fields can be greatly influenced with grazing intensity and crop type.”
- “In a study on the Peace River, most nests were found in shrub-steppe and agricultural habitats
although agricultural fields were used less than available” and
- “Agriculture acts as a ‘sink’ where habitat appears suitable but activities on the land reduce
reproductive success (Goddard 2010).”
Continued in following Cells
Final April 4, 2013 244
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 466
Comment Continued
These observations indicate that the suitability of agricultural lands as habitat varies; there is a
great deal of dependence upon the type of agriculture practiced and how it is practiced as to
whether it is good for Sharp-tailed Grouse. These conditions are highly variable and not able to be
managed by the Proponent. This situation is compounded by proposed measures to increase the
productivity of agricultural lands (described in Vol 20.3 and noted above).
2. The assertion that “... the transmission line right-of-way may increase the amount of suitable
habitat, with the creation and maintenance of younger forest types.” is not likely for Sharp-tailed
Grouse The following are a couple of quotes from Appendix R Part 5 (092e1_v2_app_r_terr-veg-
wldlf-rpt_p5-non-mig-birds.pdf) to illustrate this point:
“In a study on the Peace River, ... Aspen forest was rarely used for nesting.”
“[Sharp-tailed]Grouse in the Peace River area used steep grassland slopes along the south and west-
facing river breaks and shrub-steppe communities in moist and gently-sloped areas along the river
breaks (Goddard et al. 2009). "Forested habitat was rarely used.” (Appendix R B.1.5.1;
092e1_v2_app_r_terr-veg-wldlf-rpt_p5-non-mig-birds.pdf) noted in a paragraph on the Growing
season requirements and the ratings used.
Final April 4, 2013 245
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
466
Comment Continued
Request that the Proponent:
(a) Provide contextual information on the inputs, assumptions and uncertainties related to the
habitat models. For example the text should note that the “Reliability Qualifier” for models for
both of these species is “moderate”i.e., there is uncertainty about the models and therefore
uncertainty about the estimate of Residual Effects.
(b) Explain why Cultivated Fields were given a maximum rating of High (App R Table B.1.3). There
are a number of problems with this assumption (see Detail #1). Consider re-running the habitat
model with a reduced rating for Cultivated Fields and transmission line right-of-way and report on
how these changes affect the habitat suitability map and the estimate of Residual Effects.
(c) How were habitat models validated? Were field data used to verify habitat suitability maps?
14.5.2 19-22
467
These statements are untrue. There are no species or subspecies that are listed provincially as “a
result of provincial strategies for managing species and ecosystems at risk.” They are listed based
on a suite of criteria including trends, threats, numbers, range extent and area of occupancy. This
also applies to the statement that provincial listing is based “solely on jurisdictional boundaries”.
Refer to the criteria used.
Raptors
Final April 4, 2013 246
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
468
Selection of VCs - Raptors
Issue: The EIS Guidelines (S 12.2.3.5) state that “All species observations will be summarized” but
information is not presented on a number of raptor species that are known to breed in the study
area including Redtail Hawk, Merlin, American Kestrel, Golden Eagle, Sharp-shinned Hawk, Northern
Hawk-owl and Osprey. Birds of BC (Vol II 1990) indicates that Peregrine Falcons have been
observed in or near the study area, including breeding, but Peregrine Falcon (and other falcons) do
not appear to have been included in survey efforts, despite the fact that Peregrines are a SAR- listed
species.
Concern: The list of Raptor species described in the assessment is incomplete. Some of these
species would have been seen during other inventory work, even if targeted surveys were not
done. There appears to be no reference to surveys for cliff-dwelling raptors (Golden Eagle,
Peregrine Falcon) despite the fact that both species are recorded in the area (Birds of BC and the BC
Breeding Bird Atlas) and Peregrine Falcons are SARA-listed by COSEWIC and Red-listed by BCMOE.
An estimate of the number of nests in the area and the number of birds projected to be displaced is
only provided for Bald Eagle.
Request that the Proponent:
(a) Update the EIS to include all Raptor species known to breed in the LAA. Provide estimates of
the numbers of individuals of each species of Raptor that are known to breed in the LAA and
estimate the numbers that will be impacted by the Project.
(b) Add information about the more common species of Raptor (in addition to the more detailed
information on Bald Eagle, Broad-winged Hawk, Northern Goshawk, Northern Harrier). There is a
good overview chapter on the Owls, although numbers are lacking and the potential impact of the
Project is not included. (c)
Clarify whether surveys for cliff-dwelling raptors (Golden Eagle, Peregrine Falcon) have been
completed. If not, provide a rationale for their omission and discuss the implications for the
assessment of impacts. Consider doing surveys for cliff-dwelling raptors.
Final April 4, 2013 247
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
469
Description of VCs - Raptors
Issue: Information sought regarding the inputs and assumptions used in habitat models for Owls.
Request that the Proponent: Clarify the following re habitat models for Owls (App R Pg 27):
(i) Why is “nesting habitat” modeled for nocturnal owls and “living habitat” modeled for short-
eared owls?
(ii) What are the key differences between the two modelling scenarios?
470
Description of VCs - Raptors
Issue: Baseline surveys indicated few observations of Short-eared Owl and Northern Harrier, which
is postulated in the EIS to mean low nesting use. It should be noted that neither of these species
respond to call-playback surveys and are difficult to detect.
Concern: Few observations do not necessarily equate to low nesting use. A misinterpretation of
these data could result in an underestimation of impacts and Residual Effects.
Request that the Proponent:
(a) Consider the difficulties with detecting Short-eared Owl and Northern Harrier in estimates of
amount of nesting use and impacts to these species.
(b) Clarify whether the surveys were to RIC standards.
Final April 4, 2013 248
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
471
Mitigation Measures - Raptors
Issue: There are few details in the EIS about proposed mitigation and monitoring plans for Raptors.
Mitigation measures for individual species are not provided for any of the Raptors except Bald
Eagles, Northern Harrier and Short-eared Owl. There is also little information about monitoring to
track the effectiveness of mitigation measures.
Concern: Wetland compensation will be made available to address some habitat losses for
Northern Harrier and Short-eared Owl. However, there is no indication of whether the amount and
types of habitat eliminated will be compensated. Bald Eagles appear to be the only Raptor that will
gain some mitigation measures in the construction phase.
Request that the Proponent: (a)
Provide conceptual species-specific mitigation measures for Raptor species in addition to Bald
Eagles, Northern Harrier and Short-eared Owl. In particular, provide proposed measures for at-risk
species including those dealt with in more detail in the assessment (Broad-winged Hawk, Northern
Goshawk). (b) Clarify whether
the intent is to provide compensation equivalent to the amounts and type of habitat that will be
eliminated.
Please consider the following during detailed mitigation and monitoring planning for Raptors:
(i) Implement measures prevent Raptors from nesting on power poles along transmission line.
(ii) Refer to the recently revised MOE Best Management Practices for Raptors.
Final April 4, 2013 249
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
472
Mitigation Measures - Raptors
Issue: Artificial platforms for Bald Eagles will be unlikely to compensate entirely for loss of eagle
nests. It is also unlikely that reservoir will have the capacity to support the number of pairs of eagle
that currently exist.
Concern: The EIS projects a loss of 54% of known Bald Eagle nest sites. It is not reasonable to
assume that natural riparian habitats for Bald Eagles will be completely replaced by the
construction of artificial platforms (Pg 14-73 line 15). The proposed installation of eagle nesting
platforms adjacent to the reservoir shoreline will not necessarily be in the same habitat type as
those nests presently situated within the reservoir flood zone and will likely have a lower capacity
to support Eagles. Additionally, the effectiveness of nest platforms for Bald Eagles is not proven;
nest platforms have been very successful with Ospreys, but, based on experience, the success rate
is lower with Bald Eagles.
Request that the Proponent:
(a) Re-evaluate the estimate of Residual Effects to account for potential Project-related reductions
in carrying capacity for Bald Eagles due to changes to the riparian environment, potential
reductions in fish and waterbird prey due to the change to a large, deep impoundment, and
uncertainties related to the effectiveness of artificial nest platforms.
(b) The effects of habitat alteration and fragmentation on Bald Eagles are characterized as Low
because of the provision of nesting platforms. Provide examples from the literature on the
effectiveness of nesting platforms for Bald Eagles and the optimal habitat in which to place the
platforms (e.g., away from human disturbance, surrounded by mature forest etc.).
(c) Consider the following when planning to mitigate the loss of nest trees for Bald Eagles:
(i) Consider installing platforms in other riparian habitats that will not be directly impacted by the
reservoir;
(ii) Provide a variety of platform designs;
(ii) Monitor platforms for their effectiveness as replacement nesting habitat.
Final April 4, 2013 250
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.1.1.2 30 - 35
473
This statement is incorrect as written: Some species, including Eurasian Skylarks (Alauda arvensis),
all raptors, and 33 some native and some introduced upland game birds, have additional
protection. None of them have “additional protection”. Perhaps what they meant is that “In
addition, some non-native species are also covered under the BC WA including Eurasian Skylarks, all
non-native raptors and some introduced upland game birds”. Note that these species are added to
enable us to manage them, not necessarily to protect them. The raptors are there so we can
control falconry import/export; non-native game birds are there so we can enable hunting; species
like skylarks, starlings, House Sparrow and Rock Pigeons are there so we can manage/control them.
14.1.1.2 30 - 35
474
BCWA s 34 para provides year-round protection to the nests of Bald and Golden eagles, Peregrine
Falcons, Gyrfalcons, Ospreys, herons and Burrowing Owls regardless of whether the nest is active or
not. This is extremely relevant in the case of Bald Eagles nests that will be lost during construction
and flooding as a permit will be needed before such activities.
14.3.25 13 - 15
475
The statement: "Other species with nests within 500 m of the Project 13 activity zone include Broad-
winged Hawk (one nest) and Northern Goshawk (three 14 nests) is somewhat misleading as it
suggests these are the only other species of raptors nesting in the activity zone, rather than just the
nests they happened to find (whereas I recall finding a couple of Merlin nests during bird surveys
there in the 1970s). It would be better stated as “Other species for which nests were located within
500m....”
14.42 Table
14-16476
Removal of trees holding eagle (or Osprey) nests requires a permit regardless of time of year.
14.4 2 Table
14-16477
Note that the Wildlife Act protects some species nests whether they are active or not – including
eagles. This means removal of trees holding eagle (or Osprey) nests requires a permit regardless of
time of year.
14.7 478 This list would be more suitable in a table.
Birds - General
Final April 4, 2013 251
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
479
Assessment of Impacts - Birds
Issue: The EIS does not consider impacts to bird resulting from collisions with powerlines,
particularly if they are placed over wetlands.
Concern: Locating transmission lines over wetlands significantly increases the likelihood of birds
dying from collisions with powerlines, especially swans, raptors and sandhill cranes. In particular,
collisions with power lines could be of significance to Trumpeter Swans if the lines are close to the
wetlands where this species has been recorded breeding. Lines and towers can also increase
predation by raptors, ravens, crows and magpies.
Request that the Proponent:
(a) Include an assessment of mortality risk to birds (Trumpeter swans, Raptors and Sandhill Cranes)
as a result of collisions with powerlines built as part of the Project.
(b) Outline mitigation measures to reduce powerline collisions such as locating transmission lines
away from wetlands and, where avoidance is not feasible, applying techniques such as attaching
appropriately-placed deterrents to the wires.
Final April 4, 2013 252
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
480
Assessment of Impacts - Birds
Issue: The EIS does not consider impacts to bird resulting from collisions with powerlines,
particularly if they are placed over wetlands.
Concern: Locating transmission lines over wetlands significantly increases the likelihood of birds
dying from collisions with powerlines, especially swans, raptors and sandhill cranes. In particular,
collisions with power lines could be of significance to Trumpeter Swans if the lines are close to the
wetlands where this species has been recorded breeding. Lines and towers can also increase
predation by raptors, ravens, crows and magpies.
Request that the Proponent:
(a) Include an assessment of mortality risk to birds (Trumpeter swans, Raptors and Sandhill Cranes)
as a result of collisions with powerlines built as part of the Project.
(b) Outline mitigation measures to reduce powerline collisions such as locating transmission lines
away from wetlands and, where avoidance is not feasible, applying techniques such as attaching
appropriately-placed deterrents to the wires.
Final April 4, 2013 253
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
481
Mitigation Measures - Birds
Issue: The loss of valuable lowland riparian forested habitat will be difficult to mitigate effectively.
Concern: Impacts to birds that rely on lowland riparian forests, such as cavity-nesters, may be
underestimated if mitigation is assumed to offset this habitat loss.
(i) Species dependent on the lowland riparian forest habitats that will be entirely inundated will
lose their breeding populations with an impact disproportionate to the amount of high value
habitat lost.
(ii) There is a high level of uncertainty regarding the effectiveness of proposed mitigation for loss of
lowland riparian forests. The edge of the impoundment will move inland and cause the land/water
border to be closer to private ranch/ agricultural/ developed lands in many places where it may not
be possible to re-establish a riparian forest zone and even where it can be created, it is unlikely to
grow into the large, old-growth forests evident now on islands and lowland benches that provide
habitat for large raptors, Pileated Woodpeckers, Ruffed Grouse etc.
(ii) The EIS states that "Woodpeckers are known to persist when subject to natural disturbance,
and are considered to have high resilience to the effects of habitat alteration and fragmentations,
providing suitable nesting trees persist.” (pg 14.72 line 7). This statement does not clarify the
ability of Woodpeckers to adapt when nesting trees do not persist. Woodpecker nesting is likely to
be most dense in the lowland riparian forests that are going to be lost.
Request that the Proponent:
(a) Consider securing an equal amount of lowland riparian habitat in another location.
(b) Use data on the number of pairs of nesting birds to assess loss and effectiveness of mitigation.
Final April 4, 2013 254
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
482
Mitigation Measures - Birds
Issue: The loss of valuable lowland riparian forested habitat will be difficult to mitigate effectively.
Concern: Impacts to birds that rely on lowland riparian forests, such as cavity-nesters, may be
underestimated if mitigation is assumed to offset this habitat loss.
(i) Species dependent on the lowland riparian forest habitats that will be entirely inundated will
lose their breeding populations with an impact disproportionate to the amount of high value
habitat lost.
(ii) There is a high level of uncertainty regarding the effectiveness of proposed mitigation for loss of
lowland riparian forests. The edge of the impoundment will move inland and cause the land/water
border to be closer to private ranch/ agricultural/ developed lands in many places where it may not
be possible to re-establish a riparian forest zone and even where it can be created, it is unlikely to
grow into the large, old-growth forests evident now on islands and lowland benches that provide
habitat for large raptors, Pileated Woodpeckers, Ruffed Grouse etc.
(ii) The EIS states that "Woodpeckers are known to persist when subject to natural disturbance,
and are considered to have high resilience to the effects of habitat alteration and fragmentations,
providing suitable nesting trees persist.” (pg 14.72 line 7). This statement does not clarify the
ability of Woodpeckers to adapt when nesting trees do not persist. Woodpecker nesting is likely to
be most dense in the lowland riparian forests that are going to be lost.
Request that the Proponent:
(a) Consider securing an equal amount of lowland riparian habitat in another location.
(b) Use data on the number of pairs of nesting birds to assess loss and effectiveness of mitigation.
Final April 4, 2013 255
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
483
Impact on birding as a rec/tourism activity
Issue: There is no recognition of the residual impact on birding as a recreational activity. Examples:
Watson Slough, which will be lost if the project goes ahead, is promoted Tourism BC as a important
birding spot in Fort St John http://www.hellobc.com/fort-st-john/things-to-do/parks-wildlife/bird-
watching.aspx and that ebird has listed this location as a birding “hotspot” in British Columbia
http://ebird.org/content/canada.
(ii) Tables 1.3.4 - 1.3.6 show use of the LAA by thousands of waterfowl, especially ducks and geese.
Concern: This is a potential social and economic impact to recreation, tourism and sustenance use.
Request that the Proponent: Clarify whether the following are included in the assessment of social
and economic impacts.
(i) Loss of tourism e.g., bird-watching, nature-based tourism) related to impacts to bird species and
Watson's Slough; and
(ii) Loss of hunting opportunities as a result of impacts to waterfowl
Note: the loss of birding spots could be mitigated by creation of new wetlands that include areas
for viewing.
14.2.3 18
484
Line 18 – swallows are listed separately from songbirds whereas both are passerines and both
typically referred to as songbirds. Swallows are weak singers and often surveyed differently from
other songbirds, so it might be better to state “songbirds (including swallows)”.
Final April 4, 2013 256
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.2.3 26
485
EIS states that there are 7 R&B species, then identifies the 3 SARA species and gives their COSEWIC
rankings, but not their R&B status - and also does not identify and give status for the other 4. The
other 4 are identified in the following paragraph, but without acknowledgment of their status.
Further down the R&B status is given in lines 38-42 and line 1 on the next page for all but OSFL. For
consistency please consider placing the Red and Blue status in lines 29-32
14.2.3 19 - 20486
Cormorants and herons are neither waterfowl nor shorebirds – again – do they mean water birds?
14.2.3 20 - 21487
Songbirds are defined incorrectly as passerines (correct), swifts, hummingbirds, pigeons, doves and
kingfishers. Please clarify how this definition was formulated.
14.2.3 22 - 28
488
Of the 13 species listed as waterfowl, only the White-fronted Goose, Harlequin Duck, and Snow
Goose fit this category. Arctic, Caspian and Common terns; California, Ring-billed and Mew gulls;
and Black-bellied Plover are all in the shorebird Order Charadriiformes. The Pacific and Common
loon are in the Loon Order Gaviiformes. The Sandhill Crane is in the Order Gruiformes.
14.1.1.2 30 - 35
489
The list of bird species exempt from protection under the BCWA is complete, so no need to state
“includes”. Also “molthrus ater” is two words. Suggest revising to:
A few select species are exempted from protection for management reasons – these are crows,
European Starlings (Sturnus vulgaris), Rock Pigeons (Columba livia), Brown-headed Cowbirds
(Molothrus ater), House Sparrows (Passer domesticus), and Black-billed Magpies (Pica hudsonia).
14.3.2.4 32-33
490
Leupin (2003) only refers to Sharp-tailed Grouse. Please change grouse to Sharp-tailed Grouse.
14.2.3 40 (and
followi
ng
14
491
The text of S 14.2.3 refers to 7 species of woodpecker that occur in the Peace Region but only
identify 4 of them specifically.
App R Part
5. S 1.6.5492
The adjustment description for steep slopes as being downgraded to a maximum of low for winter
does not match the information presented in Table B.1.7.
Final April 4, 2013 257
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App R
Section 4.2493
There are a number of tables in Section 4.2 that have missed the sections on the residual impacts
associated with the operations phase (e.g. 4.2.3 Residual Effects. Waterfowl and Shorebirds Table
4.2.4 habitat alteration and fragmentation – marsh birds. Please correct.
14 494
Selection of VC’s – Non flying small mammals
Issue: The final EIS Guidelines did not include non-flying small mammals as indicators or as focal
species despite a request during the consultation phase that they be included. An explanation is
not provided Table 14. 2 Rationale for the Exclusion of Suggested Species (in the Wildlife Summary
document).
Concern: Although none of these animals are listed to be of conservation concern, they likely
comprise an important prey base for higher trophic levels and may have a key role as basal food
web species.
Request that the Proponent:
(a) Provide a rationale for why non-flying small mammals were not included in the assessment;
(b) Collate existing data and baseline information (e.g., from the literature) and provide an
assessment of impacts to non-flying mammals at the local population and species level within the
LAA and RAA ; and
(c) describe potential trophic effects of displacement of non-flying small mammals from the
inundation area, including the predators that might be affected.
14 495
Selection of VCs - bats
All bat species in the regions were included as VC in the assessment and well-described– this is
appropriate as the survey methods for all the species are similar.
Mammals - Bats & Small Mammals
Final April 4, 2013 258
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 496
Assessment of impacts - bats
Vol 2 Appendix R Part 7 Pg 226 Table 2.1.1 of the EIS states: "Project construction could directly
affect 22.7% of the available suitable foraging habitat for bats within the LAA and 11.3% of the total
reproducing habitat within the LAA."
There are serious limitations with the estimation of impacts on bats.
i) The probable outcome has been accurately described as adverse, however, by only considering
roosting habitat, rather than roosting and hibernating habitat, the magnitude of potential effects is
underestimated (see comment above).
ii) Floodplain older forests were correctly described as extremely important roosting habitat
(reproductive and non-reproductive) by a variety of methods (acoustic, radio-tracking, mist-
netting). However, these important habitats were not included in the estimation of impacts.
(iii) A < 20% loss of roosting sites associated with riparian balsam poplar forests is estimated to
have an impact of moderate magnitude (Vol 2, Section 14.5.1.1.6) but there is no estimation of
resulting impacts at the population level.
Concern: Hibernation, roost and maternity roost sites are limiting in the environment and
significant use of the LAA by bats for these specialized habitats was demonstrated during surveys.
Since the loss of important habitats can have a proportionally larger impact at the population level,
it is not defensible to assume a 1:1 correlation between loss of habitat and impact to bats. The loss
of foraging habitat is less of a concern. To estimate impacts on bats based just on habitat loss,
without considering the larger impact on populations will very likely result in an underestimation of
residual effects.
Final April 4, 2013 259
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
496
Continued
Request the Proponent:
(a) Provide a synthesis of all available bat data, including known and potential roosting, hibernating,
swarming and foraging sites by (i) year and between years, (ii) bat species, and (iii) seasonal habitat
use; (b) Use
best available science to re-evaluate potential impacts to bat habitats in consideration of project
effects on known and potential hibernation, roost and maternity roost sites; and
(c) Estimate population level impacts to bat species based on projected loss of habitats within the
LAA and RAA and report on uncertainties associated with this estimate; and (d)
Provide easily comparable summary of the data collected, so that a reviewer can readily make year
to year, season to season, habitat to habitat comparisons.
14 497
Mitigation measures - bats
Issue: Insufficient detail is provided in the EIS to assess effectiveness of proposed mitigation
measures and, therefore, residual effects on bats. The creation of man-made hibernacula at
Portage Mountain has a very high degree of uncertainty surrounding it and can be considered too
little, too late. (Vol 2 S 14.4.1, Table 14.15, Pg 14.51 - 14.56). For example, bat hibernacula have
particular microclimates (Klys and Woloczyn 2010). There is no consideration of whether a drill
hole in a logged landscape on the lakeshore will have a suitable microclimate for a hibernacula.
Concern: Overlooking the uncertainties or limitations associated with untested or ineffective
mitigation measures may result in an under-estimation of potential residual effects and a high level
of uncertainty concerning long-term outcomes for bats. Mitigation measures need to be
conceptualized in enough detail and with support from the literature to provide a level of
confidence in their effectiveness or, at the very least, to clearly identify where the main
uncertainties lie. This is important to guide monitoring efforts and to ensure that appropriate
adaptive management plans are in place.
Final April 4, 2013 260
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 497
Continued
Request that the Proponent:
(a) Provide a conceptual plan for mitigation to loss of bat habitat that is clearly tied to the impacts
identified in the assessment. Please include the following:
i) Timing of mitigation measures (pre- or post-construction)
ii) More conceptual details such as spatial and temporal buffers to disturbance and timing of
project activities
iii) References supporting the effectiveness of proposed mitigation measures for Portage Mountain
bat habitats.
iv) Monitoring to assess effectiveness as some of the mitigation measures proposed are
experimental.
v) Responsibility for maintenance of these mitigation measures.
(b) Initiate mitigation planning and implementation prior to construction to remove animals from
the area of impact and into alternative habitats and to test the effectiveness of mitigation
measures.
(reference) Klys, G, and B.W. Woloczyn. 2010. Ecological aspects of bat hibernacula in the
temperate clmate zone f Central Europe. Travaux du Museum National d'Histoire Naturelle 53: 489 -
497.
Final April 4, 2013 261
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 498
Mitigation measures - bats
Please consider the following recommendations for effective measures when developing a detailed
mitigation plan
(a) Mitigation needs to start before construction, before the impacts occur. For example, bat boxes
need to be constructed before cottonwood trees are logged and flooding commences. This will
provide an opportunity to translocate bats and test mitigation meatures before impacts occur.
(b) It is important both to avoid destruction (during construction) and to minimize disturbance
(lights, noise, vibrations etc) when the bats are using hibernacula. Need to ensure proper set-backs
and seasonal timing of construction/disturbance.
(c) Recommend the Proponent do some spot pre-construction surveys with an experienced bat
biologist in previously unsurveyed areas once access opens up and before major construction
begins.
(d) It is recommended that lights be directly downwards to minimize light pollution and attraction
of birds and potentially bats.
(e) Highway bridge locations need to be in habitat suitable for bats (i.e. foraging) to warrant the
incorporation of bat roosting features onto bridges. Similarly, bat boxes (i.e. facility walls, artificial
nest poles) need to be located within habitat suitable for bats(Vol 2 App R Part 13 pg 244 and 245).
(f) Recommend monitoring for mortality during construction for bats at Portage Mountain Quarry,
and that bat boxes be monitored for use.
(g) The use of bat boxes on Bald Eagle nesting platform poles should be investigated more fully;
bats may not use boxes in such close proximity to a potential predator (Vol 2, S 14, Pg 14-55, Table
14.5).
Final April 4, 2013 262
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 499
Estimates of residual effects - bats
Issue: It is difficult to assess whether the EIS estimates the residual effects appropriately when the
conclusions about impacts are so general and qualitative. The impact is estimated as habitat lost
whether the habitat is foraging habitat (widely distributed, not limiting and easily replaced) or
hibernating habitat (specific areas, limiting across the landscape (RAA) and not easily replaced if
ever). The impact of the habitat lost on population size and future growth (recovery) will be very
different for foraging habitat compared to reproducing or hibernation habitat.
Concern: Since the assessment of significant adverse effects is based on the assessment of residual
effects it is necessary to provide a full accounting of how residual effects were determined
Request that the Proponent:
(a) Provide a rationale for the estimation of residual effects on bats.
(b) Demonstrate how proposed mitigation measures will reduce residual effects to the EIS
determination of 'non-significance'.
(c) Provide justification for the determination of a “low” magnitude of effect associated with
construction around the bat hibernaculum at Portage Mountain (Vol 2 S14.5.1.3, Pg 14-84).
(d) Clarify if consideration was given to bat mortality resulting from winter construction and
clearing of the Portage Mountain hibernaculum when concluding that the effects of the Project on
wildlife mortality are Not Significant. (Vol 2 S 14.5.3 Pg 14.90).
Mammals - Beaver
Final April 4, 2013 263
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
500
Description of VCs - Beaver
Issue: There are limitations in the surveys for beavers. Gaps include bank dens, surveys along the
proposed transmission line and south bank access roads, which appear to intersect watercourses
and waterbodies.
Request that the Proponent: (a)
Clarify (i) the extent to which bank dens were considered in the recent surveys and used to
calculate the number of beaver potentially affected by the project; and (ii) rationale for how far
upstream the tributaries were surveyed (e.g., expected impact lines).
(b) If bank dens, the proposed transmission line and south bank access roads were not surveyed,
please provide a rationale for why these areas were not included.
Final April 4, 2013 264
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App R 501
Assessment of impacts - Beavers
Issue: The probable outcome for beavers has been accurately described as adverse, however there
are a number of weaknesses in the assessment of impacts for beavers.
(i) it is unclear how bank denning beavers factored into the total number that might be affected;
(ii) Effects of construction and operations on habitat for beaver are said to be restricted to the
Peace River; this is not strictly accurate however, because effects will extend up the tributaries and
affect beavers in these locations (Vol 2, App R, S 4.2.2, Pg 253); and
(iii) it is unclear how suitable the reservoir and flooded tributaries will be for beaver, nor how many
beaver are likely to be supported in compensatory wetlands.
Concern: Half of the beavers in the Peace River between Hudson’s Hope and the Alberta border
will be lost with the project. The current estimates (loss of 335 beavers) suggest that development
will affect half of the beavers on the Peace River system. Some assessment is needed of the
regional context of impacts to beavers at a population level.
Request that the Proponent:
(a) Provide estimates of the percentage of bank dens, lodges and beavers that will be affected by
project development.
(b) Provide a population level assessment of beavers in the local and regional context (LAA and
RAA), including effects on bank dens and tributaries to the Peace River.
(c) Explain how the effects on beavers were determined in the EIS to be 'not significant and
reversible'. Include a consideration of the suitability of the reservoir and flooded tributaries and
proposed mitigation measures (see comment below).
Final April 4, 2013 265
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.4.1 502
Mitigation measures – Beaver
Issue: There are no species-specific mitigation measures proposed for beaver, other than potential
moving of beavers, which has a high degree of uncertainty with regards to success (Vol 2 S 14.4.1
Table 14.15). The general mitigation measures have limited applicability for beaver, other than
maintenance of riparian vegetation wherever possible.
Concern: The EIS needs to be clear that mitigation measures for beavers have a low probability of
success.
Request that the Proponent:
(a) Comment on the suitability of the reservoir and compensatory wetlands as mitigating habitat for
beavers.
(b) Consider measures that could stabilize the banks to provide suitable habitat for beaver during
operations
Mammals - Fisher
Final April 4, 2013 266
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
503
Description of VCs - Fisher
Issue: Although the proponent did a thorough survey of potential den trees in the LAA, the
interpretation of the data used to determine a criteria for “suitable rearing habitat” (upon which
the majority of the effects assessment was based) appears to be flawed and should be revised. The
criteria by which suitable rearing habitat was determined was based on measurements at different
spatial scales (i.e., stand- vs. home-range scale). That is, the criteria proposed uses, in part, the
average density of Tier 3 trees across the home range (0.225 SPH) to define suitable rearing habitat.
This is not equivalent to saying that all stands that are > 0.225 are suitable for reproduction. This
minimum density does not necessarily equate with stands suitable for reproduction. Thus, the
average density of Tier 3 trees within a home range does not necessarily translate to being the
minimum that would support a female fisher, so using this metric to estimate “suitable habitat” is
not justifiable.
Concern: Errors in baseline habitat suitability mapping compound through the assessment process
resulting in high uncertainty about the overall conclusions, specifically the estimation of Potential
Effects and Residual Effects.
Request to the Proponent:
(a) Rerun the analysis to correct mis-interpretation of scale in the assessment in the identification
of suitable reproductive habitat.
(b) Recalculate density of den trees within fisher home ranges (see Details).
(c) Undertake a moving-window analysis to show where the mean density is high enough to support
female reproductive use. (d) It is
an over-statement to say that cavity tree surveys reflect 'suitable habitat'. Reword to say 'suitable
reproductive habitat' throughout the document. Use the density of Tier 3 trees that occurred in
stands used by the radio-tagged fishers rearing to identify suitable rearing habitat (Site C and KPF
dens).
Final April 4, 2013 267
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 504
Description of VCs - Fisher
Issue: An assessment of seasonal habitats for fishers does not seem to have been adequately
performed. Substantially more analysis of the considerable site-specific telemetry data could be
used to develop seasonal resource selection functions that would have provided for a much better
assessment of potential effects (E.g., build upon/revise existing RSFs for fishers developed for the
Kiskatinaw region). Why not use the habitat models from the Kiskatinaw, updated with existing
telemetry data to develop specific RSFs for rearing and resting habitat for the LAA and RAA?
Concern: The assessment does not sufficiently meet the requirement for the examination of
seasonal habitat use, other than some element-scale reporting of reproductive dens and rest sites
in winter versus non-winter periods. It only focuses on reproductive habitat - which is where most
effect will occur but there are a number of other habitat-related factors associated with project
development that could affect fisher populations - movement, foraging, resting habitats and should
be included in the assessment. The Proponent has the data to support this work.
Request to the Proponent:
(a) Provide resource selection functions to evaluation probability of use for the full range of
seasonal habitats in the LAA and RAA (including movement, foraging, rearing and resting habitats)
to develop predictive models for assessing impacts.
(b) Conduct an assessment of impacts that includes the full range of seasonal habitat uses and not
just reproductive habitat.
Final April 4, 2013 268
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
505
Description of VCs – Fisher
Issue: There are errors in the analysis of plot level data. FPP/PCP comparisons are only relevant
within stand types (i.e., site series/structural stage combinations), not among stand types, as seems
to have been done in this analysis. The analytical design that should be used is that of Weir and
Corbould 2008: 90 (Vol 2 App R Pg 95).
Concern: FPP/PCP comparisons do not hold true when all plots are lumped because they are
confounded by stand-scale habitat attributes. Thus, you can't compare the FPP/PCP in one stand
type with a pair from a different stand type.
Request that the Proponent rerun the analysis using an estimation that correctly incorporates
stand scale factors
(a) Why were there a different number of PCPs than FPPs in each stratum? If they were paired
plots (as indicated in Section 1.3.2.4), then there should be equal numbers in each, because each
FPP would be paired with a PCP in each VRI polygon in which the radiolocation occurred (Vol2 App
R Pg 110 Table 1.3.12). (b)
FPP and PCPs habitat evaluation results need to be stratified by ecosystem/structural stage (this
was the basis for the pair-wise comparison). Stand-scale habitat factors confound any comparison
between the FPPs and PCPs. Without considering stand-scale factors, these comparisons are
uninformative and potentially misleading
References: (Vol 2 App r Pg 111).Richard D. Weir and Fraser B. Corbould June 2008 PWFWCP Report
No. 315 Ecology of Fishers in the Sub-boreal Forests of North-central British Columbia
Final April 4, 2013 269
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
506
Description of VCs - Fisher
Issue: Cavity-bearing tree surveys used a negative binomial distribution to estimate measures of
central tendency for the density of Tier 3 trees in each stratum, instead of a zero-inflated Poisson
(or zero-inflated negative binomial) model, which seems to be more suited to the data as described.
Also, the measure proposed to evaluate aggregation of cavity-bearing trees could be explained by
the fact that some ecosystems produce more Tier 3 trees than others. Thus, this metric may not be
the best for estimating "clumpiness".
Concern: The use of inappropriate statistical methods can result in misleading outcomes.
Request that the Proponent : Revise the analysis using appropriate statistical methods or provide a
rationalization for a negative binomial model and use the spatial information in the surveys to
provide a better estimate of aggregation.
(a) (Vol 2 App R Pg 116) The decision to group would confound your results, if you expect
ecosystem/struct stage to be the best stratification criteria? "increasing your sample size" shouldn't
be the justification for grouping them together - you need to consider the effects of introducing
bias and chance error when deciding to group strata.
(b) Did you evaluate means and variances to consider which strata to lump, or an ecological basis?
(Vol 2 App R Pg 116)
(c) Perhaps evaluating the count data with respect to neg-binom or Poisson distn would allow for a
better evaluations of aggregation. Since the location of the Trees along the transect were recorded,
why not use nearest-neighbour measurements to assess this?
Final April 4, 2013 270
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
507
Description of VCs – Fisher
Issue: The amount of reproductive habitat in the landscape is overestimated because the definition
of 'suitable' is too coarse. Habitat is defined as either suitable or not without gradation (ie., stands
are identified only as suitable or not). Data on the density of cavity trees across the different strata
should be used to better inform this section.
Concern: Overestimation of the amount of reproductive habitat may result in an underestimation
of impacts and residual effects.
Request to the Proponent: Re-run the assessment of effects using a corrected estimate of suitable
reproductive habitat.
508
Description of VCs - Fisher
Issue: Data on the dens used by the radio-tagged fishers is not included in the cavity-tree survey
description and compared to the observed values of fisher repro dens (n=51).
Concern: Including data on actual fisher dens would provide some support for the contention that
the trees surveyed during the cavity-tree surveys look an awful lot like real den trees.
Request that the Proponent clarify whether the actual dens were used in the cavity tree
assessment. If they were not, please include this data during reassessment.
Final April 4, 2013 271
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 509
Assessment of impacts - Fisher
Issue: The scale of much of the analysis for fishers is too simplified and too small to adequately
assess potential and residual impacts (i.e., focussed in the LAA). As with other wide-range
carnivores, the impacts of development extend outside the LAA to include the RAA. This is done in
some portions of the assessment, but not all. For example, Table 14.13 just lists how much will be
removed, not how much is available (both within the LAA and RAA). This is particularly an issue for
the assessment of the loss of reproductive habitat, where the coarse nature of the classification
does not allow for a thorough evaluation of the quality of habitats lost. More detailed assessment
and reporting is needed at the LAA and RAA scales.
Concern: The scale of reporting may result in an underestimation of impacts and residual effects.
Request that the Proponent: (a)
Provide a table with the area in each of the cavity tree survey stratum in each zone within the LAA
and RAA (impacted, not impacted) (b)
Evaluate and predict the loss of reproductive denning opportunities on both the individual fishers
and the entire population.
Final April 4, 2013 272
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 510
Assessment of impacts - Fisher
Issue: The EIS states no separation of populations across the reservoir based on genetic studies
(therefore assume same population). However, one would not expect any recent changes in gene
flow associated with past developments (i.e., reservoir development, flow regulation) to be
expressed within the timeframe at which past impacts occurred (~40 years). Because of this, the
EIS makes a potentially flawed argument or at least should state that there is no HISTORIC
separation in the population.
In addition to the assumption that gene flow is not affected, the consideration of the effects of
fragmentation seem to be fairly narrow in its spatial scale (i.e., impacts on stand-scale
fragmentation to individuals). At larger scales (ie., regional, landscape), changing the Peace River to
a reservoir is also a substantial fragmentation process for both individuals and populations (Vol 2, S
14, Pg 14-26).
Concern: The effect of habitat alteration and fragmentation of the reservoir on the regional
population does not seem to be addressed for the furbearers. Converting a 300-500-m wide river
to a 1-2 km wide reservoir may restrict gene flow within the population beyond what has been
historically observed.
Final April 4, 2013 273
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 510
Continued
Request that the Proponent:
(a) Estimate how much the gene flow might be reduced from the 1940s, when the river froze in the
winter, to the 1970s when the river remained open, to the proposed open reservoir.
(b) Clarify the data used for this estimate and how it was calculated. Please report the likelihood of
detecting a difference, given that one existed, for a sample of 51 individuals (Vol 2 App R Pg 116).
(c) Provide justification (e.g., reference to scientific literature) as to why the reservoir is not
expected to impede movement of fishers across the landscape.
(d) Estimate potential population-level effects of the decrease in gene flow caused by this type of
habitat fragmentation. Kyle, C. J. 2002. Genotyping of re-introduced Williams Lake fishers (Martes
pennanti) and the identification of unknown individuals post-release. Unpublished report prepared
for Ministry of Water, Land and Air Protection
14 511
Mitigation measures - Fisher
Issue: The EIS does not explain why the proposed prescriptions are expected to mitigate losses (Vol
2 S14.4.1 Pg 14-56).
Concern: An estimation of residual effects is not possible without an evaluation of the
effectiveness of mitigation measures on specified impacts.
Request that the Proponent: (a)
Explicitly identify what loss factor each measure is attempting to mitigate.
(b) Given that the efficacy of artificial den boxes for fishers are unknown and loss of rearing habitat
is listed as a potential effect of development, other mitigation measures should be applied in
addition to den boxes (see Details). Since information has already been collected on Tier 2 trees,
why not try adding the holes necessary to facilitate formation of den trees, particularly in
depauperate stands?
Final April 4, 2013 274
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 512
Estimate of residual effects - Fisher
Issue: A thorough assessment of the net residual effects is not really calculated, as the mitigation
plan does not outline concrete mitigation results. Which leaves for a weak assessment of residual
effects. They are not really characterized or documented, just broad statements about what could
occur with the habitat loss. There is a lot of data available that could be used to create a more
quantitative analysis.
Concern: A careful and defensible estimate of residual effects is needed to determine whether
there will be a significant adverse effect to fisher as a result of the Project.
Request the Proponent provide a more quantitative analysis of residual effects that incorporates
baseline data and includes the revised methods for suitability mapping and other inputs detailed in
earlier comments.
App R 513
Estimate of residual effects - fisher
Issue: The method used to estimate residual effects would be more defensible if the assessment
was based on the proportion of each animal’s home range that will be impacted by development
rather than the number of radio tagged fishers whose home ranges overlap the LAA (Vol 2 App R Pg
228).
Request that the Proponent revisit their methods of estimating residual effects. The EIS states the
effect is 0.72 fishers, this appears to be incorrect as the Project will affect the proportion of the
home range of 6 fishers.
Final April 4, 2013 275
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.3.2 514
Estimate of residual effects – Fisher
Issue: Section 14.3.2 (Vol2 Pg 14-44) doesn’t predict what the potential effects of
construction/operation will have for displacing fishers. The assessment overlooked impacts
associated with habitat alienation from development - e.g., the proposed road will go through high
value fisher habitat. Access by trappers will also be increased, which will increase mortality risk.
Concern: It is particularly important to consider the disturbance and alienation of good habitat
downstream of dam associated with construction/operation. The amount of disturbance and
displacement affects habitat effectiveness and is an important component of any assessment of
residual effects.
Request that the Proponent:
(a) Outline all of the effects on fisher including potential for displacement due to road development
and use and increased mortality risk due to increased trapping pressure.
(b) Consider developing a predictive model to assess how much the construction and operation of
the facility would decrease habitat value. There is ample data to use in an RSF model to assess
these effects. Recommended monitoring follow-up: Monitoring of fisher harvest, follow up studies
of other mitigation (CWD piles, arboreal rest sites), also invest in research trials to understand
manner in which natural cavities form in Acb and At to develop programs to expedite development
of these features.
Final April 4, 2013 276
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 515
Assessment of cumulative effects - general
Issue: The Cumulative Effects section appears to simply list other projects that occur within the
RAA with no concrete estimation of effects to the VCs. The probability of a cumulative effect will
vary by species/habitat issue but the EIS makes blanket statements irrespective of the species that
might be affected. Statements like “A cumulative effect is not expected” need some additional
information to be supported.
Request that the Proponent: (a)
Provide a more quantitative analysis that details potential cumulative effects by species or species
groups. More information is required.
(b) Please clarify whether the EIS considers the possibility of cumulative effects regardless of
whether there were any significant residual effects of the project. If not, please justify this
approach. Examples of what's been omitted: Seismic exploration and danger tree falling will greatly
reduce the availability of reproductive dens for fishers across the landscape and will result in a
considerable cumulative effect for this VC. Forest harvest, road building, and danger tree falling
will greatly reduce the availability of reproductive dens for fishers across the landscape and will
result in a considerable cumulative effect for this VC.
14 19 24 516
Given the sampling approach (pair-plots sampled within stands)this conclusion may not be
appropriate
14 38 6 517Please change “carrying capacity” to “expected density” as it is not know what the carrying capacity
of the area is.
14 38 15 518
Recommend changing to “The abundance of marten suggests that fur-harvest may not be
substantially reducing the marten population.”
14 39 2 519
As it is uncertain whether gene flow will continue at the same rate with a reservoir. Recommend
changing “south sides of the river form” to “south sides of the river historically formed”.
Final April 4, 2013 277
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 49 8 - 9 520 Reference should be Naney et al. 2012?
14 64 Row 2 521Fishers aren’t explicitly identified, although they are previously. Mortality can be mitigated by not
clearing during March – June (as mentioned elsewhere in document).
14 82 22-23 522
Please clarify the following statement: “Residual effects of mortality during operations are not
expected for migratory birds, non-migratory birds, raptors, bats, fur-bearers, or ungulates, and are
not discussed.” - They seem to be discussed in the following sections.
App R 87 Para 4 523
Fisher citations incorrect throughout documents. Kiskatinaw study citations should be Weir and
others 2011 (density, Citation: Weir, R. D., E. C. Lofroth, and M. Phinney. 2011. Density of fishers in
boreal mixedwood forests of northeastern British Columbia. Northwestern Naturalist 92:65-69.),
2012 (reproductive habitat; Citation: ), 2013 (spatial and genetic relationships, Citation: Weir, R. D.,
E. C. Lofroth, M. Phinney, and L. R. Harris. 2013. Spatial and genetic relationships of fishers in boreal
mixed-wood forests of north-eastern British Columbia. Northwest Science 87.)
App R 88 Para 3 524
Citation should be Weir and others 2004: Weir, R., F. Corbould, and A. Harestad. 2004. Effect of
ambient temperature on the selection of rest structures by fishers. Pages 187-197 in D. J. Harrison,
A. K. Fuller, and G. Proulx, editors. Martens and Fishers (Martes) in Human-altered Environments:
An International Perspective. Springer Science+Business Media, New York, New York, USA.
App R 89
Section
1.3.2.1
and
others
525
“Trap” or “trapping” should not be used to refer to live-capture activities. Trapping is used
elsewhere in the EIS to mean killing a furbearing animal and harvesting its pelt. Instead, use live-
trap, livetrapping, or capture to indicate that the animals were captured then released for clarity
and consistency
App R 90Para 4,
last line526
Should read “hair with attached follicle roots”
App R 93 Line 7 527Citation should be Weir et al. 2011 and LFD for that study was 10 days.
Final April 4, 2013 278
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App R 94
Para 2,
last
sentenc
e
528
Consider employing the same methodology as Weir and Corbould (2006) and Weir and others
(2011) and use the empirical data that was collected on this study to generate a effective radius for
the Site C dataset.
App R 94Para 4,
line 5529
Please define “den type”. Does this refer to natal, maternal or cavity?
App R 94 Para 5 530
Consider changing this statement to “When the transmitter on a radiotagged animal indicated that
it had not moved for 8 hours and the animals was presumed to have died”
App R 95Para 4,
sent 3.531
The analytical design to which this refers is that of Weir and Corbould 2008:90, which doesn't
appear to be used in this analysis.
App R 99 Para 2 532
Please clarify if any samples were collected from trappers in 2012.
App R 100 Para 5 533
This needs to be reworded. For example: "We identified ecosystem units and structural stages that
were known to support reproductive dens for fishers in the BWBSmw (Weir et al. 2012). We then
stratified these combinations of ecosystem units and structural stages based upon the presence or
absence of balsam poplar in the ecosystem unit and age of the stand (young: <80 years old; mature:
>= 80 years old). The result was that we sampled 4 strata for cavity-bearing trees.”
App R 101 Para 1 534Reference should be Weir 2010.
App R 101 Para 2 535Reference Jenness 2008 for Longest Lines extension.
Final April 4, 2013 279
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App R 101
Table
1.3.2 &
1.3.3
536
Please clarify these 2 tables to reduce confusion, they don't identify the stratification units used for
the analysis. E.g.:
1) young - Acb absent,
2) mature - Acb absent,
3) young - Acb present,
4) mature - Acb present
App R Part
7. S 1.3.2.7101 537
Cavity tree transects were 333.3 m in length. Please provide some detail justifying this distance;
e.g., one side of a 1 km Swedish triangle.
App R 102 Para 1 538
Please consider rewording this paragraph as it is currently confusing. There seems to be
considerable confusion as the sampling are called both quadrats (which they are) and transects
(which they aren’t) in various places throughout the document.
App R 103 Para 2 539Please define what is meant by “architectural”
App R 103Para 3,
sent 3540
Move this sentence to the first paragraph on this page. It will explain things better if the reader
understands that the Tier 1 and 2 trees were assessed using variable-area quadrats, whereas the
Tier 3 trees were assessed in 1-ha fixed area quadrats.
App R 103 Para 4 541
This paragraph appears to be saying that BC Hydro estimated Tier 3 density for each age strata
(young, mature), moisture strata (mesic, moist) and for age-moisture strata, however this is
unclear. It is also unclear what happened to the Acb-age stratification. Please clarify.
App R 104 Para 1 542Please explain what information the resulting comparisons provided.
App R 104Para 1,
sent 1543
Please define the treatment classes.
App R 104Para 3,
sent 1544
Please provide data (or references) to support the statements.
App R 104 Para 5 545Capture rate is usually expressed as captures/100 trap-nights (e.g., Weir and Corbould 2006, Weir
et al. 2011)
App R 105Table
1.3.6546
Is the +/- the range, SD, or SE?
Final April 4, 2013 280
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App R 106Para 1,
sect 2547
As this is discussed later, consider reporting the capture rate of American martens for both the
south and north portions of the study area
App R 107 Para 3 548 Please clarify if these are mortalities of untagged animals.
App R 110Para 4,
sent 2549
Please clarify if these are paired plots, only 56 pairs of plots were conducted.
App R 114 Para 2 550Consider not using the word relative, otherwise the average values of these trees found at random
points should be included.
App R 115Para 2,
sent 1551
Note: Weir et al. 2011 had 16.3 fishers/1000 km² for the March 31st period.
App R 115Para 2,
sent 2552
reference should be Weir and Corbould 2006. Citation: Weir, R. D., and F. B. Corbould. 2006.
Density of fishers in the Sub-boreal Spruce biogeoclimatic zone of British Columbia. Northwestern
Naturalist 87:118-127.
App R 116Para 5,
sent 1-2553
Evidence for these statements is needed, such as descriptive statistics, assignment tests, etc. E.g.,
He, Fst, Dlr, Structure assignment tests.
App R 117Table
1.3.30554
It isn't clear which of the ecosystem codes correspond to the Acb present, Acb not present strata.
Please clarify where the "mesic, young" etc strata came from. It appears that the intent was to
have Strata as the first column and have the age and ecosystem association as footnotes - Please
clarify and correct if necessary
App R 118
Para 1,
last
sent
555
Please Include the data from this study as well
App R 118
Para 2,
last
sent
556
Unless a comparison is being made, please consider reporting the SD (not SE) and n for each.
Final April 4, 2013 281
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App R 119 Fig 3.7a 557
Please consider converting this from a histogram to a table that includes mean, SD and n for each
tier and stratum. This would provide a succinct summary of all data, which is missing from the
histogram.
App R 120Para 2,
sent 2-3558
Should this not be "more than 1" not "groups of" - from the methods it doesn't seem that "groups"
were identified on the transects, other than by tally. A spatial component (e.g., distance along the
transect) would need to be analysed to be able to comment on the "groupiness" of the trees. From
the data as presented.
App R 121 Para 1 559Please define "high densities of cavity bearing trees"
App R 121Table
1.3.35560
This table could be explained a bit better... it appears that this was figured out by how much area
was in each of the 4 strata in each home range, multiplied the area in each stratum by its estimated
density of Tier 3 trees, then estimated the total number of tier 3 trees by tallying the amount
projected in each stratum in each home range. Perhaps explain this in the text, or add another 4
columns to the table (for the area/number of trees in each stratum for each fisher).
App R 121Table
1.3.35561
Suitable REPRODUCTIVE habitat needs to be defined in the column label as "Area within home
range where >0.xx Tier 3 trees/ha occurred" (or whatever is the cutoff as identified after addressing
comment above).
App R Part
7. S 1.4.2.1123 562
The Technical Study Area is unclear on Map 1.6.23.
App R 228Throug
hout563
Consider replacing “suitable habitat” in this section with “suitable reproductive habitat”
App R Part
7. S 1.5
Map
1.6.45564
b) The fisher study area is referred to on this map. Since this map focusses on large carnivores, this
is somewhat confusing.
Mammals - Large Carnivores
Final April 4, 2013 282
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 565
Description of VCs - Cougars
Issue: There are gaps in information about Cougars in the proposed project area.
Concern: Additional information about Cougars and their status would provide a more
comprehensive assessment of potential impacts (or lack thereof) on Cougars.
Request that the Proponent provide additional information, including local knowledge where
available, about Cougars with reference to the provincial Cougar Management Plan. Include a
description of their current status in the Project Area and human-Cougar interactions and use this
information in a re-assessment of potential impacts on the species.
Final April 4, 2013 283
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 566
Assessment of impacts - Grizzly Bears
Issue: The road density analysis for Grizzly Bears was only undertaken for the Fisher study area
which has only a very small overlap with the Rocky Grizzly Bear Population Unit (GBPU). The EIS
would benefit from an equivalent road density analysis for the entire 'Grizzly Bear-Occupied Area'
within the RRA (i.e., overlaps with the Rocky and Moberly GBPUs) and subset for reporting by
Landscape Units or adult female home range equivalents. TRIM and other Resource Road data
could be used to provide a more complete study.
Concern: Basing the road density analysis for Grizzly Bears on only a small portion of the Grizzly
Bear-occupied area within the RAA may misinform the assessment of impacts to Grizzly Bears
(displacement and mortality risk).
Request that the Proponent:
(a) Provide a rationale for why the road density analysis was limited to the Fisher study area rather
than the entire 'Grizzly Bear-Occupied Area' within the RAA.
(b) Recommend repeating the road density analysis to include the entire 'Grizzly Bear-Occupied
Area' within the RAA, reported by Landscape Unit and/or adult female home range equivalents.
Final April 4, 2013 284
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 567
Assessment of impacts - Grizzly Bears
Issue: The EIS does not provide any assessment of potential incremental effects of the proposed
Project on the core Grizzly Bear habitat area to the North and the north-south linkage area itself.
There is an assessment of effects south of Peace Reach but this lacks an evaluation of overall effects
in the context of an objective to maintain north-south Grizzly bear population linkage across Peace
Reach. Factors such as increased recreational use by construction workers, incremental traffic
volumes and associated mortality risk on ungulates and therefore on Grizzly bears feeding on
ungulate carcasses, and other potential cumulative effects on Grizzly bear population linkage and
mortality risk do not appear to have been fully examined in the western part of the RAA and in the
larger area. A cursory examination of our Grizzly mortality history database shows a relatively high
concentration adult female mortalities on Dunlevy Creek (west of Hudson’s Hope, north of Peace
Arm) suggesting that there has already been a considerable negative influence on linkage through
area-concentrated mortality.
Concern: If core populations of Grizzly Bears to the north and south are healthy then occasional
dispersers may provide the genetic linkage that is a key part of our provincial and regional
objectives for Grizzly Bears. The potential for north-south linkage, already compromised by the
physiography of the Peace Canyon, is further likely to be compromised by the proposed major new
rock quarry (required for dam construction) just west of Hudson’s Hope.
Final April 4, 2013 285
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 567
Continued
Request that the Proponent:
(a) Examine the incremental effect of the proposed Project on population linkage between the
Moberly and Rocky Grizzly Bear Population Units across Peace Reach. To be meaningful, this
cumulative effects assessment must include the 'Grizzly Bear Occupied Area' north of the Peace
River (outside of the RAA) comprising Management Units 7-36, 7-43 and 7-44 (the Cameron,
Graham and Halfway River drainages that flow into the Peace River from the north).
(b) Undertake a comprehensive, localized analysis of mortality history for the RAA + Management
Units 7-36, 7-43 and 7-44.
14 568
Assessment of impacts - Grizzly Bears
Issue: Regardless of road density(see above comments), it is not clear whether the EIS accounts
for the impact to Grizzly Bears of traffic volume and human behaviour along roads within the
'Grizzly Bear-Occupied Area' within the RAA.
Concern: Road density alone may mask the potential for human-bear conflict due traffic and
human behaviour along roads.
Request that the Proponent:
(a) Clarify whether there was any evaluation of traffic volumes or human behaviour along specific
road segments to identify segments that are more or less likely to lead to lethal encounters
between humans and Grizzly Bears.
(b) If an assessment traffic volume and human behaviour along roads was not done, please provide
this assessment.
Final April 4, 2013 286
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 569
Assessment of impacts - Grizzly Bears
Issue: “...risk of grizzly bear mortality...will increase in construction areas in proximity to high-
quality food sources...”. However, on pg 232 of 347, the EIS notes “Resident grizzly use within
much of the project area is considered to be limited or not existent and habitat loss to the species is
not considered.”. Hence, are there high-quality food sources within/proximal to the project
footprint?
Concern: It is not clear whether there is high quality food sources in proximity to the proposed
Project is a risk to Grizzly Bears.
Request that the Proponent: clarify the apparently contradictory statements described in the
comment. Is the proximity of high-quality food sources to the project footprint of concern to
Grizzly Bears or is this a concern only to Black Bears?
14 570
Mitigation measures - Grizzly Bears
Issue: The EIS currently does not include proposed measures to mitigate increased mortality risks
and increased fracture of the north-south linkage for Grizzly Bears (see comment on incremental
effects on north-south linkage above).
Concern: Linkage and mortality risk are inter-twined. Any cumulative impact on mortality risk in
the Moberly or the southern section of the Rocky GBPU may affect the achievement of the
provincial objective to maintain a north-south Grizzly bear population linkage across Peace Reach.
This is because populations below carrying capacity experience less dispersal (there is less
motivation of sub-adults to venture far from their maternal home ranges as would occur naturally).
Request that the Proponent: Engage
in a direct discussion with the Province about (i) mitigation of potential impacts to the north-south
population linkage for Grizzly Bears (see comment above) and (ii) monitoring to determine if the
mitigation is being effective
Final April 4, 2013 287
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 571
Mitigation measures - Bears
Issue: There is a need for a comprehensive Human-Bear Conflict Management Plan to minimize
impacts to Bears during construction and operations. Because Grizzly Bears occasionally occur
within and near the Project footprint (LAA), a Human-Bear Conflict Management Plan for this
Project must also include Grizzly Bears.
Concern: A conflict management plan is essential to minimize risk to worker safety and the
unnecessary killing of bears. Mitigating conflict with Grizzly Bears requires a higher standard of
conflict management planning than for Black Bears alone.
Request that the Proponent:
(a) Prepare and implement a comprehensive Human-Bear Conflict Management Plan prior to the
commencement of construction and operations (see Details); and
(b) Provide a comprehensive list of Grizzly Bear sightings for the 'Grizzly Bear- Unoccupied Area'
within the RAA to assist with effective conflict management planning. If the applicant is fully
committed to zero tolerance of any incremental Black or Grizzly bear mortality associated with the
provision of bear attractants, such Human-Bear Conflict Management Plans can be highly successful
when implemented. Effective prevention of conflicts and detailed conflict response protocols can
go a long way to bringing the incremental mortality risk associated with even such large
developments to near zero. In addition, comprehensive plans include mandatory worker safety
training, providing assurance to Work Safe BC and worker Safety Committees that bear-related risks
are at least minimized, if not eliminated. Provisions for bear proof (not bear resistant) food and
waste containment, electric fencing, complete waste incineration or bear-proof transport and so
on, all need to be included in the specific plans for each component of the development. The
Management Plan is the place to lay all that out in writing, for commitment for implementation by
senior BC Hydro approvers.
Final April 4, 2013 288
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 572
Estimate of residual effects - Wolves
Issue: There is no reference to Wolves when characterizing residual effects.
Concern: A comprehensive assessment of impacts must identify all effects even if they are not
significant. The subject appendix acknowledges (pg 170 of 347) documented Wolf presence south
of the Moberly River off the proposed transmission line. Request that the Proponent review BC's
current Wolf Management Plan (2013) and provide a response with regard to potential impacts on
Wolves.
14 573
Selection of VCs - Caribou
Issue: Values assessed are considered appropriate. Mitigation is provided in Volume 1 for caribou
at West Pine Quarry, but this species is not mentioned thereafter in the EIS. It is agreed that
interaction with caribou will be next to nil, and therefore no detail on this species is required.
Concern: It is potentially confusing to provide mitigation measures for caribou but not include an
assessment of impacts for the species.
Ungulates
Final April 4, 2013 289
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 574
Assessment of Impacts - Ungulates
Issue: Intensive field work has been conducted for ungulates; however, there were no data around
the transmission line and south bank access roads.
Concern: This data gap makes it difficult to fully assess the potential effects of these developments
on ungulates. The transmission line and access road have the potential to affect movement and to
increase mortality risk due to improved predator access and vehicular collisions. Assessment of
these factors is very difficult without data on the south bank. Request that the Proponent:
(a) Provide a rationale for the lack of data for ungulates around the proposed transmission line and
south bank access roads.
(b) Describe how the lack of data could affect characterization and estimation of effects on
ungulates, particularly with respect to movement and mortality.
(c) Complete an assessment of the effects of the transmission line and access roads on ungulates.
Final April 4, 2013 290
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 575
Assessment of Impacts - Ungulates
Issue: The probable outcome for ungulates has been accurately described as adverse. However,
the EIS does not quantify the amount of habitat indirectly lost through disturbance and
displacement during construction. This indirect loss has the potential to continue into operations
around the dam area, access roads and transmission line, depending on levels of human use.
Concern: The effects of habitat alteration and fragmentation may have been underestimated
without assessment of habitat loss as a result of disturbance and displacement.
Request that the Proponent: Incorporate road avoidance into the habitat models for ungulates to
quantify indirect effects of the Project on habitat availability and displacement.
14 576
Mitigation measures - Ungulates
Issue: The proponent has identified supplemental feeding as a potential mitigation measure for loss
of ungulate habitat.
Concern: Supplemental feeding could result in damage of stored hay and other feed on
neighbouring farms, due to attraction of ungulates to certain areas. In addition, there is some
evidence that hay is not well-digested by deer and may increase mortality risk. Supplemental
feeding of wildlife is also contrary to provincial government policy.
Request that the Proponent: Remove this mitigation measure as it is against provincial
government policy.
Final April 4, 2013 291
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14 577
Mitigation measures - Ungulates
Issue: The EIS acknowledges that several thousand hectares of moose habitat, deer habitat, elk
habitat and ungulate winter range will be flooded. Further detail is required on mitigation measures
and follow-up monitoring plans.
Concern: Some level of conceptual detail with supporting references is needed to evaluate the
effectiveness of proposed mitigation measures and, therefore, the estimate of residual effects.
Request that the Proponent: Include an assessment of the suitability of BC Hydro-owned land (east
of the Halfway River and west of Wilder Creek) to mitigate loss of Ungulate Winter Range and
include this in the estimate of residual effects. Suggestions re mitigation of impacts to ungulates:
(a) The timing of clearing during the winter could result in disturbance of ungulates, particularly
within the Ungulate Winter Range. It is suggested BC Hydro consider the timing suggested within
the General Wildlife Measures to minimize impacts within the Ungulate Winter Range.
(b) Consider reducing Project-related traffic levels, where feasible, to reduce the mortality risk to
wildlife, especially ungulates.
(c) Consider directing funds to ungulate counts / inventories / ongoing monitoring of ungulate
species in management units bordering the Project area in recognition of the importance of
ungulates as game species to local residents and First Nations.
14.2 14-8 5 578
The table states that cougar was not observed during any study since detailed fieldwork began in
2005. However, this is in contradiction to Section 1.5.1 in Appendix R, Part 7, where the text states
that cougar tracks were seen sporadically during field surveys. Please clarify as it appears cougar is
present in the area.
Section 14 General Comments
Final April 4, 2013 292
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.3 25 5-8 579
Assessment of Impacts - Overall Methods
Issue: Section 14.3 Effects Assessment describes the assessment of the likelihood of mortality
resulting from the Project as follows: "The number of individuals hunted, poached, hit by vehicles,
or lost due to construction and filling of the reservoir is difficult to quantify. A qualitative
assessment of the likelihood of mortality based on the timing and frequency of activities and the
proximity of roads and other Project components to suitable habitats is included"(pg 14-25 lines 5 -
8).
Concern: A quantitative assessment of the likelihood of mortality would provide more robust
information about Project-related effects.
Request that the Proponent:
Consider quantifying the effects of habitat loss on numbers of individuals by using field data to
determine species densities.
14.3.2 41 3-13 580
Assessment of Impacts - Overall Methods
Issue: The assessment focuses on disturbance and displacement resulting from headpond flooding
(pg 14-41 lines 3 - 13)
Concern: Disturbance and displacement are also expected to occur as a result of noise, traffic and
increased levels of human activity in the area.
Request that the Proponent:
Include more detailed consideration of the effects of disturbance and displacement on species
groups and species as a result of noise, traffic and increased levels of human activity in the PAZ.
Final April 4, 2013 293
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.5.1Table
14.1969 581
Estimate of Residual Effects - Overall Methods
Issue: According to EIS Guideline 8.5.2.3, characterization of Residual Effects is supposed to be
quantitative “where possible". In the EIS, tables summarizing the characterization of Residual
Effects (e.g., Table 14.19) do not indicate whether the inputs are quantitative or qualitative or how
these inputs were used to estimate the Residual Effect.
Concern: It is not clear what quantitative data was used (if any) to characterize Residual Effects and
how qualitative descriptors and quantitative data were used to estimate effects.
Request that the Proponent:
(a) Provide a description of quantitative and qualitative data used to characterize Residual Effects
(magnitude, duration, etc.), for each key species group (e.g., bats).
(b) How is the combined quantitative and qualitative information tallied up to characterize the
Residual Effects and form a basis for determination of significance? (What is “the math”?)
(c) What are the specific Residual Effects that are characterized for each of the key species groups
in Tables 14.19, 14.20, and 14.21? Is there another table summing up Residual Effects for each
species group (e.g., bats), for purpose of characterization?
(d) Provide summary tables in future iterations of the EIS that quantify Residual Effects and, from
that, "the math" to move from that quantification to a determination of significance. Provide a
rationale for each species group for determining what is significant or not.
8.5.2.3
Final April 4, 2013 294
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.5.2 582
Determination of Significance - Overall Methods
Issue: According to Sections 13.4.2 and 14.5.2, a Residual Effect becomes significant when: (a) a
species or ecosystem is currently designated (or candidate for) threatened and endangered status
and the Magnitude of the Residual Effect is characterized as 'High'; or (b) the species or ecosystem
currently has a lower listing (e.g., provincially blue-listed or SARA Schedule 1 special concern) and
the Magnitude of the Residual Effect is characterized as 'High', which may result in the key
indicator being elevated to a threatened or endangered status listing. “Significance” is reported in
Table 13.18 for 'Vegetation and Ecological Communities' as a whole and in Table 14.22 for 'Wildlife
Resources' as a whole and not for individual species or ecosystems that may be threatened or
endangered or at risk of becoming so.
Concern:
The criteria used to interpret significance are too limiting. Under these criteria, a Moderate impact
on a red-listed species or ecosystem or federally-listed species would not qualify as significant.
Given that these are already entities for which there is considerable conservation concern this is
too conservative an approach. Similarly, the limitations attached to Blue-listed species and
ecosystems (only where Residual Effects are of High Magnitide and where the project changes the
status) are too restrictive. These species and ecosystems are characterized as such because of
recognized inherent vulnerabilities. A project does not have to result in a change in status (which
represents a dramatic shift) to be Significant, nor should the Residual Effects considered be limited
to those characterized as High.
Comment Continued in next cell
Final April 4, 2013 295
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.5.2 582
Comment Continued
Request that the Proponent:
(a) Explain whether the thresholds of determining a significant adverse effect for Vegetation and
Ecological Communities and Wildlife Resources only what is written in sections 13.4.2 and 14.5.2?
Provide a more detailed description of the method for determining significance, if one exists.
(b) If these thresholds are the only criteria for determining significance, how will the EIS identify
and address unlisted species that risk becoming listed as a result of the Project or moderately
impacted Red- or Blue-listed species whose conservation status becomes more uncertain?
(c) Provide a comprehensive reporting of the link between impacts, mitigation measures, Residual
Effects and determination of significance for each species assessed within each species group.
Explain assumptions and quantify uncertainties for each step in this process, noting how
uncertainties may compound from step-to-step. and the implications of this for the final estimate
of Residual Effects and determination of significance.
Final April 4, 2013 296
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
14.7 103 7-21 583
Mitigation and Monitoring - Overall Methods
Issue: The EIS Guidelines require specific detail to be provided for each Follow-up Plan; however,
this detail has not been provided in the outline of the Wildlife Resources Follow-up Plan in Section
14.7.
Concern: It is difficult to ascertain if proposed mitigation/compensation measures are likely to be
adequate and robust over the long-term without more detail about monitoring plans.
Request that the Proponent:
(a) Provide more conceptual details about the Wildlife Resources Follow-up Plan, such as
techniques, frequency of monitoring activities and length of time to monitor. The concept of
adaptive management should be incorporated into all monitoring with the understanding that the
design and implementation of alternative techniques/methods of mitigation/compensation
measures should be undertaken, if necessary.
(b) Consider replacing should with will with respect to what the Follow-up Plan and directed studies
might include (pg 14-103 lines 7 and 18).
(c) Clarify how the results of directed studies will be used (e.g., for adaptive management,
modification of construction schedule) (pg 14-103 lines 18 - 21).
App R Part
1, S 280 584
Please comment on the potential role of erosion during operations to result in further habitat
alteration and fragmentation.
App R Part
7. S 1.1
Throug
hout585
Please check subheading numbering, it seems inconsistent among levels. For example, the fifth
order subheading 1.1.1.1.7 is under heading 1.1.3.1.
App R Part
7. S 1.5
Map
1.6.45586
There are several roads that are located in areas mapped as 0 km/km2 road density.. Please clarify
this inconsistency
Section 15 - Greenhouse Gases
Final April 4, 2013 297
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
15 8 1 - 17 587
Please clarify why there is a section comparing reservoir emissions to natural lakes. Even if the river
has the same emissions level as a lake, which is unlikely, the volume is much smaller. This section
and similar discussions should be removed as they are potentially misleading.13
15
General
comme
nt
588
Please revise this section as In general, the section and especially the technical appendix are
confusingly written, difficult to follow at times, and repetitive at other times.13
15 11 5 - 9 589
The assumption of 100% permanent storage of merchantable carbon removed from the site is
inaccurate. Based on BC averages and the offset protocol, 25% storage for 100 years is a reasonable
assumption. See page 79-86 in BC Government (2011) and Dymond (2012). Please adjust using 25%
storage. References: BC
Government 2011. Protocol for the Creation of Forest Carbon Offsets in British Columbia. Victoria,
B.C., Dymond, C.C. 2012. Forest carbon in North America: annual storage and emissions from
British Columbia's harvest, 1965-2065. Carbon Balance and Management 7(8).
13
15
General
comme
nt
590
There are a number of places where the project emissions and impacts are underestimated:
Emissions associated with land-use change do not include burning of biomass which generates
methane and nitrous oxide in addition to CO2 and can create health (smoke) problems to nearby
communities. Extensive burning was carried out during clearing of the NW Transmission line and
caused great concern to professionals, public servants, and the public. Burning of harvest residues
contributes a significant portion of the GHG emissions caused by deforestation and forest
management. It is estimated for the NE BC, when forest is cleared for conversion to settlements,
burning of the harvest residues doubled the CO2 emissions in the first year. The burning should be
incorporated in both the emissions estimates and the plans to mitigate them.
13
Final April 4, 2013 298
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
15
General
comme
nt
591
There are a number of places where the project emissions and impacts are underestimated:
The current conditions analysis assumes that the vegetation has a net 0 flux, i.e. is carbon neutral,
and this assumption is not explained or justified. There are a number of scientific papers
demonstrating the area as a net biological sink (e.g. Chen et al. 2003, Stinson et al. 2011).
Therefore, assuming it is neutral will underestimate the impact of the project. References: Chen,
Jing M., et al. 2003. Spatial distribution of carbon sources and sinks in Canada's forests. Tellus
B 55.2 (2003): 622-641. Stinson, G, W.A. Kurz, C. Smyth, E.T. Neilson, C.C. Dymond, J. Metsaranta,
C. Boisvenue, G.J. Rampley, Q. Li, White, T.M., and Blain, D. 2010. An inventory-based analysis of
Canada's managed forest carbon dynamics, 1990 to 2008. Global Change Biology, Vol. 17 Issue 6,
p2227-2244
13
15
General
comme
nt
592
There are a number of places where the project emissions and impacts are underestimated: The
emissions associated with land-use change due to infrastructure around the flooded area appear to
be an after-thought. The methodology changed to more of a back-of-the envelope approach,
ignoring emissions from non-merchantable forests, non-forest vegetation types, dead organic
material and soil. This analysis should be redone in the same manner as the EOSD vegetation cover
types within the flooded area. Plus it is estimated for the NE BC, when forest is cleared for
conversion to settlements, burning of the harvest residues doubled the CO2 emissions in the first
year. The burning should be incorporated in both the emissions estimates and the plans to mitigate
them
15
General
comme
nt
593
In general, the EIS provides a decent first attempt at quantifying GHG emissions and removals for
the current conditions and the Site C project, especially since there is no standard practice for land
and flooded areas. 13
Final April 4, 2013 299
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
15.4 18-22 594
In year 1 of the deforestation and flooding the land-based emission are estimated at about
1,000,000 t CO2e (Figure 15.2). These are not low and the estimate should be higher. In that year,
Site C will certainly show up as a significant source in the provincial GHG emissions report. How will
these emissions be mitigated? Note that spreading them out over a number of years would not be
helpful to the atmosphere. Can the biomass be used for other purposes such as bioenerg,
landscaping, or another use where the CH4 emissions are reduced.
15.4 18-22 595
The stated criteria for low magnitude GHG emissions is <105 t CO2e/yr (Table 15.10). The stated
emissions are 45,000 t CO2e/yr for 8 years + 43,000-58,000 t CO2e/yr for 100 years. The emissions
are approximately 500 times the cut-off for low, therefore they should be characterized as high.
Please correct.
15.1 and
15.46 & 23 596
The report should compare the Site C emission estimates with those currently reported in the
Provincial GHG emissions report. For deforestation: 660-1,159 t CO2e/ha/yr and For “mature”
hydro reservoirs: 42,000 t CO2e per year and 1.6 - 5 t CO2e/ha/yr.
15.1.5.15-6 &
15
10-19
and
Tables
15.2 &
15.4
597
Note that on page 15-15, line 30-31 there is a sentence describing carbon losses due to
transmission lines and new roads. Why are these “losses” included under Operational emissions?
Are they converted to CO2e and added in the totals? 13
15.1.5.15-6 &
15
10-19
and
Tables
15.2 &
15.4
598
The spatial boundaries for land-use change only include the inundated area as reported in Table
15.4. However, a much larger area will be deforested, including for all of the physical works listed in
Table 15.2. Please include the following: i) In Table 15.2 add columns stating the temporary
affected area and permanently affected area (i.e. land-use change) for each of the rows. ii) In
section 15.1.5 explain why some GHG emissions from land-use change were not estimated how
they might influence the conclusions.
13
Final April 4, 2013 300
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
15.1.5.2 599
15.1.5.2 Greenhouse gas calculations include a 30m buffer around the project activity zone over a
100 year period. See table 15.1 for a summary of how key issues were addressed by the approach. 9.2.1 Geology, Terrain
and Soils
App F 5.2.2 29 600
According to the summary and technical reports, estimated changes in GW elevations are based on
2D steady-state GW modeling using SEEP2/W, which was calibrated to existing water levels. The
calibrated conductivities appear to be generally consistent with media conductivities shown in
Figure 2 (GEOMETRIC MEANS OF HIGH-CONFIDENCE HYDRAULIC CONDUCTIVITY VALUES). It is
noted, however, that reported conductivity values exhibit a wide range of values. For example,
conductivity of shale and silty shale varies by more than 6 orders of magnitude from about 1(-6) to
1(-12) m/s.
A sensitivity analysis should be included that discusses whether and to what extent model
predictions of GW elevation change are affected by model parameters (conductivity, anisotropy
ratio), over a reasonable range of parameter values.
9.3.3
601
EIS Guidelines state: "This will include....Regional seismicity and seismic hazard" There is mention of
increasing seismic activity reported by the Oil and Gas Commission in Volume 2 Appendix B part 2.
Please clarify how this has been taken into account.
9.2.1 Geology, Terrain
and Soils
App B 602
EIS Guidelines state: "Sources of information regarding geology and terrain stability conditions
within the technical study area will include:"- Part 1 and Part 2 of appendix B do not reference
existing soils and terrain inventory in the area including Soils of Fort St John Dawson Creek Area
(1986) and 1:20 000 bioterrain mapping of the Blueberry Area in the Fort St John TEMVRI inventory
(request by BAPID = 5608 through [email protected])
Part 2 of Appendix B references previous shoreline and landslide inspections. These are not
mentioned in section 11.
For example, the clay fan at Bear Flat was misidentified as glaciofluvial plain on the terrain map yet
it is mapped correctly in the Soils of For St John Dawson Creek Area map.
9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 301
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App B, Part
1603
Terrain mapping in Appendix B part 1 and the related PDF maps do not fully reflect the geotechnical
findings (materials and mass movement processes) outlined in Appendix B part 2, even though the
TSIL (terrain survey intensity level) takes geotechnical field visits into account.
Terrain stability is the only management and decision theme that has been produced from the
terrain mapping. The project would benefit from updating the terrain mapping in light of the
geotechnical findings (e.g., the scarps of the Cache Cr. slide are mapped as glaciolacustrine in
contrast to the detailed landslide description).
The project would also benefit from terrain hazards and constraints maps derived from the terrain
mapping, such as: erosion potential, drainage, landslide runout, rock fall runout zones, fans subject
to flooding and debris flow hazards, zones of slow mass movement, etc. These themes would
inform safety plans, more accurate road construction and maintenance cost estimates, evaluation
of inherent stability and erosion sensitivities on the project. Targeted extension of terrain
investigation up the tributary streams could identify areas of potential debris damming and flooding
potential for further investigation.
Information gained through terrain mapping and geotechnical investigation should be better
utilized and cross referenced by other sections (soils, agriculture capability, ecosystem inventory,
forestry operations, recreation planning, safety planning, etc.).
9.2.1 Geology, Terrain
and Soils
604
EIS Guidelines state: "Sources of information regarding geology and terrain stability conditions
within the technical study area will include: Topography and digital elevation models generated
from aerial photography and from LiDAR; "- DEM and LiDAR data was not provided to the province.
Images of this information were provided as a base map in PDF format. An overview of the area
was viewed in 2D with BGC on March 7, 2012 with a focus of large landslide features, slope above
the dam site, and potential geohazards along the reservoir shoreline.
9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 302
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App B2 2.35 of
13010 - 11 605
It is noted that in some areas geotechnical drillholes are spaced at greater than 5kms.
Overestimation of Impact Lines could potentially restrict future and existing development in areas
adjacent to the reservoir. This would be contrary to the recommendation contained in the EIS by
the BCUC “...that every effort be made to minimize the disruption caused by the Project by
acquiring as little land as possible.” Please provide rationale for the adequacy of geotechnical
investigation of the underlying soils stratigraphy throughout the project length to justify the
limitations to future and existing development imposed by the impact lines.
9.2
App B2
2.4.1
6 of
1306 606
Report terms of reference state, “...outlining the requirements for monitoring and updating of the
reservoir impact lines.” There appears to be no firm recommendations or details of the monitoring
and maintenance program associated with the reservoir slopes and mitigation areas. Please
provide the details on the recommended monitoring and maintenance programs for the project. 9.2
App B2
2.4.3
7 of
1302 - 10 607
Impact Lines will restrict the use of some existing structures. Please clarify when sufficient
information will be made available to make structure-specific decisions with respect to whether or
not a structure will be impacted.
9.2
App B2 13.1118 of
13011 - 14 608
3rd bullet - Please quantify and provide additional information as to the "period of time"
structures would be permitted to remain. 9.2
App B2 13.1118 of
13011 - 14 609
bullets 2 & 3 "pending site-specific geotechnical assessments" Please clarify who will be
responsible for the costs of these geotechnical assessments. 9.2
App B2 13.1118 of
13033 - 35 610
Report states a berm/slope recontouring is proposed to protect properties within the District of
Hudson's Hope from “...shoreline erosion and to offset changes in slope stability caused by the
reservoir.” Do the proposed works fully compensate for any adverse affects to the global stability
at private properties and Highway 29? Please provide technical evidence that the global factor of
safety for existing structures and Highway 29 is not reduced post reservoir construction works and
filling.
9.2
Final April 4, 2013 303
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App B2 13.1120 of
1305 - 8 611
Are the existing development guidelines for residential setbacks within the District of Hudson's
Hope still valid following proposed slope changes for the reservoir berm/slope recontouring? Has
the applicability of the existing development guidelines been confirmed by the original Engineer of
Record responsible for the development guideline recommendations? 9.2
App B2 13.1120 of
13016 - 17 612
Report states that, “...some existing segments of Highway 29 are currently situated on marginally
stable slopes.” The Stability Impact Line (shown in impact line Map #25-26) between the Halfway
Hill and Watson Hill along Highway 29 is located on the upslope side of the existing highway. Does
the presence of the reservoir result in an adverse effect on the global stability for this section of
Highway 29, located south west of the Bear Flats area. If the global stability is adversely affected,
what are the proposed measures to offset this effect?
9.2
App CFigure
1 613
Please consider revising map theming as the BC Hydro owned land dose not readily stand out at
this scale.
App B 614
Appendix B part 2 characterizes erosion and slope stability issues based on reservoir edge geology
and quantifies the expected loss of lands at the shoreline at the 5 and 100 year marks. However,
this volume of sediment influx into the reservoir/potential downstream water courses does not
appear to be considered as an impact on fish or fish habitats (in: 058_v2_s12_fsh-fsh-habitat.pdf).
There seems to be a lack of integration of studies when assessing impacts.
9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 304
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App B 615
EIS Guidelines state: "Characterization and classification of the proposed reservoir shoreline will be
carried out, including: Predictions of potential for groundwater changes, including sensitivity to
changes in recharge rates and other aquifer characteristics, that could alter the potential for
landslides;" - Issues of wind erosion and dust coming from the exposed beaches during lower
water levels in the Williston Reservoir - N end near the Tse Kay Dene community are documented
on BCHydro website and referenced in section 11.1.3. How are issues relating to dust caused by
slope failures and wind erosion of the fine textured sediments along the banks or beaches of this
proposed reservoir, which could create dust and potential air quality issues for residents at Hudson
Hope/Ft St John (report only seems to consider dust from construction activities as per 172_v2_s11-
11_fig_11-11-09_max-prdctd-30day-dust-wth-bckgrnd.pdf ), being addressed? Clarification needed
re: how this reservoir is different from the other? Have potential dust issues (from reservoir
shorelines) for residents at Hudson Hope & Ft St John been considered?
9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 305
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
19 616
It is noted throughout this document, that in many areas, consultation and information sharing
between BC Hydro and First Nations is ongoing, therefore not all concerns may yet have been
expressed by First Nations nor all concerns addressed by BC Hydro. It will also not be known until
consultation is complete, what accommodation will be required to address First Nations concerns.
As several of the Natural Resource Sector agencies would be responsible for ensuring First Nations
consultation is adequate on authorizations related to the construction and operation of the Project,
should an EA certificate be granted we request the following
a) that BC Hydro ensure that concerns expressed by First Nations on the project are documented,
not only on issues at the Environmental Assessment level, but at the permitting level as well.
b) That BC Hydro document accommodations that have been proposed by BC Hydro and identified
or requested by First Nations.
19 19 19-4 617
The approach to addressing key issues has been developed through consideration of traditional
land use studies. Although the confidentiality issues surrounding the TUSs are understood,
wherever possible please provide this information to the Natural Resource Sector Agencies for
consultation purposes on applications for authorizations related to the construction and operation
of the Project.
Volume 3
Section 16 - Local Government Revenue - Not Reviewed
Section 17 - Labour Market - Not Reviewed
Section 18 - Regional Economic Development - Not Reviewed
Section 19 - Current Use of Lands and Resources for Traditional Purposes
Final April 4, 2013 306
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
19 19.4.5 618
Many of the detailed mitigation plans, management plans and follow up measures have not yet
been completed and included in the EIS. It is anticipated that many of these plans will assist in
accommodating concerns raised by First Nations and will be critical for First Nations consultation on
applications for the construction and operation of the Project. Please clarify when these plans will
be available and how these plans will be shared with First Nations once complete.
19 19.4 19-82 619
Please provide further evidence to support the statement that there will only be a “temporary” and
not a permanent reduction to moose availability within the LAA.
19 19.6.2 19-111 620
The effects from many recent operational activities are not reflected in the baseline conditions. It is
noted that the residual effects from other projects are not known. It is also noted that a number of
current and proposed activities (eg: Gething coal mine, Portage quarries, Septimus wind, Spectra
gas plant) in the area appear to be not included in the cumulative effects assessment. More detail
could be provided on specific residual effects of the many projects and activities that were
reviewed.
20 621
Assessment identifies agricultural lands within the Stability impact line, but discounts potential loss
of land impacts due to stated low probability of land slides. No probability assessment is
mentioned, yet there exist 3 large slides bordering the valley. Bank areas are mapped as slope
stability class IV and V (potentially unstable and unstable). Therefore, impact on agricultural
capability lands is underestimated - an estimate of the probable land area that could be lost due to
landslides would be informative.
9.2.1 Geology, Terrain
and Soils
20 1 10 622
Consider including reference to Agriculture Land Commission Act (ALCA) Section 40 - Reference of a
matter to the board, as an option (Public interest).
Section 20 - Agriculture
Final April 4, 2013 307
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
20 623
Existing soil and land capability maps are included or referenced. Additional soils assessment in the
field was done. Consideration of permanent loss of agricultural land was carried out by class and in
comparison to the province, the Peace Region, and the Peace Valley. Four mitigation measures
were proposed including a proposed compensation program to increase ag productivity. However,
comparison is not made to the historic state prior to installation of the first 2 dams. This is
important information that should be included for context.
9.2.1 Geology, Terrain
and Soils
20 20-27 12 624
Has BC Hydro given consideration to the possibility that there could be diversion of local labour
away from agriculture to construction?
20 20-28 9-11 625
Note that the estimate of 25% loss of Class 1 & 2 lands within the Peace River valley excludes the
islands even though these will be inaccessible for agriculture or range (p 20-28 lines 9-11) and
excludes potential loss of land due to landslides - therefore this value is an underestimate. The
reported loss represents 2.1%+ of the most productive lands in the Peace River Region and 1.0%+
of the most productive lands in BC. (as per the table).
9.2.1 Geology, Terrain
and Soils
20 626
The executive summary fails to mention the Ha of agricultural lands lost, or the lost proportion of
total available land in the Peace Region, giving the impression that this is insignificant. The exec
summary needs to provide tables summarizing the impacts on all VECs. 9.2.1 Geology, Terrain
and Soils
20 38 17 627
There is no mention of this impact on Agricultural lands in the Exec summary. >>Vol 5 Section 38 -
Summary of potential residual effects (p 38-17) categorizes this permanent loss of high quality
Agricultural land as 'Insignificant'. Please provide additional rationale for considering a loss of 1% of
provincial class 1-2 agricultural lands as insignificant. Please include the details of impacts in the
Exec Summary.
9.2.1 Geology, Terrain
and Soils
20.15 628
Table 20.15 shows that 7663 ha of land with agricultural capability is located within the impact
lines, however section 11.2.3.7 shows total area within the impact lines = 9648 ha. What accounts
for this inconsistency/discrepancy?
9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 308
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
20.2 13 37 629
Information Requested - “Agricultural land use, determined from recent air photos...” historic
land use should also be taken into account when classifying agriculture capability.
20.1.3 2 1 630
Please Clarify - Table 20.1 (line 2 of table) – "which has been updated with current fieldwork and
technical analysis of soil conditions, climate conditions, and crop suitability" Please describe the
approach used and provide rationale. Also, please consider providing data from Canada Land
Inventory Agriculture Capability maps and discuss changes to the classification
20.1.3 2 1 631
Table 20.1 (line 4 of table) – “The agriculture assessment takes into count lands both currently
developed and undeveloped for agricultural uses, by considering land capability (irrespective of
current use) ” – In other places in the EIS (eg page 20-5 Table 20.3 and page 20-6 line 33) it states
that ag land utility is used as an indicator. Please clarify as there appears to be some inconsistency.
20.1.3 2 632
There are potential benefits that are not listed including increased road access (eg south project
access road) and potential for irrigation, consumption of local produce by camps, that may be
worthwhile to include in the discussion.
20.1.4 5 1 633
Correction: Table 20.3 Row 1/column 3. Land capability ratings are described by: Kenk, E. and I.
Cotic. April, 1983. Land Capability Classification for Agriculture in British Columbia. MOE Manual 1.
Surveys and Resource Mapping Branch, Ministry of Environment and Soils Branch, Ministry of
Agriculture and Food. Kelowna, B.C. 68 pp. ISSN 0821-0640 not by the Agricultural Land
Commission.
20.1.4 11, 12 1 634
Please clarify if the wildlife impacts on agricultural operations during dam construction and
operation have been discussed and dealt with in the EIS. If not please consider adding.
20.1.4 5 1 635
Please clarify key indicators- Table 20.3 Row 2/column 2 – Effects on individual farm operations: the
impacts in changes to wildlife/waterfowl habitat and the potential impact on agricultural operations
are not indicated as key indicators although are mentioned as a key issue in Table 20.1.
Final April 4, 2013 309
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
20.2.3 20-13 15-24 636
Please explain the rationale for jumping from Land Capability to Agricultural Suitability? The
methodology used in the Okanagan and Similkameen Valleys (Gough et al. 1994) has not been peer
reviewed in the context of use for the Peace River Valley. Two additional references related to this
subject were not used “Soil Management Handbook for the Lower Fraser Valley” (Bertrand et al.
1991), as well as “Land Suitability Rating System for Agricultural Crops: 1. Spring-seeded small
grains.” Pettapiece et al 1995.
20.2.3 20-15Table
20.6637
Please provide rationale for exclusion of oats rye wheat, canola, peas from class 4 and 3
respectively. Local experience indicates those crops (except for Canola due to some climate
portion) would be suitable up to class 4.
20.2.3 14, 15 1 638
Table 20. 5 is an acceptable discussion for Suitability not Capability as it is labelled. The reference
source for Table 20.6 is not given. Volume 3 Appendix D Agricultural Assessment Support
Documents does not contain any discussion of how Land Capability was transcribed to Crop
Suitability. Please address and correct these issues.
20.2.4 20-15 10 639
Please provide more discussion/evidence of how the term “Agricultural Utility” is defined and how
this relates to the previous discussion/interpretation of Land Capability and Crop Suitability. No
reference documentation was found to clearly demonstrate how the concept of agricultural utility
was defined or determined for individual parcels.
20.2.420-15,
20-16
4 – 14,
1 - 14640
The section describing “Agricultural Utility” appears to ignore or discount the potential for non-soil
bound agricultural operations (i.e., intensive poultry or greenhouse production) on smaller parcels
which could become viable based on the availability of local market (population) and energy
(electrical). Please include an explanation of whether this was considered or disregarded.
20.2.7 20-19 1 641
Clarification required: Was the total size of each operation determined? The relevance of those
operations classed as unknown might become clearer if the aerial extent of all 34 operations was
known. Tables 20.25 and 20.26 provide more detail and should be referenced as part of Table 20.7
20.2.7 20-19 1 642Table 20.7 - Please quantify the data source and the size/extent of these operations. Are these
Cadastral properties or individual operations?
Final April 4, 2013 310
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
20.2.7.2.2 20-21
1 – 3,
14, 25-
28
643
Data suggest that non-soil bound agricultural operations – e.g. poultry, have been considered– yet
in discussion of agricultural utility these same classes of agriculture seem to have been excluded.
Please explain this discrepancy and correct accordingly.
20.2.8.1 20-23 18 644
Note: In June 2011, British Columbia (BC) was provided notice of CFIA’s intention to withdraw
provincial meat inspection services after December 31, 2013, requiring a provincially run meat
inspection system for Class A and B abattoirs.
20.2.8.2 20-23 23 645Please include other communal settlements in the region, specifically the Macabees at Mile 95
20.2.8.3 20-24 10-33 646 Request further discussion on this section
20.2.9.2 20-25 22-31 647Data used for surplus calculations seems to include non-human grade food in
production/consumption stats. Please clarify.
20.2.9.2 20-26 4 - 5 648
Future consideration related to climate change and population change is alluded to elsewhere in
Vol 20/Section 3 – yet future economic feasibility of alternate agricultural enterprises that may be
supported by factors of population/market demand, climate change and availability of inputs are
not considered.
20.2.9.2 20-26 1-8 649 Please clarify the source of the sugars.
20.2.9.2 20-26 1-8 650The information about livestock being finished outside BC should parallel how grain is handled in
this section as well.
20.2.9.2 20-26 4 - 5 651
What is the basis of the statement regarding poultry and dairy operations being “not currently
economically feasible” in the Peace Region? Pelase provide evidence to support this statement.
20.3.1.3 20-28 9-11 652
The concept of permanent loss of land from use by agriculture needs further review. Islands that
exist prior to reservoir filling and are unusable for agricultural purposes would fall into the “low
utility” definition. However, if an island is created by reservoir filling and the island is not accessible
or useable (e.g., agricultural utility is low), then is this land not a permanent loss?
Final April 4, 2013 311
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
20.3.1.3 &
Table 20.2
20-3,
20-28
to29
653
Section 20 and Table 20.2 do discuss the potential impact of decreased precipitation during the
spring and summer (as noted in 163_v2_s11-10_fig_11-10-14_prdctd-chngs-in-prcptn-mnthly.pdf)
resulting from the presence of the reservoir, but it is unclear of increased wind speeds (which will
affect evapotranspiration) are also considered. Implications of decreased moisture availability to
crops during their active growing season, and potential crop losses or increased irrigation costs are
not discussed.
9.2.1 Geology, Terrain
and Soils
20.3.1.3 ,
Table 2654
Islands in the reservoir with Agriculture Capability are not included in the lands lost, even though it
is likely that these lands would be inaccessible for the purposes of agricultural operations. This
then under-estimates total area with Agriculture Capability that is impacted.
9.2.1 Geology, Terrain
and Soils
20.3.10.1.1 20-62 19 655
Projects for the compensation fund need further discussion. The conversation about options should
precede the decision about the scope of options. The EIS appears to have concluded that a regional
approach is needed. The ALR is a provincial resource that suggests a provincial approach.
20.3.10.1.120-62
20-6328 – 41, 656
The discussion of improvements and support for agriculture to mitigate the permanent loss of
agricultural land refers to the Environmental Farm Plan Program (EFP) in several places as a
mechanism to fund activities. The concept of the EFP and its complementary Beneficial
Management Practices (BMP) program are a means of assessing a farm operation and the types of
activities that the farm should undertake to mitigate agri-environmental risk. A Site C mitigation
program should be designed to provide mitigation for the loss of agricultural production in a
broader sense, not the mitigation of agri-environmental risks in a narrow sense like the EFP/BMP
Programs.
20.3.10.1.1 20-64 1 – 38, 657
The list of projects the proposed fund may support presupposes some ideas and may be best
generated with the agriculture sector as proposed in the document, at a later date. Perhaps higher
levels bullets provide enough detail?
20.3.2.1 20-34 1-3 658 Is this flooding from freshet/storm generated events?
20.3.2.1 20-34 1-3 659 Can mitigation not be put in place (i.e., dykes) to prevent this flooding?
Final April 4, 2013 312
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
20.3.2.1 20-34 5 660Reference is made in the text to a section 20.3.2.4 supposedly containing a summary table. Section
20.3.2.4 is missing.9.2.1 Geology, Terrain
and Soils
20.3.2.1 20-34 1-3 661The flood impact area has total area of 203 ha – what is the anticipated inundation depth and
duration that was used to calculate this?
20.3.2.1 20-34 1-3 662 What is the flooding risk and potential?
20.3.3.220-38,
39, 40all 663
Discussion of loss of by agriculture utility class needs more review.
20.3.4.1.2
20-41
(and 20-
71)
35 664
“Relocation of suitable quality soils” concept raises some considerable concerns. The
appropriateness of moving topsoil to areas without a good handle on the site specific
needs/concerns is questionable. It may make sense to salvage topsoil from areas that are going to
be flooded and store that soil for use in reclamation of temporary disturbance area. Invasive
species management will be critical. As noted in section 20.4.2 the use of topsoil for local
reclamation is more advisable than whole sale transfer.
20.3.4.1.2 20-41 37 665“will be implemented...” Discussion of how to apply compensation fund is premature.
20.3.4.1.2 20-42 2-27 666
Has BC Hydro considered providing hydrants for water access by agriculture, fully realizing that
there would be water licensing issues to sort out? This could be similar to the water stations at
Blackfoot park, on the Peace at the Clayhurst Bridge.
20.3.4.1.2 20-42 2-27 667The hydrant water access idea applies not only to irrigation, but for many other agriculture uses,
such as crop spraying, livestock watering, etc.
20.3.7.1.2 20-53 11-17 668 What will the process be to identify individual producers whose current practices are impacted by
wildlife?
20.3.7.1.2 20-53 11-17 669How will agriculture wildlife (including waterfowl) impact issues be attributed to dam construction?
Dam operation?
20.3.7.1.2 20-53 18-24 670How will crop maturity issues be addressed? Is it expected that crops or varieties suitable for this
land will change due to microclimate?
Final April 4, 2013 313
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
20.3.7.1.2 20-53 18-24 671How will impacts on producers(especially renters) be handled in terms of compensation and
assistance in education?
20.3.7.1.2 20-53 11-17 672
Please include discussion that construction activities may also affect the migration and movement
patterns of ungulates and wolves leading to increased agriculture wildlife conflicts through the term
of the project.
20.3.7.1.2 20-52 1 673
Table 20.28 Mitigation of Operation-Specific Effects Farm yard and field access - Is this also being
negotiated with rental land access issues? Specific examples like access to Peck’s bottom fields
currently in grain crops, and changes in access due to stream back up. Will site specific details be
worked out with the renter and owner?
20.3.7.1.2 20-53 11-17 674
The loss of habitat and changes in use may result in longer term wildlife depredation issues for the
region. Is there a mitigation strategy, and any linkages drawn with or to current compensation
program?
20.3.8.1
20-54
and 20-
55
11- 37
and 1 -
20
675
Please provide more discussion and evidence of how the term “Agricultural Utility” is defined and
how this relates to the discussion/interpretation of Land Capability and Crop Suitability and apply
those definitions to the land base. The discussion in these sections needs to be revisited.
20.3.8.4 20-57 1 676
Table 20.31 - The table omits all non-soil bound agriculture (including livestock or greenhouse)
operations. Future agriculture development should consider the impact of climate change and
population/market growth.
20.4.1 20-67 11-28 677It should be noted that wildlife impacts could occur during construction also.
20.4.1 20-67 11-28 678More discussion is needed about compensation for the adverse affect on economic opportunities.
20.4.1 20-67 11-28 679
Please clarify if agriculture land offers have been made for producers inside of the impacted area
(i.e. land for producers outside of the impact zone of equal value)?
Final April 4, 2013 314
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
20.4.1 20-68 680
Table 20.37: Please clarify who manages “agricultural compensation fund in evaluating and funding
irrigation and drainage improvements and in evaluating and funding other opportunities to increase
production on remaining lands”?
20 68 681Please clarify if it is expected that micro-climate will affect downstream operations
20 68 35 682Please clarify if it is expected that water levels will affect downstream operations.
20 68 35 683Please clarify if the quality of quarries and other material site been inventoried for invasive plants
presence.
21 684There is no mention of soils in this section. 9.2.1 Geology, Terrain
and Soils
21 8 / 13 33 / 32 685
Correction - The Timber Supply Review for the Dawson Creek TSA is anticipated to be complete in
2013 and the Timber Supply Review for Fort St. John is anticipated to start in 2013.
21 1 18 686
Correction: Section 8 (1) of the Forest Act stipulates that the chief forester must determine an
allowable annual cut at least once every 10 years after the date of the last determination, not 5
years as indicated in the EIS.
2121-1 to
21-19All 687
Mill capacity and harvest trends are presented with the indication that the merchantable volume
cleared from the Project area can be utilized by the existing timber processing facilities. Please
provide additional information on BC Hydro's contingency plans to utilize or dispose of
merchantable timber volume should exisiting facilities not be able to fully utilize merchantable
timber volume harvested as a result of this project.
Section 21 - Forestry
Final April 4, 2013 315
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
2121-1 to
21-19All 688
There are some errors noted in Table 21.8 in the total volume under licence in both the Dawson
Creek & Fort St John Timber Supply Areas that require correction. Updated information is available
from the Ministry of Forests Lands and Natural Resource Operations upon request.
21.1.3 2 1 689
PTable 20.1 (line 5 of table) – Regional food self reliance is included, but it does not appear that ag
products exported from the region are dealt with. Please clarify and provide rationale for this
approach.
21.3.5
21-10
to 21-
11
All 690
Please ensure that section 21.3.5 is reviewed for changes resulting from updates to table 21.8
based on updated information provided by the Ministry of Forests, Lands and Natural Resource
Operations.
21 All 691 Throughout - Correction - AAC is Allowable Annual Cut (not annual allowable cut)
22.1.2 3 1 692a) Has BC Hydro confirmed that all well heads are above the new water level, and that any wells
that are to be inundated are appropriately sealed?
22.1.2 3 1 693
Has BC hydro or contractors completed geotechnical assessment work to understand whether any
wells, sealed in the vadose zone, would remain sealed once the surrounding sediments were
saturated?
22.1.2 3 1 694
On Table 22.1 the key issue that “the project would limit fracking activity in the vicinity of the Site C
dam site due to seismic concerns” lists an approach that BC Hydro would not request restrictions.
Whether BC Hydro requests restrictions in fracking may not address the key issue. Has the OGC
been contacted to satisfy whether fracking could be safely conducted in the vicinity of Site C? Has
BC Hydro evaluated whether normal faults and deep seated basement faults could interact with
hydraulically generated fractures? If so, what would the impact be?
Section 22 - Oil, Gas and Energy
Final April 4, 2013 316
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
22.1.2 3 1 695
There are deep seated basement faults in the area that appear to control the geography of the
Peace River. Saline aquifers underlying the Peace River in this region appear to be significantly
fresher than elsewhere according to the Geoscience BC Montney Water Project Aquifer study of
2012 (http://www.geosciencebc.com/s/Report2011-11.asp). Has BC Hydro evaluated whether
raising the water level will drive fresh water into to saline aquifers? If so, what, if any would the
impacts be?
22.3.1 8 17 - 18 696
According to Canadian Association of Petroleum Producers, oil and gas industry expenditures for
the previous 8 years, not including 2009, totalled $37 billion, not $30 billion as indicated. - Please
correct
22.3.2 9 5 - 7 697
Correction: The Montney now accounts for almost 43% of BC’s total daily gas production, not 26%
as indicated. - Please correct
22.3.3 9 10 - 21 698
Note comment made in Volume 2, Section 11.3 regarding separation of Oil and Gas Commission
(OGC) permits and approvals discussed in this section (surface tenures) versus Ministry of Energy,
Mines and Natural Gas-issued title (subsurface).
The well and facility information in this section (Section 22.3.3) contains some errors in interpreting
the OGC data sources: wells with the status “wag” in the OGC database are Not water-air-gas
injectors. They are wells that have well authorization granted (“wag”) but have not yet been
drilled. This results in more wells being identified than physically exist (Figure 22.3). OGC data
indicates NO Wells with ground level elevation below peak reservoir level elevation +461.8 m,
rather than the one well identified. Communication with the OGC is recommended regarding OGC
approvals, well and facility data, and surface tenure to land.
22.3.4 9 28 - 29 699
Clarification to correct intent of this information: All subsurface titles that fall within the Site C
Order-in-Council reserve are both advertised and issued with caveats advising of this, and these
caveats adhere to the titles throughout their duration.
Final April 4, 2013 317
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
22.3.5 10 7 - 8 700
Clarification regarding accessing coalbed gas resources by directional drilling in future: A directional
drilling technique known as “slant hole” drilling may be used over moderate lateral distances
(approximately 600 metres) to access thick coalbed gas-bearing coals beneath the flooded area,
from the north bank of the river. Due to the great thickness of the coal measures, horizontal
drilling is not applicable; however slant holes can cross all the coals in the objective zone, with
lateral reach limited by the relatively shallow depths of the coal measures.
22.3.7 13 15 - 25 701
Clarification and correction of detail regarding outlook for oil and gas development affected by the
proposed Peace River – Boudreau Lake protected area, the Peace Moberly Tract (PMT - MEMNG
Information Letter TITLES-08-08), and the Area of Critical Community Interest (ACCI) -
http://www.ilmb.gov.bc.ca/slrp/srmp/north/peace_moberly/index.html:
Directional drilling to access existing subsurface title under the proposed Peace R - Boudreau area is
currently allowed (MEMNG Information Letter EMD99-01) and this policy is expected to continue if
the area becomes designated protected or a park. Development of a Sustainable Resource
Management Plan in the PMT or the ACCI may result in acceleration of subsurface oil and gas title
disposition and drilling. In this case the Montney Formation is expected to be developed by
horizontal drilling from multi-well pads.
22.3.7 13 5 - 8 702
Clarification: Development has curtailed in many regions in northeast British Columbia, but activity
within the Montney has remained relatively steady because of the liquids-rich potential.
22.3.7 13 5 - 14 703
Clarification: Lower natural gas prices over the past three years have reduced dry natural gas
activity in Alberta and parts of BC, but investment and activity has remained strong in a number of
areas in British Columbia’s Montney play that contain natural gas liquids (NGL).
22.3.712 &
13
29 - 22
and 1
- 4
704
Please provide the most recent National Energy Board and British Columbia Ministry of Energy,
Mines and Natural Gas estimates of undiscovered remaining conventional natural gas, and of
recoverable or marketable unconventional natural gas in the Montney Formation. These figures are
important to demonstrate the value of these resources to backstop the proposed mitigation
solutions.
Final April 4, 2013 318
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
22.3.7 12 33 705
Table 22.8 - Updated CAPP number for remaining established reserves of Natural gas liquids (2010)
in British Columbia is 28,900 Thousand m3. Updated CAPP number for BC’s remaining established
reserves of Pentanes plus (2010) is 11,000 Thousand m3. - please correct
22.4.1 14 10 706
An apparent error appears on line 10: Oil and Gas Commission (OGC) data indicates NO wells with
ground elevations below the peak reservoir elevation +461.8 metres.
Communication with the OGC is recommended regarding OGC approvals, well and facility data, and
surface tenure to land. Note: Six wells, eight facilities, and 2.9 hectares of pipeline-right-of-way
exist within the Local Assessment Area
22.4.1 15 21 - 22 707
Request: Please include mitigation measures for oil and gas companies tenure holders adjacent to
the LAA. The proposed mitigation measures would apply to tenure holders within the LAA.
However, mitigation measures may also be required to address impacts to oil and gas companies
who hold tenure adjacent to the LAA and use Hwy 29 and the other petroleum development roads
in the area to access their lands. These companies may also be impacted by change in land use
associated with the development and construction of the Site C dam project.
22.4.1 13 37 - 39 708
While the proponent recognized the current status of oil and gas activity in the LAA, it should be
noted that current development in the area has been postponed due to low commodity prices.
When gas prices increase and/or LNG projects move forward as planned, gas development and
production activity will significantly increase. Realignment of Hwy 29 and the construction access
roads will have significant impacts for industry, in terms mobilization time and costs, and potentially
the pace and cost of development.
22.4.2 and
22.8
14, 15
& 19
31 – 41
1 – 19
25 – 35 709
Affect on Spectra Energy water intake in the Peace River, due to changes in water temperature as
well as increased suspended sediment : Increased river temperature will increase the number of
days Spectra Energy will be required to reduce operating capacity. Has BC Hydro developed a plan
to mitigate economic losses to Spectra Energy incurred from increased water temperature?
Final April 4, 2013 319
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
22.4.4
15, 16,
17 &
18
30 – 38
1 – 27
1 – 12
8 – 11
710
Impacts on drilling access to subsurface title, proposed mitigation of these impacts by directional,
horizontal, and slant-hole (for coalbed gas) drilling are addressed in previous comments on Volume
3, Section 22. However, has the Oil and Gas Commission (OGC) been interviewed and supplied
comments regarding impacts on, and proposed mitigation solutions for, the surface activities that
the OGC regulates?
23 711
There is an outstanding question as to the specific requirements for BC Hydro's quarry/aggregate
extraction operations that will need to be addressed during the following Mines Act stages: Notices
of Work (NOW), Mine Permitting, and Reclamation Bonding. BC Hydro will need to work closely
with MEMNG Inspection and Permitting staff to discuss Mines Act Permitting and Inspection
options and considerations.
23 712
Please consider adding further detail on how extraction operations will be designed, operated and
reclaimed (e.g., Portage Mountain Quarry's pit slope, drainage, reclamation, etc.)
23 713
The EIS states that there were, "no mineral tenures in the LAA" (local area assessment).
It is MEMNG review indicates Coal and Mineral Tenures in the LAA. It is suggested that BC Hydro
conduct a final check against the tenure map and documentation as highlighted in comments made
in relation to EIS Section 11.3.4.
23 714
It should be noted that there are a few coal reports that fall within the Site C Project Area, These
Include report 894 (Knnecott) in the Farrell Ck Watershed that concluded seams were not
economically viable from a single drill hole. Also of note is report 577 (Cinnabar Peak Mines) for an
open-cut mine at Peace River Canyon.. It is worth noting that estimated cumulative coal
thicknesses of 14 to 18 meters and might be worth further comment within the EIS. Further
information is available on request.
Section 23 - Minerals and Aggregates
Final April 4, 2013 320
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
23 715
There is an outstanding question about the application of regulatory requirements as it applies to
mining/quarrying for private, Ministry of Transportation and Infrastructure (MOTI) and BC Hydro
mining operations for this project. Addressing the issue of tenure, ownership, permitting,
reclamation, safety and the regulatory oversight of mining will be required during the course of the
Project. BC Hydro should work closely with MEMNG Permitting and Inspection staff to address this
issue and add further information to the EIS where appropriate.
23.1.1 1 16-35 716
Discussion of Acts – There is no mention of the BC Hydro Authority Act. This should be included as
it may have impact on applicability of other legislation.
23.1.4 4
Ln 7,
Table
23.2
717
“Identifies the Volume of aggregate that may be for other applications ” From Vol 1, Appendix C:
yield rates in quarries are as low as 20%. Please include discussion on the quality of material that
will be left for others and provide rationale.
23.3.1 7 7-9 718
“...at the 5% confidence level (a low level of confidence) occur in the LAA (Kilby 2004). At the 90%
confidence level (a high level of confidence), there are no deposits indicated.” Please provide the
standards or guidelines used.
23.3.4 10 4 719
“Future pit development...” Please clarify if this future pit development is for the project of for the
“Total aggregate consumption” of the previous paragraph. “...over the next two decades...” Please
provide rationale for this timeframe (Eg: MOTI plans for 50 years.)
23.4 23 11 720(Ln 9 “The first two aspects...” appears to refer to the 1st and 3rd aspect.) - this appears to be an
error, please correct.
24.1.1 2 18-40 721
All the changes listed in this section are related to the “use” of the resources. Even though the
“supply” aspect of the resource may have been dealt with in another section, it should still be
recognized and mentioned here that potential adverse effects will also impact the “supply” of fish
and wildlife populations, not only their “use”.
Section 24 - Harvest of Fish and Wildlife Resources
Final April 4, 2013 321
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
24.1.1 3 27 722
Another important consideration is the replacement of river habitat for high-throughput reservoir
habitat. A survey of current users may indicate a lower perceived value of reservoir habitat, so that
the two areas are not weighted equally, meaning a significant VC loss overall. LGL 2009 (and
roughly, table 24-7) indicates that the vast majority of fishing effort is currently upstream of Site C.
To answer this properly, a proper stated preference survey (or some similar method) would have
been useful
24.1.1 3 10 - 12 723
The does not appear to be supporting evidence for statement “not anticipated”. Suggest it should
be “unknown”. Angling may in fact be a very attractive recreational activity for a workforce that will
stationed in camps at the project site.
24.1.1 4Table
24.1724
Second “Key Issue” under “Hunting Opportunities” should also include “and those non-game
populations which impact game species”
24.1.2 5 14 725
Statement is made that a Traffic Management Plan will mitigate effects on fish and wildlife harvest.
Looking at the plan in Vol 5 Sec 35 (pages 35-6 and 35-7) this plan deals solely with mitigating
impacts on wildlife from traffic-related causes. Wildlife harvest may also be impacted by increased
access into previously inaccessible areas. Wildlife harvest will still go on based on hunting
opportunities created within the regulatory framework, minimizing road mortalities does not
mitigate fish and wildlife harvest.
24.1.2 5 7 - 14 726
The text refers to Table 2 of Vol 2 Appendix A having rankings of 0 and 1. Looking at Table 2 it has
rankings of 0, 1, 2 and n/a. These rankings are not explained in the table, at least 2 and n/a are not.
24.1.1 5Table
24.2727
Under “Project Component and Activities” Hwy 29 realignment and worker Accommodation
Construction and Operations are not identified as impacting changes in fishing opportunities. This
may not be the case, please provide additional rationale to support this statement
Final April 4, 2013 322
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
24.1.1 7Table
24.3728
It is unclear whether BC Hydro is going to examine spatial shift in effort or even if effort on the
Peace River in general is maintained (in terms of angler days). You may be able to maintain effort in
the region, but it may be spatially shifted to smaller populations (i.e. in lakes), potentially leading to
collapse of other, more vulnerable populations
24.1.1 7Table
24.3729
Please clarify if creel surveys are going to be conducted to monitor the change in catch
composition and effort.
24.1.3 7Table
24.3730
Please clarify if First Nations harvest levels for food and ceremonial purposes where considered as
an indicator, and provide rationale why it was excluded
24.1.3 7Table
24.3731
Under “Key Aspects” the “Opportunities” are being measured by metrics such as license sales,
trapping returns, etc. This approach is incorrect; many of these metrics are affected by a variety of
factors which may have little to do with opportunities or potential for harvest or recreation of fish
and wildlife resources. The table assumes a direct and causal relationship between “opportunities”
and current utilization.
24.2.3 9 40 732
You state that LGL 2010 includes information on spatial distribution of angling effort, but is not
reported, please include.
24.3.2.2 22Table
24.11733
Percent change figures in the last column do not appear to be correct, and it’s not clear if that
change is supposed to be calculated for the years 1999 and 2010.
24.4.1.2 30 39 734
Harvested fish are those that have been removed from the system, so yes, there won’t be an effect
on them, but there will be an effect on those fish that are still in the river. Perhaps what is meant
here is game fish populations. Please clarify
Final April 4, 2013 323
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
24.4.2 31 27 735
Please clarify what is meant by changes in “public fishing areas”. Is it the number of public access
points or area of access points?
24.4.2.1 31 39 736
“Good navigational opportunities to support fishing” – unsure what this means, there will be more
surface area of water in the reservoir, but increased erosion may decrease the access to shore for
fishing-related activities (ex. angling from shore, camping, etc.). Please explain.
24.4.2.1 31 34-35 737
Given that a “fishing area” has not been defined, it’s not clear how the reservoir would provide new
ones both from the water and shoreline. Presumably there are many fishing areas from the
shoreline right now, and an even greater number from the water. There will be “new” areas
because it will be a totally different ecosystem, but that does not provide a quantitative measure of
this descriptor.
24.4.2.1 32 15 738
It is assumed that all fishing areas are equal, but while there will be an increase access to fishing
areas in general, access to highly used river fishing areas upstream has been removed, which may
be of intrinsically higher value to anglers than the reservoir. Due to its importance to the
community, this should be addressed and acknowledged
24 32 16 738
“In summary, the Project would result in a beneficial effect on fishing areas during operations.” -
this statement requires further rationale to support it in light of the identified effects or the project
that indicate otherwise.
24.4.2.2 32 24 739
Again, each species has been weighed equally, which is misleading. Surveys of anglers for species
preference and relative access to different species within the LAA may indicate that species whose
biomass decreases (such as walleye) may have a higher weighting than others, meaning that
although biomass increases, the total value of harvestable species declines. It may be that users
(anglers) will find that the new harvestable community is preferable to that in place now, Please
provide additional information to support the weighting.
24.4.2.2 32 30 740Consideration should be given to relative weighting of species and the weighting of how far and
where anglers want to travel to access various species
Final April 4, 2013 324
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
24.4.2.1 32 11-14 741
Please qualify the statement “supports a wider variety of boats”. There may be new ice fishing
opportunities, but at best they may replace open water fishing that occurs presently during winter.
24.4.2.1 32 15-16 742
Please provide further rationale for this statement, and clarify what the metric used is.
24.4.2.1 32 6, 7 743Angling opportunities may not change, but angling pressure will be concentrated in certain
locations due to structures and restrictions.
24.4.3 33 13 744
What is the impact of trap and haul activities on fish populations, particularly bull trout? It is
understood from the Columbia is that survival is lower than other methods of bypass
24.4.4 33 26 745
Please clarify what is meant here, is it number of areas for hunting, access to them, etc.?
24 33 5 - 8 746
Please replace ...will mitigate...”
with “...will aid in mitigating...” as this statement implies that the identified mitigation measures
will be 100% effective.
24.4.4.1 34 20-21 747
Unclear statement, presumably if new roads are created, there would be changes to hunting
access.
24.4.4.2 35 5 - 6 748
Unclear of how the statement about current harvest level is related to displacement of ungulates
by construction activities.
24.4.4.2 35 8 - 11 749
Please clarify why black bears are excluded from large carnivores. Also, please explain what is
meant by “additive effect”, is this trying to portray an increase in numbers?
24.4.5.1 35 27-29 750
Full boater use assumes unrestricted access to the whole reservoir shoreline, This will likely not be
the case and should be clarified in the EIS.
Final April 4, 2013 325
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
24.4.7 36 26-28 751
The term “population” in this case refers to human population, this was not evident until confirmed
by looking at the referenced report, adds ambiguity if not properly described.
24.4.7 37 13-15 752
Please clarify the spatial boundary that the Peace Region is meant to describe. Is this governments
(NRS agencies) administrative boundary. This conflicts with figures from Table 24.13. Please clarify
24.4.7 37 21-22 753
Please clarified how positive is measured in this instance.
24.4.8 37 24-28 754
Increased participation in hunting and harvest due to the project may result in regulatory changes
by the Ministry. Mitigation measures for this are not being considered because increased
participation is seen as a Ministry goal. However, in this case there is no choice of where the
increased participation is occurring and it may not be compatible with wildlife population levels.
24.4.9.1 38 18 755
Please clarify which regulatory tools will BC Hydro anticipates being used to restrict trapping.
24.5 451, Table
24.21756
There will not necessarily be a net positive increase in the VALUE of harvestable fish during
operations
24.5 48 3 - 6 757
The conclusion are not well supported. The use of "Beneficial” is subjective and not referring to any
specific aspect. There is no guarantee that fishing opportunities will increase, some aspects of
fishing will change, but opportunity is also used subjectively here. And it’s important to note that
the term “baseline conditions” implies that we’ll have the same ecosystem after the flooding, with
directly comparable attributes when in fact we have a river ecosystem before flooding and a
reservoir ecosystem after flooding.
Final April 4, 2013 326
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
24.6.1 50 3 758
As a whole, the changes to public fishing areas and harvest may be within historic norms, but when
weightings are placed on various species and the relative access to get to them, there are certainly
significant changes outside of historic norms (i.e. some species will be lost in some areas).
24.6.2 53 25 759
As considered in the previous section, it is possible that anglers will move to other fishing
opportunities in response to changes in the harvestable community. This could potentially result in
changes to the regulations in those other areas (although they may be outside the Peace River) to
protect them from overharvest, which could be perceived as crossing the significance threshold.
24 all 760
Spatial information on effort and harvest has not been included. Please consider providing this
information if available.
24 all 761
Please provide rationale for the assumption that a reservoir is of equal value to anglers as a river.
24 all 762
Values differ between river and reservoir habitat. Similarly, there is higher value in catching a bull
trout than a kokanee, but overall harvest is the value examined. Talking to the resource users about
their perceived valuation of these components would be useful (and relevant), and could by used to
further define the VC's
25 1 36 763
List of legislation on this line should also reference the Forest and Range Practices Act.
25 1 39 764consider replacing "approved and established" with "Authorized"
Section 25 - Outdoor Recreation and Tourism
Final April 4, 2013 327
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
25 2 18 764
“...Changes in outdoor recreation and tourism infrastructure including:...” - Consider including
identification of the impact the dam structure to “Water travel passage” as a bullet under this
heading.
25 30 17 765“Boat access restricted permanently at the Site C dam site for safety reasons” Reference should be
made to specific figures in section 26 Navigation (26.4.1.1) for clarity.
25 32 38 766
“...shoreline recreation within the Peace River and tributaries through to the Alberta...”
Consider re-wording to: “...shoreline recreation within the RAA, Peace River and tributaries
through to the Alberta...”
25 33 16 767
“The involvement of Aboriginal groups is also supported” Suggest also including other groups such
as Provincial Government agencies, local governments and user groups.
25 33 23 768Please Clarify - identified hunting camp on private or Crown Land? If on Crown Land is this a
tenured interest that will be impacted?
25 33 6 - 9 769
While mitigation for loss of recreation opportunities and impacted sites are identified in the EIS, it
appears that the majority of the identified mitigation will not come into effect until after
construction of the project is complete. Impacts to recreation will begin to occur as soon as
construction of the Project is initiated, and will persist throughout the muli-year construction
period. Has BC Hydro identified mitigation measures to offset impacts to recreation opportunities
during the construction period of the project? If not please include discussion of this in the EIS.
25.5 36, 37 N/A 770
The mitigation proposed in Table 25.17 is not considered to adequate to offset the proposed
removal of 28 river-based recreation sites within the LAA and the change in current recreation
opportunities from river-based recreation to reservoir-based recreation, especially considering the
Recreation Plan is to be funded but not implemented or monitored by BC Hydro, and no ongoing
monitoring to evaluate the effectiveness of the mitigation is proposed. To increase the success of
the mitigation strategy, BC Hydro should consider broadening the area where the fund could apply
to allow for development of alternative river-recreation based sites in the South Peace. BC Hydro
may want to also consider implementation and monitoring of the plan to evaluate the effectiveness
of the mitigation and an alternative strategy should the mitigation be determined to be
unsuccessful.
16.7.3
Final April 4, 2013 328
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
26.1 26-1 1 771Table 26.1 mentions vessel clearances for navigation for Highway 29 bridges. Does the pipe-arch
structure at Dry Creek on Highway 29 also need navigable clearance?
27.2.2 3 3 772
This paragraph makes reference to the Project Interaction Matrix found in Table2 of Vol 2-App A,
which shows the Project Activities that were ranked as “0” i.e. not interacting with visual resources,
including the activity “Right-of-way vegetation maintenance” shown on p.11 of the appendix.
Depending on how this maintenance is carried out, it could impact the visual resources so the “0”
ranking may not be appropriate for this activity. Transmission line corridors are permanent features
on the landscape and the usual harsh straight boundaries used for the clearing soften over time
with the growth of vegetation by reducing the contrast in shape and colour. Eliminating all the
vegetation using herbicides simply re-create the same visual impact over and over. A better
alternative from a visual impact point of view is to eliminate only the deciduous and coniferous
trees and leave as much of the shrubs/ground cover intact. Please provide additional information
on how this activity will be carried out and re-assess its ranking and mitigation measures in light of
the comments above. If alternative measures need to be taken, keep in mind that these would
apply only to the portions of the transmission line corridors within the scenic area polygons found
on the Ministry’s Visual Landscape Inventory data warehouse.
27.2.3 3 8 773
The 5 receptor sites chosen as key indicators are fine but their number and coverage are
insufficient. All are from Highway 29 and none offer views to the dam site itself, unlike what is
stated in Table 27.3. Recommend two additional Receptor Sites be added: one on the reservoir
upstream from the proposed dam and one just downstream. These water-based points are
accessible to the public so should be considered valid for analysis and visual simulations.
Section 26 - Navigation
Section 27 - Visual Resources
Final April 4, 2013 329
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
27.3 4 24 774
For clarity, please consider rewording the sentence starting on line 24 as follows: "Visually
Sensitive Areas are areas of specific concern for visual quality and usually include ratings on their
Existing Visual Conditions.”
27.3 4 24 775
The baseline viewpoints were selected from the Visual Landscape Inventory (VLI) but none of the
viewpoints selected in the EIS include the VLI viewpoints on the Peace River. When the VLI was
completed in 1996, it was done not only from Highway 29, but also from the Peace River by jet
boat. These viewpoints are shown in the provincial VLI database but were not included in the EIS.
Some of these key river viewpoints should be added to the baseline viewpoints and analyzed similar
to how the ground-based viewpoints were treated.
27.3 4 31 776should more sites be added, the number of receptor sites and Figure 27.3 will need to be updated.
The same adjustment needs to be done on page 27-11, line 7.
27.3.1 5 15 777
This sentence is not technically correct and should be clarified. The VLI does provide ratings for
Existing Visual Conditions (EVC) but not for "each" Visually Sensitive Area. Only those polygons
inventoried in the field are rated for EVCs, among other things, like the ones on the south side of
the Peace River. The proponent should be aware that field mapping was only originally done for
the south side of the river and broad visual polygons on the north side of the river were added later
as an office exercise based on contour line interpretation as the Peace River viewshed was deemed
important by river users and various planning tables. Although broad in nature, these Visually
Sensitive Areas have the same legal status as the detailed areas inventoried in the field. Since these
broad polygons have no rating under the EVC field, it appears that they were inadvertently
excluded when producing the map in Figure 27.2 which is likely to create confusion. Please add the
missing polygons to the map and add a new entry in the legend explaining that no EVC ratings are
available for those broad polygons.
27.3.1 Table
27.55 21 778
The wording in the table was slightly modified compared to the source document it makes
reference to, please restate the caption at the bottom of the table to say: "Source: Adapted from
BCMOF (1997)".
Final April 4, 2013 330
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
27.3.1 5 23 779
Please add a caveat to this paragraph explaining that using the EVC ratings as an input to the
baseline description do not present the complete picture of the existing visual condition since many
of the ratings are missing from the VLI. Equally important is the fact that the EVC ratings that are in
place represented the visual conditions in 1996, so the conditions have likely changed in the past 17
years.
27.3.2 Table
27.67 1 780
Should water-based viewpoints be added as requested, the baseline viewpoints listing will need to
be updated accordingly.
27.3.4,
Table 27.79 N/A 781
This table is intended to provide the definitions of the VQO ratings used by the Province of BC and
makes specific reference to the source document where these definitions are coming from and so
the wording should not be changed. It is also noted that these definitions are the old VQO
definitions used under the Forest Practices Code. The source document referred to in the text is
the old Visual Impact Assessment Guidebook that is currently being updated. Since 2004, the legal
VQO definitions that are entrenched in FRPA's Forest Planning and Practices Regulation, Section 1.1
have been used. These are the definitions that must be used in the table, verbatim.
27.4 10 2 782
The text states: "Prominent hills are found in the southwest, with Portage Mountain (located 1 km
west of the LAA) being one of the most noticeable topographical 1 features (see Figure 27.2)". It is
not indicated on the map where Portage Mountain actually is.
27.4 10 40 783
In reference to other comments on this section, this sentence should be revised, suggest the
following wording: "Accordingly, the Visual Landscape Inventory determines Visual Sensitive Areas
on the southern slopes of the Peace River Valley as seen from Highway 29 and the Peace River and
on the northern slopes as approximated from the Peace River." also, please replace the "Halfway
River" with "Moberly River" as a valley within the LAA where there is a Visual Landscape Inventory
in place. There is a section of Halfway River mapped but it is significantly north of the project area.
27.4 11 1 784This paragraph should also describe the established VQOs situation on the northern slopes of the
Peace River.
Final April 4, 2013 331
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
27.5 11 10 785As a general comment for the entire section, the text will require updating should receptor sites be
added to the reservoir and river.
27.5.1.1 11 33 786
There may have not been any ground-based receptor sites with a line of sight to the Site C dam but
by adding water-based viewpoints near the proposed dam those views would be provided. This
sentence should be deleted should sites be added.
27.5.1.3 12 34 787
This kind of prediction is receptor site dependent and since boaters will be on the reservoir, the
Hudson's Hope shoreline protection project would be visible. Recommend the proponent assess
potential impact on visual resources even if an activity is outside a Visually Sensitive Area.
27.5.1.7 14 6 788
The EIS States "The resulting visible disturbances would be rated as acceptable for an established
visual quality objective of “modification”, since they could dominate the views in the short term."
Please clarify if consideration has been given to the long-term. Has consideration of this issue been
given to reclamation and rehabilitate plans for quarry and pit sites?
27.5.2.1 15 9 789
Please consider providing visual simulations of the proposed Site C dam site and its surroundings
from various locations as all that appears to be available at this point is the bird’s eye view
simulation shown on the cover of the EIS documents.
27.5.2.2 15 47 790Please consider adding the following statement to this sentence: "... and from the reservoir itself as
seen by boaters."
Final April 4, 2013 332
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
27.7.3,
Table 27.1122 18 - 24 791
As currently identified in the EIS, the determination that the effects of the project on visual
resources are not significant is not supported. Request that the proponent revisit its assessment of
the significance of the effects of the Project on visual resources for the following reasons.
1. Inundation of a portion of the landscape and the addition of major structures to it such as dam,
generating stations, transmission lines, and other related components will significantly and
permanently alter the current landscape
2. The use of only 3 of the 9 criteria to characterize the residual effects on visual resources to make
a final decision on significance has not been adequately rationalized. In the EIS the proponent has
rated the Direction criterion as being "adverse" i.e. the project is worsening the condition of the VC
compared to the baseline conditions and trends. Other sections of the text have also indicated that
the acceptable level of disturbance would be exceeded in certain areas in reference to the VQO
definitions and that scenic values would be lowered.
3. The 5 receptor sites selected are limited in coverage and do not take into account views and
baseline viewpoints from the Peace River itself and future reservoir.
Final April 4, 2013 333
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
791
Comment Continued
4.The statements concerning existing anthropogenic disturbances (including industrial
developments in the LAA) and social context referring to an environment previously disturbed by
human development require further discussion and rational. The presence of existing
anthropogenic disturbance in the area does not necessarily mean that the addition of this project
would not add significantly to the already disturbed state of the project area. This is very similar to
the Visual Absorption Capability (VAC) rating that is assessed for each visual unit. As an example
Natural or human-made openings on a landform make it easier to add a cutblock because of the
higher VAC but there is still a threshold to respect, which is expressed in the form of the VQO set
for that landform. It is not clear that a defensible disturbance threshold has been established for
the Peace River corridor and that the disturbance created by the Project would fall within those
thresholds. Additional detail explaining how existing versus forecasted disturbances will be
rationalized should be added or the section should be revised accordingly.
As currently identified in the EIS the determination that the effects of the project on visual
resources are not significant is not supported.
27.6, Table
27.8
16 &
171 792
As correctly stated in this section, the project construction and operations phases will create
changes to the visual resources. The construction of the Project features and a number of its
components will undoubtedly alter the existing condition of the landscape. The re-alignment of
Hwy 29 and the reservoir itself will create new viewing opportunities while others will be
eliminated. The actual extent of these changes will have to be assessed by re-doing the Visual
Landscape Inventory of the Peace Valley corridor. The proponent has identified no mitigation
measure to assess the actual changes to the landscape in the field after project completion.
Request that BC Hydro provide funding as mitigation for this impact to undertake the Visual
Landscape Inventory after project completion. Such funding has been proposed for other VCs such
as Vegetation and Ecological Communities, Wildlife Resources, Navigation, Heritage Resources, and
Outdoor Recreation and Tourism. It would be appropriate to extend similar funding measures to
the Visual Resources VC so that past investments by the Province are not lost.
Final April 4, 2013 334
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App C3 3 24 - 29 793
For additional information and clarification regarding the caveats attached to posted parcels in
Project area: If a parcel is south of the Peace River in the Area of Critical Community Interest ACCI -
http://www.ilmb.gov.bc.ca/slrp/srmp/north/peace_moberly/index.html
then it will have a caveat advising of consultation requests from Saulteau and West Moberly First
Nations; if a Sustainable Resource Management Plan is developed within this area in the Peace
Moberly Tract (PMT - MEMNG Information Letter TITLES-08-08) parcels dispositions may resume
with caveats attached to parcels.
App C3 1 22 - 25 794Note that Canadian Association of Petroleum Producers drilling activity numbers in Table 1 differ
from the Oil and Gas Commission’s official drilling activity totals.
App C3 3 18 - 19 795
Request wording change for clarification and correction, as explained on page 4 of same document:
“drilling licences, conveying the exclusive right for permission to drill wells exploring for oil and gas”
Delete reference to “in a defined area” because a drilling licence may contain only certain zones
and other title may exist in the same area.
App C3 3 7 - 9 796The area of the Montney play region in NEBC is 26,412 square kilometres, not 7,669 km2 as
indicated. Please consider correcting
App E 4 797
In addition to the objectives that were considered in the development of the Project's Outdoor
Recreation Mitigation Plan, please consider adding mitigation to enhance Family Friendly Fishing
opportunities (i.e., fish stocking program, fishing facilities/docks, learn to fish program) inside the
RAA, for the lost opportunities during construction and water and shoreline based access
restrictions.
Figure
27.1,27.2,
27.3
N/A N/A 798
It is unclear in the legends of these 3 maps what the small red polygon just south of Boudreau Lake
is supposed to represent. Please correct or discuss.
Volume 4
Section 28 - Population Demographics - Not Reviewed
Final April 4, 2013 335
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
31 31-18Table
31.12799
District sideroads: Please ensure that all permits are in place on district side-roads for work within
right-of-way not being commissioned by MoTI. For example; the conveyor belt, improvements to
Old Fort Road.
31 31-18Table
31.12800
85th Industrial Lands: There are currently MoTI RoW within the extents of where BC Hydro will be
extracting gravel. MoTI would like to define a permit and agree to what the RoW will be left as
following reclamation of the lands.
3131.3.1.
510 801
Are there any roads the BC Hydro requires year-round that are not 100% during spring?
31 31-45Table
31.29802
BC Hydro will monitor fog in the area, especially near Taylor, but what are mitigative measures?
And what is the warrant threshold for action?
31 31-18Table
31.12803
Chetwynd: please address concern for turning movements into Canfor Sawmill on H29 and
increased traffic on H29 causing delays. There is also local concern from District of Chetwynd over
left turn lane length from H97 to H29. (Maybe signal timing could be considered).
3131.3.1.
510 804
Does BC Hydro predict the need to haul overweight (greater than 100% axle loading) on any road,
including numbered highways, during the course of the construction project?
Section 29 - Housing - Not Reviewed
Section 30 - Community Infrastructure and Services - Not Reviewed
Section 31 - Transportation
Final April 4, 2013 336
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
31 31-18Table
31.12805
H97 - South Taylor Hill: Please note that the Ministry of Transportation and Infrastructure is
tentatively scheduled to 4-lane the bottom 2 kilometres of H97 - South Taylor Hill beginning in
Summer 2014, ending Fall 2015. Traffic delays could be cause for concern for BC Hydro. The
Ministry may proceed with 4-laning the remainder of the South Taylor Hill during the construction
of Site C which could result in additional traffic delays.
31 31-18Table
31.12806
Maintenance: There are concern over BC Hydro expectations for summer and winter maintenance
on MoTI roads, especially sideroads. For example, will the level of expectation for winter
maintenance increase on Jackfish Lake Road? (currently a class ‘c’)
31 31-34 38 807Please clarify if BC Hydro is reviewing all intersections for illumination. What standard is BC Hydro
using as a warrant base?
31 31-18Table
31.12808
Please ensure all new right-of-way acquired during the projects are properly surveyed and
registered.
31 31-18Table
31.12809
Please include considerations for 100 Avenue between YXJ Airport and Fort St John. The MoTI
District is undergoing conceptual options review of this corridor in 2013. Increased traffic from
airport to town, combined with growth of corporate offices along the road could make this section
a point of congestion.
31 31-18Table
31.12810
Taylor Bridge: The steel deck on Taylor Bridge continues to wear, and requires a greater frequency
of repair. Possible construction delays or even re-routing of traffic in the event of an emergency
deck repair.
31 31-25 13 811
The EIS predicts level of service change at signalized intersection, but no comment is made of
mitigation efforts. This could be as simple as investigating signalized light timing. This should be
included in the EIS
31 31-2Table
31.1812
While in existence, would other industrial users or groups (such as the Ministry of Transportation
and Infrastructure) be permitted to utilize the temporary construction bridge for access across the
Peace River, or would it be restricted to BC Hydro use only. And if so, to what level.
Final April 4, 2013 337
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
31.3.1.5 14 10 813
The technical data report on Microclimate (Volume 2, Appendix K) indicates a rise of 1 degree
Celsius in average temperature within 1 km of the new reservoir. How much sooner will Regional
Road Restrictions likely have to be imposed on Hwy 29 and other roads adjacent to the reservoir
due to this higher temperature? If road restrictions on these roads need to be put on sooner, it may
put them out of sync with other roads in the area and lengthen the overall duration of restrictions
for industrial traffic.
32 814EIS Guidelines 32 - Please include further discussion of residual effects and how they will be dealt
with and mitigated8.5.3.2
32 815EIS Guidelines P24 Baseline description re and inventory are OK, but please provide further
description of context as well as synthesis: 8.2
32 816 EIS Guidelines P33 - Please provide a clear characterization of the residual effects 8.5.2.4
32 817EIS Guidelines p23: no real hypotheses or models have been presented and there are limited
discussion of gaps. Please consider addressing these issues.8.1
32 818EIS Guidelines P25 - Please clarify why a predictive model was used and if not why? If so, why was
it not presented?8.3
32 819
General Comments: Technical Merit -Generally looks OK for this level of assessment but as noted
missing any predictive models and needs follow up on specimen Identification.
Assumptions- Not well explained, in particular not sure exactly how the numerical values in
appendix C Table E were determined explicitly
Strategies -Too general, not enough discussion of which are best for which types of sites, see earlier
points, Discussion of residuals too brief to estimate how much effort and of what kind needs to be
applied to which specific sites
Gaps : Geological context missing, Predictive models missing, Specific mitigation strategies missing,
P32-28 line 23 mitigation strategy must include detailed geological strata mapping , Strategies for
residuals missing, Explicit explanation of ranking (Overall significance score) and certainty
percentage a few specific example calculations would help, P32-62 (32.4.3) seems inadequate as an
explanation
Section 32 - Heritage Resources
Final April 4, 2013 338
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
32 820
Please include a separate discussion of the occurrence of Quaternary deposits and fossils and
potential relationship to First Nations sites and resources, especially knowing the old age of nearby
arch sites such as Charlie Lake cave
32 821Please ensure a very thorough inventory and study of vertebrate remains is undertaken by
vertebrate paleo experts.
32 822
Please include an assessment of potential Quaternary deposits and section that might be impacted
thus providing an opportunity for microfossils studies (pollen spores diatoms etc.).
32 823
The report contains and great deal of data from varying sources and of varying quality. It consists
largely of field visit data and literature review, with limited consultation with experts, and pending
expert analysis of field collections. However more needs to be done to construct a mitigation
strategy and mechanism to deal with residual effects.
32.2 824
Field collections should be fully identified before preparation of final Paleontology report. Please
include further discussion and explanation of geological and stratigraphic and paleontological
context.
32.2 825
Baseline: Consider including synthesis of the paleontological resource in comparison to other better
known sites outside (uniqueness and quality) in the area and in context of the geological
framework. Please include a detailed map of sites and rankings of bedrock geology (including
lithological facies) would be very helpful to identify zones of high concern and likely impact, and
would help quickly appreciate the extent of impact.
Final April 4, 2013 339
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
32.4 826
Please clarify the following:
• What time period?
• Which sites provide best representation for each age? What kinds of fossils do they contain? At
which sites
• Summary occurrence and description of content of the sites, and are there representative of
other sites elsewhere in the region, on the continent ? globally?
• Characteristics of the site geology and exposure (see a Table 32-2 in Vol 4 p32-11 to help assess
indicators)
o physical characteristics (slope, extent): Kind of fossils found in the exposures and outside of
exposures (loose on the surface)
o Paleo characteristics: lithology, special features, abundance, quality of preservation
32.4 827
Request: all Class I and II sites that are likely to be inundated or destroyed, or at least a solid
representative sample (if there are duplications) need to have their stratigraphy and lithology
described and comprehensive fossil collections made for future study. The site may not be available
for study for many decades and even centuries otherwise. In this context if Class II sites on p32-29
require 20 % representative collections then Class I sites require at least this which is not suggested
(an oversight perhaps).
32.4 828
Please clarify how the index of “Overall Significance Score” (see page 11 of 108 I appendix E) was
derived. An example of how this can be done based on paleontologically important criteria was
used in the comparison of sites representing the McAbee beds of Eocene age in southern interior
BC. Without a more comprehensive context and analysis it becomes difficult to estimate the need
for resources for mitigation and certainly for dealing with adverse residual effects.
Final April 4, 2013 340
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
32.4 829
Request: please clarify the results by providing more context and data synthesis. Should include an
analysis of the paleontological significance of the LAA, or RAA compared to extra regional,
continental and global paleontology nor an analysis among sites (this site is a better representation
than that site or group of sites etc.) for a particular geological age and paleo-environment. Such an
analysis is fundamental in developing a ranking system.
32.4 830
Request: please include a clear statement of the need for these specimens to go into properly
curated facilities and the need for these facilities to be financially supported. The likely number of
specimens and space required for them will be large. Considering the likely residual effects,
probably thousands of specimens will need to be collected and these need to be collected by
professionals who also correctly describe the context (stratigraphy, lithology, distribution of fossils)
at each collecting site. Following, or in tandem with construction activities, monitoring and
presumed collecting as impacts occur will generate additional material.
32.4 831
Request: please include a description of the regional Paleontology through the interval represented
by the sites in the Site C area, certainly those in the LAA and RAA.
32.4 832
Request: please include greater context and comparative assessment and develop more specific
mitigation and residual effects analysis.
32.4 833
Request: The large clusters of Extreme Sensitivity sites (Figure 4.5) need to be individually
identified, characterized and analyzed with respect to value, impact, mitigation or otherwise.
Examples are Moberly River, Tea Creek, Wilder Creek and so on up the drainage. The PRA clearly
identifies the Site C project will have unambiguous adverse effects on Paleontological Heritage
Resources (PHR) p 32-27 173 positive Paleontologically sensitive areas). Summary maps clearly
indicate that much of the river course to be inundated and impacted has high to extreme
paleontological value (purple and red dots) and can be thought of as a more or less continuous
paleo sensitivity area.
Final April 4, 2013 341
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
32.3.3 32-27 34-35 834
Request: 35 please note the importance of the opportunity to add to the knowledge base of paleo,
however to do this must have a more comprehensive description of sites and analysis of sites
compared to each other and the regional geological and paleontological context including: at each
site abundance, uniqueness, specimen quality (both individually and as assemblages), representivity
of the fossils.
32.3.3 32-28 41 835P 32-28 line 41 Please note the high number of positive PSA’s
32.3.3.1 836Please make mitigation measures more specific. It is not well spelled out and not well linked to
specific sites or to the considerable value of the resource.
32.3.3.3 32-46
38 (Also
Table
32.6)
837
Please consider expanding measures of compensation in kind to include signage and other
measures: "compensation-in-kind (including replication)" as mitigation of Rocky Mountain Fort
should also include other compensation-in-kind mitigation measures (e.g., near-site
commemorative signage).
32.4.3 838
Residual effects not well explored and are needing more specific discussion and explicit
recommendations for dealing with them. As it stands seems to be left to some future discussion
with experts and institutions.
32.3.3.2 28 839Clarificaiton required: what is a systematic data recovery program p32-28?
Final April 4, 2013 342
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App C
Section
5.2.5.5
154-
169840
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance. " and
“Archaeological and historical site inventory field work will include surface and subsurface
inspections, completed in accordance with British Columbia Archaeological Impact Assessment
Guidelines (BCMNRO1998:13) and permits issued under the Heritage Conservation Act. ”
Request:
a) Please provide estimates of the areal extent of the Archaeological deposits that would be
impacted by the project based on the data obtained during the archeological impact assessment
fieldwork.
b) Request the proponent address the question of "How much archaeological deposit would be
impacted by the Project?”
18.2.3
App C
Section
5.2.5.5
154-
169841
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance. "
Request that the proponent address Treaty 8 Tribal Association’s stated concern that the
archaeological impact assessment study has focused on the discovery of large, complex sites, and
has given insufficient attention to understanding the distribution of smaller, sparser sites.
18.2.3
Final April 4, 2013 343
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App C
Section
5.2.5.5
169 842
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance."
Request that the proponent explain the derivation of the estimated numbers of archaeological sites
in different parts of the LAA that were generated by earlier studies, and reconcile these estimates
with the data obtained during the archaeological impact assessment fieldwork reported in the EIS.
Analysis of the limited data presented in the EIS suggests that the earlier estimates significantly
under-represent the number of archaeological sites in the LAA.
18.2.3
App C
Section
5.2.5.5
169 843
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance."
Request that the proponent clarify the statement that “based on statistical tests, few large sites
(often the most significant sites) have been missed”, by identifying the statistical tests employed,
and quantitatively defining the terms “few” and “large.”
18.2.3
App C / App
F Section
5.2.5.5
1 –
311;
Figs.
5.16.1
–
5.16.24
1
844
Figs. 5.16.1 – 5.16.241
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance."
Request that the proponent define archaeological sites in a consistent manner, based on the
observed distribution of archaeological materials, so as to facilitate estimation of the quantity of
archaeological deposit that would be impacted by the Project.
18.2.3
Final April 4, 2013 344
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App C / App
F Section
5.2.5.5
76-77;
Figs.
5.16.1
–
5.16.24
1
845
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance." and
“Archaeological and historical site inventory field work will include surface and subsurface
inspections, completed in accordance with British Columbia Archaeological Impact Assessment
Guidelines (BCMNRO1998:13) and permits issued under the Heritage Conservation Act.”
Request the proponent complete the reported ‘adaptive testing’ program, where necessary, to
allow consistent estimation of the extent of the archaeological deposit associated with each
positive systematic test.
18.2.3
App C
Section
5.2.5.5
158 846
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance." and
“Archaeological and historical site inventory field work will include surface and subsurface
inspections, completed in accordance with British Columbia Archaeological Impact Assessment
Guidelines (BCMNRO1998:13) and permits issued under the Heritage Conservation Act.”
Request the proponent calculate the density of identified archaeological deposits as the number of
artifacts identified in subsurface tests, divided by the total excavated area within the site boundary,
rather than the number of identified artifacts divided by the total area within the defined site
boundary.
18.2.3
Final April 4, 2013 345
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App C
Section
5.2.5.4
75 &
113847
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance." and
“Archaeological and historical site inventory field work will include surface and subsurface
inspections, completed in accordance with British Columbia Archaeological Impact Assessment
Guidelines (BCMNRO1998:13) and permits issued under the Heritage Conservation Act.”
Request the proponent individually report the areas subjected to surface inspection in: 1) fallow
fields; 2) cultivated fields; and 3) vegetated lands “when proceeding to and from targeted testing
locations.”
18.2.3
App C
Section
5.2.5.4
75 &
113848
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance." and
“Archaeological and historical site inventory field work will include surface and subsurface
inspections, completed in accordance with British Columbia Archaeological Impact Assessment
Guidelines (BCMNRO1998:13) and permits issued under the Heritage Conservation Act.”
Request the proponent address the reported failure to employ “Prescribed tillage with a plough,
cultivator, or harrow to increase visibility in previously cultivated fields.” Request that proponent
provide for completion of this prescribed program.
18.2.3
Final April 4, 2013 346
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App C
Section
5.1.5.4
75 &
113849
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance." and
“Archaeological and historical site inventory field work will include surface and subsurface
inspections, completed in accordance with British Columbia Archaeological Impact Assessment
Guidelines (BCMNRO1998:13) and permits issued under the Heritage Conservation Act.”
Request the proponent estimate the extent of archaeological deposits on lands modeled as having
low or moderate archaeological potential, with reference to the data recorded during systematic
survey of cultivated and fallow fields .
18.2.3
App C
Section 8.0
224
850
Mitigation - In section 8.3.4, the report identifies documentation of existing conditions as one
means of mitigating the adverse effects of the Project on heritage resources. However, it does not
specifically refer to archaeological data in this context, and distribution of the results of the
completed and recommended studies is not discussed.
Request that publication of all data that have been collected during the development of the model
of archaeological potential (including the underlying LIDAR data) and the archaeological impact
assessment, as well as the results of any future archaeological data recovery projects, be identified
as a potential mitigative measure.
18.2.3
Final April 4, 2013 347
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App C
32.2.2.220 39-44 851
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance." and
“Archaeological and historical site inventory field work will include surface and subsurface
inspections, completed in accordance with British Columbia Archaeological Impact Assessment
Guidelines (BCMNRO1998:13) and permits issued under the Heritage Conservation Act.”
Request the proponent compare different parts of the LAA (e.g., the north and south banks of the
Peace River) in terms of the areal extent of identified archaeological deposits, rather than the
number of identified sites. This will require that sites be consistently defined with reference to the
observed distributions of archaeological materials. Comparison in terms of the numbers of
reported sites is less meaningful, due to the considerable variability in the size and density of
reported sites.
18.2.3
App C 5.1 168 852
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance." and
“Archaeological and historical site inventory field work will include surface and subsurface
inspections, completed in accordance with British Columbia Archaeological Impact Assessment
Guidelines (BCMNRO1998:13) and permits issued under the Heritage Conservation Act.”
Request the proponent identify, and report the size of “Certain locations (that) could not be
assessed in the field due to access restrictions (section 5.1, p 68)”, and propose remedies for these
omissions.
18.2.3
Final April 4, 2013 348
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
App C
5.1.5.172 853
The EIS Guidelines State: "The EIS will summarize the potential adverse effects of the Project on
heritage resources, including physical and cultural heritage resources, and any structure, site or
thing that is of historical, archaeological, paleontological or architectural significance." and
“Archaeological and historical site inventory field work will include surface and subsurface
inspections, completed in accordance with British Columbia Archaeological Impact Assessment
Guidelines (BCMNRO1998:13) and permits issued under the Heritage Conservation Act.”
Request the proponent indicate whether identified discrepancies between the archaeological
potential model, based on LIDAR data, and assessed potential, based on field observation during
model testing, were used to revise and improve the model, prior to its implementation for
archaeological inventory. Request that the extent of all re-evaluated areas be reported.
18.2.3
32 10, 26
P10: 21-
22
&
p26: 13-
16
854
The EIS appears to present contradictory conclusions as to the expected effects of installation of
worker accommodations.
On page 10 of Section 32 it states,
‘Activities for which there is no interaction between the Project activity or component and heritage
resources ... include:
Temporary accommodation – dam and generating station: installation of 21 prefabricated units in
the north and south bank camps; operation of both camps “
On page 26 it states,
“Ground-disturbing activities associated with erecting worker accommodation and infrastructure
have the potential to affect heritage resources, if present. Increased 15 loading from temporary
facilities may cause compaction to buried heritage resources. “
Request the proponent clarify the expected effects of installation of worker accommodation on
heritage resources.
18.2.3
Final April 4, 2013 349
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
32.3.327 &
28
P 27: 18-
43;
P 28: 1-
20
855
Request that the proponent acknowledge that a significant proportion (possibly the majority) of the
archaeological resources that would be affected by the Project have not been, and are not
expected to be, identified.
Request that the proponent acknowledge that it will not be possible to mitigate the effects of the
Project on unidentified archaeological resources through intentional avoidance, protective
measures, data recovery or documentation.
18.2.3
32 56-61Table
32.9856
Table 3.29 represents the Magnitude of the Residual Heritage Effect of most Project activities as
Low. This includes activities such as site clearing; dam construction; road construction, upgrading &
realignment; aggregate extraction; diversion & channelization, etc., which are likely to result in total
destruction of archaeological sites, including many sites that have not been and are not expected to
be identified.
Request the proponent explain the evaluation of the Magnitude of the Residual Heritage Effect of
Project activities on heritage resources.
18.2.3
App C 221 N/A 857Please include Ministry of Environment, BC Parks in relevant parties for mitigation discussions
regarding heritage resources moving forward
33 2 33-35 858
For recreational water quality, MOE adopts Health Canada’s water quality guidelines for recreation.
This standard should be used. http://www.hc-sc.gc.ca/ewh-semt/water-eau/recreat/index-eng.php
. You may also wish to consult with Ministry of Health and Health Authorities regarding recreational
water quality.
33 2Table
33.11859
Recreational water quality and exposure through primary and secondary contact is not included,
please explain why this was omitted.
33.1.1 2 860
Please clarify if the proponent consulted with the Ministry of Health regarding the authority to issue
fish consumption advisories. The Ministry of Health may advise if this is a function authorized by
the Public Health Act. Managing the risks of environmental contaminants in country foods is a
provincial responsibility lying with the Ministry of Health and/or Health Authorities
33.1.1 2 861Please clarify why the following source water guidelines were not considered in this table: total
organic carbon, phosphorus.
Section 33 - Human Health
Final April 4, 2013 350
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
33.1.1 2 862Please include whether the guidelines are maximum acceptable concentrations (MAC) or aesthetic
concentrations (AO).
33.1.1 2 863Please indicate which recreational water quality guidelines are relevant to this project and also
consider placing them in a table for comparison.
33.1.1 2 864Regulatory Framework. Please include a section on the Environmental Management Act.
33.1.1 2 865
Table 33.1 Drinking Water Guidelines. It is unclear why these contaminants were included in this
table. Are these the potential contaminants of concern? They are not the full suite of drinking
water guidelines. For most contaminants, the BC Ministry of Environment has policy to adopt the
Guidelines for Canadian Drinking Water Quality when Health Canada’s guideline is also appropriate
as a source water benchmark. Therefore, when Health Canada updates a guideline, MOE will
typically update its guideline as well. Please see
http://www.env.gov.bc.ca/wat/wq/BCguidelines/working.html#table1 for a list of working water
quality guidelines including those for drinking water sources.
33.1.1 2 866
The Ministry of Environment establishes Water Quality Guidelines (see Environmental Management
Act Part 5). MOE’s “drinking water guidelines” are developed to be achieved at the source. These
benchmarks are used to assess changes in source water quality used for drinking water, irrigations
supplies and aquatic life.
33.1.1 2 867
The Public Health Act may need to be included for food contamination and possible fish
consumption advisories (please check with the Ministry of Health and Health Canada regarding First
Nations).
33 3 868
Please clarify what ‘studies’ were used to determine if a water quality contaminant exceeded a
guideline and was therefore screened as a COPC? Eg. Baseline monitoring, studies showing that
contaminant x increased as a result of flooding, etc....
33 22Table
33.11869
Please clarify why ingestion of birds such as ducks that may feed on MeHg fish is not carried
forward?
33 22Table
33.11870
Section 33.2.2 : Please clarify if this section is an assessment specific to MeHg or an outline of the
screening procedure for all COPC. Best to keep specific assessments and general procedures
separate for clarity.
Final April 4, 2013 351
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
33 24 871
Often agencies use screening values for contaminants in fish tissue in monitoring programs. If
monitoring demonstrates that a screening value is exceeded, a more thorough health assessment is
conducted to determine appropriate consumption limits. The Ministry of Environment is currently
updating the health-based guideline for Hg in fish and shellfish tissue and therefore, this may not be
an appropriate screening value at this time. Please clarify if the proponent has consulted with
Health agencies such as Ministry of Health, Health Authorities, or First Nations and Inuit Health
Branch to determine if the recommendations in Table 33.29 are appropriate.
33 25Line 30-
31872
Please clarify the specific "First Nations Communities" that are being referred to here and where
they obtain drinking water?
33.3.1 25 873
Please clarify if there has been a survey of surface water intake licences? Has the proponent
considered all surface water users including intakes serving small water systems and individual
dwellings?
33 26Line 11-
13874
Please note that for drinking water parameters, it is important to report how often (ie frequency)
parameters exceed maximum acceptable concentrations (MAC) rather than reporting means or
averages.
33 26 Line 7 875
Please be specific regarding what parameters exceeded Health Canada’s drinking water or
recreational guidelines rather than reporting “in general, these baseline parameters....etc”
33 27Table
33.12876
Please clarify why only these parameters were reported? How does this compare to those listed in
Table 33.1.? Please clarify what are the water quality parameters of potential concern as a result of
this project.
Final April 4, 2013 352
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
33 27Table
33.12877
The turbidity guideline has been misinterpreted. Turbidity needs to be considered in collaboration
with Health Canada’s turbidity guideline which should also be reported here. The purpose of BC
MOE’s water quality guideline for turbidity is to assess where resource activities may impact the
quality of drinking water sources. Turbidity is an important parameter with respect to
microbiological contamination reaching the consumer. Increased or high turbidity levels may result
in the need for improved treatment technology for water systems on surface supplies. Therefore,
please clarify and report the baseline turbidity levels. What are the projected changes and what
receptors may be impacted if any?
33 37Table
33.18878
Is this a consumption advisory that the proponent intends to issue for the impacted area? If so,
please clarify that the proponent consulted with the Northern Health Authority and First Nations
and Inuit Health? Normally these advisories are issued under the Public Health Act by a Medical
Health Officer.
33 37Table
33.18879
Please clarify if the consumption limits considered background Hg levels and the much lower TDI for
children.
33 39 Line 27 880
Please clarify here which water quality parameters are anticipated to change as a result of the
project. Would it not be more appropriate to state that “changes are not anticipated to result in
exceedances of drinking water”
33 40Line 15-
17881
Is this referring specifically to groundwater quality? Although surface water quality is not
anticipated to exceed guidelines, please clarify how the proponent anticipates confirming this once
the project begins. Will a monitoring program be established in indicator areas or with water
suppliers?
33.4.1.0 62 882
Please clarify if the proponent has consulted with local Health Authorities regarding this monitoring
program to ensure that local knowledge about susceptible populations and consumption patterns
are considered. Typically consumption advisories are issued by Medical Health Officers in BC
authorized under the Public Health Act. Please clarify the process and partners being proposed.
Volume 5
Final April 4, 2013 353
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
34.3.2.3 883Consider referencing the recent Federal Court ruling in Daniel vs. Canada, 2013 and any potential
relevance to this project.
34.3.3 12 37 884Consider removing reference to the Treaty 8 Tribal Association. The association does not hold any
Aboriginal or Treaty Rights. Suggest referencing individual nations.
34.7.1 28 6-25 885Consider addressing the Province’s position on the potential future application of a FN to convert
fee simple land transfers to their Indian Reserve (Additions To Reserve)
App 6 27 886
Please consider including a copy of the "Telling a Story of Change; The Dane-Zaa Way" into the EIS.
Please discuss how this document was considered and incorporated into project planning and
design?
35 887
Several major landslide features are identified in the terrain stability mapping of the project activity
zone. Landslides are not addressed in the public safety plan 35.3.1.2 (e.g., road signage at crossings
of major landslide features - 'no stopping landslide risk zone' or the like, weather related work
stoppage rules, etc.)
9.2.1 Geology, Terrain
and Soils
35 888
Several major landslide features are in the project activity zone. Landslides are not addressed in the
worker safety and health management plan as outlined in WCB regulations Part 26 Forestry
Operations and Similar Activities
26.18 Landslides
In a forestry operation where there may be a risk of a landslide
(a) the risk must be assessed in accordance with a standard acceptable to the Board,
(b) if a risk is found to be present, written safe work procedures must be developed meeting the
requirements of the standard, and
(c) workers must be educated in the safe work procedures.
[Amended by B.C. Reg. 312/2010, effective February 1, 2011.]
It is recommend that a map is made outlining the zones in which these regulations apply and the 3
regulated items be addressed to assess and reduce risks (e.g., signage, landslide magnitude
frequency studies, work safe procedures such as stop work in wet conditions)
9.2.1 Geology, Terrain
and Soils
Section 34 - Asserted or Established Aboriginal and Treaty Rights, Aboriginal Interests, and Information Requirements
Section 35 - Summary of Environmental Management Plans
Final April 4, 2013 354
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
35.2.1.4 6,7 19, 20 889
"to ensure that traffic is managed in and around the construction sites" It is not entirely clear that
the Traffic Management Plan would address traffic in and around and access to all Project
Components not just the primary construction sites. Please Clarify.
35.2.2.19 35-21 4-36 890
This section outlines the expected content of the soil management site restoration and re-
vegetation plan, and provides a relatively comprehensive discussion of the considerations
necessary for the development of such a plan. Although discussion of post construction end use for
rehabilitated lands is discussed form the agricultural perspective, similar discussions for other end
uses, e.g., forestry, wildlife or special ecological values are not present. This section is also lacking
any discussion of how the results of the reclamation efforts will be monitored, which is essential for
high value areas like agricultural land, forestry or other areas where (for example) ecosystem
restoration techniques have been applied. The final soil reclamation plan should include such topics
9.2.1 Geology, Terrain
and Soils
35.2.2.2,
35.2.2.18
35-39
and 35-
20/21
11-17,
34-36,
and 1-2
891
Monitoring and Reporting – Recommend that the monitors report real time to a database to
increase transparency of issuing air quality advisories.
35.3.2 892
There is no provision for long term climate and meteorological monitoring. BC Hydro has installed
stations in the valley. Please clarify if any of these station have been designated as long term
monitoring sites, and if not, please consider doing so.
37 37-9 37 893 Does not consider debris dam and flood. 9.2.1 Geology, Terrain
and Soils
37.1.13.2 37-46 Floods 894Please clarify if the flood discharge effect on downstream infrastructure such as Taylor Bridge and
Clayhurst Bridge been considered?
Section 36 - Compliance Reporting - No Comments
Section 37 - Requirements for the Federal Environmental Assessment
Final April 4, 2013 355
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
37.1.3.3 37-8 29 895
Please note that the new bridges, culverts and other structures on Highway 29 must be designed to
accommodate the high channel flows from extreme weather events as well as the debris typically
contained in those high flows.
37.1.8.3 37-21 5 896
The 50 year return period indicated in the document is not correct. The design earthquake is
dependent on bridge importance, the type of bridge structure and the seismic risk associated with
the geographic location of the bridge. Please correct.
37.1.9 37-21 12 897
Consider adding additional detail regarding potential effects of wildfire on the construction phase of
the Project. Wildfire could have a disruptive influence (albeit of fairly short duration) on
construction through blocking of access, smoke and visibility problems and perhaps an influence on
the actual work sites including the dam and clearing areas of the reservoir. A review of historical
fires that could affect the construction phase shows the last major event occurred in 1976 when a
wildfire of some 17, 000 ha happened on the south side of the Peace River drainage and if occurring
during the construction phase would have impacted the transmission line and access roads
proposed for this project. Construction on the north side of the Peace River is not expected to be
adversely impacted by wildfire due to the different fuel type and probable direction of fire spread.
37.2.2.2.2
and 37.2.2.3
37-52
to 37-
59
18 898
Please clarify what affect a dam breach would have on the bridge structures over the Peace River at
Taylor and Clayhurst and on the Moose Mouth Bridge over the Alces River near Clayhurst.
Section 39 - Complete Lists of Mitigation and Follow-Up Measures
Section 38 - Summary of Potential Residual Effects of the Project - No Comments
Final April 4, 2013 356
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
39 899
The NRS agencies take the view that as long as the proposed mitigation is feasible, reasonable or
the proposed technology or approach has been used successfully elsewhere, then we are fine with
the level of information provided at the EIS stage knowing that detailed plans would be required
prior to permitting decisions. However, in some instances, these plans were heavily relied on as
rational for assumptions and findings. To address this, the NRS agencies request BC Hydro include
any developed plans, and specifically those plans that have been used as rationale for findings, into
the amended EIS.
39 900
Green house gas emissions from decay of flooded biomass is not addressed in this section. Loss of
carbon sequestration ability by soils and vegetation in the forests and wetlands in the flooded area
is not addressed. If this is covered in another section it should be cross referenced here.9.2.1 Geology, Terrain
and Soils
39 901Though soil mitigation and reclamation is to be addressed in a management plan, detailed baseline
data is not included.9.2.1 Geology, Terrain
and Soils
Final April 4, 2013 357
B.C. Natural Resource Sector Agencies Site C Clean Energy Project
EIS Review Comments
Section # Page # Line #Comment
# Comment EIS Guidelines
39 902
Estimate of Residual Effects - Overall Methods
Issue: Vol 5 Table 39.1 Complete List of Mitigation Measures presents proposed mitigation
measures for each potential effect (e.g., for three effects for “wildlife resources”: habitat
alteration/fragmentation; disturbance/displacement; and mortality).
o The next column indicates whether there is, or is not, a potential Residual Effect (Y/N), but there
is no indication as to what exactly are the Residual Effects.
o The last column indicates (Y/N) whether the potential Residual Effect is “Significant” or not.
Concern: Neither the identification of Residual Effects, nor the information on calculation of
Significance, is specific enough to be meaningful to understand what exactly the residual adverse
effects are, and why they are significant or not significant.
Request that the Proponent: Clarify the location in the EIS of details and rationales about the
assessment of Residual Effects and the calculation of Significance. Cross-reference these in other
sections/ volumes so that the reader is able to access this information more easily. If this
information is not currently provided in the EIS, please consider adding it.
Section 40 - Conclusions and Conditions - No Comments
Final April 4, 2013 358