13 lecture project management
DESCRIPTION
TRANSCRIPT
![Page 1: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/1.jpg)
Project Management
Prepared by Sebghatullah Karimi( Lecturer of Kabul Polytechnic University)
1392
Kardan UniversityCivil Engineering Faculty
![Page 2: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/2.jpg)
Characteristic of a project
A project is a temporary Endeavour involving a connected sequence of activities and a range of resources, which is designed to achieve a specific and unique outcome and which operates within time, cost and quality constraints and which is often used to introduce change.
2
A unique, one-time operational activity or effortRequires the completion of a large number of interrelated activitiesEstablished to achieve specific objectiveResources, such as time and/or money, are limitedTypically has its own management structureNeed leadership
Project
![Page 3: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/3.jpg)
Examples– constructing houses, factories, shopping malls,
athletic stadiums.– developing military weapons systems, aircrafts,
new ships– launching satellite systems– constructing oil pipelines– developing and implementing new computer
systems– planning concert, football games, or basketball
tournaments– introducing new products into market
3
![Page 4: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/4.jpg)
What is project management
• The application of a collection of tools and techniques to direct the use of diverse resources towards the accomplishment of a unique, complex, one time task within time, cost and quality constraints.
4
![Page 5: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/5.jpg)
Project Management Process• Project planning• Project scheduling • Project control• Project team
– made up of individuals from various areas and departments within a company
• Matrix organization (Trade)– a team structure with members from functional areas, depending on skills
required• Project Manager
– most important member of project team• Scope statement
– a document that provides an understanding, justification, and expected result of a project
• Statement of work– written description of objectives of a project
• Organizational Breakdown Structure– a chart that shows which organizational units are responsible for work items
• Responsibility Assignment Matrix– shows who is responsible for work in a project
5
![Page 6: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/6.jpg)
Work breakdown structure
• A method of breaking down a project into individual elements ( components, subcomponents, activities and tasks) in a hierarchical structure which can be scheduled and cost.
• It defines tasks that can be completed independently of other tasks, facilitating resource allocation, assignment of responsibilities and measurement and control of the project.
• It is foundation of project planning.• It is developed before identification of dependencies and
estimation of activity durations.
6
![Page 7: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/7.jpg)
Project Planning
• Resource Availability and/or Limits– Due date, late penalties, early completion
incentives– Budget
• Activity Information– Identify all required activities– Estimate the resources required (time) to complete
each activity– Immediate predecessor(s) to each activity needed
to create interrelationships7
![Page 8: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/8.jpg)
Project Scheduling and Control Techniques
8
Gantt Chart
Critical Path Method (CPM)
![Page 9: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/9.jpg)
9
Graph or bar chart with a bar for each project activity that shows passage of time
Provides visual display of project scheduleProvides visual display of project schedule
Gantt Chart
![Page 10: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/10.jpg)
Project Network
• Use of nodes and arrows Arrows An arrow leads from tail to head directionally
– Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work.
Nodes A node is represented by a circle- Indicate EVENT, a point in time where one or more activities start and/or
finish.
10
• Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects
• Activity
– A task or a certain amount of work required in the project
– Requires time to complete
– Represented by an arrow
• Dummy Activity
– Indicates only precedence relationships
– Does not require any time of effort
![Page 11: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/11.jpg)
• Event– Signals the beginning or ending of an activity– Designates a point in time– Represented by a circle (node)
• Network– Shows the sequential relationships among activities using nodes
and arrows
11
Activity-on-node (AON)
nodes represent activities, and arrows show precedence relationships
Activity-on-arrow (AOA)
arrows represent activities and nodes are events for points in time
Project Network
![Page 12: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/12.jpg)
AOA Project Network for House
12
32 0
1
31 1
11 2 4 6 7
3
5
Lay foundation
Design house and obtain financing
Order and receive materials
Dummy
Finish work
Select carpet
Select paint
Build house
AON Project Network for House
13
22
43
31 5
1
61
71Start
Design house and obtain financing
Order and receive materials
Select paintSelect carpet
Lay foundations Build house
Finish work
![Page 13: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/13.jpg)
Situations in network diagram
13
AB
C
A must finish before either B or C can start
A
B
C both A and B must finish before C can start
D
C
B
Aboth A and B must finish before either of C or D can start
A
C
B
D
Dummy
A must finish before B can start
both A and C must finish before D can start
![Page 14: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/14.jpg)
Network example
14
Illustration of network analysis of a minor redesign of a product and its associated packaging.
The key question is: How long will it take to complete this project ?
![Page 15: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/15.jpg)
15
For clarity, this list is kept to a minimum by specifying only immediate relationships, that is relationships involving activities that "occur near to each other in time".
![Page 16: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/16.jpg)
Questions to prepare activity network• Is this a Start Activity?
• Is this a Finish Activity?
• What Activity Precedes this?
• What Activity Follows this?
• What Activity is Concurrent with this?
16
![Page 17: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/17.jpg)
CPM calculation
• Path– A connected sequence of activities leading from
the starting event to the ending event
• Critical Path– The longest path (time); determines the project
duration
• Critical Activities– All of the activities that make up the critical path
17
![Page 18: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/18.jpg)
Forward Pass• Earliest Start Time (ES)
– earliest time an activity can start – ES = maximum EF of immediate predecessors
• Earliest finish time (EF)– earliest time an activity can finish– earliest start time plus activity time
EF= ES + D
18
Latest Start Time (LS)
Latest time an activity can start without delaying critical path time
LS= LF - D
Latest finish time (LF)
latest time an activity can be completed without delaying critical path time
LS = minimum LS of immediate predecessors
Backward Pass
![Page 19: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/19.jpg)
CPM analysis
• Draw the CPM network
• Analyze the paths through the network
• Determine the float for each activity
– Compute the activity’s float
float = LS - ES = LF - EF
– Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project
• Find the critical path is that the sequence of activities and events where there is no “slack” i.e.. Zero slack
– Longest path through a network
• Find the project duration is minimum project completion time
19
![Page 20: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/20.jpg)
CPM Example: • CPM Network
20
a, 6a, 6a, 6a, 6
f, 15f, 15f, 15f, 15
b, 8b, 8b, 8b, 8
c, 5c, 5c, 5c, 5e, 9e, 9e, 9e, 9
d, 13d, 13d, 13d, 13
g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9
i, 6i, 6i, 6i, 6
j, 12j, 12j, 12j, 12
![Page 21: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/21.jpg)
CPM Example
• ES and EF Times
21
a, 6a, 6a, 6a, 6
f, 15f, 15f, 15f, 15
b, 8b, 8b, 8b, 8
c, 5c, 5c, 5c, 5
e, 9e, 9e, 9e, 9
d, 13d, 13d, 13d, 13
g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9
i, 6i, 6i, 6i, 6
j, 12j, 12j, 12j, 12
0 6
0 8
0 5
![Page 22: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/22.jpg)
CPM Example
• ES and EF Times
22
a, 6a, 6a, 6a, 6
f, 15f, 15f, 15f, 15
b, 8b, 8b, 8b, 8
c, 5c, 5c, 5c, 5
e, 9e, 9e, 9e, 9
d, 13d, 13d, 13d, 13
g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9
i, 6i, 6i, 6i, 6
j, 12j, 12j, 12j, 12
0 6
0 8
0 5
5 14
8 21
6 23
6 21
![Page 23: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/23.jpg)
CPM Example
• ES and EF Times
23
a, 6a, 6a, 6a, 6
f, 15f, 15f, 15f, 15
b, 8b, 8b, 8b, 8
c, 5c, 5c, 5c, 5
e, 9e, 9e, 9e, 9
d, 13d, 13d, 13d, 13
g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9
i, 6i, 6i, 6i, 6
j, 12j, 12j, 12j, 12
0 6
0 8
0 5
5 14
8 21 21 33
6 23 21 30
23 29
6 21
Project’s EF = 33Project’s EF = 33
![Page 24: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/24.jpg)
CPM Example
• LS and LF Times
24
a, 6a, 6a, 6a, 6
f, 15f, 15f, 15f, 15
b, 8b, 8b, 8b, 8
c, 5c, 5c, 5c, 5
e, 9e, 9e, 9e, 9
d, 13d, 13d, 13d, 13
g, 17g, 17g, 17g, 17
h, 9h, 9h, 9h, 9
i, 6i, 6i, 6i, 6
j, 12j, 12j, 12j, 12
0 6
0 8
0 5
5 14
8 21 21 33
6 23
21 30
23 29
6 21
21 33
27 33
24 33
![Page 25: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/25.jpg)
CPM ExampleCPM Example
• LS and LF Times
25
a, 6a, 6a, 6a, 6
f, 15f, 15f, 15f, 15
b, 8b, 8b, 8b, 8
c, 5c, 5c, 5c, 5
e, 9e, 9e, 9e, 9
d, 13d, 13d, 13d, 13
g, 17g, 17g, 17g, 17
h, 9h, 9h, 9h, 9
i, 6i, 6i, 6i, 6
j, 12j, 12j, 12j, 12
0 6
0 8
0 5
5 14
8 21 21 33
6 23
21 30
23 29
6 21
4 10
0 8
7 12
12 21
21 33
27 33
8 21
10 27
24 33
18 24
![Page 26: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/26.jpg)
CPM ExampleCPM Example• Float
26
a, 6a, 6a, 6a, 6
f, 15f, 15f, 15f, 15
b, 8b, 8b, 8b, 8
c, 5c, 5c, 5c, 5e, 9e, 9e, 9e, 9
d, 13d, 13d, 13d, 13
g, 17g, 17g, 17g, 17
h, 9h, 9h, 9h, 9
i, 6i, 6i, 6i, 6
j, 12j, 12j, 12j, 12
0 6
0 8
0 5 5 14
8 21 21 33
6 23
21 30
23 29
6 21
3 9
0 8
7 12 12 21
21 33
27 33
8 21
10 27
24 33
9 24
3 4
3
3
4
0
0
7 7
0
![Page 27: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/27.jpg)
CPM Example
• Critical Path
27
a, 6a, 6a, 6a, 6
f, 15f, 15f, 15f, 15
b, 8b, 8b, 8b, 8
c, 5c, 5c, 5c, 5
e, 9e, 9e, 9e, 9
d, 13d, 13d, 13d, 13
g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9
i, 6i, 6i, 6i, 6
j, 12j, 12j, 12j, 12
![Page 28: 13 lecture project management](https://reader034.vdocuments.net/reader034/viewer/2022051609/5470ae3fb4af9fc30a8b481d/html5/thumbnails/28.jpg)