Oak Harbor Facilities PlanCity Council Workshop

March 6, 2013

Page 2: 130306 city council workshop revised

Oh910i1-8594.pptx/2Oh910i1-8594.pptx/2

Tonight’s Agenda

• Facilities Plan Status Update

• Rate Analysis Update

• Schedule and Next Steps

– Technical Aspects

– Public Interface

– Milestone Council Decisions

• How to Stay Involved

• Questions?

Page 3: 130306 city council workshop revised

Oh910i1-8594.pptx/3Oh910i1-8594.pptx/3

Facilities Plan Status

Page 4: 130306 city council workshop revised

Oh910i1-8594.pptx/4Oh910i1-8594.pptx/4

Proposed SiteWindjammer Vicinity

Page 5: 130306 city council workshop revised

Oh910i1-8594.pptx/5Oh910i1-8594.pptx/5

Windjammer Charrette Concept for MBRConceptual Plan View

Page 6: 130306 city council workshop revised

Oh910i1-8594.pptx/6Oh910i1-8594.pptx/6

Total Project Cost SummaryYear 2030

$83.0

$7.6

$2.9

$50

$55

$60

$65

$70

$75

$80

$85

$90

$95

$100

All Facilities Through Year 2030

Proj

ect C

ost,

Mill

ions

Treatment Facility Wastewater Conveyance Effluent Discharge

Page 7: 130306 city council workshop revised

Oh910i1-8594.pptx/7Oh910i1-8594.pptx/7

Phasing Scenarios Depend on City Growth

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

2000 2005 2010 2015 2020 2025 2030 2035

Max

imum

Mon

th F

low

, mgd

Measured Data

Scenario 1, No Growth

Scenario 2, Intermediate Growth

Scenario 3, Comprehensive Plan

1

23

Notes:1: Current measured capacity is 3.0 mgd.2: Capacity required at projected year of startup (2017) ranges from 3.0 to 3.2 mgd.3: Assuming 3.4 mgd of capacity is constructed in Phase 1, years of service

(prior to Phase 2) range from 4 to 13 years.

1

2

3

Page 8: 130306 city council workshop revised

Oh910i1-8594.pptx/8Oh910i1-8594.pptx/8

Phasing Also Depends on Navy Participation

• Navy currently contributes about 20% of flow to City facilities

• Scenario 1: Navy continues as a customer

– WWTP sized for City and Navy flows/loads

• Scenario 2: Navy does not continue as a customer

– WWTP sized for City only flows/loads

Page 9: 130306 city council workshop revised

Oh910i1-8594.pptx/9Oh910i1-8594.pptx/9

$83.0

$72.1

$7.6

$7.6

$2.9

$2.9

$50

$55

$60

$65

$70

$75

$80

$85

$90

$95

$100

All Facilities Through Year 2030 Scenario 1: City + Navy

Proj

ect C

ost,

Mill

ions

Treatment Facility Wastewater Conveyance Effluent Discharge

The City's cost sharefor this scenario is

$60.0 M

Total Project Cost SummaryPhase 1, Scenario 1

Page 10: 130306 city council workshop revised

Oh910i1-8594.pptx/10Oh910i1-8594.pptx/10

$83.0

$72.1

$64.8

$7.6

$7.6

$2.9

$2.9

$2.9

$50

$55

$60

$65

$70

$75

$80

$85

$90

$95

$100

All Facilities Through Year 2030 Scenario 1: City + Navy Scenario 2: City Only

Proj

ect C

ost,

Mill

ions

Treatment Facility Wastewater Conveyance Effluent Discharge

The City's cost sharefor this scenario is

$60.0 M

The City's cost sharefor this scenario is

$67.7 M

Total Project Cost SummaryPhase 1, Scenarios 1 and 2

Page 11: 130306 city council workshop revised

Oh910i1-8594.pptx/11Oh910i1-8594.pptx/11

Phase 1 Scenario Summary

Scenario 1City + Navy

Scenario 2City Only

Phase 1 Project Cost $82.6 M $67.7 M

Navy Share (%) 27% n/a

Navy Share of Cost $22.6 M n/a

City Share of Cost $60.0 M $67.7

Page 12: 130306 city council workshop revised

Oh910i1-8594.pptx/12Oh910i1-8594.pptx/12

Milestone Dates for Plan Approval

Date Action

March 6, 2013 Present Draft Plan to Public

March 19, 2013 Seek Council Approval to Submit Draft Plan

Summer 2013 Ecology Conditional Approval (pending environmental)

Q4 2013 - Q1 2014 Final Environmental Approvals

Page 13: 130306 city council workshop revised

Oh910i1-8594.pptx/13Oh910i1-8594.pptx/13

Rate Analysis Update

Page 14: 130306 city council workshop revised

Oh910i1-8594.pptx/14Oh910i1-8594.pptx/14

Two Scenarios for Navy Participation

• Scenario 1: City + Navy

– City provides service to Navy at startup of Phase 1 and through Year 2030

– All project/O&M costs are shared

• Scenario 2: City Only

– City, Navy operate independent facilities through Year 2030 (Navy no longer a customer)

– All project/O&M costs are born by City

Page 15: 130306 city council workshop revised

Oh910i1-8594.pptx/15Oh910i1-8594.pptx/15

Navy Cost-Sharing Assumptions

• WWTP Project Costs– Navy share based on percentage of

maximum month flow (ranges from 21% to 18%)

• WWTP O&M Costs– Navy share based on percentage of average

annual flow (ranges from 17% to 14%)• Collection System Project Costs– Navy provides 100% of costs associated with

conveying Navy flow to Windjammer Vicinity• Outfall Project Costs– Navy share based on percentage of peak

flow (approximately 19% at 2030)

Page 16: 130306 city council workshop revised

Oh910i1-8594.pptx/16Oh910i1-8594.pptx/16

WWTP Funding Assumption Review

• 2010 rate study included assumptions for the WWTP funding

• Assumptions were conservative given the project was 5 plus years in the future

• Revised assumptions are conservative yet still reflect current conditions

• Question: How do the assumptions impact the adopted rate transition plan?

Page 17: 130306 city council workshop revised

Oh910i1-8594.pptx/17Oh910i1-8594.pptx/17

Estimated Rate Impact, August 14, 2012“Base Case” Assumed $70 million Project

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20

$0.00

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

$80.00

$90.00

$100.00

Mon

thly

Sew

er B

ill

Summary of Required Single Family Monthly Sewer Bill

“Base Case”Monthly Rate:

$92.20

Page 18: 130306 city council workshop revised

Oh910i1-8594.pptx/18Oh910i1-8594.pptx/18

Variables include:1. Borrowing term2. Interest rate3. Navy participation

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20 Option 1 $40.00 $42.00 $47.00 $52.88 $59.48 $68.41 $80.38 $96.45 $115.74 Option 2A $40.00 $42.00 $47.00 $52.00 $57.50 $66.13 $76.04 $89.35 $104.99 Option 2B $40.00 $42.00 $47.00 $52.00 $57.50 $64.69 $74.39 $85.55 $98.38 Option 3 $40.00 $42.00 $47.00 $52.00 $57.50 $63.54 $70.21 $77.58 $85.73

$0.00

$20.00

$40.00

$60.00

$80.00

$100.00

$120.00

$140.00

Mon

thly

Sew

er B

ill

Summary of Required Single Family Monthly Sewer Bill

Estimated Rate Impact, August 14, 2012Rate Scenarios for $93.5 million Project

Monthly Rates range from $85 to

> $115(Depending on

variable assumptions)

Page 19: 130306 city council workshop revised

Oh910i1-8594.pptx/19Oh910i1-8594.pptx/19

Updated WWTP Funding Assumptions

• 2 Borrowing terms evaluated: 20 and 30 years• 2 Interest Rates evaluated: 4.5% and 6.0%• Updated City’s sewer reserves balance• Reconciled other key rate analysis

assumptions– Project cost escalated to mid-point– City portion of project cost based on Navy

participation– Cost of bonding– WWTP O&M components and costs– Project start/end dates

Page 20: 130306 city council workshop revised

Oh910i1-8594.pptx/20Oh910i1-8594.pptx/20

Three Potential Phase 1 Funding Scenarios

• Scenario 1: City + Navy– 30 years, 4.5% interest– Results in lowest City rate

• Scenario 2A: City Only– 30 years, 4.5% interest– Rate is higher than Scenario 1; still < “Base

Case”• Scenario 2B: City Only– 20 years, 6.0% interest– Highest rate; > “Base Case”

Page 21: 130306 city council workshop revised

Oh910i1-8594.pptx/21Oh910i1-8594.pptx/21

Comparison of Potential Monthly Sewer Bills

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9Base Case $40.00 $42.00 $47.00 $52.00 $57.50 $64.75 $72.85 $81.95 $92.20 Scenario 1: City + Navy; 30-yrs; 4.5% $40.00 $42.00 $47.00 $51.70 $56.87 $62.56 $68.81 $75.69 $83.26 Scenario 2A: City Only; 30-yrs; 4.5% $40.00 $42.00 $47.00 $52.00 $57.50 $64.40 $72.13 $80.78 $90.48 Scenario 2B: City Only; 20-yrs; 6.0% $40.00 $42.00 $47.00 $52.88 $59.48 $68.11 $77.99 $89.68 $107.62

$0

$20

$40

$60

$80

$100

$120

Mon

thly

Sew

er B

ill

Required Single Family Monthly Sewer Bill

Page 22: 130306 city council workshop revised

Oh910i1-8594.pptx/22Oh910i1-8594.pptx/22

Summary of Rate Impacts, WWTP

• Lowest City rates result from City + Navy partnership in new facilities

• For “City Only” scenario, City rates held below “Base Case” with current, reasonable assumptions

• Opportunities to reduce City rate impact due to new WWTP continue to be explored– Grants/low-interest loan programs– Borrowing strategy– “Value Engineering”– Project Delivery Method

• Overall rate analysis for sewer utility is ongoing

Page 23: 130306 city council workshop revised

Oh910i1-8594.pptx/23Oh910i1-8594.pptx/23

Schedule/Next Steps

Page 24: 130306 city council workshop revised

Oh910i1-8594.pptx/24Oh910i1-8594.pptx/24

Objectives for Next Phase of ProjectThrough Year-end

• Facilities Plan approved

• Confirm planning assumptions through “Value Engineering”

• Select final location for WWTP within Windjammer Vicinity

• Complete preliminary design of WWTP

• Select most appropriate method of construction

• Complete final design of outfall to Oak Harbor

Page 25: 130306 city council workshop revised

Oh910i1-8594.pptx/25Oh910i1-8594.pptx/25

Key Features of Approach Moving Forward

• Continue to make every effort to deliver an appropriate facility while controlling cost and impact on ratepayers

• Maintain flexibility by considering options for final WWTP site location

• Select final location considering public input, cost and City policy directives

Page 26: 130306 city council workshop revised

Oh910i1-8594.pptx/26Oh910i1-8594.pptx/26

Step 1 – Value Engineering

• Completed on large projects to add value, control cost

• Condition of some funding sources• Facilitated by an independent 3rd party and

panel of experts• Summer 2013: Results and

recommendations offered to City Council for consideration

Page 27: 130306 city council workshop revised

Oh910i1-8594.pptx/27Oh910i1-8594.pptx/27

Step 2 – Select Final WWTP Location Within Windjammer Vicinity

Page 28: 130306 city council workshop revised

Oh910i1-8594.pptx/28Oh910i1-8594.pptx/28

Step 2 – Select Final WWTP Location Within Windjammer Vicinity

A. Spring/Summer 2013: Public meetings, Council deliberations establish policy, guiding principles

– Property acquisition

– Use of open space

– Additional features/benefits associatedwith facility

– Integration with othernearby land-use plans

Page 29: 130306 city council workshop revised

Oh910i1-8594.pptx/29Oh910i1-8594.pptx/29

Step 2 – Select Final WWTP Location Within Windjammer Vicinity

B. Summer/Fall 2013: Working Group Meetings, Charrette leverage public input to develop options within Windjammer Vicinity

Page 30: 130306 city council workshop revised

Oh910i1-8594.pptx/30Oh910i1-8594.pptx/30

Step 2 – Select Final WWTP Location Within Windjammer Vicinity

C. Fall 2013: Project team presents analysis of options to City Council for decision

– Confirm Value Engineering Recommendations

– Confirm treatment facility location

– Confirm approach to integrate facility into surroundings

• Transportation

• Parks/Open Space

• Commercial/Retail

• Government/Public Facilities

Page 31: 130306 city council workshop revised

Oh910i1-8594.pptx/31Oh910i1-8594.pptx/31

Step 3 – WWTP Preliminary Design

A. Fall 2013: Procure key process equipment for design (membranes, UV) based on qualifications and competitive pricing

Page 32: 130306 city council workshop revised

Oh910i1-8594.pptx/32Oh910i1-8594.pptx/32

Step 3 – WWTP Preliminary Design

B. Combine technical detail, public input to develop final “look & feel” of facility

Concept inspired by June 2012 Charrrettprocess.

Page 33: 130306 city council workshop revised

Oh910i1-8594.pptx/33Oh910i1-8594.pptx/33

Step 3 – WWTP Preliminary Design

B. Combine technical detail, public input to develop final “look & feel” of facility

Alternate concept showing potentially different site use.

Page 34: 130306 city council workshop revised

Oh910i1-8594.pptx/34Oh910i1-8594.pptx/34

Step 3 – WWTP Preliminary Design

B. Combine technical detail, public input to develop final “look & feel” of facility

Working Group Meetings

throughout preliminary

design.

Page 35: 130306 city council workshop revised

Oh910i1-8594.pptx/35Oh910i1-8594.pptx/35

Step 3 – WWTP Preliminary Design

C. Develop drawings and specifications to 30 percent level detail

D. Evaluate alternatives to complete the Project– Design-Bid-Build– Design-Build– General Contractor/Construction Manager

E. Spring 2014: Select delivery option and proceed to final design in early 2014

Page 36: 130306 city council workshop revised

Oh910i1-8594.pptx/36Oh910i1-8594.pptx/36

Step 4 – Outfall Final Design

• “Fast track” to provide necessary information for permitting

• Complete in parallel with Steps 1 – 3• Design complete in fall 2013• Construction possible in 2014, pending

results of construction delivery analysis

Page 37: 130306 city council workshop revised

Oh910i1-8594.pptx/37Oh910i1-8594.pptx/37

Significant Council Actions & Decisions

Date Action/Decision

Mar 19, 2013

Council authorizes submission to Ecology; Approves next phase of project

Summer 2013

Council sets policy and guiding principles to select final location

Fall 2013Council selects final location of treatment facility

Spring 2014Council approves approach to complete project

Page 38: 130306 city council workshop revised

Oh910i1-8594.pptx/38Oh910i1-8594.pptx/38

Overall Project Schedule

OAK HARBOR CLEAN WATER FACILITYPROPOSED SCHEDULE FOR PROJECT COMPLETION

2013 2014 2015 2016 2017

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

PREDESIGN PHASE

APPROVEFACILITIES PLAN

CONSTRUCTION PERIOD

START UP

Agency DraftSubmission

Submit Plans & Specs

FINAL DESIGN PHASE

Page 39: 130306 city council workshop revised

Oh910i1-8594.pptx/39Oh910i1-8594.pptx/39

How can I stay involved?

Page 40: 130306 city council workshop revised

Oh910i1-8594.pptx/40

Send an email or give us a call if you would like to participate:

Joe Stowell, City Engineer 360-279-4520 [email protected]

Page 41: 130306 city council workshop revised

Oh910i1-8594.pptx/41Oh910i1-8594.pptx/41

Questions?