14 June 2011
Integrating biogas in the regional gas grid
![Page 2: 14 June 2011 Integrating biogas in the regional gas grid](https://reader036.vdocuments.net/reader036/viewer/2022062511/551a7073550346b52d8b4f13/html5/thumbnails/2.jpg)
14 June 2011
Renewable gases
Renewable Biomass
Gasification
Anaerobic digestion
Direct use
Upgrading
Upgrading
Natural gas grid
Biomethane
Biogas
Bio Synthetic Gas
Dedicated grid
Cleaning
Cleaning
![Page 3: 14 June 2011 Integrating biogas in the regional gas grid](https://reader036.vdocuments.net/reader036/viewer/2022062511/551a7073550346b52d8b4f13/html5/thumbnails/3.jpg)
14 June 2011
1
2
3
Three current feed-in projects
1. De Marke, Hengelo (Gld)
2. Schoteroog, Haarlem
3. HVC, Middenmeer
![Page 4: 14 June 2011 Integrating biogas in the regional gas grid](https://reader036.vdocuments.net/reader036/viewer/2022062511/551a7073550346b52d8b4f13/html5/thumbnails/4.jpg)
14 June 2011
De Marke, Hengelo (Gld)
Specifications
• Parties involved: Wageningen UR Livestock Research, GreenChoice
• Source: Manure (cows)
• Upgrading: Gas washing
• Max. flow: 14 m3/hr
• Location: Hengelo (Gld)
• Gas pressure: 100 mbar
![Page 5: 14 June 2011 Integrating biogas in the regional gas grid](https://reader036.vdocuments.net/reader036/viewer/2022062511/551a7073550346b52d8b4f13/html5/thumbnails/5.jpg)
14 June 2011
Schoteroog, Haarlem
Specifications
• Parties involved: Essent, Gas Treatment Services, NV Afvalzorg, Hoogheemraadschap Rijnland en Gemeente Haarlem
• Source: Landfill and waste water treatment plant
• Upgrading : GPP® - cryogene technique
• Max. flow: 300 m3/hr – 1000 m3/hr
• Location: Haarlem
• Gas pressure: 4 bar
![Page 6: 14 June 2011 Integrating biogas in the regional gas grid](https://reader036.vdocuments.net/reader036/viewer/2022062511/551a7073550346b52d8b4f13/html5/thumbnails/6.jpg)
14 June 2011
HVC, Middenmeer
Specifications• Parties involved: HVC, DHV• Source: Compostable waste• Upgrading: Gas washing• Max. flow: 1000 m3/hr• Location: Middenmeer• Gas pressure: 8 bar
![Page 7: 14 June 2011 Integrating biogas in the regional gas grid](https://reader036.vdocuments.net/reader036/viewer/2022062511/551a7073550346b52d8b4f13/html5/thumbnails/7.jpg)
14 June 2011
Pattern of gas demand
Example for an 8 bar grid
![Page 8: 14 June 2011 Integrating biogas in the regional gas grid](https://reader036.vdocuments.net/reader036/viewer/2022062511/551a7073550346b52d8b4f13/html5/thumbnails/8.jpg)
14 June 2011
Optimal location choice
Location & opportunities
– Feed in location: Highway or Dirt Road
– Optimal solution; costs
– Central Upgrade Unit
– Injection 40 Bar?
– Demand vs. Production
![Page 9: 14 June 2011 Integrating biogas in the regional gas grid](https://reader036.vdocuments.net/reader036/viewer/2022062511/551a7073550346b52d8b4f13/html5/thumbnails/9.jpg)
14 June 2011
Feed-in station
Monitoring:
• Chemical composition
• Pressure
• Volume flow
Including:
• Filter
• Safety valves
• Data communication
![Page 10: 14 June 2011 Integrating biogas in the regional gas grid](https://reader036.vdocuments.net/reader036/viewer/2022062511/551a7073550346b52d8b4f13/html5/thumbnails/10.jpg)
14 June 2011
Biogas in the natural gas grid
![Page 11: 14 June 2011 Integrating biogas in the regional gas grid](https://reader036.vdocuments.net/reader036/viewer/2022062511/551a7073550346b52d8b4f13/html5/thumbnails/11.jpg)
14 June 2011
Biogas grids
Gas Station
User 2
Prod 2
Prod 1
User 1
40 Bar
8 bar
Injection: If demand all users < producers
![Page 12: 14 June 2011 Integrating biogas in the regional gas grid](https://reader036.vdocuments.net/reader036/viewer/2022062511/551a7073550346b52d8b4f13/html5/thumbnails/12.jpg)