14 th esls rf meeting – trieste, september 2010 alba rf status 1/28 alba rf status francis perez
TRANSCRIPT
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 1/28
ALBA RF StatusFrancis Perez
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 2/28
The RF Group: Paco Sanchez
Angela Salom
Bea Bravo (since Oct. 2009)
Support Engineering DivisionSupport Computing DivisionSupport Operators Group
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 3/28
• ALBA overview and status
• Booster RF System
• Storage Ring RF System
• Next
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 4/28
Synchrotron Light Source in Cerdanyola (Barcelona, Spain)
December 2009
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 5/28
ALBA Accelerators
LINAC100 Mev
BOOSTER100 MeV – 3 GeV
STORAGE RING3 GeV
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 6/28
Booster commissioning started:- 2 weeks in January- 2 weeks in July- Afternoons since Monday 27.09
SR installation completed. Some testing of subsystems pending. SR commissioning starts November 2010 without IDs.
SR commissioning with IDs by March 2011
1st beam for beamlines commissioning April 2011
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 7/28
“Stored Beam 100 MeV”: RF ON
5 seconds,5 injections
BOOSTER COMMISSIONING
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 8/28
1st Synchrotron Light in Spain
BOOSTER COMMISSIONING
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 9/28
90 % Energy
and
70% current
of nominal values
2.7 GeV with 0.7 mABOOSTER COMMISSIONING
January 2010
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 10/28
Booster RF System
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 11/28
Booster Transmitter
Spring 2009:
DC Commissioning (with Thomson)
Oct - Nov 2009:
RF Power Commissioning (with Thomson)
-RF shutter closed and full RF power on load-
SAT passed on November 5th, 2009
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 12/28
Booster Cavity
November 2009:
Cavity installed and aligned
Vacuum OK
Cabling and Sensors installed
Water cooling connected
Air cooling (RF window and WATRAX)
EPS and interlock OK
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 13/28
Booster LLRF: Conditioning and Calibration
Nov – Dec 2009:
Full RF Plant ready Tunnel closed (Operation in parallel with the Bo PS testing) 60 kW in the cavity (35 kW used during Booster commissioning) Calibration done Closed Loop Calibration
0
5
10
15
20
25
30
35
40
45
0 100 200 300 400 500 600
Cavity Voltage [mV]
RF
Po
we
r [k
W]
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 14/28
LLRF: Automatic Start upFeb 2010:
After the experience during the Booster commissioning
To easy the recovery after a trip To avoid operator errors
Automatic Start up:
Stored Beam: RF ON
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 15/28
RF Power
Automatic Start up:
- After a trip LLRF set all parameters to minimum:- Low RF drive- Disable tuning - Open loops (I&Q)
- Operator reset the interlock and switch on the transmitter- LLRF detect the presence of RF power at cavity input- LLRF tune the cavity before allowing high power- LLRF close the loops and check loops stability- Smooth power increase- Message RF ready for beam
Tuning pulses
Plungers direction
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 16/28
Storage Ring RF System
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 17/28
Layout 6 cavities
Dampy
CaCo
IOT
Load
Circulator
Watrax
DigIQAnIQ
Control System
DigitalLLRF
RF Voltage 3600 kV
TRANSMITTER
Tube type IOT
Number 6 x 2 IOTs
Power 2 x 80 kW
Combination CaCo
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 18/28
SR Transmitters
March - September 2010:
RF Commissioning (with Thomson)
12 SR transmitters has passed the SAT
Details by Paco Sanchez
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 19/28
SR Dampy Cavities
April 2009 to January 2010
Dampers flanges temperature behaviour
Dampy 01 - Nov08: T [ºC] = 1,61 P[kW] + 23,2
Dampy 01 to 06, average: T[ºC] = 0,20 P [kW] + 23,6± 0,06 ± 0,5
0
10
20
30
40
50
60
0 10 20 30 40 50 60 70 80 90
Power [kW]
Tem
pera
ture
[ºC
]
Conditioning at RF lab
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 20/28
SR Dampy Cavities
All 6 performing well
Installed and bake-out in situ
Alignment, cabling and cooling ready
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 21/28
Waveguide system: Circulator problemsFerrite Inc. (USA)
Control by minimising the VSWR: - Measure forward and reflected power
- Compute VSWR
- Act on the PS of the circulator
Problems during cavity conditioning:
Pulsed conditioning: No responding due to slow control
CW conditioning: During autotune it changes slightly the IOT load, i.e. IOT power, so sudden increase of power to the cavity and (ussualy) a vacuum trip.
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 22/28
Waveguide system: Circulator problems
Solution:
Condition the cavities with the circulator on Manual Mode(no very convenient, but ok)
In addition we have to send a circulator back to Ferrite since it was wrongly adjusted to cope with 160 kW of power.
Bias current drift
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 23/28
Digital LLRF System
All modules installed:
Analogue Front ends
Amplitude and Phase Control Loop
Tuning loop
Timing system
RF detectors
Arc detector
Fast Interlock Modules (FIM)
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 24/28
Conditioning and Calibration
June – September 2010:
All RF Plants ready Cavities:
Four cavities conditioned up to 70 kW One cavity under conditioning this week Last cavity under cooling reparation (flowmeters)
Calibration on going
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 25/28
NEXT:
Linac RF pulse digitalisation:
…
CaCo improvement:
See Bea presentation
ALBA commissioning:
Linac + Booster + SR + Beamlines
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 26/28
RF Linac Pulses Characteristics RF Frequency: 500MHz & 3GHz
Pulse width: 4μs
Repetition rate: 1Hz – 3Hz
Available RF SignalsFw PB1, FwPB2 & FwB, FwK1 & FwK2, FwAS1 & FwAS2
Linac RF pulse digitalisation
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 27/28
0.5 1 1.5 2 2.5 3 3.5
x 105
0
5
10
15
20
25
30
35
t(ns)
mV
- (
º)
I (mV)
Q(mV)Amp (mV)
Phase(º)
2.66 2.67 2.68 2.69 2.7 2.71
x 105
0
5
10
15
20
25
30
35
t(ns)
mV
- (
º)
Amp (mV)
Phase(º)
Front EndDownconversion of 3GHz signals to 500MHz (IF)LO: 3.5GHz
Digital Board 8 ADCs and Virtex-4 IF signals undersampled at 80MHz Amp & Ph information to CS
Control System (CS)At present: Manual Phase adjustment of RF signals Next Step: Automatic phase adjustment
First Tests (4us pulse)Amp Error: 0.2mVpp
Phase error : 0.6ºpp
2.675 2.68 2.685 2.69 2.695
x 105
33
33.5
34
t(ns)
mV
- (
º)
Amp (mV)
Phase(º)
2.66 2.665 2.67 2.675 2.68 2.685 2.69 2.695 2.7
x 105
4
4.5
5
5.5
6
t(ns)
mV
- (
º)
Amp (mV)
Phase(º)
Pulse 4us Amplitude Resolution
Phase Resolution
14th ESLS RF Meeting – Trieste, September
2010
ALBA RF Status 28/28
Thank you