15.project report - uwssrp1 - masvingo final draft
TRANSCRIPT
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 1
TECHNICAL PROJECT
REPORT
October
2013
To
May 2015
Rehabilitation of Water and
Sewage Systems in
Masvingo, Zimbabwe.
REHABILITATION OF WATER
AND SEWAGE SYSTEMS IN
MASVINGO, ZIMBABWE.
Contents Page
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 2
Chapter
Page
i. PREFACE
3
ii. ACKNOLEDGEMENTS
3
iii. INTRODUCTION
4
1. THE PROJECT 5
2. BUSHMEAD WATER TREATMENT WORKS
6
2.1. Raw Water Intake 7
2.1.1. Challenges 8
2.2. Flow Regulation 9
2.3. Flow Measurement and Aeration
9
2.4. Activated Carbon Addition 9
2.5. Coagulation 9
2.6. Flocculation and Sedimentation
10
2.7. Filtration 10
2.7.1. Challenges 11
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 3
2.8. Chlorination 12
2.8.1. Challenges 12
2.9. Treated Water Pump Station
12
3. RAW SEWAGE PUMPING 13
3.1. Raw Sewage Pump Station No.1
13
3.2. Rujeko Raw Sewage Pump Station
14
4. MASVINGO SEWAGE TREATMENT WORKS
15
4.1. Preliminary Treatment
16
4.2. Primary Treatment
16
4.3. Secondary/ Tertiary Treatment
17
4.3.1. Biological Filtration
17
4.3.1.1. Challenges 20
4.3.2. Biological Nutrient Removal Plant
20
5. SITE ORGANISATIONAL STRUCTURE
22
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 4
6. ROLES AND RESPONSIBILITIES
23
7. SUMMERY OF CONTRACT INFORMATION
24
8. CHALLENGES 24
9. CONCLUSSION 25
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 5
i. PREFACE
This report is part of the requirements by the Zimbabwe Institute
of Engineers for registration as a Civil Engineering Technician. It
aims to show the relevant working experience I gained during the
implementation of Masvingo Water Supply and Sanitation
Rehabilitation Project from October 2013 to May 2015. Although
the project did not touch each and every component of
Masvingo’s Water and Sewage Treatment systems, I have included
description of the treatment processes. However, I gave more
emphasis to sections that the Project directly focused on for
example where equipment was replaced or refurbished. This
report also shows how implementation of the project had an
effect on the sewage and water treatment systems of Masvingo
City Council.
ii. ACKNOWLEDGEMENTS
Credit in preparing this report is given to all various organisations
that made it possible for me to be part of the Urgent Water Supply
and Sanitation Rehabilitation project in Masvingo City. I am
thankful of all my work colleagues for their aspiring assistance,
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 6
invaluably beneficial criticism and friendly advice during the
course of the project and during preparation of this report.
Sincere and grateful appreciation is also given to the above
mentioned for sharing their truthful and illuminating views on a
number of issues integrated in this report.
iii. INTRODUCTION
I had just returned home to Zimbabwe for a short break from my
work in South Africa and the advertisement for position of Clerk
of Works from Brian Colquhoun Hugh O’Donnell and Partners
caught my eye. I made some further enquiries and found out what
the job entailed.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 7
The job was to be based in Masvingo Town where an Urgent Water
and Sanitation Rehabilitation Project was to be implemented. The
job specifications included site supervision and inspection of
civil, mechanical and electrical works related to water and sewage
treatment systems; Assisting the Resident Engineer to apply and
maintain the Contract Plan; Monitoring of work to ensure
compliance with specifications; Compiling and summarising
materials data; Measurement of the works and agreement of
quantities with the contractor; Maintenance of daily diaries and
weekly reports.
The successful candidate would report to the Resident Engineer
as well as to the Project Managers.
To prepare myself for the interview, I read books and browsed the
internet for information on Water and Sanitation infrastructure
and processes. This tremendously helped me for any eventuality
in any Municipal Water Supply and Sanitation Rehabilitation work
as Technician and further helped me spruce up my otherwise
decaying knowledge on Water Supply and Sanitation that I learned
at college ten years back.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 8
1. THE PROJECT
I was offered the job as a Clerk of Works with an initial contract
of ten months which could be extended on condition that the
project I was to be involved in was also going to be extended.
The project entailed implementation of the Urgent Water Supply
and Sanitation Rehabilitation Project (UWSSRP) in the City of
Masvingo in Zimbabwe (the beneficiary). The original value of the
project was US$2,850.000.00 approximately and the
implementation period was 10months in the contract. The project
was funded by Zimbabwe Multi-Donor Trust Fund (Zim-Fund)
administered by the African Development Bank (ADB) and The
Crown Agents for Oversea Governments and Administrations
Limited (Crown Agents) was the Procurement Agent. I was an
employee of Brian Colquhoun Hugh o’Donnell and Partners
(BCHOD). Lahmeyer GKW Consult and its local partner Brian
Colquhoun Hugh o’Donnell and Partners (BCHOD) were mutually
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 9
the Implementing Entity. Technofab - Gammon Joint Venture
(TGJV) was the contractor.
The project comprised of the repair and or replacement of critical
components of the water supply and sewage systems located in
Masvingo in order to restore operations and increase capacity of
services provided by the Municipality. The project focused on
rehabilitation of three sections of the water supply and sanitation
infrastructures of Masvingo City Council namely; Bushmead Water
Treatment Works, Sewage Treatment Works, Raw Sewage
Pumping Stations.
My duties were to measure works done by the contractor for
payments purposes and ensuring that the contractor executed
the works according to the contract specifications. My daily work
included progress tracking by recording daily works done and
capturing weekly progress. It was my duty to ensure that good
workmanship was achieved during work. I was responsible for
keeping records including Site diaries, instructions, progress and
programme records and keeping measurement records.
Inspection of the works, identification of defects was also part of
my work. I was also ensuring that safe methods of working were
used by the contractor by enforcing the use of proper personal
protective equipment and by assessing and reporting on
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 10
environmental damage caused by the works. My other duties were
to capture minutes of technical meetings.
2. BUSHEMEAD WATER TREATMENT WORKS
The City of Masvingo gets its water from Lake Mutirikwi which
also provides water for the irrigation of nearby sugar plantations.
Masvingo Water Treatment Process has six main stages namely
abstraction, conveyance, sedimentation, filtration, chlorination
and pumping. Below is the process flow chart for Bushmead Water
Treatment works.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 11
Bushmead Water Treatment Flow Chart
2.1. RAW WATER INTAKE
Raw water is extracted from Lake Mutirikwi at the intake tower.
The design set up is that there is provision for three vertical
turbine pumps with an operational system of two on duty and one
stand-by. The purpose of the Vertical Turbine Pumps is to convey
raw water from Lake Mutirikwi to the Treatment plant through
two parallel pipelines of 300mm and 400mm diameters.
Before the Urgent Rehabilitation project, only one pump was
running. The second pump was due for services and the third
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 12
pump was down. The Municipality was operating with only one
raw water vertical turbine pump and the City was running dry
during breakdowns.
During the Project two new raw water vertical turbine pumps with
the following characteristics; System head 66m, flow 600 m3/hr
were supplied and installed. Gate valves, non-return valves and
air release valves for the two pumps were also installed during
the project.
Installation of 400 V, 3 phase, 50 Hz main switch panel with
voltage protection unit was also installed.
Minor civil works were also done during the rehabilitation of the
intake tower and they mainly comprised of internal and external
painting works.
After installation of the pumps was complete we tested the
capacity of the pumps to check if they had the required
characteristics by use of flow meter and flow charts. The two new
pumps had an average capacity of approximately 800m^3/hr.
The picture below was captured during the installation of the
vertical turbine pumps.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 13
Installation of vertical turbine pumps
2.1.1. Challenges
During the installation of the two new vertical turbine pumps, one
of the challenges that we faced was that the two new pumps and
motors were bigger than the existing pumps and motors. This
caused the new equipment not to fit in the space within the tower.
To resolve this problem, the overhead slab above the pumps were
trimmed in order to accommodate the protruding motors. The
other challenge was that flanges on the existing pipework did not
match with some flanges on the new equipment. They had
different number and size of holes. This delayed the installation
time frames and conclusively installation of pump and
components being completed outside shut down periods.
Thorough checking of all components to be installed had to be
done to compare with the existing equipment in order to limit
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 14
delays due to incompatibility of new and existing components.
Personally I had challenges in the inspection of electrical
components of the control panels since I do not have a typical
electrical bare ground. This was a challenge and a learning point
throughout the whole project.
2.2. FLOW REGULATION
The vertical turbine pumps convey raw water up to the inlet
control valve. The system design at Bushmead Water Treatment
Works has one butterfly valve used for controlling or regulating
the flow of raw water into the inlet channel. The existing butterfly
valve which was out of order was replaced with a new butterfly
valve. Removal of the existing control valve was a challenge since
it had been worn out and dilapidated for years.
2.3. FLOW MEASUREMENT AND AERATION
From the flow regulation chamber, the raw water passes through
another chamber with a V-Notch which serves the purpose of
measuring discharge into the inlet channel. Turbulences in this
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 15
chamber also have an aeration effect to the raw water before it
enters the inlet channel. This is the initial stage in the treatment
process of the raw water at Bushmead were oxygen is added.
2.4. ACTIVATED CARBON ADDITION
Originally the water treatment system at Bushmead did not
incorporate activated carbon addition. However, this is
improvised during periods of high pollution in Lake Mutirikwi. To
tailor the high pollution periods, activated carbon is manually
dosed at the mouth of the inlet channel. Activated carbon
removes the bad odours that are caused by high pollution of the
water source.
2.5. COAGULATION
Coagulation is the addition of a coagulant to capture impurities
and stick them into larger particles. At Bushmead Water
Treatment Plant aluminium sulphate is added at the inlet channel
for this process. The municipality has improvised some buffers
along the channel to create turbulences that create a uniform
mixing effect of the coagulant and the raw water before it reaches
the sedimentation tanks.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 16
2.6. FLOCULATION AND SEDIMENTATION
After addition of the coagulant at the inlet channel, the water
passes through conical basins. This is where the impurities stick
together into larger particles due to the effects of the coagulant.
The larger particle that form during this process are called flocs
and the process is known as flocculation. The flocs become
heavier and sink at the bottom in a process called sedimentation.
There are ten sedimentation tanks at Bushmead water treatment
works. At the Masvingo Water Treatment Plant the heavier flocs
are collected from the bottom of the basins as sludge and are
disposed into a small pond before being dumped on a small
Banana field. Water is collected from the top section of the basins
and is conveyed to the filter beds for further treatment processes.
2.7. FILTRATION
Water collected from the top side of the sedimentation tanks
passes through eight filter beds for the next stage of treatment.
At this stage water travels through large filter beds of sand to
remove any remaining microscopic particles or micro-organisms.
At Bushmead Water Treatment Works, water is pre-chlorinated
before passing through the filter beds if the pollution levels of
the raw water are higher than normal. Aeration and backwashing
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 17
systems are used to cleanse the filter materials of sludge that
clogs during the filtration process. The main components of the
filtration process are the filter beds, air-blowers and backwash
pumps. During the project, two new horizontal, single end –
suction, centrifugal pumps were supplied and installed with
motors. They had a head 10m and flow of 1000m^3/hr. Four cast
iron gate valves and two check valves were also installed.
One rotary piston roots type air-blower with motor was also
supplied and installed to replace the existing broken down one.
The backwash system was designed for two pumps operating as
one duty one standby and the air blower system was designed to
operate as one duty and one standby. Two new electric panels for
the air blowers and back wash pumps were installed with starter
switches, emergency stop switches, voltage protection and surge
protection units.
2.7.1. Challenges
Most of the challenges on the back-wash pumps and the air-
blower were faced during the testing phase. The main challenge
we faced with the back-wash pumps was the breaking of
couplings between the motor and the pump. This problem caused
numeral breakdowns and shut downs of water supply to the
users. The main cause of this problem was identified to be miss-
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 18
alignment of the pump and the motor. To rectify this problem a
more accurate method of aligning i.e. laser alignment was used
instead of the traditional manual alignment. The air blower also
had challenges tripping and cutting airflow during the testing
period. This hindered the normal procedure for filter media
backwashing. The main cause of this problem was identified to
be the small air release valve and a larger size of valve was
installed to solve this problem.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 19
2.8. CHLORINATION
The existing chlorination system at Bushmead Water Treatment
Plant was failing to dose the water during times of high pollution
levels in the source river. To cater for these periods of high
pollution the municipality had improvised a pre-chlorination
method by use of a tank a hose pipe dosing directly into the
channel before the filters. The existing chlorinator had a capacity
of 4mg/l. A new standby chlorinator and control panel with a
capacity of 20mg/l was supplied and installed. Chlorine cylinder
tank, liquid trap, gas detector, emergency kit and other related
items were supplied/ installed. Refurbishment of the chlorinator
room was also done to upgrade the facility. Refurbishment
included painting, installation of ventilators and chlorine
detectors.
2.8.1. Challenges
The main challenge that we faced during installation and testing
of the chlorinator was that the existing water pipe system feeding
the chlorinator was of a smaller size and did not have enough
pressure required by the new chlorinator. This reduced the
dosing capacity specified in the contract. To rectify this problem
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 20
a variation was made to install 50mm diameter pipe work to feed
the new chlorinator in order archive the specified dosing capacity.
2.9. TREATED WATER PUMP STATION
The project included supply and installation of one new set of
high lift pump unit, actuated suction and discharge valves with
bypass valves, two new actuated delivery valves with bypass
valves for the existing high lift pump units. Electric panels for the
high lift pumps, air-blowers and back wash pumps and low lift
pumps at the intake tower. Suction and delivery pressure gauges
for the new pump were also installed during the project.
High Lift Pump Installation
The electrical works comprised of installation of control panel and
motor starters. Replacement of 250W flood lights was done for
the whole treatment plant to improve lighting.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 21
3. RAW SEWAGE PUMPING
There are two raw sewage pump stations in Masvingo namely
Rujeko Pump Station and Pump Station No.1.
3.1. RAW SEWAGE PUMP STATION NO.1
Raw Sewage Pump Station No. 1 was designed to operate with two
pumps on duty and one on standby. Before the ZIMfund/ AfDB
project, all three pumps were not operational and had been
dismantled and removed from the pump room. The UNICEF
contract had supplied two new pumps however installations had
not been done.
The civil works included survey works & designs for remedial
works to correct overflow problems and modification to the pump
station overflow to prevent premature spillages into Mucheke
River. The works involved levelling of the overflow structures.
Upgrading of the pump station building was done during the
project and comprised of interior wall painting, installation of new
windows, new doors, new gutters & down- pipes and new site
fencing. Surface treatment of all metal works comprising of hand
- railings, walkways, chequer plates etc. was also part of the civil
works package.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 22
Supply and installation of a new horizontal, single end-suction,
centrifugal pump with 40 m head and 700 m3/h flow was done
at the pump station complete with a motor, two gate valves and
one check valve. The two pumps that had been supplied under
the UNICEF contract were also installed during project.
A new electric panel was also supplied and installed complete
with motor starters, emergency stop switches and protection
units.
3.2. RUJEKO RAW SEWAGE PUMP STATION
Rujeko Pump station was designed with three raw sewage pumps
operating as two on duty and one on standby. Only one pump
was operational before the AfDB project and raw sewage often
spilled into the nearby Mucheke river.
Civil works the we carried out included upgrading of the site
buildings comprising of interior wall painting, installation of new
windows, new doors, painting of the existing site fencing,
upgrading of the site new facility, surface treatment of metal
works like hand - railings, walkways, chequer plates etc.
Supply and installation of two new horizontal, single end-suction,
centrifugal pumps with electric motor drives was done during the
project. The two pumps had characteristics of 40 m system head
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 23
and 750 m3/h flow. All the accessory valves were also supplied
and installed.
A new electric panel was supplied and installed complete with
motor starters, emergency stop switches and protection units.
A new standby generator was Supplied and installed. The
generator was a 400V, 150KVA complete with weather proof
enclosure and changeover switch to feed pump No. 3.
4. MASVINGO SEWAGE TREATMENT WORKS
Masvingo Sewage Treatment Plant was designed to treat raw
sewage from the residential area. The raw sewage is pumped
from two pump stations namely Sewage Pump Station No.1 and
Rujeko Pump Station. Raw sewage from a nearby Army Barrack is
also treated at the plant.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 24
Masvingo Sewage Treatment works has four main stages namely
Preliminary, Primary, secondary/ Tertiary and Effluent disposal.
4.1. PRELIMINERY TREATMENT
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 25
The preliminary stage comprises of; inlet works that collect raw
sewage from Barracks, Rujeko and Sewage Pump Station No.1;
Course and fine screens that remove debris, rags, papers,
plastics, bottles and other large materials that may cause damage
or blockages in pipes; Grit channels that remove heavy organic
suspended solids (grit) from the waste water. Only installation of
handrails (60m) on the grit channels was done during the project.
4.2. PRIMARY TREATMENT
This stage comprises of the primary sedimentation tanks.
Masvingo sewage treatment plant has four primary sedimentation
tanks. The purpose of these tanks is to separate solid organic
matter from the liquid waste. Solid matter settles at the bottom
and the liquid waste floats on top.
During the project, all four primary sedimentation tanks were
rehabilitated since they were not operational. Rehabilitation
included desludging of the tanks, supply and installation of gate
valves, penstock gates, scum pipes, weir plates, pipe work and
protective coating.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 26
4.3. SECONDARY/ TERTIARY TREATMENT
The main purpose of tertiary treatment is to restore waste water
to a state where it can be safely disposed back to the water course
or ground. This is basically achieved by reducing the levels of
nitrates and phosphates. At Masvingo Sewage Treatment Plant
there are three types of tertiary treatment namely; anaerobic
digestion, biological filtration and biological nutrient removal.
Raw sewage from the grit channels at Masvingo Sewage
Treatment is diverted to the Biological Nutrient Removal Plant for
tertiary treatment and/or to the primary sedimentation tanks.
Sludge collected from the bottom of the primary sedimentation
tanks is diverted to the anaerobic digesters for tertiary treatment
as well. Liquid waste collected from the top of the sedimentation
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 27
is conveyed to the trickling filters for tertiary treatment. For the
purposes of this project report, I will emphasis on the biological
filtration and biological nutrient removal components where
rehabilitation works where involved.
4.3.1. Biological Filtration
Masvingo has three trickling filters for processing liquid waste
from the sedimentation tanks. Liquid waste or supernatant from
the primary sedimentation tanks is sprinkled on to the trickling
filter media (stones). Micro-organisms that culture on the
surfaces of the filter media basically feed on nitrogen, organic
carbon compounds and phosphates releasing water, carbon
dioxide, humus sludge and nitrogen compounds there by treating
the liquid waste. The treated water (effluent) is collected from the
bottom of the tanks and is used for irrigating a nearby farm, the
sewage works area and is also recirculated back to the primary
sedimentation tanks for the removal of scum.
The three trickling filters had not been operational before the
project and were clogged with sludge. The distribution arms,
centre pivots and components had been corroded and
dilapidated.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 28
During the project, the filter media was removed up to a depth of
2m, cleaned to wash away sludge and replaced back into the
tanks. Remedial works to spalling concrete and exposed rusting
reinforcement was also done to the tanks. The distribution arms
and stay rods were replaced with new ones. The centre pivots
were repaired. Repair of broken down hand rails and protective
coating was done on the trickling filters.
Effluent from the trickling filter is collected from the bottom of
the tanks and conveyed to the effluent ponds at the treatment
works. This effluent is used for irrigating a nearby farm in
Masvingo and also for irrigating the plant’s area. Some of the
effluent is recirculated back to the primary sedimentation tanks
for scum removal. Effluent recirculation and discharge is done at
the effluent pump station.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 29
Before the project, all two effluent discharge pumps and two
effluent recirculation pumps where broken down. Raw liquid
waste was just passing through inlet works, PSTs, Trickling filters,
effluent pond and finding its ways to the nearby stream since all
pumps were down.
The two effluent disposal pumps were replaced with two new
vertical centrifugal pumps and motors with characteristics of 80m
system head and 250 m3/hr flow together with two gate valves,
check valves and air release valves. The effluent recirculation
pumps were also replaced with two new vertical centrifugal
pumps and motors with characteristics of 10m head and
62m^3/hr flow together with gate valves, check valves and air
release valves.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 30
New control panels for effluent disposal and recirculation pumps
were also supplied and installed with motor starters, emergency
stop switches, voltage protection, surge protectors and float
switches.
The pump house was rehabilitated by painting and repairing
broken down windows and doors. Installation of 10 new pole
mounted flood lights was done and 8 existing pole mounted flood
lights were refurbished. All internal lighting for the pant buildings
was also refurbished during the project.
Before & After Rehabilitation of the Effluent Pump Station
4.3.1.1. Challenges
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 31
The main challenge that was faced during rehabilitation of the
filtration process was during cleaning of the filter media. There
were no drawings for the trickling filter to refer to during our
work. This delayed our work since extra care had to be taken in
order not to damage unforeseen components within the media.
However, with the assistance and consultation from the
Municipality’s staff we were able to overcome this problem. The
other challenge was that it was difficult to use heavy equipment
operating from ground due to the height of the tanks (3m) and
operation with manual labour delayed progress as well. We had
to erect ramps and platforms on the tanks so that the equipment
would be able to remove the media without damaging it.
4.3.2. BIOLOGICAL NUTRIENT REMOVAL PLANT
The third tertiary treatment of sewage in Masvingo is the Bio-
Nutrient Removal process. This process removes nitrogen and
phosphorous before disposal into the nearby stream, Shagashi.
Removing nitrogen and phosphorous also reduces the bio-
oxygen demand by reducing the amount of organic substances
that consume oxygen. At Masvingo Sewage Treatment Plant, this
is the only process that produces a blue category of effluent
which may be disposed directly into the stream.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 32
The Bio-Nutrient Removal Plant mainly consists of three zones
namely the aerobic zone, anaerobic zone and anoxic zone.
Aerobic bacteria develop in the aerobic zone and decomposes
almost all of the dissolved organic matter in the waste water. The
aerobic zone is adjacent to an anoxic zone, where most of the
nitrification occurs. The anaerobic zone is where digestion of
waste takes place in the absence of oxygen. The content of the
tank is kept homogenous by using large mixers and aerators, and
the sewage is re-circulated numerous times between the three
zones to attain maximum treatment using Return Activated
Sludge pumps. The resultant liquid is taken from the top layer of
the BNR basin and collected into secondary sedimentation tanks
(clarifiers) to separate the liquid from the solids.
Supernatant liquor will form on the top layer of the clarifier ready
for disposal into the river.
Sludge will settle at the bottom of the clarifier and is re-circulated
or pumped back into the BNR system to maintain the amounts of
cultured micro-organisms. This is known as the Return Activated
Sludge.
Excess sludge or Waste Activated Sludge is collected in the two
settlement tanks for thickening and then pumped by diaphragm
pumps and disposed onto the Town Council’s gumtree
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 33
plantation. Some of the waste sludge is pumped back to the BNR
to increase or maintain the number of micro-organisms. The
liquid collected from the top of the thickeners is conveyed to the
effluent pump station. Contents from the thickener are not
disposed directly into the river since they have micro-organisms
that will reduce oxygen levels in the water there by killing life.
Before the project, the BNR plant was not operational and sludge
had settled and solidified at the bottom. Some sections had
floating islands with fully grown grass and reeds within the BNR
plant. The aerators and mixers could not rotate in these
conditions. During the project, removal and disposal of the
sludge in the plant was the only work done on the BNR plant.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 34
Disludging of the BNR Plant
Surface treatment, painting and protective coating of all metal
works like hand railings, walkways and bridges was done on the
clarifiers.
Two new axial flow Propeller pumps with motors for return
activated sludge with 0.4 m system head and 156 l/s flow were
supplied and installed during the project.
A new control panel with motor starters, emergency stop
switches, voltage and surge protection units for the RAS pump
control room was supplied and installed.
For the thickeners, two new variable speed air operated
diaphragm pumps with 27m head and 2.5l/s flow where supplied
and installed complete with 2 gate valves and check valves. A new
compressor with a capacity of 3.4m^3/min was also supplied and
installed complete with a motor for the treatment plant. A control
panel for the diaphragm pumps was also supplied and installed
complete with motor starters, emergency stop switches and
protection units.
5. SITE ORGANISATIONAL STRUCTURE
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 35
6. ROLES AND RESPONSIBILITIES
As a Clerk of Works, my main duties at site are summarised
below.
Maintaining daily records of work done by the contractor.
Measuring and agreeing with Contractor daily quantities of
sludge removed and disposed during the rehabilitation of
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 36
the BNR plant and calculating total quantities after
completion of works.
Measuring and agreeing with the Contractor daily quantities
of filter media removed, cleansed and replaced during the
rehabilitation of three trickling filters at the Sewage
Treatment Works.
Ensuring that steel pipes were properly treated to prevent
corrosion before being used and monitoring the
workmanship and general finishes of mechanical works to
detect irregularities.
Ensuring that the correct number and size of gate valves,
non-return valves, air release valves, pumps and motors for
each work station has been supplied and installed and
keeping record thereof.
Ensuring that materials are stored properly at site i.e. pipe,
valves and pumps.
Monitoring of all civil, mechanical and electrical works to
ensure compliance with specification.
Ensuring that the correct type, number and size of tools and
equipment were being handed over to the Masvingo City
Council.
Measuring the capacity of pumps after completion of
installation works.
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 37
Recording and reporting to the Resident Engineer on daily
progress at site.
Participating in technical meetings and keeping records of
the meetings.
Keeping records of site diaries, instructions, progress,
progress photos and measurement of works.
Reporting to the Resident Engineer describing plant and
labour used in each section of work, location, type and
extent of work carried out, stoppages and any unusual
events noted at site.
Assisting the Resident Engineer to assess and report on
environmental damages or damages to existing structures
caused by the works and ensuring that the contractor adopt
safe, healthy and environmentally friendly practices at site.
Assisting the Resident Engineer with final inspections of
works and issuing snags to the contractor before handing
over of structures to the end user.
7. SUMMERY OF CONTRACT INFORMATION
The original value of the contract was US$2,847,391.00 and the
commencement date was 17 May 2013. The contractor was
handed over the site 02 June 2013 and the original contract
duration was 300days however works exceeded this period by
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 38
more than 250 days mainly due to late deliveries of materials
imported from India. The contractor incurred some liquidated
damages of approximately US$143,000.00 due to delays in
completing the contract within the specified timeframe. The
original contract was exceeded by approximately US$550,000.00
mainly due to additional works that had to be done in order to
commission some of the works. The defects liability period was
for a duration of one year from the issuing of the completion
certificate in May 2015. Snags highlighted on the completion
certificate included repainting of handrails at Pump Station No.1,
replacement of a burnt coil on the generator switch over box for
Rujeko Pump Station and replacement of a soft starter display unit
for pump No.3 at the Effluent Pump Station at the Sewage
Treatment Plant.
8. CHALLENGES
The late delivery of mainly mechanical and electrical materials
was one of the major challenges faced during the project. This
was the main cause of delay since the project mainly targeted
installation of mechanical and electrical equipment. Late
deliveries may have been caused by poor planning and inefficient
communication before concluding materials schedules. Labour
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 39
shortages were also encountered from time to time during the
course of the project. This had effects on the quality of mainly
civil works and the overall finishing of mechanical and electrical
works. The main challenge related to labour was the difficulty in
finding the right sub-contractors to execute the available works
at the main contractor’s rates. Labour related challenges also led
to most of the works being completed beyond scheduled time
frames. The main reasons for labour challenges could have been
due to differences in socio-economic costs differences between
the main contractor’s origin and the local sub-contractors.
Shortages of tools and equipment were also encountered during
civil works i.e. during cleaning of trickling filter media and
disludging of Bio-Nutrient Reactor plant. This also led to late
completion of works with some taking more than four times the
scheduled periods. Poor workmanship was another challenge
faced during the project. This was associated mainly with the
sub-contractors’ labour and probably an effect of the labour
shortages contributing to defective works.
9. CONCLUSSION
The installation of new pumps at Bushmead intake tower ensured
a continuous supply of raw water for treatment thereby having a
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 40
positive effect on the quantity of clean water supplied to the
community of Masvingo Town. An average capacity of
860m^3/hr. of raw water could be pumped from each new pump
for treatment. Installation of new equipment like backwash
pumps, air-blower and chlorinator unit at Bushmead water
treatment plant had a positive effect on the quality of water
supplied to the community by the municipality. The new
chlorinator unit that was installed under the AfDB project could
inject up to 20mg/l compared to the 4mg/l capacity on the
existing chlorinator ensuring enough chlorination even in times
of high pollution of the water source. Work done at the two raw
sewage pump stations i.e. supply and installation off pumps and
a generator had a positive effect mainly on the environment and
the community at large. The new pumps insured that no pollution
of the environment would be done due to raw sewage overflowing
into the river/ stream. The generator supplied by the project also
ensured that there would be limited pollution of the river even
during periods of power shortages. At Masvingo Sewage
Treatment Works, the rehabilitation of PSTs, trickling filters and
Desludging of the BNR re-established the treatment of waste
water thereby controlling the quality of effluent being disposed
into the river and environment. Effluent in the blue category was
now being disposed into the river system after the project in
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 41
comparison to the red category effluent before implementing the
AfDB project. This also limited the community from contracting
water borne diseases. The new pumps supplied and installed at
the effluent pump station ensured that there is constant supply
of nutritious effluent to the beneficial nearby farm. This boosted
the agricultural production on this relative farm.
In conclusion, the ZIMfund/ AfDB project improved the water
quality and quantity supplied to the community of Masvingo. The
project also significantly reduced the pollution of water sources
and the environment at large in Masvingo town. In short the
project had a good impact in providing a good living environment
to the community of Masvingo town.
Future projects should also work on the distribution systems of
treated water and sewerage systems. Improvements on the water
distribution systems will limit the amounts of water lost due
leakages and burst pipes. Improvements on the sewerage system
will limit pollution due to leakages and bursts on sewage
pipelines.
In relation to the challenges encountered during the projects
adequate planning should be done before drafting materials
schedules to avoid unrealistic project duration. The implementing
entity should be directly involved in the hiring of sub-contractors
REHABILITATION OF WATER AND SEWAGE SYSTEMS IN MASVINGO, ZIMBABWE.
Page 42
to avoid poor workmanship. The type of equipment to be used on
various work sections should be carefully chosen in order to avoid
using wrong equipment for certain works and prolong project
duration.
During the project I managed to learn more about construction
supervision and inspection, progress tracking, quality control and
the basics of project management. I also managed to learn more
about health, safety and environment at work sites and the
importance of hazard identification and assessments of risks
before executing work.