16 - 1© 2011 pearson education, inc. publishing as prentice hall 16 jit and lean operations...

45
16 - 1 © 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to PowerPoint presentation to accompany accompany Heizer and Render Heizer and Render Operations Management, 10e Operations Management, 10e Principles of Operations Principles of Operations Management, 8e Management, 8e PowerPoint slides by Jeff Heyl

Upload: paulina-cobb

Post on 17-Dec-2015

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall

1616 JIT and Lean Operations

JIT and Lean Operations

PowerPoint presentation to accompany PowerPoint presentation to accompany Heizer and Render Heizer and Render Operations Management, 10e Operations Management, 10e Principles of Operations Management, 8ePrinciples of Operations Management, 8e

PowerPoint slides by Jeff Heyl

Page 2: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 2© 2011 Pearson Education, Inc. publishing as Prentice Hall

JIT/Lean OperationsJIT/Lean Operations

Good production systems require Good production systems require that managers address three issues that managers address three issues that are pervasive and fundamental that are pervasive and fundamental

to operations management: to operations management: eliminate waste, remove variability, eliminate waste, remove variability,

and improve throughputand improve throughput

Page 3: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 3© 2011 Pearson Education, Inc. publishing as Prentice Hall

1. Eliminate Waste1. Eliminate Waste

Waste is anything that does not add value from the customer point of view

Storage, inspection, delay, waiting in queues, and defective products do not add value and are 100% waste

Page 4: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 4© 2011 Pearson Education, Inc. publishing as Prentice Hall

Ohno’s Seven WastesOhno’s Seven Wastes

Overproduction

Queues

Transportation

Inventory

Motion

Overprocessing

Defective products

Page 5: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 5© 2011 Pearson Education, Inc. publishing as Prentice Hall

Eliminate WasteEliminate Waste

Other resources such as energy, water, and air are often wasted

Efficient, sustainable production minimizes inputs, reduces waste

Traditional “housekeeping” has been expanded to the 5 Ss

Page 6: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 6© 2011 Pearson Education, Inc. publishing as Prentice Hall

The 5 SsThe 5 Ss

Sort/segregateSort/segregate – when in doubt, throw it out

Simplify/straightenSimplify/straighten – methods analysis tools

Shine/sweepShine/sweep – clean daily StandardizeStandardize – remove variations

from processes Sustain/self-disciplineSustain/self-discipline – review

work and recognize progress

Page 7: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 7© 2011 Pearson Education, Inc. publishing as Prentice Hall

The 5 SsThe 5 Ss

Sort/segregateSort/segregate – when in doubt, throw it out

Simplify/straightenSimplify/straighten – methods analysis tools

Shine/sweepShine/sweep – clean daily StandardizeStandardize – remove variations

from processes Sustain/self-disciplineSustain/self-discipline – review

work and recognize progress

Two additional Ss

Safety – build in good practices

Support/maintenance – reduce variability and unplanned downtime

Page 8: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 8© 2011 Pearson Education, Inc. publishing as Prentice Hall

2. Remove Variability2. Remove Variability

JIT systems require managers to reduce variability caused by both internal and external factors

Variability is any deviation from the optimum process

Inventory hides variability

Less variability results in less waste

Page 9: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 9© 2011 Pearson Education, Inc. publishing as Prentice Hall

Sources of VariabilitySources of Variability

1. Incomplete or inaccurate drawings or specifications

2. Poor production processes resulting in incorrect quantities, late, or non-conforming units

3. Unknown customer demands

Page 10: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 10© 2011 Pearson Education, Inc. publishing as Prentice Hall

Sources of VariabilitySources of Variability

1. Incomplete or inaccurate drawings or specifications

2. Poor production processes resulting in incorrect quantities, late, or non-conforming units

3. Unknown customer demandsBoth JIT and inventory

reduction are effective tools

in identifying causes of

variability

Page 11: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 11© 2011 Pearson Education, Inc. publishing as Prentice Hall

3. Improve Throughput3. Improve Throughput

The time it takes to move an order from receipt to delivery

The time between the arrival of raw materials and the shipping of the finished order is called manufacturing cycle time

A pull system increases throughput

Page 12: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 12© 2011 Pearson Education, Inc. publishing as Prentice Hall

Improve ThroughputImprove Throughput

By pulling material in small lots, inventory cushions are removed, exposing problems and emphasizing continual improvement

Manufacturing cycle time is reduced

Push systems dump orders on the downstream stations regardless of the need

Page 13: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 13© 2011 Pearson Education, Inc. publishing as Prentice Hall

Just-In-Time (JIT)Just-In-Time (JIT) Powerful strategy for improving

operations

Materials arrive where they are needed when they are needed

Identifying problems and driving out waste reduces costs and variability and improves throughput

Requires a meaningful buyer-supplier relationship

Page 14: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 14© 2011 Pearson Education, Inc. publishing as Prentice Hall

JIT and Competitive JIT and Competitive AdvantageAdvantage

Figure 16.1

Page 15: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 15© 2011 Pearson Education, Inc. publishing as Prentice Hall

JIT and Competitive JIT and Competitive AdvantageAdvantage

Figure 16.1

Page 16: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 16© 2011 Pearson Education, Inc. publishing as Prentice Hall

JIT PartnershipsJIT Partnerships JIT partnerships exist when a

supplier and purchaser work together to remove waste and drive down costs

Four goals of JIT partnerships are: Removal of unnecessary activities

Removal of in-plant inventory

Removal of in-transit inventory

Improved quality and reliability

Page 17: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 17© 2011 Pearson Education, Inc. publishing as Prentice Hall

JIT PartnershipsJIT Partnerships

Figure 16.2

Page 18: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 18© 2011 Pearson Education, Inc. publishing as Prentice Hall

JIT LayoutJIT Layout

Table 16.1

Reduce waste due to movementJIT Layout Tactics

Build work cells for families of productsInclude a large number operations in a small areaMinimize distanceDesign little space for inventoryImprove employee communicationUse poka-yoke (fail safe) devicesBuild flexible or movable equipmentCross-train workers to add flexibility

Page 19: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 19© 2011 Pearson Education, Inc. publishing as Prentice Hall

Distance ReductionDistance Reduction

Large lots and long production lines with single-purpose machinery are being replaced by smaller flexible cells

Often U-shaped for shorter paths and improved communication

Often using group technology concepts

Page 20: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 20© 2011 Pearson Education, Inc. publishing as Prentice Hall

Increased FlexibilityIncreased Flexibility

Cells designed to be rearranged as volume or designs change

Applicable in office environments as well as production settings

Facilitates both product and process improvement

Page 21: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 21© 2011 Pearson Education, Inc. publishing as Prentice Hall

Impact on EmployeesImpact on Employees Employees may be cross trained

for flexibility and efficiency

Improved communications facilitate the passing on of important information about the process

With little or no inventory buffer, getting it right the first time is critical

Page 22: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 22© 2011 Pearson Education, Inc. publishing as Prentice Hall

Reduced Space and Reduced Space and InventoryInventory

With reduced space, inventory must be in very small lots

Units are always moving because there is no storage

Page 23: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 23© 2011 Pearson Education, Inc. publishing as Prentice Hall

JIT InventoryJIT InventoryInventory is at the minimum level necessary to keep operations running

Table 16.2

JIT Inventory Tactics

Use a pull system to move inventoryReduce lot sizesDevelop just-in-time delivery systems with suppliersDeliver directly to point of usePerform to scheduleReduce setup timeUse group technology

Page 24: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 24© 2011 Pearson Education, Inc. publishing as Prentice Hall

Reduce VariabilityReduce Variability

Inventory level

Process downtimeScrap

Setup time

Late deliveries

Quality problems

Figure 16.3

Page 25: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 25© 2011 Pearson Education, Inc. publishing as Prentice Hall

Inventory level

Reduce VariabilityReduce Variability

Figure 16.3

Process downtimeScrap

Setup time

Late deliveries

Quality problems

Page 26: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 26© 2011 Pearson Education, Inc. publishing as Prentice Hall

Inventory level

Reduce VariabilityReduce Variability

Figure 16.3

Process downtime removed

No scrap

Setup time

reducedLate

deliveries

Quality problems removed

Page 27: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 27© 2011 Pearson Education, Inc. publishing as Prentice Hall

Reduce InventoryReduce Inventory

Reducing inventory uncovers the “rocks”

Problems are exposed

Ultimately there will be virtually no inventory and no problems

Shingo says “Inventory is evil”

Page 28: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 28© 2011 Pearson Education, Inc. publishing as Prentice Hall

Reduce Lot SizesReduce Lot Sizes

Figure 16.4

200 –

100 –

Inve

nto

ry

Time

Q2 When average order size = 100average inventory is 50

Q1 When average order size = 200average inventory is 100

Page 29: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 29© 2011 Pearson Education, Inc. publishing as Prentice Hall

Reduce Lot SizesReduce Lot Sizes Ideal situation is to have lot sizes

of one pulled from one process to the next

Often not feasible

Can use EOQ analysis to calculate desired setup time

Two key changes necessary Improve material handling

Reduce setup time

Page 30: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 30© 2011 Pearson Education, Inc. publishing as Prentice Hall

Reduce Setup CostsReduce Setup Costs

High setup costs encourage large lot sizes

Reducing setup costs reduces lot size and reduces average inventory

Setup time can be reduced through preparation prior to shutdown and changeover

Page 31: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 31© 2011 Pearson Education, Inc. publishing as Prentice Hall

Lower Setup CostsLower Setup Costs

Figure 16.5

Sum of ordering and holding costs

Holding cost

Setup cost curves (S1, S2)T1

S1

T2

S2

Co

st

Lot size

Page 32: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 32© 2011 Pearson Education, Inc. publishing as Prentice Hall

Reduce Setup TimesReduce Setup Times

Figure 16.6

Use one-touch system to eliminate adjustments (save 10 minutes)Step 4

Step 5Training operators and standardizing work procedures (save 2 minutes)

Initial Setup Time

Step 2

Move material closer and improve material handling

(save 20 minutes)

Step 1

Separate setup into preparation and actual setup, doing as much as possible while the

machine/process is operating (save 30 minutes)

Step 3

Standardize and improve tooling

(save 15 minutes)

90 min —

60 min —

45 min —

25 min —

15 min —13 min —

—Repeat cycle until subminute setup is achieved

Step 6

Page 33: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 33© 2011 Pearson Education, Inc. publishing as Prentice Hall

JIT SchedulingJIT Scheduling Schedules must be communicated

inside and outside the organization

Level schedules Process frequent small batches

Freezing the schedule helps stability

Kanban Signals used in a pull system

Page 34: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 34© 2011 Pearson Education, Inc. publishing as Prentice Hall

Table 16.3

Better scheduling improves performance

JIT SchedulingJIT Scheduling

JIT Scheduling Tactics

Communicate schedules to suppliersMake level schedulesFreeze part of the schedulePerform to scheduleSeek one-piece-make and one-piece moveEliminate wasteProduce in small lotsUse kanbansMake each operation produce a perfect part

Page 35: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 35© 2011 Pearson Education, Inc. publishing as Prentice Hall

Level SchedulesLevel Schedules

Process frequent small batches rather than a few large batches

Make and move small lots so the level schedule is economical

“Jelly bean” scheduling

Freezing the schedule closest to the due dates can improve performance

Page 36: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 36© 2011 Pearson Education, Inc. publishing as Prentice Hall

Scheduling Small LotsScheduling Small Lots

A B CA AAB B B B B C

JIT Level Material-Use Approach

A CA AA B B B B B C CB B B BA A

Large-Lot Approach

TimeFigure 16.7

Page 37: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 37© 2011 Pearson Education, Inc. publishing as Prentice Hall

KanbanKanban

Kanban is the Japanese word for card

The card is an authorization for the next container of material to be produced

A sequence of kanbans pulls material through the process

Many different sorts of signals are used, but the system is still called a kanban

Page 38: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 38© 2011 Pearson Education, Inc. publishing as Prentice Hall

KanbanKanban

1. User removes a standard sized container

2. Signal is seen by the producing department as authorization to replenish

Part numbers mark location

Signal marker on boxes

Figure 16.8

Page 39: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 39© 2011 Pearson Education, Inc. publishing as Prentice Hall

KanbanKanban

Figure 16.9

Kanban

Kanban

Final assembly

Work cell

Kanban

Material/Parts Supplier Finished

goodsCustomer

order

Page 40: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 40© 2011 Pearson Education, Inc. publishing as Prentice Hall

JIT QualityJIT Quality

Strong relationship JIT cuts the cost of obtaining good

quality because JIT exposes poor quality

Because lead times are shorter, quality problems are exposed sooner

Better quality means fewer buffers and allows simpler JIT systems to be used

Page 41: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 41© 2011 Pearson Education, Inc. publishing as Prentice Hall

JIT Quality TacticsJIT Quality Tactics

Use statistical process control

Empower employees

Build fail-safe methods (poka-yoke, checklists, etc.)

Expose poor quality with small lot JIT

Provide immediate feedback

Table 16.4

Page 42: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 42© 2011 Pearson Education, Inc. publishing as Prentice Hall

Lean OperationsLean Operations

Different from JIT in that it is externally focused on the customer

Starts with understanding what the customer wants

Optimize the entire process from the customer’s perspective

Page 43: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 43© 2011 Pearson Education, Inc. publishing as Prentice Hall

Building a Lean OrganizationBuilding a Lean Organization

Transitioning to a lean system can be difficult

Lean systems tend to have the following attributes Use JIT techniques

Build systems that help employees produce perfect parts

Reduce space requirements

Page 44: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 44© 2011 Pearson Education, Inc. publishing as Prentice Hall

Building a Lean OrganizationBuilding a Lean Organization

Develop partnerships with suppliers

Educate suppliers

Eliminate all but value-added activities

Develop employees

Make jobs challenging

Build worker flexibility

Page 45: 16 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 16 JIT and Lean Operations PowerPoint presentation to accompany Heizer and Render Operations

16 - 45© 2011 Pearson Education, Inc. publishing as Prentice Hall

Lean Operations in ServicesLean Operations in Services

The JIT techniques used in manufacturing are used in services Suppliers

Layouts

Inventory

Scheduling