1mw utility scale solar pv power plant

Upload: ksksirhot

Post on 02-Jun-2018

245 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    1/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 1

    Acknowledgement

    This analysis based report is done for the readers of my previous report 1MW Utility Scale SPV

    Power Plant, mainly for the readers from South region of INDIA as they are asking repeatedly

    about the probability and feasibility-technical & Financial-of a SPV power plant in their region.

    At the same time its not possible for me to design a report for each and every state from South

    India, so I took Chennai city. Also the previous report was not so detail, was very basic and

    meant to the readers who want to get an overview on how a utility scale power plant works.

    Now, in this report, I discuss about in depth. From panels selection to CB sizing all are

    presented in very detail. Hope, this time you get a strong knowledge on designing and

    estimation of 1MW solar PV power plant. Unlike the previous report, the financial aspect

    discussed at the end of the paper. In this paper, the financial assessment has done in very detail

    and considering the current scenario of SPV market including the cost of solar PV modules,

    inverters cost, cable, transformer etc. prices and the funding, interest rate.

    And if you have any queries or need clarification, please contact at [email protected] or

    [email protected] .

    Disclaimer

    The presented data here are NOT TAKEN from any copyright materials and not showing under

    my name. The meteo data collected from NASA website and NREL database which is free over

    the internet. Designing of PV system is totally based on the practical experience of the author.

    Assumption & Consideration

    Shading consideration: No shading has been considered at the site during the calculation

    design. So it is advised that at the time of execution, please check whether there is any kind of

    obstacle in the site which may cause partial/full shading on PV strings and/or PV array. If the

    shading occurs, then the estimated power generation will not match the actual power

    generated.

    Load Factor: It is assumed that the produced power from the PV plant will be fed to the local

    utility grid. So, while designing the system, no unbalanced load considered in 3 phase

    configuration.

    Meteo data: The calculation based on the meteo data collected from NASA website which isvery reliable. Now, based on the co-ordinates the values have been presented in this report. So,

    total design is based on this data. For a different location (coordinates), the system design will

    differ. It is advised not to copy and implement the design without consulting the author or any

    certified PV professional because this design estimation is valid only for a particular site.

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    2/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 2

    Site consideration: this design has been done by considering the PV modules & array will be

    ground-mounted and the site-elevation angle taken 30

    .

    Cost Estimation: 1MW Solar PV power plant cost estimation has done considering the current

    PV market scenario (Sept-Dec 2013), so after few months the cost may vary according the

    market.

    CAD design & layout: I have not uploaded/attached the CAD design. If anybody interested in

    setting up the plant then only contact at the given e-mail ids to get the design file.

    Transmission & wheeling losses: Here, in this report, while doing the technical assessment, the

    distance from nearest substation to the 1MW solar PV power plant taken within 1.5 KM and so

    the wheeling losses considered as 3% of total power transmission. And in the financial

    assessment, no wheeling charges have been considered.

    Design Criteria: While designing & estimating the technical components & solutions, all the

    required/applicable standard design codes have been considered. Mainly the IEC (International

    Electrotechnical Commission) Codes, IS codes from BIS have been considered thoroughly.

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    3/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 3

    Contents

    1) Introduction 4

    2) Project details 5

    3) Location metrological details 6

    4) Determination of optimum tilt angle 7

    5) Solar power plant overview 8

    6) Module selection & sizing 9

    7) Inverter selection & sizing 11

    8) Transformer selection 12

    9) Other protective devices including switch gear details 13

    10) Cable sizing & selection 1411) Civil works details 16

    12) Performance analysis & simulation 17

    13) Timeline of the project 21

    14) Operation & maintenance structure of the plant 22

    15) Financial calculation, estimation of NCF, Payback period 23

    16) Guide on selection of various components 27

    17) Conclusion 28

    18) About the Author 28

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    4/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 4

    Introduction

    India is densely populated and has high solar insolation, an ideal combination for using solar power in

    India. India is already a leader in wind power generation. In the solar energy sector, some large projects

    have been proposed, and a 35,000 km2 area of the Thar Desert has been set aside for solar power

    projects, sufficient to generate 700 GW to 2,100 GW. Also India's Ministry of New and Renewable

    Energy has released the JNNSM Phase 2 Draft Policy, by which the Government aims to install 10GW of

    Solar Power and of this 10 GW target, 4 GW would fall under the central scheme and the remaining 6

    GW under various State specific schemes.

    The Electricity Act, 2003, paves way for an innovative approach to solve our countrys power problems.

    It has paved the way for a competitive environment; open access to existing transmission and

    distribution network to transmit electricity across regions; de-licensing of generation, captive power and

    dedicated transmission lines; licensing of distribution and supply companies and the restructuring of

    State Electricity Boards.

    The Ministry of Power has mandated to promote cogeneration and renewable sources for Power

    generation under Nodal agencies and hence it will play a major role in mainstreaming renewable energy

    sector. The advantage or renewable resources includes their capacity to produce energy without

    producing carbon-based warming and polluting agents into the atmosphere. The financial cost of its

    applications is not always cheap but if the environmental costs of using fossil are accounted for,

    renewable energy wins hands-down. There are also indirect savings on health and its costs as there are

    no harmful emissions.

    In the above backdrop, YOUR COMPANY NAMEhas decided to set up a 1/1000 MW/KWSolar Power

    Plant. This Detailed Project Report (DPR) brings out all technical details and overall costs justifying theselection of the project. The total power generation is envisaged to be 1050KW from Solar Photovoltaic

    Cell. It is a very important document that is required for Environmental Impact Assessment (EIA) studies,

    fixation of tariff, finalizing Power Purchase Agreement (PPA) and also for submission to Financial

    Institutions for obtaining project funding. The total project cost is expected to be Rs ___ Crores and the

    average cost of generation is expected to be Rs. 7.5/kWh (ASSUMED).

    For this project, poly-crystalline technology based 3rd

    generation Solar PV modules will be used. Along

    with this, highly efficient, photon-tested string inverters going to be integrated to the system. These

    technologies are the best in the industry. So, Its clear that our project is not compromising with the

    quality of the materials and or the components which obviously led this project to success.

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    5/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 5

    Client details

    Country India

    Location CHENNAIContact id [email protected]

    Contact Person abc

    company ABCXYZ

    Purpose Power generation &

    distribution to State utility grid

    Project Details

    Type of installation Ground-mounted

    Estimated array peak

    power

    1100KWp

    Shading consideration Shade-free

    Grid voltage 11KV

    Phase connection 3-phase

    Grid frequency 50Hz

    Available/required area 20000 m2(apprx)

    Safety level IP65

    Site Location/Layout

    Site & Meteo Details

    Location coordinates 10.5, 78.5 (assumed)

    Ambient

    Temperature(0C)

    Max Average Min

    28.5 27.2 25.5

    Relative humidity 72.5%

    Daily Solar irradiation-

    Horizontal

    5.19 KWh/m2/day

    Atmospheric Pressure 100.1 kPA

    Wind Speed 2.7 m/s

    Earth temperature Max Average Min

    29.6 28.8 26.4

    Height from sea level 10m

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    6/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 6

    0

    1

    2

    3

    4

    5

    6

    7

    KWh/m2/day

    Solar Irradiation

    Solar Irradiation

    23

    24

    25

    26

    27

    28

    29

    30

    31Air & earth temperature-monthly

    Air temperature

    earth temperature

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    7/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 7

    Optimum Tilt Angles For Solar PV Array Adjusted by Months

    Jan Feb Mar Apr May Jun34 26 13 0 11 14

    Jul Aug Sep Oct Nov Dec12 5 6 19 29 35

    Figures shown in degrees from vertical

    Irradiation Data on different tilt angles (respect to horizontal surface, KWh/m2/day)

    Months 100

    250

    120

    January 5.04 5.35 5.41

    February 5.98 6.16 6.16

    March 6.51 6.41 6.52

    April 5.76 5.39 5.85

    May 5.78 5.65 5.78

    June 5.28 5.22 5.29

    July 4.99 4.9 4.99August 5.09 4.9 5.1

    September 5.33 5.14 5.34

    October 4.67 4.69 4.71

    November 4.27 4.44 4.45

    December 4.5 4.78 4.84

    Annual avg. 5.26 5.25 5.36

    * Here, 120

    angle at AM1.5 has been chosen as fixed south faced model for the project

    Winter

    56 angle

    Spring/Autumn

    80angle

    Summer

    104angle

    On the 21st December, the sun will rise 87 east of due south and set 87 west of due south.

    On the 21st March/21st September, the sun will rise 91 east of due south and set 91 west of due

    south.

    On the 21st June, the sun will rise 95 east of due south and set 95 west of due south.

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    8/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 8

    Solar PV System Design

    System Overview

    SPV Array Peak Power 1082KWp

    No. of SPV strings 206

    Connection of PV modules in each string Series

    Inverter 20KW MPPT based 3 phase string Inverter

    Inverter Type/Topology MPPT & Transformer Less

    Total no. of Inverters 53

    Strings/Inverter 4/1

    Modular Components

    Components Specification Quantity Make

    Solar PV modules Max Peak Power=250Wp

    Voc= 36V ;Vmp= 29V

    Isc= 9.25A ; Imp= 8.65A

    4326

    Non-Modular Components

    Components Electrical Specification Quantity Make

    Inverters 20KW, 3Phase &MPPT;

    Vmax= 800V

    53

    Transformer 1250KVA 1

    SCADA/Monitoring

    System

    Integrated with Remote

    Monitoring system web based

    1

    Circuit Breaker Inverter to Busbar= 46A 3p;

    busbar/Panel box to

    transformer= 1600A 3p;

    53

    1

    DC Disconnect 1000V,20Amps 206

    Switch Gear Rated voltage=12KV;Rated main busbar

    current(Max)=1250A;

    SC withstand capacity = 25KA/3s

    Dynamic capacity= 50KA

    1

    Distribution Panel NA 1

    Isolator Vmax= 12KV;

    Max cont. current=1250A

    1

    Cables DC Side= 10 mm2

    AC Side=LT: 16mm2

    & HT:

    185mm2

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    9/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 9

    Solar PV Module Specification & Array Sizing Details

    Required Electrical Characteristics of SPV Modules

    Design criteria IEC-61853-1

    Watt Peak 250Wp

    VOC 37.20V

    VMPP 30.10V

    ISC 8.87A

    IMPP 8.30A

    Module

    Efficiency/module area

    15%

    Power Tolerance 2%

    Technology Si-PolyNo. of cells 60 cells in series

    Required Temperature Co-efficient Characteristics

    @ STC

    NOCT (oC) 45 2

    oC

    Module Efficiency (%/oC) -0.07 0.01

    Temp. Co-Eff. Of Pmax (%/oC) -0.43 0.05

    Temp. Co-Eff. Of Voc (%/oC) -0.34 0.05

    Temp Co-Eff. of Isc (%/oC) 0.065 0.05

    PV Module Behavior at different irradiance level

    PV Parameters @ 1000W/m2

    @800 W/m2

    @ 400 W/m2

    PMPP 249.8.2W 200.6 W 100.00

    VOC 37.2V 36.8 V 35.8V

    VMPP 30.1V 30.2 V 30.1V

    ISC 8.87A 6.64A 3.55A

    IMPP 8.31A 7.10A 3.33A

    Module efficiency 15.54% 15.32% 15.27%

    Temperature co-eff -0.43%/0C -0.43%/

    0C -0.44%/

    0C

    Required Operating Condition Details:

    Maximum System

    Voltage (IEC)

    1000V

    Maximum Fuse Rating 15A

    Limiting Reverse

    Current

    15A

    Operating Temp

    Range

    (-10 to 60)0C

    Max Static Load-

    front(Snow+Wind)

    5500PA

    Max Static Load-

    Rear(wind)

    2500PA

    Model design parameters

    R shunt 250 ohm

    R shunt (G=0) 2100 ohm

    R series model 0.29 ohm

    R series max 0.37 ohm

    R series apparent 0.47 ohm

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    10/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 10

    Solar PV Array Sizing & Connection Details

    conditions At STC (250C) At Avg. Ambient temp. (28

    0C)

    Suggested array Size 1100 KWp 1100KWp

    Actual Solar PV Array Size 1082KWp 1100KWpWatt Peak of each SPV module 250Wp 263Wp

    Total nos. of SPV module

    required

    4326 4326

    Total nos. of strings 206 206

    Nos. of SPV modules in each

    string

    21 21

    SPV connection in each string Series Series

    String voltage (VMPP) 609V 630V

    String current (ISC / IMPP) 8.87A/8.3A 9.51A/8.82A

    Connection of strings Parallel Parallel

    Array voltage (VOC / VMPP) 780V/635V 750V/620V

    Array current (ISC / IMPP) 1830A/1710A 1960A/1816A

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    11/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 11

    Detail Solar Inverter Specification & Design Details

    Inverter Type String Inverter (MPPT)

    Quantity 53

    INPUT (DC)

    Max. Power23KW

    Max absolute Input Voltage 1000V

    Start Voltage 350V

    Nominal MPP voltage range 490V-800V

    Max Input Current per string 41.5A

    Nos. of Independent MPP inputs/strings

    per MPP inputs

    1/6

    OUTPUT (AC)

    Rated Output Power 20000W

    Max. Apparent AC Power 20000VA

    Power Threshold 20W

    Nominal AC Voltage/range 3/N/PE;230/460VAC Power Frequency/ range 50Hz

    Max. output current 3x29A

    Power factor at rated power 1

    Feed-In phases/connection phases 3/3

    Efficiency

    Max. Efficiency 98.7%

    Protection Details

    DC Disconnect Available

    DC Surge Arrester Available

    Protection Class I (as per IEC 62103)

    Total harmonic distortion

  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    12/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 12

    Transformer Sizing

    Design Criteria IS-2026 / IEC-60076

    Transformer type Power transformer, core type with oil-immersed ;

    650C winding temp rise

    Cooling type ONAN(Oil Natural Air Natural)

    Rated KVA 1250KVAHigh Voltage rating 11000V

    Low Voltage Rating 460V

    Nominal impedance 4.7%

    Impedance tolerance 7.5%

    Nominal secondary amps 1250A

    Max SC withstand current 20KA/3s

    HV connection DELTA

    LV connection Wye

    Operating frequency 50Hz

    Tap changer 5% of full load capacity

    Protective devices

    components Specification Quantity

    DC Disconnects String to inverter= 1000V, 15A; 2 pole

    (As per IEC-60947)

    206

    Switch gear Rated voltage=12KV;

    Rated main busbar current(Max)=1250A;

    SC withstand capacity = 25KA/3s

    Dynamic capacity= 50KA

    IP55

    1

    Circuit breakers (MCCB)(NOT required if Inverter has inbuilt

    protection)

    Inverter to Busbar= 60A 3p;

    busbar/Panel box to transformer= A 3p;

    53

    1

    Main Isolator (HT side)

    Design criteria IS-9921/IEC-129

    Operating frequency 50hz 3% Rated peak withstand

    current (KA peak/rms)

    63.5KA

    Nominal system voltage 11KV 1.2/50 micro sec lighting

    withstand Volts (KV peak)

    To earth and

    isolating poles

    Across the isolating

    distances

    170 195

    Max system voltage 12KV Rated 1 minute power

    frequency withstand

    voltage(KV r.m.s)

    To earth and

    isolating poles

    Across the isolating

    distances

    75 85

    Max continuous current 2500A No. of poles 3

    Rated SC current for 3s 40KA Min creepage distance 320mm

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    13/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 13

    Cable Sizing

    DC Side Cables (strings to inverter)Design criteria IEC-60811 & IEC-60216

    Cable material Copper

    Single cable length per string to inverter 70 ft

    Cross section per string 4 mm2

    Voltage drop 0.18V

    Relative power loss reference to Max DC power 0.07%

    Max withstand temp. Normal condition Short-circuited

    condition

    900C 250

    0C

    Max withstand current capacity 42KA/1sec

    Conductor type Stranded

    Insulation material XLPE

    LT Cables (Inverters to busbur/distribution panel)Design criteria IEC-60228 & IEC-60811

    Cable material Copper

    Max Single cable length per inverter to panel box 60 ft

    Cross section 16 mm2

    Voltage drop (3phase) 0.46V

    Relative power loss reference to Max AC nominal

    power

    0.23%

    Max withstand temp Normal condition Short-circuited

    condition

    900C 2500C

    Max withstand current capacity 2KA/1sec

    Conductor type Stranded

    Insulation PVC

    HT Cables (from distribution panel to feed-in point)Design criteria IEC-60502

    Cable material Al

    Cable length from distribution panel to feed-

    in point

    25 ft

    Cross section 185mm2

    Voltage drop (total) L1 1.37V

    L2 1.37V

    L3 1.37V

    Relative power loss reference to Max AC

    power

    0.57%

    Voltage grade 11KV(UE), heavy duty

    SC withstand current capacity 26KA @1s

    Insulation XLPE

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    14/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 14

    Line Losses

    DC Side AC Side Total

    Total cable length 8120 ft 3070 ft 11180 ft

    Cable cross section 4 mm2

    16 mm2

    +185 mm2

    4 mm2

    +16 mm2

    +185

    mm2

    Power loss @ nominal

    operation

    35 KW 5 KW 40KW

    Relative power loss @

    nominal operation

    0.07% 0.76% 0.83%

    Busbar constructional Analysis

    Busbar material Main busbar Auxilury busbar

    Al alloy E91 E

    grade

    Copper

    Busbar insulation Fully insulated

    Busbar length Main Aux

    3.5mt 0.75mt x 52

    Earthing bus materials GS (IEEE std. 80/IEC-60439-1)

    Earthing & Lighting Protection

    Design Criteria IEEE Standard-80

    Grounding System Earth grid resistance Less than 10 ohm

    Placing of earth

    electrode

    Earth Pit

    Earth Electrode sizing

    Physical Parameters Heavy duty GI pipes, 32mm dia, 3mt long

    Material Galvanized Steel(GS), flat type

    Min depth of earth pit 600mm

    Components grounding Min 75x10mm GS stripLightning Protection

    Design criteria As per IEC-62305

    Placing On the highest panel of array

    Dimension 40mm dia with 3m height (vertical air

    termination)

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    15/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 15

    CIVIL WORKS

    Live Loads estimation of control room + admin building (as per IS 875:1987)

    parameters details Remarks

    Roof load 1750 kg/ m2

    As per IS-456Ground floor load Control room 18000kg/m

    2As per IS-456

    Office 5000kg/ m2

    IS-456

    Piping load 50 kg/ m2

    As per IS-456

    Electrical + HVAC 26 kg/ m2

    As per IS-456

    Seismic load As per IS-456

    Roof drainageRoof drain heads 6

    Construction detailsInterwall

    Cement : Sand 1:6Interwall thickness 230mm

    Parapet walls

    Cement : Sand 1:4

    thickness 115mm

    Steel work Reinforced bars will be provided

    as per IS 800:2007

    PV Array mounting & constructional details

    PV tilted angle (optimized) 130

    (@1070 W/m2

    /day)Mounting type Ground mounted

    Overall dimension As per design

    Foundation Plain cement concrete (PCC)

    Foundation grade 1:5:10

    Wind load 9.72 Km/hr

    Fixing type SS 304 fasteners

    Total Land required 5 acres

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    16/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 16

    System Performance Analysis & Simulation

    Solar Paths at site on monthly basis Reference Incident energy in collector plane

    Normalized production per installed KWp

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    17/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 17

    Performance Ratio (PR) Normalized Production & Loss factor

    Daily System Output Energy SPV Array Power Distribution

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    18/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 18

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    19/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 19

    Overall Power plant performance Summery

    Total no. of PV modules 4326 (250Wp)

    Total nos. of Inverters 53 (20KW)

    Max DC input per Inverter 21KW

    Nominal PV power 1082 KWp

    Max. PV power output 1027 KWdcNominal AC power 1060KWac

    Max operating power @ STC 962KWac

    Max operating power @Ambient Temp. 1027KWac

    Plant production 1655 MWh/year

    Specific production 1526KWh/KWp/year

    Normalized production 4.2 kWh/KWp/day

    Array losses 0.87 KWh/Kp/day

    Overall losses 0.22 KWh/KWp/day

    Performance ratio 0.80

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    20/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 20

    Time line of the project

    Design

    Preparation of design & estimation of the plant

    15 working days required.

    Land

    acquisition

    As per design requirement, proper land selection & acquisition processed.

    Time required 1 month

    PPA

    Power Purchase Agreement(PPA) with private power purchaser need to be finalized at a feasible rate.

    Required time is 15 working days

    DPR

    Preparation of Detailed Project Report including technical feasibility of the project prepared.

    Time required 6 working days.

    finance

    Arrangement of finance/fund for the project from nationalized or private financing agency with significant interest rateand equity share will be finalized.

    Required time for this stage is 1 month.

    procurement

    After finalizing PPA and arrangement of fund for the project, procurement work starts including preparation & finalizinvendor selection, BOM, BOQ, order placing, follow-ups of delivery to site/warehouse.

    Estimated time for this step is 1 month.

    construction

    After the processing of procurement, first civil construction at the site starts for PV mounting structure set-up andcontrol-room, administrative building. Finishing the civil works, PV installation & all electrical construction works incluthe Grid Evacuation will be processed.

    Estimated time for this whole work is 2 months.

    commission

    ing

    Commissioning of the plant by authorized govt. body or certified 3rd party will be done followed by Completion of projeexecution.

    required time for this step is 6 working days.

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    21/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 21

    Operation & Maintenance of Plant

    Why do we need an O&M for Solar PV power plant?

    As every plant needs a regular maintenance work to make it functional & in well-condition, so

    in this case also, a PV power plant also requires a sound & efficient operation & management

    team to perform all the work after plant commissioning.

    A detailed structure of O&M team has been provided here in a hierarchy model to demonstrate

    in a simpler way.

    Plant manager

    Maintenanceengineer(E&IE)

    Technician1

    skilled labour1

    Technician2

    skilled labour2

    control roomtechnician

    maintenanceEngineer(Mech)

    Skilled labour1 skilled labour2

    operationmanager

    Supply chainexecutive

    Accountsexecutive

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    22/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 22

    Financial Analysis & feasibility

    Initial Investment in terms of components cost & service charges

    Sl.

    No.Components/services Total cost

    (in INR)

    Remarks

    1. Solar PV modules 45,100,000 41rs/Watt peak

    2. Solar inverters 11,660,000 11rs/Watt peak

    3. Transformer 2,940,000 From international vendor

    4. Protective devices 1,200,000 From international vendor

    5. Wires/Cables 1,000,000 Considering IEC codes & ISO

    certified

    6. SCADA/RMS 1,000,000

    7. Project execution & commissioning 2,000,000

    8. Construction works 4,000,000

    9. Grid evacuation 1,000,000 (assumed) Assumed because of having

    no sufficient data

    10. Other official works 1,000,000 Subject to change as per

    rules

    Total Project investment 70,900,000 INR

    Total expenses over the year for plant O&M and staffing = 2,000,000

    This expense is considered for regular maintenance cleaning of PV array, checking the status of

    inverter, cable-fault checking, emergency maintenance & replacement of components and

    annual salaries of O&M team of the plant.

    Loan Interest rate is @12% over 70% of total project cost which shall be completed within next

    7 years (the rest 30% as equity shares).

    Estimated time period 7 years 10 years

    Total Loan amount 49,630,000 49,630,000

    Interest rate 12% 12%

    EMI 876,110 712,050

    Monthly interest 285,270 298,460

    total Interest paid 23,962,830 35,815,600

    *all the amounts are considered in INR currency.

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    23/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 23

    Detailed Analysis of Installment, EMI, Interest of the 70% project

    finance/fund

    Sl.

    No.

    Installments EMI Monthly principle Monthly Interest

    1) 0 0 0 0

    2) 1 876,105 379,805 496,300

    3) 2 876,105 383,603 492,502

    4) 3 876,105 387,439 488,666

    5) 4 876,105 391,314 484,792

    6) 5 876,105 395,227 480,878

    7) 6 876,105 399,179 476,926

    8) 7 876,105 403,171 472,934

    9) 8 876,105 407,203 468,903

    10) 9 876,105 411,275 464,831

    11) 10 876,105 415,387 460,71812) 11 876,105 419,541 456,564

    13) 12 876,105 423,737 452,369

    14) 13 876,105 427,974 448,131

    15) 14 876,105 432,254 443,851

    16) 15 876,105 436,576 439,529

    17) 16 876,105 440,942 435,163

    18) 17 876,105 445,351 430,754

    19) 18 876,105 449,805 426,300

    20) 19 876,105 454,303 421,802

    21) 20 876,105 458,846 417,259

    22) 21 876,105 463,434 412,67123) 22 876,105 468,069 408,036

    24) 23 876,105 472,749 403,356

    25) 24 876,105 477,477 398,628

    26) 25 876,105 482,252 393,853

    27) 26 876,105 487,074 389,031

    28) 27 876,105 491,945 384,160

    29) 28 876,105 496,864 379,241

    30) 29 876,105 501,833 374,272

    31) 30 876,105 506,851 369,254

    32) 31 876,105 511,920 364,185

    33) 32 876,105 517,039 359,06634) 33 876,105 522,210 353,896

    35) 34 876,105 527,432 348,674

    36) 35 876,105 532,706 343,399

    37) 36 876,105 538,033 338,072

    38) 37 876,105 543,413 332,692

    39) 38 876,105 548,847 327,258

    40) 39 876,105 554,336 321,769

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    24/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 24

    41) 40 876,105 559,879 316,226

    42) 41 876,105 565,478 310,627

    43) 42 876,105 571,133 304,972

    44) 43 876,105 576,844 299,261

    45) 44 876,105 582,613 293,492

    46) 45 876,105 588,439 287,66647) 46 876,105 594,323 281,782

    48) 47 876,105 600,266 275,839

    49) 48 876,105 606,269 269,836

    50) 49 876,105 612,332 263,773

    51) 50 876,105 618,455 257,650

    52) 51 876,105 624,640 251,466

    53) 52 876,105 630,886 245,219

    54) 53 876,105 637,195 238,910

    55) 54 876,105 643,567 232,538

    56) 55 876,105 650,002 226,103

    57) 56 876,105 656,502 219,60358) 57 876,105 663,068 213,038

    59) 58 876,105 669,698 206,407

    60) 59 876,105 676,395 199,710

    61) 60 876,105 683,159 192,946

    62) 61 876,105 689,991 186,114

    63) 62 876,105 696,891 179,214

    64) 63 876,105 703,860 172,246

    65) 64 876,105 710,898 165,207

    66) 65 876,105 718,007 158,098

    67) 66 876,105 725,187 150,918

    68) 67 876,105 732,439 143,66669) 68 876,105 739,763 136,342

    70) 69 876,105 747,161 128,944

    71) 70 876,105 754,633 121,472

    72) 71 876,105 762,179 113,926

    73) 72 876,105 769,801 106,304

    74) 73 876,105 777,499 98,606

    75) 74 876,105 785,274 90,831

    76) 75 876,105 793,127 82,979

    77) 76 876,105 801,058 75,047

    78) 77 876,105 809,068 67,037

    79) 78 876,105 817,159 58,94680) 79 876,105 825,331 50,774

    81) 80 876,105 833,584 42,521

    82) 81 876,105 841,920 34,185

    83) 82 876,105 850,339 25,766

    84) 83 876,105 858,842 17,263

    85) 84 876,105 867,431 8,674

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    25/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 25

    Net Cash Flow/year Estimation (all amounts are in INR)

    Initial Investment 70,900,00

    Expenses for O&M per year 2,000,000

    Total amount paid/year for loan(7 years term

    considered)

    10,513,320

    Tolerance factor 2%

    Total amount to be paid per year 12,763,600Energy generated per year 1,655MWh

    PPA rate for next 12 years 7.5rs/KWh

    REC floor price 12,000rs/MWh (approx.)

    Gross cash flow through PPA 12,412,500

    Gross cash flow through REC trading 19,860,000

    Net Cash Flow (NCF) per year 21,759,180

    0

    100000

    200000

    300000

    400000

    500000

    600000

    700000

    800000

    900000

    1000000

    1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85

    Installment

    EMI

    Monthly Princip

    Monthly Interes

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    26/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 26

    NET CASH FLOW & PAY BACK PERIOD

    Now according to Discounted Cash Flow method (considering @10% DCF)

    years Present value of rs.1 @10%

    1 0.909 19,779,094.622 0.826 17,973,082.68

    3 0.751 16,341,144.18

    4 0.683 14,861,519.94

    5 0.621 13,512,450.78

    6 0.564 12,272,177.52

    7 0.513 11,162,459.34

    8 0.467 92,145,357.80

    9 0.424 83,660,898.56

    10 0.386 76,162,987.84

    So, Pay Back Period= 6 years 1 month (approx.)

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    27/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    w w w . r e n e w p o w e r z o n e . i n Page 27

    Most suitable vendors/suppliers of the project componentsSolar PV modules 1. Vikram Solar

    2. Waaree Energies

    3. Sova Power4. Canadian Solar

    5. Trina Solar

    6. First Solar

    Inverter 1. Power One

    2. SMA

    3. Smart Power

    4. REFusol

    5. Delta

    6. Schneider Electric

    Transformer 1. ABB2. Schneider Electric

    3. Ascott transformer

    4. Voltech

    Switch gear 1. Schneider Electric

    2. Megawin

    DC Disconnect 1. Schneider Electric

    Circuit breaker 1. Megawin

    2. ABB

    SCADA/RMS 1. Draker

    Cables 1. Havells

    2. Finolex cables

    3. RR Kabels

    4. Anchors

    Isolator 1. ABB

    2. Schneider Electric

    3. Megawin

    mailto:[email protected]:[email protected]
  • 8/10/2019 1MW Utility Scale Solar PV Power Plant

    28/28

    Queries@ [email protected]

    Detail Project Report

    1MWp SPV Power Plant

    Conclusion

    Id like to thank you for reading the whole paper. Hope you have got clear view on design &

    estimation of 1MW utility scale Solar PV Power Plant. Though I have discussed about the

    technical part as well as the financial part in detail, I might have been forgot to add anythingmore important. So, you are most welcome to give your valuable feedback & suggestion on this

    report. At the end, I discussed about some companies for the components. I have chosen these

    companies because their products are fulfilling my design criteria. It is not that Im representing

    these companies and their products.

    About Myself: Im a Solar PV professional currently working with a solar EPC company as

    Project Engineer. Ive done B.Tech in Electrical Engineering & holding a PG certificate in

    Advanced Solar Energy from delft Technical University, Netherlands.

    Personally I provide technical consulting including site survey, technical design, CAD design,preparation of DPR, guide in procurement & Construction.

    You can review my papers/reports at www.wbut.academia.edu/amritmandal

    Connect to my professional profile in linkedIn at

    http://www.linkedin.com/pub/amrit-mandal/55/667/a3

    Read solar PV related articles & learn about new technologies at- www.renewpowerzone.in

    Contact me or send your queries at- [email protected] , [email protected]

    THANK YOU

    mailto:[email protected]://www.wbut.academia.edu/amritmandalhttp://www.linkedin.com/pub/amrit-mandal/55/667/a3http://www.renewpowerzone.in/mailto:[email protected]:[email protected]:[email protected]:[email protected]://www.renewpowerzone.in/http://www.linkedin.com/pub/amrit-mandal/55/667/a3http://www.wbut.academia.edu/amritmandalmailto:[email protected]