200,000 gallon litchfield tank assessment report...the litchfield elevated water tank is a 200,000...
TRANSCRIPT
111618Georgetowncountyfullreport.docx
200,000 Gallon Litchfield Tank
Assessment Report
Assessment Date November 16, 2018
Prepared for: Georgetown County Water and
Sewer District 4145 Highmarket St
Georgetown, SC 29440
Prepared by: AECOM
425 South Cashua Drive Florence, SC 29501
Certified By: Brad Poston
NACE Certified Coating Inspector Level 1
111618Georgetowncountyfullreport.docx Page 2
Contents
1.0 General Information ........................................................................................................ 3
2.0 Summary of Field Observations .................................................................................... 4 2.1 Exterior ..................................................................................................................................... 4 2.2 Interior ...................................................................................................................................... 6
3.0 Recommendations .......................................................................................................... 8 3.1 Exterior ..................................................................................................................................... 8 3.2 Interior ...................................................................................................................................... 9
4.0 Probable Cost of Construction ................................................................................................ 11
Appendices
Appendix A Inspection Photos
Appendix B Laboratory Report
111618Georgetowncountyfullreport.docx Page 3
1.0 General Information
The Litchfield Elevated Water Tank is a 200,000 gallon welded steel tank, located on Blackgum
Rd near Hwy 17 in Pawley’s Island. It was constructed in 1975*.
AECOM assessed the condition of the tank at the request of the Georgetown County Water and
Sewer District on November 16, 2018. The primary purpose of this assessment was to inspect
the coating and overall condition of the tank. Recommendations for noted deficiencies will also
be included in this report.
The assessment consisted of a visual observation of the coating system as well as the interior
and exterior components of the tank. Assessment data was documented using digital still
photographs.
Date: November 16, 2018
AECOM Project No.: 60592576
Water System: Georgetown County Water and Sewer District (GCWSD)
Tank Name: Litchfield Elevated Water Tank
Tank Location: Blackgum Road, Pawley’s Island, SC
Nearest Intersection: Blackgum Road and Hwy 17
Latitude/Longitude: 33.4811876, -79.1035831
Capacity: 200,000*
Erection Date: 1975*
Manufacturer: Taylor Iron Works*
Design Type: Double Ellipsoidal
Number of Columns: 6
Column Diameter: 36”
Riser Diameter: 36”
Riser Manhole Size: 16”x12”
Height to Overflow: 149’-0”*
Construction Type (welded or riveted): Welded
Security: 6’-0” Chain Link Fence
Notes: *Values listed are from the Name Plate located on the tank riser.
111618Georgetowncountyfullreport.docx Page 4
2.0 Summary of Field Observations
Assessment personnel met with staff from GCWSD on November 16, 2018. Conditions noted
during the field assessment are documented below and are supplemented with color
photographs at the end of the report.
In general, the assessment showed that most areas of the tank exterior and interior surfaces are
in poor condition. The exterior coating has significant corrosion, delamination, “mud cracking”,
and poor adhesion. The interior coating also has significant corrosion.
There is also unused conduit/electrical service on the tank and areas of deteriorated metal on
the bases, bolts, ladder rungs, ladder brackets, and other areas.
2.1 Exterior
2.1.1 Concrete Base, Anchor Bolts, and Base Plate
The coating on the concrete base, anchor bolts, and base plates is in poor condition.
There is significant corrosion and delamination to the point to where there is bare metal
showing.
There appears to be minor metal loss on the base plates.
There are several anchor nuts/bolts that have corroded to the point of becoming
deteriorated with a significant amount of metal loss.
2.1.2 Columns, Struts, and X-Rods
The coating on columns is in poor condition.
There is significant corrosion, “mud cracking”, and delamination present.
There is mildew present.
There appears to be no metal loss on the columns.
The coating on the struts and x-rods have significant corrosion, “mud cracking”, and
delamination.
There appears to be minor metal loss on the turnbuckle nuts and bolts where the x-rod
and struts connect.
2.1.3 Riser
The coating on the riser is in poor condition.
There is significant corrosion, “mud cracking”, and delamination present.
There is a 16”x20” manway in the riser.
There is a sample port installed on the riser.
The name plate is installed on the riser.
111618Georgetowncountyfullreport.docx Page 5
2.1.4 Catwalk, Handrails, and Vertical Shell Plates
The coating on the catwalk, handrails, and vertical shell plates is in poor condition.
There are significant areas of corrosion, “mud cracking”, and delamination.
There are areas on the catwalk floor that appear to have moderate metal loss.
There are ten to fifteen low lying areas on the catwalk floor where water cannot drain
properly.
There does not appear to be any metal loss on the vertical shell plates.
The level indicator appears to be out of service.
There is what appears to be a corral installed at the top of the vertical shell plates. The
coating on it matches the condition of the rest of the tank.
2.1.5 Roof
The coating on the roof of the tank is in poor condition.
There are significant areas of corrosion, “mud cracking”, and delamination.
There is a 24”x24” hatch with curb.
There are no cellular antennas mounted to the roof of the tank.
2.1.5 Vent
There is an 18” diameter vent.
The coating is in poor condition.
There is a screen installed.
There is an aviation light mounted to the top of the vent.
2.1.6 Ladders and Safety Devices
The coating on the exterior ladders is fair.
There moderate corrosion on the rungs and brackets.
It was indicated by GCWSD that some repairs had been made to the ladder, however
there is still moderate metal loss on the column ladder and the dome ladder.
Galvanized cable safety climbs are installed on both exterior ladders.
2.1.7 Aviation Light
There is an aviation light mounted to the top of the vent.
At the time of the inspection the light was not on.
2.1.8 Logos
There is a logo on the tank.
2.1.9 RF Antennas
There are no antennas mounted on the tank.
2.1.10 Security
The site has a 6’-0” chain link fence with a gate locked by a combination padlock.
111618Georgetowncountyfullreport.docx Page 6
The ladder gate is locked with a Master Lock Key # 2402.
The access hatch is locked with a Master Lock Key # 2402.
2.2.11 Coating
The finish coat on the exterior of the tank appears to be an epoxy.
The adhesion is poor. There is severe delamination of the existing coating system.
Exterior paint samples were taken at the inspection. The results are attached in
Appendix B.
2.2.12 Site Considerations
The tank is located on a wooded lot with a few houses somewhat close by.
2.2 Interior
Assessment of the tank interior (via the upper access hatch) revealed the following:
2.2.1 Riser
Due to the amount of water in the tank during the time of the inspection, the interior of
the riser of the tank could not be inspected thoroughly.
2.2.2 Bowl
Due to the amount of water in the tank during the time of the inspection, the bowl of the
tank could not be inspected thoroughly.
There is a minor amount of sediment present in the belly of the tank.
2.2.3 Vertical Shell Plates and Braces
The coating on the vertical shell plates and braces is fair.
There is minor corrosion on the vertical shell plates around where the braces attach.
There is moderate corrosion on the braces.
2.2.4 Roof
The coating on the roof is fair.
There is minor corrosion on the roof.
2.2.5 Ladders and Safety Devices
The coating on the interior ladder is poor.
There is significant corrosion on the rungs and brackets.
There is significant metal loss on the rungs and brackets.
2.2.6 Overflow
The overflow is a 6-inch diameter pipe that starts on the interior and exits the tank to run
down a column leg on the exterior.
The coating is poor.
111618Georgetowncountyfullreport.docx Page 7
The pipe connects to a pipe that leads underground.
2.2.7 Coating
The interior coating is an epoxy system.
The coating system is in poor to fair condition.
111618Georgetowncountyfullreport.docx Page 8
3.0 Recommendations
3.1 Exterior
Overall, the exterior coating of this tank is in poor condition. AECOM recommends that the
exterior of this tank receive a full renovation immediately.
3.1.1 Coating Recommendations
Exterior Steel:
Surface Prep- Pressure wash with the chemical Chlor*Wash to remove all mildew, dirt,
salt and any surface containments with a 5,000+ pound-per-square-inch (PSI) pressure
washer before blasting to remove all the old existing coating. The surface should be
washed daily with Chlor*wash prior to any prep work or coatings being applied.
o Blast all exterior steel to SSPC SP6 Commercial Blast Cleaning standards,
minimum 2.5 surface profile.
Prime Coat - Apply one (1) full coat of aromatic urethane, zinc rich (performance equal
to Tnemec Series 91 H2O or 94 H2O HYDRO-ZINC) at 2.5-3.0 dry mils.
Stripe Coat – Apply one (1) stripe coat of polyamidoamine epoxy (performance equal to
Tnemec Series 66) at 3.0-5.0 dry mils to all handrails, hard edges, roof laps, weld
seams, and deep pits.
Full Prime Coat - Apply one (1) full coat of polyamide epoxy (performance equal to
Tnemec Series 161HS) at 3.0-5.0 dry mils.
Intermediate Coat - Apply one (1) full coat of aliphatic acrylic polyurethane
(performance equal to Tnemec Series73 ENDURA-SHIELD) at 2.5-3.0 dry mils.
Finish Coat - Apply one (1) full coat of advanced thermoset solution fluoropolymer
(performance equal to Tnemec Series 700 HYDROFLON) at 2.5-3.0dry mils.
Concrete Base:
Surface Prep -Wash the mildew, dirt, and surface containments off of the tank with
5,000+ PSI pressure washer with a rotating nozzle. Hand/Power tool loose coating and
corroded areas to a specification of SSPC SP2/3.
Prime Coat - Apply one (1) full coat of polyamidoamine epoxy (performance equal to
Tnemec 161HS) at 4.0-8.0 dry mils.
Finish Coat - Apply one (1) full coat of polyamidoamine epoxy (performance equal to
Tnemec 161HS) at 4.0-8.0 dry mils.
Additional Coat - Apply one (1) two inch layer of modified aliphatic polyaspartic
(performance equal to Tnemec 265 Elastoshield TG) at 50.0-100.0 dry mils between
concrete base and metal plate.
111618Georgetowncountyfullreport.docx Page 9
3.1.2 Exterior Repairs
1. Remove galvanized safety cable climb from column and dome ladder.
2. Install stainless steel safety climb on column leg ladders. Install neoprene gasket
between safety climb device and ladder rungs.
3. Drill (10-15) ¾” holes in the catwalk floor to allow adequate drainage.
4. Install new sample port on riser.
5. Install pressure gauge on riser.
6. Install multiple 2”x8”x1/4” flat bar standoffs adjacent to exterior leg and dome ladders
with spacing no greater than 10’ on center.
7. Remove unused conduit.
8. Repair or remove level indicator.
9. Repair areas with metal loss as required on structural steel.
10. Replace anchor bolts.
11. Replace riser manway with 24” diameter manway.
12. Install new 24” diameter frost free vent.
13. Remove corral.
3.2 Interior
The interior coating is in fair condition with areas of corrosion. AECOM recommends that the
interior of this tank receive a full renovation at the same time as the tank exterior.
3.2.1 Coating Recommendations
Interior Steel:
Surface Prep-Blast all interior steel to SSPC SP10 Near-White Blast standard, minimum
2.5 surface profile.
Prime Coat - Apply one (1) full coat of aromatic urethane, (performance equal to
Tnemec Series 91 H2O or 94 H2O HYDRO-ZINC) at 2.5-3.0 dry mils.
Stripe Coat- Apply one (1) stripe coat of polyamidoamine epoxy (performance equal to
Tnemec series N140 POTA-POX) at 4.0-6.0 dry mils to all hard edges, roof laps, weld
seams, ladders, handrails, deep pits, and clips.
Intermediate Coat - Apply one (1) full coat of polyamidoamine epoxy (performance
equal to Tnemec Series N140 POTA-POX) at 4.0-6.0 dry mils.
Finish Coat - Apply one (1) full coat of polyamidoamine epoxy (performance equal to
Tnemec Series N140 POTA-POX) at 4.0-6.0 dry mils.
111618Georgetowncountyfullreport.docx Page 10
3.2.2 Interior Repairs
1. Install stainless steel safety climb to interior ladder. Install a neoprene gasket between
safety climb device and ladder rungs.
2. Remove and replace interior bowl ladder.
3. Repair or remove the interior components of the old float system.
111618Georgetowncountyfullreport.docx Page 11
4.0 Probable Costs of Construction
Cost estimates are provided for the recommendations identified in Section 3. Any opinions of
probable construction costs provided by AECOM represent AECOM's good faith professional
judgment in light of its experience, knowledge and the information reasonably available to
AECOM at the time of preparation of the opinion. However, since AECOM has no control over
the market, economic conditions or the bidding procedures, AECOM does not make any
guarantees or warranties with respect to such opinions.
The table below represents budget level cost estimates based upon current market conditions
and do not incorporate any considerations for impacts of future inflation. Table 4.1 presents the
estimated costs for rehabilitation.
Table 4-1. Estimated Costs for Rehabilitation
Treatment Location Surface
Prep
Coating System Expected
life cycle
Cost
Full
renovation Wet Interior SSPC SP10 Zinc, Epoxy, Epoxy 15+ years $80,000
Full
renovation Exterior SSPC SP6
Zinc, Epoxy,
Polyurethane,
Fluoropolymer
15+ years $180,000
Repair Items $50,000
Containment $100,000
Contingency (~15%) $40,000
Total Estimated Costs $450,000
111618Georgetowncountyfullreport.docx
APPENDIX A
INSPECTION PHOTOS
Name Plate Hatch on Riser
Corrosion of Riser Corrosion of Column and Base
Corrosion of X-Rod Corrosion of Anchor Bolt
Corrosion of Anchor Bolt Nut Corrosion of Overflow Pipe
Corrosion of Anchor Bolt Corrosion of Column Base
Tank Belly Corrosion on Column
Column Coating Adhesion Test 1
Coating Adhesion Test 2 Ladder/ Ladder Gate
Corrosion of Ladder Bracket Corrosion of Ladder Rung
Corrosion of Strut and X-Rod Connection Strut
Corrosion of Ladder and Bracket Corrosion of Ladder and Bracket
Corrosion of Column and Moss on X-Rods Corrosion of Column
Corrosion of Column X-Rod
Unused Conduit and Wire Strut
Corrosion of Ladder Strut
Rust on Safety Climb Cable Corrosion of Ladder Bolt
X-Rods Corrosion of X-Rod
Delamination on Tank Belly X-Rods and Braces
Corrosion under Balcony Floor Corrosion under Balcony Floor
Underneath Balcony Floor Tank
Corrosion of Balcony Floor at Ladder Corrosion of Balcony Floor at Ladder
Corrosion of Balcony Floor at Ladder Column Connection
Tank Wall Dome Ladder and Level Board Indicator
Delamination of Coating on Tank Wall Corrosion of Balcony Floor
Corrosion of Balcony Floor Delamination of Coating on Tank Wall
Tank Wall and Corral Corrosion of Balcony Floor
Corrosion of Balcony Floor Corrosion of Balcony Floor
Corrosion of Handrail on Balcony Corrosion on Overflow Pipe
Dome Ladder Dome Ladder at Knuckle
Dome Hatch Knuckle of Tank
Knuckle of Tank Corrosion of Level Indicator
Vent Corrosion of Tank Roof
Corrosion of Hatch Curb Corrosion of Interior Ladder
Corrosion of Interior Ladder Corrosion of Interior Brace Rods
Interior Brace Rods Interior Brace Rods
Interior Tank Roof Interior Ladder Rung
Dome Hatch Corral
Gap Between Tank and Corral Brace Rod
Brace Rod Brace Rod
Tank Belly Ladder Gate Secured upon leaving
Gate Secured upon leaving Gate Secured upon leaving
111618Georgetowncountyfullreport.docx
APPENDIX B
LABORATORY REPORT
SHEALY ENVIRONMENTAL SERVICES, INC.
The electronic signature above is the equivalent of a handwritten signature.This report shall not be reproduced, except in its entirety, without the written approval of Shealy Environmental Services, Inc.
Shealy Environmental Services, Inc.106 Vantage Point Drive West Columbia, SC 29172 (803) 791-9700 Fax (803) 791-9111 www.shealylab.com
Report of Analysis
AECOM101 Research DriveColumbia, SC 29203Attention: Nathan Ward
Project Name: Georgetown Co W&S - Litchfield Tank
Project Number: 60592576, Task 1
Lot Number:TK29036
Date Completed:12/05/2018
12/11/2018 3:22 PMApproved and released by:
Project Manager: Kelly M. Nance
Page 1 of 8
SHEALY ENVIRONMENTAL SERVICES, INC.SC DHEC No: 32010001 NELAC No: E87653 NC DENR No: 329 NC Field Parameters No: 5639
Shealy Environmental Services, Inc.106 Vantage Point Drive West Columbia, SC 29172 (803) 791-9700 Fax (803) 791-9111 www.shealylab.com
Case NarrativeAECOM
Lot Number: TK29036
This Report of Analysis contains the analytical result(s) for the sample(s) listed on the Sample Summaryfollowing this Case Narrative. The sample receiving date is documented in the header informationassociated with each sample.
All results listed in this report relate only to the samples that are contained within this report.
Sample receipt, sample analysis, and data review have been performed in accordance with the mostcurrent approved NELAC standards, the Shealy Environmental Services, Inc. ("Shealy") QualityAssurance Management Plan (QAMP), standard operating procedures (SOPs), and Shealy policies. Anyexceptions to the NELAC standards, the QAMP, SOPs or policies are qualified on the results page ordiscussed below.
Where applicable, all soil sample analysis are reported on a dry weight basis unless flagged with a "W"qualifier
If you have any questions regarding this report please contact the Shealy Project Manager listed on thecover page.
Page 2 of 8
SHEALY ENVIRONMENTAL SERVICES, INC.Sample SummaryAECOMLot Number: TK29036
Sample Number Sample ID Matrix Date Sampled Date Received001 11/27/2018Paint Chips - Litchfield Tank Solid 11/29/2018
(1 sample)
106 Vantage Point Drive West Columbia, SC 29172 (803) 791-9700 Fax (803) 791-9111 www.shealylab.comShealy Environmental Services, Inc.
Page 3 of 8
SHEALY ENVIRONMENTAL SERVICES, INC.Detection SummaryAECOM
Lot Number: TK29036
Sample Sample ID Matrix Parameter Method Result Q Units Page001 Paint Chips - Litchfield Tank Solid Barium 6010D 5900 W mg/kg 5001 Paint Chips - Litchfield Tank Solid Chromium 6010D 59 W mg/kg 5001 Paint Chips - Litchfield Tank Solid Lead 6010D 190 W mg/kg 5(3 detections)
106 Vantage Point Drive West Columbia, SC 29172 (803) 791-9700 Fax (803) 791-9111 www.shealylab.comShealy Environmental Services, Inc.
Page 4 of 8
RCRA MetalsDescription: Matrix:
Date Received:
Client: Laboratory ID:Date Sampled:
AECOMPaint Chips - Litchfield Tank
TK29036-00111/27/201811/29/2018
Solid
Run Prep Method Analytical Method Dilution Analysis Date Analyst Prep Date Batch1 3050B 6010D 10 12/05/2018 0409 CJZ 12/04/2018 0922 911731 7471B 7471B 1 12/02/2018 2126 JCF 12/02/2018 1318 91116
AnalyticalCASParameter Number Method Result Q LOQ Units RunArsenic 7440-38-2 6010D ND W 1mg/kg6.3Barium 7440-39-3 6010D 5900 W 1mg/kg11Cadmium 7440-43-9 6010D ND W 1mg/kg2.1Chromium 7440-47-3 6010D 59 W 1mg/kg4.2Lead 7439-92-1 6010D 190 W 1mg/kg4.2Mercury 7439-97-6 7471B ND W 1mg/kg0.076Selenium 7782-49-2 6010D ND W 1mg/kg8.4Silver 7440-22-4 6010D ND W 1mg/kg4.2
LOQ = Limit of Quantitation B = Detected in the method blank E = Quantitation of compound exceeded the calibration rangeP = The RPD between two GC columns exceeds 40%ND = Not detected at or above the LOQ N = Recovery is out of criteria
H = Out of holding time W = Reported on wet weight basis
106 Vantage Point Drive West Columbia, SC 29172 (803) 791-9700 Fax (803) 791-9111 www.shealylab.comShealy Environmental Services, Inc.
Page 5 of 8
Chain of Custodyand
Miscellaneous Documents
106 Vantage Point Drive West Columbia, SC 29172 (803) 791-9700 Fax (803) 791-9111 www.shealylab.comShealy Environmental Services, Inc.
Page 6 of 8
SHEALY ENVIRONMENTAL SERVICES, INC.
106 Vantage Point Drive West Columbia, SC 29172 (803) 791-9700 Fax (803) 791-9111 www.shealylab.comShealy Environmental Services, Inc.
Page 7 of 8
SHEALY ENVIRONMENTAL SERVICES, INC.
106 Vantage Point Drive West Columbia, SC 29172 (803) 791-9700 Fax (803) 791-9111 www.shealylab.comShealy Environmental Services, Inc.
Page 8 of 8