2009-09-25

1
Site work was very minimal throughout the week because of all the rain. Electrical rough-in at the service yard is ongoing. Had 2.40” of rain this week. Tuesday 9.22.09 was considered a rain day. Installing carton forms on the west side of the crawl space at the HQ. Installing the remainder of the 30” Storm Sewer Run-out to Inlet Boxes is ongoing. 50% complete on the cisterns miscellaneous drain lines (6”-12”) to building. The luffing crane was used for the first time this week to assist in shoring for the 2nd floor deck. Stopped backfill at the crawlspace walls at the VC because of rain. Started grade beams at VC. Storm lines to underground tank ongoing. Texas A&M University Agriculture Headquarters Weekly Report: 9/21/09-9/25/09 North View Shoring for 2nd Floor Deck @ HQ View @ Northeast Corner of HQ Luffing Crane Shoring for Elevated Decks Carton Forms at HQ

Upload: texas-am-agrilife

Post on 12-Mar-2016

218 views

Category:

Documents


3 download

DESCRIPTION

• Tuesday 9.22.09 was considered a rain day. • Stopped backfill at the crawlspace walls at the VC because of rain. • Installing carton forms on the west side of the crawl space at the HQ. • Installing the remainder of the 30” Storm Sewer Run-out to Inlet Boxes is ongoing. • The luffing crane was used for the first time this week to assist in shoring for the 2nd floor deck. • Electrical rough-in at the service yard is ongoing. • Had 2.40” of rain this week. North View

TRANSCRIPT

Page 1: 2009-09-25

• Site work was very minimal throughout the week because of all the rain.

• Electrical rough-in at the service yard is ongoing.

• Had 2.40” of rain this week.

• Tuesday 9.22.09 was considered a rain day.

• Installing carton forms on the west side of the crawl space at the HQ.

• Installing the remainder of the 30” Storm Sewer Run-out to Inlet Boxes is ongoing.

• 50% complete on the cisterns miscellaneous drain lines (6”-12”) to building.

• The luffing crane was used for the first time this week to assist in shoring for the 2nd floor deck.

• Stopped backfill at the crawlspace walls at the VC because of rain.

• Started grade beams at VC.

• Storm lines to underground tank ongoing.

Texas A&M University Agriculture Headquarters

Week ly Repo r t : 9 / 2 1 / 09 - 9 / 25 / 09

North View Shoring for 2nd Floor Deck @ HQ

View @ Northeast Corner of HQ Luffing Crane Shoring for Elevated Decks

Carton Forms at HQ