2009-09-25
DESCRIPTION
• Tuesday 9.22.09 was considered a rain day. • Stopped backfill at the crawlspace walls at the VC because of rain. • Installing carton forms on the west side of the crawl space at the HQ. • Installing the remainder of the 30” Storm Sewer Run-out to Inlet Boxes is ongoing. • The luffing crane was used for the first time this week to assist in shoring for the 2nd floor deck. • Electrical rough-in at the service yard is ongoing. • Had 2.40” of rain this week. North ViewTRANSCRIPT
• Site work was very minimal throughout the week because of all the rain.
• Electrical rough-in at the service yard is ongoing.
• Had 2.40” of rain this week.
• Tuesday 9.22.09 was considered a rain day.
• Installing carton forms on the west side of the crawl space at the HQ.
• Installing the remainder of the 30” Storm Sewer Run-out to Inlet Boxes is ongoing.
• 50% complete on the cisterns miscellaneous drain lines (6”-12”) to building.
• The luffing crane was used for the first time this week to assist in shoring for the 2nd floor deck.
• Stopped backfill at the crawlspace walls at the VC because of rain.
• Started grade beams at VC.
• Storm lines to underground tank ongoing.
Texas A&M University Agriculture Headquarters
Week ly Repo r t : 9 / 2 1 / 09 - 9 / 25 / 09
North View Shoring for 2nd Floor Deck @ HQ
View @ Northeast Corner of HQ Luffing Crane Shoring for Elevated Decks
Carton Forms at HQ