2009 ENVIRONMENTAL SEMINARBoat Bottom Pressure Washing
Requirements &
General Permit for the Discharge of Stormwater Associated with Industrial
Activity
Tuesday, August 18, 2009
Management of Vessel Pressure Washing Wastewater
Spring 2006: Discharge of pressure wash water to surface or ground water no longer allowed
December 31, 2008: Original deadline to cease discharge
May 2008: DEP publishes guidance for pressure wash water management
September 30, 2009: Deadline extension
March 2009: After much negotiation with DEP to extend Sept. deadline, CMTA sends letter to legislature and Consent Order is negotiated
Quick History of the Issue
DEP Guidance on Boat Bottom Pressure Washing (as of May 2008)
• Contain & collect wastewater deflected from any boat surface during boat bottom pressure washing . Wastewater cannot be discharged to ground or surface waters
• Handle wastewater as “process wastewater.” Process wastewater is not covered by the Stormwater General Permit and cannot be discharged to ground or surface waters
PW WASTEWATER MANAGEMENT OPTIONS
COLLECT, TREAT & PIPE TO SANITARY SEWER• Treat water in compliance with General Permit for Miscellaneous Discharges of
Sewer Compatible Wastewater (“MISC General Permit”) and regulations of municipal water pollution control authority
COLLECT, TREAT & HAUL TO SANITARY SEWER• Transport water by the marina operator, or by a contract hauler licensed under
CGS Section 22a-454 for discharge to a municipal sewage treatment plant in compliance MISC GP & local regulations
COLLECT & HAUL TO INDUSTRIAL WASTEWATER TREATMENT FACILITY• Collect wastewater in a tank and transport by licensed waste hauler to licensed
industrial wastewater treatment facility
*Facilities must either cease discharge of pressure wash waste water by September 30, 2009 or
enter into Consent Order Agreement with CT DEP to extend
deadline to December 31, 2010
YOU DON’T HAVE TO SIGN THE CONSENT ORDER
If you don’t sign the consent order, you must:
1. stop discharging pressure wash wastewater to ground or surface water; or2. stop pressure washing boats…
BY SEPTEMBER 30, 2009
IF YOU DO SIGN THE CONSENT ORDER
If you do sign the Consent Order, you must:
1. Officially sign onto Consent Order by September 15, 2009; and
2. abide by the Terms and Conditions of the agreement and complete all enforceable milestones
BY DECEMBER 31, 2010
Implement 2002 Clean Marina BMPs for pressure washing
Submit copy of Exhibit A to Ed Finger @ CT DEP’s Water Permitting & Enforcement Division, to officially enter into Consent Order
Prepare & complete all plans and specifications for project
File all state and local permit applications (including COP)
Obtain all state and local permits, licenses & approvals
File Miscellaneous General Permit registration, if required
Submit Reporting & Certification Form to CT DEP describing timeline, certifying interim BMPs implemented & actions complete
Cease all unpermitted discharges of pressure wash wastewater
Submit Reporting & Certification Form to CT DEP certifying that all actions have been complete or certifying that PW discharges have ceased TI
MEL
INE
FOR
CON
SEN
T O
RDER
Pad constructed of impervious material coated with a sealant
DEP
GU
IDAN
CE O
N P
AD D
ESIG
NDes
igned
to m
inimize
storm
water
running o
n
to th
e pad
NOTE: 1) Pads constructed to allow stormwater to overflow when not pressure washing are considered a point source and subject to the conditions of the Industrial Stormwater General Permit.
Process wastewater should not overflow or run off the pad at any time, nor should it accumulate and discharge to ground or surface water
Lockable valve, watertight cover or plug, or dedicated power source that can be secured is required for pumps used to divert stormwater
sump
Stormwater discharge
Discharge to tank or sanitary sewer
EXAMPLE ONLY-NOT FOR CONSTRUCTION
Post signs outlining proper operation
DEP
GU
IDAN
CE O
N O
PERA
TIO
N &
MAI
NTE
NAN
CESweep and rinse pad prior to activating stormwater diversion
NOTE: 1)O&M for pad must be identified in SWPPP, included in weekly inspections, staff training, stormwater monitoring including sample location and procedures2)Inspection of pad must be included in Comprehensive Site Compliance Evaluation as part of SWPPP
Secure stormwater conveyance prior to pressure washing.
sump
EXAMPLE ONLY-NOT FOR CONSTRUCTION
Maintain equipment, including hoses, to prevent discharges. Leaks from hoses and equipment are considered process wastewater discharges. Use a minimal amount of pressure & water
Transport resulting solid waste to a permitted waste disposal facility
Discharge to tank or sanitary sewer
Stormwater discharge
DEP Guidance on Managing Overspray
*No need to contain overspray as long as water source is a potable water supply and no additional chemicals or pollutants are added
*If chemicals are added (eg., treated recycled water source) , no collection necessary if the wastewater meets the target criteria for copper, lead and zinc as specified in the Stormwater GP. The discharge of recycled water from a pressure washing gun must not exceed the following concentrations : Copper 1.3 mg/l
Lead 0.04 mg/lZinc 0.50 mg/l
Photo credit: Thomas MaGuire, Massachusetts Department of Environmental Protection
“process wastewater”
“overspray”: the incidental spray discharged from a pressure washing gun during boat bottom pressure washing activities that does not come into contact with any boat surface, including any that may drift by air current away from its point of origin
Facilities that do not sign on to the Consent Order will be
subject to the full enforcement authority of DEP
as of September 30, 2009*